GLAST LAT Project Gamma-ray Large Area Space Telescope ISOC Peer Review - March 2, 2004 GLAST Large Area Telescope ISOC Peer Review Section 7.1 Pre Launch Operations and Calibrations Eduardo do Couto e Silva Manager of the Science Verification Analysis and Calibration Department of I&T Subsystem Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 1 GLAST LAT Project ISOC Peer Review - March 2, 2004 Outline • Connection between I&T/SVAC and ISOC/SOG • I&T/SVAC Requirements • Examples of I&T/SVAC activities – Lessons Learned from I&T/SVAC – Examples of preliminary data analysis • Summary Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 2 GLAST LAT Project ISOC Peer Review - March 2, 2004 Connection between SVAC/I&T and SOG/ISOC The Science Verification Analysis and Calibration (SVAC) Department of the I&T subsystem will gradually transition into the Science Operations Group of the ISOC. The main responsibilities of the SVAC Department are • Coordinate Data Analysis for Science Verification • Perform final pre launch calibrations • Perform first in-flight calibrations prior to hand off to ISOC/SOG (see talk in section 7.2) • Deliver calibration products to ISOC/SOG Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 3 GLAST LAT Project ISOC Peer Review - March 2, 2004 I&T Pre Launch Experience with EM • The Science Operations Group (SOG) has been recently created and does not yet have all of its documentation in place • In this talk we will present an overview of the I&T/SVAC experience using the Engineering Model (EM) test as an example of the activities that will be performed by the SOG during mission operations • The lessons learned on following items will be discussed – Documentation – Data Processing – Operations – Calibrations – Data Analysis Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 4 GLAST LAT Project ISOC Peer Review - March 2, 2004 Science Verification, Analysis and Calibration (SVAC) Plan Science and Calibration requirements from Subsystems Plans were captured in LAT-MD-00446 Level II Science Requirement Document 443-SRD-00010 LAT Performance Specifications LAT-SS-00010 Levels III and IV ACD, CAL, TKR Specifications Level III GLAST LAT SVAC Plan Calibration Document: LAT-PR-03213-01 Data Analysis LAT-SS-00016, LAT-SS-00017 LAT-SS-00018, LAT-SS-00152, LAT-SS-00210 LAT-MD-00446 Science Verification Section 7.1 Pre-launch Operation and Calibration 5 GLAST LAT Project ISOC Peer Review - March 2, 2004 SVAC Plans and Technical Documents LEVEL III LAT-MD-00446 LAT-MD-01587 Co-owned with Project Scientist Co-owned with Systems Engineering LEVEL IV Contributed Manpower Plan Existing docs are shown in red boldface Hardware Test Plan/Results LAT-MD-00573 Engineering Model EM Calibrations LAT-TD-01588 Simulations Databases LAT-TD-00582 LAT-TD-00578 LAT-TD-01593 LAT-MD-00575 LAT LAT-MD-00613 Interfaces LAT-TD-00571 LAT-TD-01340 LAT-TD-01590 SAS responsibility LAT-TD-00580 LAT-TD-00573 LAT-MD-00576 LAT-MD-00577 LAT-MD-00581 Co owned with Instrument Operations Center LAT-TD-01595 At this time we are reviewing the EM documents and lessons learned to produce the necessary documentation for the LAT Integration Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 6 GLAST LAT Project ISOC Peer Review - March 2, 2004 Level III Documents - Contents Co owned with Project Scientist • LAT-MD-00446 - SVAC Plan – – – – Instrument Calibrations SVAC Compliance Pre Launch Test Matrix Post Launch Test Matrix Contributed Manpower Plan • LAT-MD-00613 - SVAC Plan – – – Engineering Model • TKR,CAL,SAS Calibration Unit • ACD,TKR,CAL,SAS,IOC LAT • ACD,TKR,CAL,SAS,IOC Document: LAT-PR-03213-01 Co owned with Systems Engineering • LAT-MD-01587 – SVAC Test Requirements Plan – – – – – – – – – – – – – – – – – Hardware Required Flight Software Required Test Configuration EGSE Required MGSE Required Test Software Support Instrumentation Test Data Record Data Format Test Products Analysis Activities Environmental Conditions Test performance Procedures Facility Requirements Quality Program Performance Requirements System Assurance Requirements Test Equipment Calibration Section 7.1 Pre-launch Operation and Calibration 7 GLAST LAT Project ISOC Peer Review - March 2, 2004 Level IV Technical Documents – Contents • Test Plan/Results – LAT-MD-00573 – SVAC EM Plan • Using Engineering Model as an example Describes the hardware data taking configurations, infrastructure needed for calibrations, calibration types, data analysis requirements. Run time estimation using MC simulation – LAT-MD-01593 – SVAC Results from the Engineering Model Test • • Calibrations – LAT-TD-01588 – Calibration Algorithms for the Engineering Model • • Describes the geometry used in the simulation, includes table to translate nomenclature from software developers to engineers and also contains traceability Database – LAT-TD-00578 – SVAC Database for the Engineering Model • • Describes the calibration algorithms developed in conjunction with SAS and subsystems Simulations – LAT-TD-00582 – EM Geometry for the Monte Carlo Simulation • • Describes the results and how requirements were met Describes the table schema and how a web based engine will allow access to a subset of calibration data for the purpose of tracking changes in time. Interfaces – LAT-TD-00571 – SVAC/SAS Interface Control Document • Describes the responsibilities between SAS and SVAC for data analysis (Statement of work) – LAT-TD-01340 – SAS Calibration Infrastructure • Describes SAS calibration infrastructure that holds the primary calibration data Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 8 GLAST LAT Project ISOC Peer Review - March 2, 2004 Documentation – Lessons Learned • EM Lessons Learned – Lots of documents and not enough time for people to read them (i.e., less than optimal feedback from subsystems) – In some cases ideas were discussed in details but were not mature enough to be implemented (e.g. EM database) – Difficult to keep up with update needs given the manpower limitations within I&T • For SOG – Documentation shall be kept at a level that is adequate to guide planning while allowing for technical reviews – Interfaces need more attention and shall be more detail oriented Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 9 GLAST LAT Project ISOC Peer Review - March 2, 2004 Data Analysis Chain In the future the FSW Filter will go in here SAS/ONLINE EM EBF Online Analysis tools online scripts Converter ROOT tree Files (digi) SAS Recon Calibration scripts Calibration Constants ROOT tree Files (recon) SAS User Interface “GENERAL” USER Document: LAT-PR-03213-01 ROOT ntuple files SAS Converter IDL Structures Section 7.1 Pre-launch Operation and Calibration 10 GLAST LAT Project ISOC Peer Review - March 2, 2004 Data Processing – Lessons Learned • EM Lessons Learned – Data transfer was tedious and was partially automated – Reprocessing of data occurred more often than expected – The Information about datasets necessary for data analysis was not available through a user friendly interface (despite our planning!) • For SOG – Fix communication problems between interfaces and devise system tests to minimize needs to reprocess data – Investigate with SAS how to automate Data Processing – Create better requirements to implement database queries Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 11 GLAST LAT Project ISOC Peer Review - March 2, 2004 Calibrations – Lessons Learned • EM Lessons Learned – In some cases procedures were developed on the fly (not a serious impact since we did not have to deal with many software versions) – I&T was not directly involved in all calibrations • For SOG – Implement better configuration control of data and procedures to produce data – Develop sufficient expertise within SOG to handle all possible calibrations – Understand better requirements for interfaces with FSW Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 12 GLAST LAT Project ISOC Peer Review - March 2, 2004 Operations – Lessons Learned • EM Lessons Learned – In some cases it was difficult to determine the data taking configuration – Not all information was available during data taking – New configurations were added during the data taking period without adequate planning • For SOG – Implement better user guides and operator training – Develop a process to critically review operational procedures and to address unscheduled configuration changes – Understand interface with FSW Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 13 GLAST LAT Project ISOC Peer Review - March 2, 2004 EM Ground Calibration Set-up Cosmic Background Gammas:66% 17.6 MeV Not a monochromatic beam! 34% 14.6 MeV, FWHM = 1.5 MeV + CAL TKR lots of electrons Beam pipe Electrons are produced by gamma conversions in the iron shield in front of the accelerator Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 14 GLAST LAT Project ISOC Peer Review - March 2, 2004 CAL Energy Spectrum 400 Preliminary Photon Source OFF From Gary Godfrey 300 200 100 0 1 10 100 1000 2500 Photon Source ON 2000 Mostly photons 1500 1000 500 0 1 Document: LAT-PR-03213-01 10 100 Energy (MeV) 1000 Section 7.1 Pre-launch Operation and Calibration 15 GLAST LAT Project ISOC Peer Review - March 2, 2004 Source Calibration Preliminary From Gary Godfrey Expect two energy lines Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 16 GLAST LAT Project ISOC Peer Review - March 2, 2004 Flux Measurement Preliminary 9% of the of photons produced by the source are measured by the EM From Gary Godfrey Extrapolation to Photon Source Top TKR face 10% error is dominated by the knowledge on the BGO position EM EM Rec Direction cosine In 0.02 bins 1200 N EM (0.02 2 ) sr 0.093 0.01 N BGO 1152 s 13.35Hz (0.15) sr BGO t 7 pipe Document: LAT-PR-03213-01 9 45 cos 180 BGO (6cm) 2 4 e 4 (21.84cm) 2 Section 7.1 Pre-launch Operation and Calibration 0.15 17 GLAST LAT Project ISOC Peer Review - March 2, 2004 Energy Measurement Operational Settings IDs are described in LAT-MD-00446 Perform C18,C19,C20,C22,C23,C24 to establish baseline for data taking Raw spectrum of individual crystals ROOT tree Files (digi) Perform Calibrations C14,C15,C16,C18 on each crystal Calibration Constants ROOT tree Files (recon) ROOT ntuple files Produce Energy Calibrated Spectrum using all crystals Calibrations Use Data Analysis Cuts and VDG Flux Calibration to obtain final spectrum Data Analysis Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 18 GLAST LAT Project ISOC Peer Review - March 2, 2004 EM Energy Spectrum (VDG DATA) Preliminary Event selection: nTkrTracks>=1 && zDir < -0.9 (25 deg from vertical) && maxCal>4MeV From Xin Chen Expected Spectrum Delta function (17.6 MeV) Breit-Wigner (mean 14.5, width=1.5MeV) Energy (MeV) Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 19 GLAST LAT Project ISOC Peer Review - March 2, 2004 Energy Spectrum (VDG MC) Preliminary Event selection: nTkrTracks>=1 && zDir < -0.9 (25 deg from vertical) && maxCal>4MeV From Xin Chen Events converted in top layer of Tracker only Expected Spectrum Delta function (17.6 MeV) Breit-Wigner (mean 14.5, width=1.5MeV) Energy (MeV) Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 20 GLAST LAT Project ISOC Peer Review - March 2, 2004 Data Analysis – Lessons Learned • EM Lessons Learned – Expected experimental backgrounds were not thoroughly studied prior to the test – Some algorithms and pieces of the offline software were not validated prior to the data taking period – Calibrations took longer than expected • For SOG – Develop with SAS, I&T and LAT Collaboration tools for instrument and sky simulations to address needs of firstyear operations – Develop better communications across interfaces and sharpen calibration requirements Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 21 GLAST LAT Project ISOC Peer Review - March 2, 2004 Summary • Lessons Learned – The I&T/SVAC group will revisit all EM technical issues to ensure a successful LAT integration. I&T/SVAC will participate in the planning process to build the infrastructure required for the SOG during the I&T integration • Concerns – More discussions and planning are needed to address how the operational procedures and calibrations exercised during Integration will be adapted to the Flight Software environment (not present during EM) Document: LAT-PR-03213-01 Section 7.1 Pre-launch Operation and Calibration 22