GLAST LAT Project Test Beam Meeting, Apr 18, 2006 Beam Test Hardware Delivery Status Eduardo do Couto e Silva February 18, 2006 E. do Couto e Silva 1/2 GLAST LAT Project Test Beam Meeting, Apr 18, 2006 High Level Schedule for Hardware • • • • • • • • • Review of Flight Hardware Handling Plan – April 14 Arrival of Ancillary Detector from Bari – April 27 Arrival from CU Hardware from SLAC – May 2 Start of CU System tests – May 15 Workshop 2 in Pisa – May 15-18 CU and Ancillary Systems Test – June 19 Workshop 3 in Pisa – mid June? Arrival of Hardware at CERN – July 24 PS Beam Test Starts – July 27 E. do Couto e Silva 2/2 GLAST LAT Project Test Beam Meeting, Apr 18, 2006 Update on Reviews • Flight Hardware Handling Plan – Recommendations from Review on Friday (April 14, 2006) – verify that 1x4 grid has been load tested with dummy loads before we proceed with hardware integration » including rotations and additional loads due to transportation) – avoid usage of water as coolant – provide control and monitor temperatures and relative humidity » avoid condensation – using dray air bottles instead of Nitrogen for transportation from Pisa to CERN. – Have one general Healthy & Safety responsible for all operations. – Ship the assembled unit back to SLAC instead of separate items. – Outcome – Praise to Italian Collaborators (Luca et al) for preparing the review – We were authorized to ship flight hardware spares to Italy – Upcoming Reviews by the end of the month – MGSE – CU procedure for integration (LAT-PS-8132) E. do Couto e Silva 3/2 GLAST LAT Project Test Beam Meeting, Apr 18, 2006 Hardware Delivery from SLAC • Monday April 17, 2006 – TKRFM8 – ACD FREE card + 2 ACD Tiles – Breakout Boxes – the polarity is not standard in one of them. Jeff Tice will send details to Italy • Tuesday April 18, 2006 – CAL FM101, CAL FM109 • Upcoming deliveries by May 10 (hopefully) – ACD cables (@ SLAC) – already tested at SLAC, will be sent by FedEx – Remaining 3 ACD tiles (@ SLAC) – to be removed from the QualUnit after agreement with I&T – Two 28 V power supply with remote control – sent to company to be converted to 240 V and recalibrated – EGSE for data taking – need feedback ASAP so that we can start procurement – see next slides • Anything else missing? E. do Couto e Silva 4/2 GLAST LAT Project Test Beam Meeting, Apr 18, 2006 CAL Comprehensive Performance Tests @ SLAC • Eduardo asked Luca, Johan and David to look at the data in detail – 10 min muon run had wrong thresholds – but FLE trigger works E. do Couto e Silva 5/2 GLAST LAT Project Test Beam Meeting, Apr 18, 2006 EGSE Description (from Ric) May change after feedback from CERN (via Pasquale) • CISCO switch and shelves – standard 19 inch rack • 3 computers • 2 Dell 1850 with a KVM switch • Uninterrupted Power Supplies – back-up and filtering • Need feedback to start procurement !!! – CERN requirements on – firewall, switches, IP addresses » current baseline NO firewall – Pasquale is in contact with CERN – UPS requirements • filtering and power back-up – Gary is investigating that at SLAC – Control Room Requirements • Cable lengths, space in the control room, space in rack , are shelves needed? – Who? E. do Couto e Silva 6/2 Diagram from Luca Latronico PWR1 28V PS Gary is looking into grounding issues and will consult with Mike Huffer TEM TEM XXX VL BBB MC RRR EB DDD TEM GASU TPS GRID CHO TKR Therm CAL ISC TPS TPS GND INS XY table INS XY table motor PWR2 PWR3 LEGEND PWR – Multiple power plug INS - Electrical insulating layer CHO-Therm – electrical insulator, thermal conductive for heat dissipation Control/Signal connection Page Number Power connection (including ground) Direct electrical connection (ground) VME2 Ancillary Systems