I Councillor Derek Antrobus, Lead Member for Planning, in exercise of the powers conferred on me by Paragraph H 8a7 (Engineering Service), of the Scheme of
Delegation of the Council do hereby approve the implementation of the A580
Maintenance Scheme at a target cost of £460,497.20
The Reason is to improve road safety, carriageway condition and in addition improve street lighting to current standards along this highway.
Assessment of Risk : Medium
The source of funding is Department for Transport Exceptional Maintenance Grant
Legal Advice obtained Yes Richard Lester 0161 793 3084
Financial Advice obtained Yes 20 th December 2010 Peter Butterworth 0161 793
2319
The following documents have been used to assist the decision process.
Report submitted to Planning Lead member Briefing held on 18 th January, 2011
Contact Officer: Steve Mangan Tel No 0161 603 4034
* This decision is not subject to consideration by another Lead
Member/Director
* The appropriate Scrutiny Committee to call-in the decision is the
Sustainable Regeneration Scrutiny Committee.
Signed: Councillor Derek Antrobus
Lead Member for Planning
Date : 18 th January, 2011
* This decision was published on 18 th January, 2011.
* This decision will come in force on 26 th January, 2011unless it is called-in in accordance with the Decision Making Process Rules.