GLAST LAT Project March 24, 2003 GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope Tracker Subsystem WBS 4.1.4 6C: Ladder Fabrication A. Brez I.N.F.N. Pisa Brez@pi.infn.it 6C Tracker Peer Review, WBS 4.1.4 1 GLAST LAT Project March 24, 2003 Ladder construction flow down • LAT ladder construction follows the block diagram (see LAT-PS00635 and LAT-PS-00831 for details) WS1: Receiving and Inspection Storage WS2: SSD Edge Bonding WS5: Electrical Tests Storage WS6: Wire-Bond Encapsulation WS3: Metrology Storage WS7: Encapsulation Inspection Storage WS4: Wire Bonding WS8: Electrical Tests Storage WS9: Storage of Completed Ladders Assembly in G&A Engineering (251 flight ladder produced) Assembly in Mipot staring up (PRR in April) 6C Tracker Peer Review, WBS 4.1.4 2 GLAST LAT Project March 24, 2003 SSD edge bonding Ladder assembly tool alignment errors 100 90 Manual fast AND precise method 24 ladder assembly tools used in parallel Very good ladder alignment obtained 6C m 80 70 60 50 40 30 20 10 0 -20 -15 Tracker Peer Review, WBS 4.1.4 -10 -5 0 5 10 15 m 3 20 GLAST LAT Project March 24, 2003 Encapsulation Dam & Fill encapsulation Dam Nusil 1142 Fill Nusil 15-2500 Requirements: 1. Height <0.5mm 2. Lateral overflow <0.05mm 3. Coverage of all the bondings and pads Fast system to check encapsulation height 6C Tracker Peer Review, WBS 4.1.4 4 GLAST LAT Project March 24, 2003 Ladder electrical test: methods 2 PA200 probe stations with modified chucks to accept ladders are in activity (G&A and Mipot) Tests: IV curve (ladder leakage current from 0V to 200V) CV curve (ladder total capacity and depletion voltage) Single channel AC test: 100 V voltage step to measure AC insulation and AC capacity t>to IV,CV test scheme t<to Connected strips Interrupted strips AC strips test scheme I(5t)>10nA AC short 6C Tracker Peer Review, WBS 4.1.4 5 GLAST LAT Project March 24, 2003 Electrical Tests: Results 2000 1800 Leakge current history Expected Post-encaps. 1600 current (nA) 1400 1200 1000 800 600 400 200 Depletion voltage 0 1142 ladder ID 1163 1183 1203 1224 1244 1266 70 ladder dep. V expected from SSD 60 50 The causes of problems 3 and 4 have been corrected, foreseen rejection rate ∼1% 6C 40 30 20 10 90 80 70 60 50 40 30 0 20 Electrical test results: 1. Ladder tested 251 2. Accepted 243 (97%) 3. Broken edge 4 4. Probe accident 1 5. Not understood 3 Depletion voltage (V) Bad channels caused by bonding (coupling shorts)=0.016% (accepted limit 1%) No broken or bad bondings Tracker Peer Review, WBS 4.1.4 6 150 1121 140 1101 130 1076 120 1054 110 1034 100 1014 GLAST LAT Project March 24, 2003 Database A Access database system installed in the two assembly centers, collects all the relevant data of the ladders: •SSDs alignment •IV curve •CV curve •Bad channels (AC insulation test) •Not bonded channels The database allows a fast and accurate monitoring of the ladder production. This database adds to the traveler systems installed in the assembly company (ISO9001) which ensure the whole traceability of materials, instruments, procedures. 6C Tracker Peer Review, WBS 4.1.4 7 GLAST LAT Project March 24, 2003 Conclusions • The ladder construction successfully started (9% of the ladders have been produced with a 97% yield, possible increase of the yield to 99%). • Electrical and dimensional ladders characteristics well within specifications • Production rate > 10 ladders/day in both assembly centers that will work in parallel (G&A Engineering and Mipot), so there are no schedule problems with this item 6C Tracker Peer Review, WBS 4.1.4 8