Part 1 (OPEN TO THE PUBLIC) ITEM NO. ___________________________________________________________________ REPORT OF STRATEGIC DIRECTOR FOR CHILDREN’S SERVICES ___________________________________________________________________ TO THE LEAD MEMBER FOR CHILDREN’S SERVICES AND LEAD MEMBER FOR CUSTOMER AND SUPPORT SERVICES ON 9 May 2011 ___________________________________________________________________ TITLE: CHILDRENS SERVICES CAPITAL PROGRAMME UPDATE 2011/12 ___________________________________________________________________ RECOMMENDATION: That approval is given to: Implement the proposed schemes at 4.1 and 8.1 of this report Obtain tenders/agree target costs in accordance with the City Council’s partnering framework, or procure via North West Construction Hub in accordance with separate city council decisions regards alternative procurement arrangements; within the total available funding for the schemes identified at 4.1.7 of this report £50,000 available from the 2010/11 programme be allocated to perform surveys to update the Asset Management Plan (AMP) condition data as the first year of a continuous programme as detailed at 1.10 of this report ___________________________________________________________________ EXECUTIVE SUMMARY: In December 2010 the Department for Education (DfE) provided details of Salford schools capital allocations for 2011-12 for capital maintenance (previously NDS modernisation) and basic need. The purpose of this report is to update members on the proposed use of this funding from that approved by Council on 2 March 2011.Consideration has now been given to the priorities for this capital investment which are detailed in this report. ___________________________________________________________________ BACKGROUND DOCUMENTS: (Available for public inspection) Lead member report on 3 October 2008 Budget report to Council on 2 March 2011 ___________________________________________________________________ KEY DECISION: D:\219513485.doc YES 1 ___________________________________________________________________ KEY COUNCIL POLICIES: ___________________________________________________________________ EQUALITY IMPACT ASSESSMENT AND IMPLICATIONS - All works and services provided under the capital programme will be undertaken in accordance with relevant DDA legislation and guidance. ___________________________________________________________________ ASSESSMENT OF RISK: High ___________________________________________________________________ SOURCE OF FUNDING: Capital grant provided by the DfE through their capital maintenance and basic need funds for 2011/12 ___________________________________________________________________ LEGAL IMPLICATIONS : None ___________________________________________________________________ FINANCIAL IMPLICATIONS : Developed with Customer and Support Services and information provided by Pat Manning - Education Capital Accountant ___________________________________________________________________ OTHER DIRECTORATES CONSULTED: None ___________________________________________________________________ CONTACT OFFICER: Sue Wilkinson TEL. NO. 0161 778 0228 ___________________________________________________________________ WARD(S) TO WHICH REPORT RELATE(S): All ___________________________________________________________________ DETAILS: CAPITAL MAINTENANCE 1. Background 1.1 In October 2008 Lead Member approved a 3 year programme of works for all community and voluntary controlled primary schools, funded by 50% of the New Deal for Schools (NDS) modernisation funding allocations for 2008/9,2009/10 and 2010/11,with the remaining 50% being allocated as a contribution to the Primary Capital Programme (PCP) (as approved by Cabinet on 27 May 2008). 1.2 The programme of works related to the backlog of maintenance identified from the Asset Management Plan (AMP) and priority was given to those projects which exceeded £1,000 per pupil. Any projects which fell below this figure D:\219513485.doc 2 were excluded from the prioritisation for NDS modernisation funds and referred to individual schools to be funded from their Devolved Formula Capital (DFC) allocations. 1.3 A total of 17 NDS projects were undertaken between 2008-2011 (see details below). All 17 projects involved works to the 4 key areas of the school building, which are roofs, walls windows and doors, electrical and mechanical services. These areas were selected as they could present the highest health and safety risk, potentially resulting in school closure:Barton Moss Cadishead Primary Charlestown Lewis Street Lower Kersal Peel Hall St Luke's CE St Luke's CE Summerville Wardley CE Wardley CE Beech Street Clarendon Road Westwood Park Alder Brook Brentnall Emergency Lighting Roofing Repairs Fire alarm, intruder alarm, emergency lighting Partial Re-roofing Replacement Windows & Roof repairs Mechanical Works Electrical Repairs Roofing Repairs Boiler Plant Fire Alarm, Emergency Lighting Structural Stabilisation Roofing Repairs Boiler Plant Re-roofing External Works Roof repairs 34,853 422,311 22,973 19,148 127,677 4,205 14,340 95,631 91,189 54,702 34,687 128,609 94,239 292,704 22,183 10,000 1.4 The Tootal Drive and North Grecian Street schemes, which were included in the original programme, were removed due to their closure. A further 4 schemes at Wharton, Peel Hall, St Pauls Neville Road and Grosvenor Road were deferred as it was considered that they were less urgent and could be undertaken beyond the 2008-2011 programme. All but one of these schemes is included in the 2011/12 capital maintenance programme. 1.5 In addition to the 17 planned projects, works were undertaken at 8 schools which were not originally included as part of the NDS programme. These works were unforeseen identified urgent health and safety issues:Marlborough Road emergency health and safety works identified during schools last Ofsted inspection £269,273 St Georges CE Clarendon Road emergency electrical works asbestos removal and electrical works electrical works roofing works electrical works hall roof internal and external structural works £25,805 £285,877 Lewis Street St Johns CE Lower Kersal St Luke’s CE St. Andrews Eccles CE 1.6 £34,133 £237,885 £268,519 £34,129 £195,064 All except two of these schemes are now complete, and subject to receipt of final accounts, there will be approx £50,000 of unallocated funding. D:\219513485.doc 3 1.7 The evidence of inaccurate AMP condition data is clear from the eight unforeseen schemes identified at 1.5, five of which were large schemes. 1.8 AMP condition updates have not been undertaken on a planned basis since 1998. Rather updates have been executed on an ad-hoc basis to suit the needs of e.g. BSF, or the Primary Capital Programme. However this has resulted in the AMP data becoming increasingly out of date in some areas. 1.9 It is proposed to undertake a rolling programme of condition surveys to address the age of the data, and to ensure that into the future the data is kept up to date. The Government requirements for the content held within the AMP, and methodology for collecting data, has changed and is far less stringent than previous guidance. However, indications from the DfE are that this position will change soon and we will need to be in a position to respond to their request for information. It is therefore proposed that the rolling programme of updates be undertaken for the 4 key areas, commencing in May 2011. 1.10 It is proposed that the £50,000 unallocated funding is used to employ the services of surveyors via Urban Vision to update AMP condition in 50 % of all community and voluntary controlled primary schools between May and September 2011.This programme of work will be agreed in detail at the earliest opportunity. 1.11 Voluntary aided primary schools are responsible for updating their own AMP condition data. We will be requesting this information to include in the complete AMP data set for the whole primary school estate, in advance of the known intentions of the DfE to request this updated information. 2. Capital Maintenance Grant Allocation 2011 and beyond. 2.1 In December 2010 the DfE provided details of Salford school’s capital grant allocations for 2011/12. Salford has received £2,513,478 capital maintenance funding (previously NDS modernisation) for all community and voluntary controlled primary schools. This is higher than the average of the previous 3 years allocation which was £2,001,368 per annum. 2.2 The government have indicated that capital allocations for each year to 2014/15 are expected to stay in line with the total amounts allocated for 2011/12, as stated in the DfE’s letter to all authorities dated 13th December 2010. 2.3 The capital maintenance grant is not time limited and can be carried forward to future financial years. 3. Devolved Formula Capital (DFC) 3.1 In previous years schools included in capital building programmes have agreed to contribute their DFC towards their scheme. 3.2 Those schools included in this years capital maintenance programme will be D:\219513485.doc 4 asked to contribute approx 10% of their DFC towards their scheme. However for some schools this may not be possible due to schools having an insufficient DFC balance due to their DFC allocations being reduced significantly for 2011/12, by 80%, compared to previous years. The 2010/11 DFC allocation was £2,839,913 compared with the 2011/12 allocation of £548,936. 4. Proposed use of Capital Maintenance Grant Allocation 2011/12 4.1 Details of previous commitments, proposals and detailed explanations and rationale are provided for the allocation as follows:- 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 Capital Maintenance Grant Committed schemes Contribution to PCP(River View primary school) Extra contribution to River View Proposed Schemes Schools Access SEN Children’s Centre Maintenance Children’s Homes Maintenance Contribution to Classroom Extensions at St Andrews Boothstown Primary School Capital Maintenance Programme Unallocated Balance 2,513,478 794,918 23,427 50,000 85,314 45,000 37,000 1,247,467 230,352 4.1.1 The contribution of £794,918 NDS modernisation funding (now capital maintenance grant) for River View Primary School (PCP scheme) was previously approved by Cabinet on 27th May 2008. 4.1.2 The extra contribution of £23,427 for River View Primary School is to replace part of the DFC contributions from the two closing schools as their DFC funding has been reduced. 4.1.3/ There is no other available funding for Schools Access and SEN Children’s 4.1.5 Homes Maintenance, therefore a contingency of £95,000 has been provided from the capital maintenance grant for these items. 4.1.4 The capital maintenance grant allocation for 2011/12 includes funding for the maintenance of Sure Start Children’s Centres as indicated in the DfE’s letter to all authorities dated 13th December 2010, therefore £45,000 has been allocated for this purpose as a contingency. 4.1.6 St. Andrew’s Boothstown have vacated their old school building due to its D:\219513485.doc 5 poor condition and health & safety issues. The school propose to create two classrooms in the main school building to accommodate the pupils displaced from the old school building and have requested a contribution of £37,000 towards the £187,000 scheme. The school will fund the remaining £150,000 from their revenue budget and DFC balance. This project will be the subject of a separate Lead Member report. 4.1.7 The unallocated balance of £230,352 is a contingency amount for the capital maintenance programme, given that we have experienced unforeseen projects in previous years. The unallocated balance will be used for reserve capital maintenance projects in the event that this remains available. 5. Programme of Capital Maintenance works 2011/12 Prioritisation 5.1 Details of the £1,247,467 capital maintenance programme, priority works and estimated costs (provided by Urban Vision) for 2011/2012 are detailed below. If the target costs for the schemes are less than is currently estimated any surplus funding will then be allocated to the 2 reserve list schemes which have been identified. The 2 reserve schemes are roofing works at Wardley CE primary school at an estimated cost of £184,696 and WWD at Wharton primary school at an estimated cost of £14,677. Element Roofs School Lower Kersal Roofs Peel Hall Roofs Roofs Cadishead Primary Nursery Building Wharton WWD North Walkden WWD Marlborough Road D:\219513485.doc Cost £126,031 £82,655 £155,000 £70,000 £65,385 £145,685 Justification This roof has bee in poor condition for a number of years. Minimum repairs only were instructed and executed as part of 2008/11 NDS programme. The roof remains poor overall. Minimum repairs were instructed in 2008 as it was then proposed to close the school as part of PCP rationalisation. Those repairs were executed as part of the 2008/11 NDS programme. The school still have an issue with roof leaks so it is recommended to include this in the 2011/12 programme. Not identified on AMP as last roof survey was 1998, however dry rot has been discovered in the roof timbers causing part of the school to have to be closed for H&S reasons. Not identified on AMP as last roof survey was 1998, however dry rot has been discovered in the roof timbers causing part of the school to have to be closed for H&S reasons. City Council removed this from the NDS programme in 2008 due to low cost. 2008/11 report indicated school to undertake work via DFC. A later H&S visit indicated there were H&S issues so the work was added back to the NDS programme 2010/11. However, higher priority electrical works displaced this. Some of the work has been undertaken by the school. City Council removed this from NDS programme in 2008 due to low cost work via DFC. An Urban Vision surveyor visited the school during w/c 4th April 2011. The main front elevation of the old Victorian school building is 6 WWD Lower Kersal £49,868 Electrical St. Paul’s Peel £84,250 Electrical Moorfield Grosvenor Rd. £106,343 £287,500 Mechanical St. Luke’s CE Elements Total Mechanical the highest priority and is recommended to be included in the 2011/12 programme. Much of the reminder are poor with perhaps only a 1-2 year lifespan. It would be prudent to inspect these annually. City Council instructed only emergency repairs to be executed as part of 2008/11 NDS programme as the school was proposed to have major refurb as part of PCP. This never happened . Repairs/replacements have been executed to the major problem areas in the quad where full height screens were unsafe. An Urban Vision surveyor visited this school during w/c 4th April 2011. One elevation requires windows replacing, the remainder have 2-3 year lifespan but it would be prudent to inspect them annually. Works to address improvements to the infilled external walkways, whilst desirable and form the bulk of the £318,022 identified in the AMP are not considered essential or appropriated from the 2011/12 capital maintenance programme. A review of all schools electrical installation were undertaken by the Electrical Surveying team, outside the AMP. This was undertaken separately due to the way the AMP captures and presents electrical work, which does not always represent a good reflection of cost. A 3 year NDS programme of the main priorities was produced in 2010 and was used to inform the final year of the 2008/11 NDS programme. The two schools represent the next outstanding priorities from that review. The two projects prioritised are the two most important. These are both boiler replacement schemes, involving conversion from oil to gas. . £74,750 £1,247,467 5.2 As in previous years the capital maintenance programme has been drawn up using the 4 key areas as detailed previously at 1.3 of this report. 5.3 Condition data for the 4 key elements has not been updated for a number of years. Whereas the Mechanical and Electrical elements were resurveyed in 2007 (now approaching 4 years ago) the roofs and external walls windows and doors (WWD) were not updated then as this was not required for the purposes of the Primary Capital Programme strategy. The WWD and roof elements data date back, in some cases, as far as 1998. 5.4 Due to the age, and consequently limited reliability of the data, further informal analysis site visits by surveyors have been undertaken to inform the prioritisation process as follows: Roofs and WWD D:\219513485.doc Reports have been produced from the AMP identifying the priority 1 7 and 2 requirements Other priorities that both Children’s Services and Urban Vision have become aware of, though not captured on the AMP, have been added The 2008/11 final programme of priorities indicated that numerous items would be undertaken from schools DFC rather than via NDS funds. Urban Vision surveyors have visited those premises to check the current requirements The 2008/11 NDS programme indicated that some items would be excluded due to proposed school closures/major refurbishment included within the Primary Capital Programme strategy. Urban Vision surveyors have visited those premises to check the current requirements All the above has been brought together and rationalised to produce the 2011/12 prioritised programme of works detailed at 5.1 of this report Electrical Although updated in 2007 the electrical element data is now 4 years old. A separate analysis of electrical needs was undertaken to inform the final year of the 2008/11 NDS programme, resulting in the top two priorities – Clarendon and Lower Kersal Primary Schools rewires – being undertaken. This analysis has been reviewed and the next two priorities have been recommended for inclusion in the 2011/12 prioritised programme of works detailed at 5.1 of this report. Mechanical 5..5 The identified priorities in 2008/11 could not all be funded from that programme. Reports have been produced from the asset management plan (amp) identifying the priority 1 and 2 requirements The two schools having the greatest need – Grosvenor Road and St Luke’s CE primary schools – both of which require new boilers and conversion from oil to gas, have been recommended for inclusion in the 2011/12 prioritised programme of works detailed at 5.1 of this report. This process of identification is not the most satisfactory and will be reviewed for the 2012/13 capital programme onwards using the more reliable data obtained from the surveying work to be undertaken between May 2011 and September 2011 as detailed previously at 1.9 of this report. BASIC NEED 6. Background 6.1 For the period 2008/11, Salford’s allocation for Basic Need was £678k per D:\219513485.doc 8 annum, which was allocated to support the Primary Capital Programme, as approved by Cabinet in May 2008. 7. Basic Need Grant Allocation 2011 and Beyond 7.1 Basic need funding is for the provision of new pupil places. There are significant pressures for additional school places particularly at primary age, in many areas of the country because of the rising birth rates and changed migration patterns. 7.2 Salford have identified such pressure on reception class places for September 2011,with increasing pressure across all primary year groups in future years .Recently the DfE undertook a survey on basic need within each Authority, to identify the extent of issues local authorities are facing regarding shortage of primary pupil places. Salford’s return to the DfE identified that we require an estimated £15 million to provide an adequate number of primary pupil places by September 2015. 7.3 In acknowledgement of the pressure on school places, in the December 2010 announcement, Salford’s allocation for 2011/12 has increased significantly to £3.2m. 7.4 The Basic Need allocation has to be used for all categories of taxpayer funded schools including Voluntary Aided as well as community and controlled schools. The Local Authority have the responsibility for ensuring sufficient school places in Salford and when planning for growth in pupil numbers we have to consider all sector in prioritising this funding. As with the Capital Maintenance Grant, the government have indicated that future capital allocations until 2014/15 are expected to stay in line with the total amounts allocated in 2011/12, subject to the outcome of the capital review. 7.5 The Basic Need grant is not time limited and can be carried forward to future financial years. D:\219513485.doc 9 8. Proposed use of Allocation 2011/12 8.1 Details of previous commitments, proposals and detailed explanations and rationale are provided for the allocation as follows: 8.1.4 Basic Need Allocation Committed schemes River View School (PCP) Extra Contribution to River View New Eccles Primary School Proposed Schemes Lark Hill CP Phase 2 Works 8.1.5 Unallocated balance 8.1.1 The contribution of £678,030 basic need funding for River View Primary School (PCP Scheme) was previously approved by Cabinet on 27 th May 2008. 8.1.2 The extra contribution of £23,427 for River View Primary is to replace part of the DFC contribution from the closing schools as their DFC funding has been reduced. 8.1.3 The £308,164 allocated to the new Eccles Primary School (PCP Scheme) is to replace the extended schools grant of £191,058 Schools Access funding of £117,106, both of which have been cut. 8.1.4 The £441,025 for Lark Hill phase 2 works were approved by Lead Member for Children’s Services on 7th April 2011 and Lead Member for Customer Support Services on 14th April 2011. 8.1.5 Some of the unallocated balance of £1,750.008 will be used to facilitate the prioritisation of an additional 345 reception class places required across the primary school estate for September 2011. We have approached those primary schools with surplus capacity to accommodate the additional reception class pupils with little or no capital investment. However, it is likely that one temporary classroom will be requested to augment the existing accommodation across the primary school estate at an approx cost of £40,000 in 2010/11 and then £10,000 per annum hire costs thereafter. 8.1.6 The holding position for September 2011 will provide us with time to undertake a strategic review of pupil places . This will enable us to utilise the unallocated Basic Need funding more strategically for the required provision of pupil places from September 2012 onwards. 8.1.1 8.1.2 8.1.3 D:\219513485.doc 3,200,654 678,030 23,427 308,164 441,025 1,750,008 10 9. Recommendations D:\219513485.doc Implement the proposed schemes at 4.1 and 8.1 of this report Obtain tenders/agree target costs in accordance with the City Council’s partnering framework, or procure via North West Construction Hub in accordance with separate city council decisions regards alternative procurement arrangements; within the total available funding for the schemes identified at 4.1.7 of this report £50,000 available from the 2010/11 programme be allocated to perform surveys to update the Asset Management Plan (AMP) condition data as the first year of a continuous programme as detailed at 1.10 of this report 11