Report of the Head of Regeneration and Improvement and Director... Services to Strategy and Regeneration Scrutiny Committee on the Progress...

advertisement
Report of the Head of Regeneration and Improvement and Director of Housing and Planning
Services to Strategy and Regeneration Scrutiny Committee on the Progress on Regeneration
Programmes and Projects – Monday 8th May 2006
Purpose of Report
To inform and up date Strategy and Regeneration Scrutiny Committee on progress and issues
surrounding key regeneration funding programmes and projects.
Detail
This report is formatted according to Community Committee Areas. It includes projects underway in
community committee areas and the following funding programme’s which facilitate many of the
developments:
Secured -
NDC
SRB5
HMRF
Neighbourhood Renewal Fund
Objective 2 Priority 1 ‘Business and Ideas’
Objective 2 Priority 2 ‘Improving People and Communities’
Objective 2 Priority 2 ‘Manchester Salford Sustaining Neighbourhoods’
Objective 2 Priority 3 ‘Irwell Corridor Economic Development Zone’
Knowledge Capital
Transforming Your Space (NOF)
SHIFT
LIFT
Central Salford URC
Salford Construction Partnership
Summary of Key Issues

Key developments that have occurred over the past six weeks within the
following areas:
Pledge
All
Area
Seedley &
Langworthy
All
Charlestown &
Lower Kersal
Higher
Broughton
Enhancing
Life
Enhancing
Life
Enhancing
Life
Enhancing
Life
Higher
Broughton –
Community
Hub
Lower
Broughton
Magistrates
Court and
Key Developments
Previews of Urban Splash properties will be shown 01/04/06.
A sales tent will be pitched in Chimney Pot Park on w/c
03/04/06 ready for properties going on sale 08/04/06.
Sports Village launch planned 12th March 2006
Final consultation event now carried out and the results
indicate agreement from most residents of the design and
construction of the first phase of new ‘homeswap’ houses
planned for Vincent Street. The scheme has since gone out
to tender and work started on site in February 2006.
Objections to the CPO for the Top Street area have now
been received from GONW and evidence is being collated to
determine the council’s case at the forthcoming Public
Inquiry.
14th February 2006 Cabinet considered first stage of the
Higher Broughton Community Hub.
Site investigations to start during February 2006.
Rehousing of the last remaining household on Kempster
Street has been completed.
14th February – Cabinet approved location of proposed new
Magistrates & County Court at John William Street, Eccles
1
Justice Centre
Initiative
Barton
Strategic Site
(approx half current car park).
Salford
Innovation
Park
Greengate
Started on site 20th February.
Interim project manager appointed from Capita Symonds.
Enhancing
Life
/Creating
prosperity
Springfield
Lane
A detailed application for the first phase is expected by June
2006 with a start on site in January 2007. Discussions are
taking place with Contour and Irwell Valley Housing
Associations regarding an element of shared ownership
within the first phase.
Creating
prosperity in
Salford/
Enhancing
life in
Salford
TESCO Shopping City
Meeting with Tesco and Shopping City owners on 8th March
where plans for new proposal are expected to be presented.
Pledge
All
Area
Seedley &
Langworthy
Key Developments
Urban Splash held a pre launch to the local community at the
end of March 2006. 10 properties were sold.
Properties went on general public sale on 8th April 2006 and
all phase 1 has now been sold.
All
Charlestown &
Lower Kersal
All
URC
Sports Village was launched on 12th March 2006
An Oscar event for community members involved in New
Deal was held 31st March.
The URC Board have agreed the Central Salford Vision.
Enhancing
Life
Higher
Broughton
Creating
Prosperity
Creating
Prosperity
Enhancing
Life
/Creating
prosperity
Salford Reds:
GONW reached decision to call application in and subject to
public enquiry – date to be determined.
Approval granted for further detailed design work to be
commissioned from Urban Vision/Feilden Clegg Bradley to
take public realm areas to submission of planning application
stage.
The first 19 ‘new for old’ Homeswap houses are now under
construction and are expected to be completed by August
2006. The initial allocation of these units has now also been
carried out.
The Rule 7 statement has been submitted to the GONW for
the Top Streets CPO Area and a formal review of the
Council’s case will take place before the Public Inquiry which
is expected to be held in October 2006.
Cabinet agreed to the creation of Broughton Renewal Area
on 25/04/06, to be effective for 4th May 2006.
An outline Planning Application for the Magistrates Court and
the Justice Centre is due on the 19th May.
Enhancing
Life
Eccles
Enhancing
Life
Ordsall
Signing of Development Agreement with LPC is expected in
early May 2006.
Construction of new primary school and Children’s Centre
has started.
Enhancing
Greengate
Network Rail/ AS joint venture now signed.
2
Life
/Creating
prosperity
Creating
prosperity in
Salford/
Enhancing
life in
Salford
TESCO Shopping City
Detailed discussion has commenced with Robert Gubbay in
relation to the land and financial transactions associated with
the sale of the Pendleton way car parks
The relocation church site has been assembled without a
contested CPO as all interests were acquired beforehand.
Single Regeneration Budget Round Five
The end of scheme evaluation draft report is due in May 2006, the final report anticipated end June
2006.
Safer Stronger Communities Fund
Currently completing agreement with GONW to release funding of £1.38 million.
Funding will be targeted at three most deprived Super Output Areas in both Winton and Little Hulton.
Delivery plans for projects in each area are currently being drawn up.
3
Claremont and Weaste
Areas covered within this report:
Claremont Village
Weaste Renewal Area



Work on the alleygating schemes in Weaste, whilst ongoing, has been delayed
due to an adverse Public Enquiry decision.
Footpath refurbishment is now complete in New Cross Street and Barff Road
following the completion of Block Improvements.
There are a number of environmental schemes nearing completion in the Weaste
area. These are being completed with a combination of HMRF and ERDF
funding allocated to year 2005/2006.
Eccles New Road Renewal Area
 The Weaste Seedley Claremont Area Action Plan is now being progressed by
Mike Arnold in the Planning Department.
 The Lead Member for Housing authorised a clearance area for 35 properties in
the Eccles New Road Area (Nelson Street). There have been two objections to
this order. Proof of Evidence is now being prepared for the Public Enquiry.
4
CLAREMONT VILLAGE
Project: Weaste Renewal Area
Pledge: Enhancing Life
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
Claremont Village
Kevin Scarlett, Housing Services
925 1023
To provide a strategic framework for the physical, social and economic
renewal of neighbourhood; securing its long-term sustainability by
making the areas more attractive and safer places to live, more
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
 There are a number of environmental schemes nearing completion
in the Weaste area . These are being completed with a
combination of HMRF and ERDF funding.
 Work on the alleygating schemes in Weaste, whilst ongoing, has
been delayed due to an adverse Public Enquiry decision. Gates
are being fitted with the intention of using new legislation to
introduce temporary gating orders on the affected alleyways as
soon as possible.
 Footpath refurbishment is now complete in New Cross Street and
Barff Road following the completion of the Block Improvements.
Minor completion works remain in Glendore.
HIP and HMRF
ERDF
Priorities and Milestones

Complete environmental works.
Timescales
May 2006
Risks and barriers
 Uncertainty about the future of ‘The Willows’.
Communication
Opportunities
 Launch of early intervention projects on completion.
5
Project: Eccles New Road Renewal Area
Pledge : Enhancing life in Salford
Area Covered
Enterprise Park/Quays
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Kevin Scarlett, Housing Services
925 1023
To provide a strategic framework for the physical, social and economic
renewal of areas’ neighbourhood; securing its long-term sustainability
by making the areas more attractive and safer places to live, more
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
 The Weaste Seedley Claremont Area Action Plan is now being
progressed by Mike Arnold in the Planning Department.
 Lead Member for Housing authorised a clearance area for 35
properties in the Eccles New Road Area (Nelson Street). There
have been two objections to this order. Proof of Evidence is now
being prepared for the Public Enquiry.
 The Lead Member for Housing has now declared a clearance area
with regards to 24 unsatisfactory properties within the Eccles new
Road Area (Bridson Street). There have been two objections to this
order. Proof of Evidence is now being prepared for the Public
Enquiry.
Progress to Date
Funding sources
HIP and HMRF
Priorities and Milestones:
 To acquire all 24 properties on Bridson St Phase 2
 To acquire all 35 properties on Nelson St
 Public CPO enquiry Bridson St
Nelson St
Timescales
Ongoing
Ongoing
16th/17th May 06
9th/10th May 06
Risks and barriers
 Difficulties in achieving equitable relocation for residents affected
by clearance.
 CPO not confirmed
 Uncertainty about the future of the Weaste Bus Depot and
adjoining streets.
 WSCAAP not supported by LM
Communication
Opportunities
 Launch of early intervention projects on completion.
 WSCAAP Community Forums
 Newsletter
6
East Salford
Areas covered within this report:
Broughton
Chapel Street
Charlestown & Lower Kersal
Claremont Village
Broughton
Higher Broughton – Homeswap to new build
 Work now started on site for the first 19 ‘New for Old’ Homeswap units on Vincent Street
expected to complete mid August 2006. The initial allocation of these houses has also
been made and kitchen/bathroom choices have been carried out by the relocating
residents.
 Details around the purchase agreement with the Higher Broughton Partnership being
finalised.
Higher Broughton – Investigation works to playing fields
 Remediation of the existing sports pitches is now complete.
 Work started on relocating the sports pitches to the new site. These are expected to be
completed in Autumn 2006 and ready for use in the following year.
Higher Broughton-Broughton Top Streets CPO area
 The Rule 7 statement to objections to the CPO was submitted to the GONW within the
deadline set (13.03.06).
 The Council has agreed to review the case for comprehensive clearance in time for the
Public Inquiry due in October.
 Planning applications subject to negotiation for both Top Streets and Bond Square sites.
Higher Broughton - Other Issues
 Cabinet agreed to the creation of Broughton Renewal Area on 25/04/06, to be effective
from 4th May 2006.
Higher Broughton – Community Hub
 First phase site investigations completed.
 Consultation exercise due to take place imminently. Flyer
leaflet currently being produced to update local community
on future activity.
Lower Broughton
 Demolition of Lowry High School is currently in progress..
 The first of two landscape improvement teams has recently
completed work to reduce overgrown and non maintained
areas.
 An Outline Planning Application was submitted on 6 March
2006.
 Demolition has commenced and progressed from 2 – 50
Kempster Street to numbers 1 – 61 Kempster Street.
 Moss Street CPO confirmed 13th April 2006.
7
Chapel Street
Charlestown and Lower Kersal
Adelphi Media Quarter

Terms now agreed between Salford University and Salford City Council
for Adelphi Street and Meadow Road and for Irwell Valley campus.

The transaction to be completed early June 2006.
NDC




Greengate
 Network Rail/ AS joint venture now signed.
 First phase of archaeological investigations at BSC site completed
February 2006.
Springfield Lane
 Urban Splash have purchased the derelict, former King William IV public
house, required for the comprehensive redevelopment.
Sports Village launched 12th March 2006.
Arrowhead housing due to complete May 2006.
Phase 5 of Littleton Road Improvements start imminent.
Oscar event for community members involved in New Deal held
March. Young People Oscars to be held June/July 06
Salford Innovation Park
 Started on site 20th February.
 Interim project manager appointed from Capita Symonds.
Claremont Village
Duchy and Pendlebury Renewal Area.
 April 2006 – Alleygating of Clearance Area completed.
 April 2006 – Legal action (possession order) obtained to vacate property on Duchy Bank site.
 April 2006 - Duchy Bank Developers Agreement – Agreed and ready to sign.
8
BROUGHTON
Project: Higher Broughton Regeneration Initiative – Homeswap to new build
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Higher Broughton Partnership area
Kevin Scarlett x 1023
Provide access to new properties in the redevelopment for owners
living in the clearance area.
 The road closure issue has now been resolved and work has
started on site, on Vincent Street.
 The initial allocation of the first 19 Homeswap houses has taken
place and choices around kitchen and bathroom choices have also
been made. The offsite manufacture of these units is now well
underway and they are expected to be delivered to site around the
end of May 2006.
 The planning application for Bond Square is still subject to
negotiation and it is expected that work will start on site in around
6-8 months.
 The new Relocation Assistance policy has now come into effect.
35 residents have made applications under the old policy.
 The planning application for the Top Streets area is also subject to
discussion with the council and progress is being made.
Higher Broughton - Community Hub
 First phase Site investigations completed.
 Consultation exercise due to take place imminently. Flyer leaflet
currently being produced to update local community on future
activity.
 Cabinet on 14th February to consider first stage of the Higher
Broughton Community Hub.
Funding sources
 Housing Market Renewal 2004/06 Programme.
Priorities and Milestones
Timescales
Ongoing

Completion of the work on the homeswap model.
August 06

Vincent Street complete
Sept - Nov 06

Bond Street on Site
Risks and barriers
 Residents frustration with the pace of progress
 Residents objecting to the change in relocation assistance policy
which will remove the entitlement to the relocation grant by March
2006.
 Residents being unhappy about not being allocated the first phase
of Homeswap properties on Vincent St.
Communication
 Future positive publicity will be required when a model is agreed.
Opportunities
9
Project: Higher Broughton Regeneration Initiative Site Investigation Works to Playing Fields
Northumberland Street
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Higher Broughton Partnership Area
Kevin Scarlett, Housing Services,
Tel; 925 1023
To establish ground conditions and soil analysis to determine the level
of improvement works required to deal with those conditions found as
part of the site investigation work before the house building process
can commence.
 Works have started on relocating the sports pitches to the new
site. These are expected to be completed in Autumn 2006 and
ready for use in the following summer.
 The remediation of the playing fields is now complete and all HMR
funds have now been paid to the Higher Broughton Partnership.
Funding sources
HMRF
Priorities and Milestones
 Completion of the ground remediation contract.
 Sports pitches ready to use
Timescales
Autumn 2006
Sumer 2007
Risks and barriers
 There have been complaints about noise, vibration and disruption
to neighbouring residents. These complaints have been reducing
since the majority of the heavy earthworks have been completed.
Communication
Opportunities
 The establishment of a communication plan to support the
feedback and work on site during and after the investigation is
complete. This information is being routed through the general
meetings of the Solutions Group.
10
Project: Higher Broughton – Broughton Green Development and Related issues
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Broughton
Kevin Scarlett, Housing Services
925 1023
Maintain and support existing communities whilst seeking opportunities
for new development through a range of interventions.
 There are now over 100 new build houses on site in Phase 1 of the
development. The first show house is expected to be ready in May
2006.
 The demolition of the remaining houses in the Bottom Streets area
(Rigby Street, Wellington Street East and Bradshaw Street) is now
underway. All other vacant property has now been demolished.
 Temporary alley-gating of the Top Streets area is now underway
and multi-lingual leaflets on disposal of refuse are being delivered
to all occupied households.
 The Solutions Group continues to meet on a monthly basis to
provide a forum for consultation and discussion for all aspects of
the redevelopment.
 Works to enhance the council estate around the redevelopment
area are still in the process of development.
 The Rule 7 statement to the objections to the CPO has now been
submitted to the GONW within the deadline set (13/03/06).
 The Council have agreed to review the case for comprehensive
clearance in time for the Public Inquiry which is due to be held in
mid-October.
 Planning applications are currently subject to negotiation for both
the Top Streets and Bond Square sites.
 The council continue to acquire property from owners by voluntary
agreement in advance of the CPO.
 A small number of residents have decided to use Relocation
Assistance to move to housing for sale in Central Salford and are
expected to move over the next few months.
Proposed Broughton Renewal Area:
 Cabinet agreed to creation of Broughton Renewal Area on
25/04/06, to be effective from 4th May 2006.
 Statutory Consultation. An overwhelming majority of respondents to
the consultation were in favour of the declaration.
 Declaration report presented to lead member on 16/04/06.
 The proposed Renewal Area is bounded by Camp St to the South,
the River Irwell to the West, Bury New Road to the East and the
Kersal border to the North.
Funding sources
B.C.A. Housing Investment Programme.
Housing Market Renewal Fund 2005/06 Programme.
Priorities and Milestones
Timescales
July 2006

Demolition of empty houses on Bottom St completed
Mid Oct 06

Public Enquiry
Risks and barriers
Much of the negative press coverage connected with the CPO activity
on the Bottom Streets has now passed. It is important to ensure
that Top Streets CPO opposition is reduced to the minimum by
developing rehousing solutions that are acceptable to the
community.
Communication
 New for Old Homeswap provides a good news story at the point
Opportunities
that residents are able to move from the CPO area in Top Streets.
11
Project: Lower Broughton Regeneration
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
Broughton
R G Wynne, Development Services
793 3750
Regeneration of large area (150 acres) of public and private
residential and commercial / mixed use property.
 Demolition of Lowry High School is currently in progress.
The first of two landscape improvement teams has recently
completed work to reduce overgrown and non maintained areas.
 Demolition has commenced and progressed from 2 – 50
Kempster Street to numbers 1 – 61 Kempster Street
 Two workshops were convened on 13th February and 13 March
2006. Home visits are still being undertaken to engage with
residents affected by the first phase of the redevelopment on a 12-1 basis these visits are expected to be completed by the end of
April 2006.
 A Drop-In session has been arranged between 2 – 4p.m. every
Wednesday at the Humphrey Booth Day Centre on Heath Avenue
in Lower Broughton. Residents and stakeholders have been sent
invitations to come along to discuss with staff from the Housing
Market Renewal Team and Contour Housing any issues or
queries they may have regarding the regeneration proposals for
the area.
 The next issue of the Lower Broughton Newsletter is currently
being compiled and will include a section on Frequently Asked
Questions and Answers.
 Moss Street CPO confirmed 13th April 2006.
 Work on establishing flood depths in various scenarios has been
established and is being discussed between SCC, EA & CPPLC
HMRF
Private
Priorities and Milestones
Timescales
On-going

Quarterly public meetings
Autumn 2006

First phase developments expected.
Risks and barriers
 Poor public reaction.
 Difficulty in acquisition of properties.
 Flooding.
Communication
 Press briefing once consultation mechanism agreed.
Opportunities
 Local newsletter established.
 Future briefing opportunities as plans and developments come
available and consultation events take place.
12
Project: Adelphi Media Quarter
Pledge: Encouraging learning, leisure and creativity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Chapel Street
R G Wynne, Development Services
779 6127
Redevelopment of vacant land and outdated industrial properties
either side of Adelphi Street.
 Terms now agreed between Salford University and Salford City
Council for Adelphi Street and Meadow Road and terms agreed for
Irwell Valley campus. Solicitors now instructed. Completion
targeted for early June 2006.
 Other private sector developers purchasing sites and securing
planning permission.
 Architects appointed for building for the Faculty of Music and
Performing Arts.
 Planning discussions are underway on the development of the site
on the corner of Adelphi Street/ Silk Street, adjacent to the Trinity
residential area. Planning APPeal lodged - stilon going.
 Proposal of possible signature building within Central Salford
Vision and Regeneration Framework.
Funding sources
None directly
Priorities and Milestones
 Complete Adelphi Street land transfer
Timescales
June 2006
Risks and barriers
 Difficulty of purchasing for non-residential development aspirations
at residential values.
Communication
Opportunities
 Probably as and when any agreement reached.
 As and when land transaction completed
13
Project: Greengate
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Chapel Street
P Baker, Housing and Planning
778 0983
Redevelopment of vacant and underused land and industrial property
in Greengate to create a new mixed-use urban quarter at core of
conurbation. Area includes former Exchange Station. Need to ensure
links with City Centre Transportation Strategy (e.g. Exchange Bus
Station), River Irwell Corridor and Springfield Lane site.
Progress to Date
 Network Rail/ASK joint venture now signed.
 URC Business Plan considered by Board on 5th April - priority
projects not yet publicly available.
 Archaeological investigations at BSC site completed in February
2006.
 Consideration being given to setting up focused working groups to
support Steering Group e.g. on land assembly and public realm
procurement.
 Development commencing on site - Abito, Dandara and
Chestergate Land Ltd schemes progressing well.
Funding sources

English Partnerships, NWDA and Private Sector.
Priorities and Milestones
 Design work by Urban Vision/ Feilden Clegg Bradley complete
Risks and barriers
Communication
Opportunities
Timescales
May 2006
 Need to tie in other landowners (and their development proposals
and aspirations).
 Cost of infrastructure
 Potential need for compulsory acquisitions of key sites.
 Discussions and involvement of MCC important to gain their
support for proposals.
 Some publicity in MEN about Greengate - linked to the launch of
the Abito residential scheme by ASK Developments
14
Project: Springfield Lane
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Chapel Street
S Gwatkin, Urban Vision
779 6098
Redevelopment for residential and mixed use scheme with Urban
Splash
 Urban Splash have purchased the derelict former King William IV
public house required for the comprehensive redevelopment.
 Urban Splash submitted three outline planning applications in
October 2005 giving a range of mixes of uses for the
redevelopment of the site. All three were approved by the Planning
and Transportation Regulatory Panel on the 15th December 2005.
 Weston Williamson architects have been commissioned to prepare
detailed plans for the first phase of development.
Funding sources
Not known at this stage.
Priorities and Milestones
 First phase on site
Risks and barriers
Detailed planning permission for each phase
Sufficient demand from the property market
Communication
Yes
Opportunities
Timescales
Early 2007
15
Programme: Charlestown and Lower Kersal New Deal for Communities
Pledge: All 7
Area Covered
Lead Officer &
Contact Details
Start Date
Themes
Number of
Projects: 2005/06
Expenditure
Progress to date
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
North Irwell Riverside
Tim Field – NDC Chief Executive
607 8523
April 2001
End Date
March 2011
 Building Communities
 Crime and Community Safety
 Education, Children and Young people
 Physical Environment
 Health
 Business, Employment and Skills
75
Key

Housing redevelopment in riverside locations
projects Projects

Remodelling and renewal of existing housing public
and private estates.

Salford Innovation Park hub.

The Beacon Centre.

Sports Village.

Property Marking/security scheme for all residents

2 Healthy Living Centres.

Alley gating.

Public realm improvements.

Pendleton Gateway.

CRASY sports development.

Targeted policing.

Job Shop.
Target Spend
Actual Spend
Target Spend
Actual Spend
2004/2005
2004/05
2005/2006
2005/06
£7.3 million
£7.24 million
£6.3 million
£7.0 million

Oscar event for community members involved in New Deal held March.
Young People Oscars to be held June/ July 06

St Aidan’s Healthy Living centre underway (complete summer 2006)

Sports Village launched 12th March 2006

Arrowhead housing due to complete early May

Phase 5 of Littleton Road Improvements to start imminently

St Aidan’s Healthy Living Centre underway.

Environmental Improvement work at Matlock Cross, Lower Kersal due to
commence on site April 2006 - start imminent

Community Consultation for Neighbourhood Park in Lower Kersal on-going

Development Framework approved.










First stage of Development at Kersal High - Winter 06
Commencement of second stage of Private Sector housing improvements at
Littleton Road
Environmental improvements at Whit Lane and Kersal Way.
Planning policies.
Flood.
Match funding from partners
Re-phasing of funding from G0-NW
NDC News letter.
Summer Activities.
Press releases in connection with project launches (e.g. Beacon Centre,
LIFT Centres)
16
Project: Salford Innovation Park (SIP)
Pledge: Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
NDC
Matthew Lynn, Economic Development Section
793 3408
Salford Innovation Park will form the basis of a new ‘Knowledge
Quarter’ in the city, it aims to benefit businesses, the community and
education by being:
 Be an exemplary and innovative model for the co-location of
business, industry and education.
 Develop mutually supportive and challenging environments
which stimulate innovation, creativity and entrepreneurship at
all levels in society.
 Generate and nurture businesses to develop an
entrepreneurial spirit.
 The Salford Innovation Forum is the first major phase of the
SIP and will provide high quality managed workspace /
incubation facilities for growth SME’s.
 On site 20th February
 Project manager appointed
 Seeking 3rd party operator
 Funding for the project approved from all 3 funding sources.
£3.4m
£6.0m
£300K
£9.7m
ERDF
NWDA
NDC
Total capital costs
Priorities and Milestones –

Fit out stage completed and opening of building
Risks and barriers
Communication
Opportunities
Timescales
June 07
 Awaiting ERDF offer letter.
 Maintaining project costs under £10m limit.
 Agreement with University of Salford Enterprises Ltd over Heads of
Terms.
 Confirmation of grant approval for the project.
 Start on site.
 Marketing strategy currently being progressed by partners.
17
Project: Duchy & Pendlebury Renewal Area
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Claremont Village
Kevin Scarlett, Housing Services
925 1023
To provide a strategic framework for the physical, social and economic
renewal of areas’ neighbourhood; securing its long-term sustainability
by making the areas more attractive and safer places to live, more
desirable places to visit and more inviting areas for private sector
investment; building on a strong local identity and aspiration and
involving the communities and other stakeholders.
 April 2006 – Alleygating of Clearance Area completed
 April 2006 – Legal action (possession order) obtained to vacate
property on Duchy Bank site
 April 2006 - Duchy Bank Developers Agreement – Agreed and
ready to sign
 March 2006 - 31 applications received for Relocation Assistance
 March 2006 – Planning Approval obtained for 37 new-build
affordable family houses (Duchy Bank)
 March 2006 – Public Inquiry held for Duchy Clearance Area CPO
order (outcome not yet known)
 March 2006 – AHP bid for 10 shared ownership properties
approved by Development Partner (SP@CE)
 February 2006 – Public Meeting (management of Clearance Area
and allocation policy)
 February 2006 – 6 x traffic restriction boulders placed in alleyways
within clearance area in response to vehicular crime incidents
 January 2006 – Burglary Reduction ‘Target Hardening’ promoted
throughout clearance area
 January 2006 – Duchy Bank Development contractor appointed
Funding sources
HIP and HMRF
Priorities and Milestones
 Development site Vacated
 Development site cleared
 Development works – start on site
 Public Inquiry – outcome publicised
 Presentation meetings for new development
 Allocations strategy for development site agreed with displaced
residents and properties allocated
Timescales
June 2006
June 2006
June 2006
June 2006
June 2006
June 2006
Risks and barriers



Site not vacant and cleared
Development works start on site delayed
Public Inquiry – Objections to CPO upheld
Allocations Strategy not agreed by displaced residents
Communication
Opportunities


Salford Housing Conference presentation
Series of community involvement events as part of the areas
re-design process
Attendance at Residents Group meetings
Newsletter Updates
Development liaison/presentation to clearance residents


18
Eccles
Areas covered within this report:
Eccles
Liverpool Road
 Shopfront Improvement Scheme ongoing as dictated by funding availability
 Tenders invited for supply and installation of 8 X CCTV along Liverpool
Road between Peel Street Eccles and Patricroft Bridge - Submission
deadline 7/4/06
 Traders Group secured funds via Fairshare to support monitoring and
maintenance of CCTV for first 3 years.
 Initial discussions underway with Eccles and Salford Mosque Islamic Society
to discuss investment potential of properties owned by the society.
Eccles Town Centre
Eccles Town Centre
 Proposal for Magistrates Court to be located in Eccles Town Centre.
Magistrates Court and Justice Centre Initiative
 Cabinet now agreed location of Court and car park as John William Street,
Eccles.
 Outline Planning Application due 19th May.
19
Project: Liverpool Road Regeneration
Pledge: Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Eccles
Ruth Shields, Economic Development Section
793 2349
To stem and turn around the decline of the Liverpool Road Corridor
by implementing a series of physical improvements. The challenge
is not simply to make regeneration happen, but to ensure that it
builds long term sustainability in every respect, economic, social and
environmental. This will involve balancing the retention of existing
communities, improving their social and economic prospects, with a
need to attract newcomers into the area.
Progress to Date
 Shopfront Improvement Scheme ongoing as dictated by funding
availability.
 Tenders invited for supply and installation of 8 X CCTV along
Liverpool Road between Peel Street Eccles and Patricroft Bridge.
 Traders Group secured funds via Fairshare to support monitioring
and maintenance of CCTV for first 3 years.
 Initial discussions underway with Eccles and Salford Mosque
Islamic Society to discuss investment potential of properties owned
by the society.
 Key Development Site - Crown Theatre, Church Street – Planning
application approved for the development of the grade II listed
building into 37 apartments together with retail space at the ground
floor.
NRF
Funding sources
2005/06 - £100,000
Capital budget
2005/06 - £180, 000
SRB 5
2005/06- £64,000
Priorities and Milestones
Timescales
Shop Front Improvement Scheme completion
On-going 2006 - 07
Risks and barriers
Communication
Opportunities
 A high level of investment is needed for the project to have the
necessary impact.
 There is a risk that sufficient funding, additional to that above, will
not be secured.
 Low take up of grants from local traders
Press Release to be circulated
Press Release published in MEN and Advertiser (Sept 26th) to
publicise Ministerial Visit
20
Project: Eccles Town Centre
Pledge: Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
Eccles
Matthew Lynn, Operations Manager, Economic Investment, Economic
Development Section
793 2932.
To undertake a study to identify the most sustainable approach to be
taken by the City Council, in partnership with retailers, owners and the
local communities, which will lead to the enhanced viability and vitality
of Eccles Town Centre and Liverpool Road.
 A close relationship with landowners being maintained
 Proposal for Magistrates Court to be located in Eccles Town
Centre
 A number of Traders have received the Eccles Town Centre Study
(Paul Butler)
 Planning application approved 16/03/06 for Eccles LIFT scheme
on the site of Eccles Library extension and Eccles Health Centre.
NRF and SCC mainstream
Priorities and Milestones
 Response required by Threadneedle on Eccles Town Centre
study

Risks and barriers


Communication
Opportunities
Timescales
April 2006
Lack of private sector buy-in. The successful implementation
of the strategy will require support from the private sector.
Lack of public sector funding. Although, private sector funding
is key to the implementation of the strategy, public sector
funding is also required.
Forward investment strategy needed by Threadneedle.
Yes
21
Project: Magistrates Court and Justice Centre Initiative
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Eccles SDA
R G Wynne, Development Services
793 3750
Confirmation of site for new courthouse at John William Street
Car parking solution will involve multi storey car parking.
Progress to Date
 Cabinet now agreed location of Court and car park as John William
Street, Eccles.
 Outline Planning Application due 19th May.
 Interim parking being investigated - on-going.
 Terms need to be agree with DCA & HMCS
Funding sources
None
Priorities and Milestones
 HMCS & DCA approval
 Outline Planning application
Risks and barriers
Communication
Opportunities
Timescales
On-going
19th May 2006
Yes
22
Irlam & Cadishead
Areas covered within this report:
Barton
Barton Strategic Site
Red City Developments
 Planning Panel resolved to grant planning permission at its meeting on
17th November 2005. Application referred to Secretary of State (GONW)
on 24th November 2005. Initial 21 day period for reply has been extended
by GONW. Now called in for inquiry to start on 20th June 2006.
Peel Holdings
 Consultation with local community and statutory consultees now carried
out.
 Highways Agency pronouncement expected in May 2006
23
Project: Barton Strategic Site
Pledge: Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Barton
D Evans / C Findley, Development Services
793 3641
Employment development of large Brownfield site. Two main
elements proposed:Salford Reds: 20,000 seat stadium with retail, casino, hotel, fast food
etc to support the stadium use; and
Peel Holdings: multi modal freight terminal; to include 2-berth port,
rail freight terminal, and 200,000 sq m warehousing.
Salford Reds:

Planning Panel resolved to grant planning permission at its
meeting on 17th November 2005. Application referred to
Secretary of State (GONW) on 24th November 2005. Initial 21
day period for reply has been extended by GONW. Now called
in for inquiry to start on 20th June 2006.
Peel Holdings:
 Consultation with local community and statutory consultees now
carried out.
 Highways Agency pronouncement expected in May 2006

Awaiting Peel Holding response to issues made following
consultation.
Funding sources
Private
Priorities and Milestones
Salford Reds
 Heads of terms issued and negotiations in progress for City Council
land.
 Site allocation in the review unitary development plan considered at
Public Inquiry. Inspector’s decision awaited.
Peel Holdinggs
 Highways Agency pronouncement


Risks and barriers

Communication
Opportunities
Timescales
Ongoing
Ongoing
End May
2006
Call in by secretary of State.
Objections to Port Salford by Strategic Rail Authority
overcome.
HA/ NWDA/ NWRA/ GONW still have objections to the
proposals.
Yes
24
Ordsall & Langworthy
Areas covered within this report:
Chapel Street
Ordsall
Pendleton
Seedley Village
Salford Quays
Chapel Street
Salford Central Station
 Final Phase 1 design being consulted on for approval by partners. Drawings will
then be submitted as working amendments to approved planning and listed
building consents.
 Possible additional funding from Railway Heritage Trust for historic conservation
now being considered.
 Chris Farrow has requested a meeting with GMPTE to discuss Phase 1 and
future work - in particular, the links with URC's vision for the wider station area.
Manchester Bury and Bolton Canal
 Acquisition of Valley & Vale land complete.
 Acquisition of Granada land with solicitors for completion.
 Final design in progress, tenders to be issued with a start on site September
2006, with completion September 2007.
Ordsall
 Construction of new primary school and children’s centre
commenced.
 Heads of Terms for development agreement with LPC approved.
Development Agreement and indicative infrastructure programme
approved by lead members.
25
Pendleton
Seedley Village
Pendleton Masterplanning
 Issues and Options report approved by Lead Member for planning
27/3/06.
 PFI Expression of Interest approved by Lead Member for Housing
23/3/06.
Seedley and Langworthy
 Urban Splash held a pre launch to the local community at the end of
March 2006. 10 properties were sold.
 Properties went on general public sale on 8th April 2006 and all phase 1
has now been sold.
 Renovation work to 10 properties has begun on Co-operative Street,
work is expected to be completed by October 2006. All 10 properties
have been chosen by Homeswappers.
 Budget provision approved for Phase 2 Langworthy Road shops
refurbishments. Programme for start on site being negotiated with
partner contractor.
 CPO for 132 - 174 Langworthy Road (shops) confirmed. Mixed use
development including residential expected to start on site Autumn
2006.
 CPO for Langworthy South East confirmed March 2006.
 Seedley West Phases 3 & 4 Block Improvement Scheme
commenced on site January 2006, expected completion September
2006.
Proposed TESCO adjacent to Shopping City
 7th April agreement over scheme between Gubbay /Tesco. Agreement
with Council for comment. Scheme detail still awaited.
 The relocation church site has been assembled without a contested CPO
as all interests were acquired beforehand
Salford Quays
Dock 9
 Detroit Bridge refurbishment (£0.25m) completed.
 Planning and Transportation Regulatory Panel approved Extension of
time limit on the outline planning permission for Dock 9 in March 2006.
 Mixed use development off Michigan avenue approved by planning panel
March 2006.
Clippers Quay
 Planning application submitted for approx 290 studio residential units
(Abito) on former pub site approved by Planning Panel April 2006.
26
Project: Salford Central Station
Pledge: Creating prosperity in Salford
Area Covered
Lead Officer & Contact
Details
Aims/
Objectives/Themes
Chapel Street
P Baker, Housing and Planning
778 0983
 To improve the station and its approaches
 To provide a major transport interchange for surrounding
development in Chapel Street and Manchester City Centre
Progress to Date
 Final Phase 1 design being consulted on for approval by
partners. Drawings will then be submitted as working
amendments to approved planning and listed building consents.
 Possible additional funding from Railway Heritage Trust for
historic conservation elements of the scheme now being
considered.
 Chris Farrow has requested a meeting with GMPTE to discuss
Phase 1 and future work - in particular, the links with URC's
vision for the wider station area. Station considered as part of
URC Business Plan 2006 - 2009 on 5th April - decisions on
priority projects not yet publicly available.
 Phase 1 contract will start on site September/October 2006 and
be completed June 2007. Slippage due to advanced repair and
repainting works now being done to the three listed railway
bridges by Network Rail. This £2 million contract started on site
in April for 20 weeks.
Funding sources
Phase 1: EDZ
£1,080,848
GMPTE £3,352,442
Priorities and Milestones
 Phase 1 contract start on site
 Phase 1 completed
Risks and barriers
Communication
Yes
Opportunities
Timescales
Sept/Oct 2006
June 2007
27
Project: Restoration of Manchester, Bury & Bolton Canal
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Line of the Canal from Trinity Way / Hampson St to Clifton Junction
(and on into Bury & Bolton)
Phase 1 Middlewood Development Castlefield area
Salford City Council
David Evans
0161 – 793 3641
British Waterways
Martin Clarke
01925 847745
martin.Clarke@britishwaterways.co.uk
Aims/
Objectives/Themes
Progress to Date
To see the restoration of the canal to navigation, as a catalyst to
regeneration & redevelopment along its line.
 Acquisition of Valley & Vale land complete.
 Acquisition of Granada land with solicitors for completion.
 Final design in progress, tenders to be issued with a start on site
September 2006, with completion September 2007.
 The MBB Canal Society made a bid for Living Landmarks Lottery
funding, pledging in principle support from both BW and the City
Council (amongst others). However, this bid was unsuccessful.
 Phase 1 maintenance funding now resolved. (Costs shared
between City Council and developer of adjoining site).
 ERDF (EDZ) funding approved for phase 1 Middlewood.
Funding sources
Phase 1
ERDF £2,488,511
NWDA £1,100,000
S106
£1,000,000
Private sector £1,000,000 (contribution of land)
Priorities and Milestones
Timescales



Start on site of phase 1
Expected Completion
Securing NWDA approval to project outline for future phases of
the canal
Risks and barriers
Communication
Opportunities
Sept 2006
Sept 2007
Post 2006
 Securing public funding at all stages
 Securing transfer of land from private owners (outstanding)
The project offers great opportunity to
 Highlight water based regeneration & development in Salford
 To demonstrate linkage between major initiatives in Central Salford
28
ORDSALL
Project: Ordsall Development
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
South Irwell Riverside
M Sykes, Development Services
793 3600
Regeneration and development within the Ordsall estate.
 Construction of new primary school and children’s centre
commenced.
 Heads of Terms for development agreement with LPC approved.
Development Agreement and indicative infrastructure programme
approved by lead members.
 Development Framework adopted.
 231 apartments under construction by LPC Living, at Quay 5,
Ordsall Lane, were all sold within 6 weeks.
 Construction of a further 750 new apartments, by Bellway, David
McLean Homes and Lowry Homes on site.
 Lead member approval to closure of Collingburn Court, allowing
assembly of development site at Hilton Street.
Funding sources
Private sector-led development, predominantly on Council-owned
land. Infrastructure works funded from land values. Sources of gap
funding to be identified.
Priorities and Milestones
Timescales
Early May 2006
 Sign development Agreement with LPC
June 06
 Quay 5, Ordsall Lane apartments complete
Summer 2006
 Submission of planning applications for new family housing in
South Ordsall
Summer 2007
 Opening of new primary school
Risks and barriers
 Lack of clarity as to which sites are required for public buildings
and which are available for development.
 Slippage in programme for new school.
 Market led redevelopment subject to commercial confidence.
 Local opposition to individual building proposals.
Communication
From time to time as plans unfold.
Opportunities
29
Project: Pendleton Masterplanning
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Pendleton Centre
Kevin Scarlett, Housing Services
925 1023
To develop a masterplan for the central Pendleton area.
Funding sources
HMRF, Private
 Issues and Options report approved by Lead Member for Planning
27/3/06.
 PFI Expression of Interest approved by Lead Member for Housing
23/3/06
 Consortium (led by Halcrow) completed Stage 1A: Confirmation of
key objectives, opportunities and constraints.
 Baseline study finalised.
 Pendleton Steering Group and Community Forum continue to meet
regularly.
Priorities and Milestones






Consultation on Issues and Options report and housing options
planned
Expected OPDM announcement on PFI
Aim to identify preferred options
Consultation on preferred options
Aim to refine preferred option.
Aim to have Pendleton Area Action Plan examination and
adoption complete.
Risks and barriers
Communication
Opportunities
Timescales
19/5/06 – 29/6/06
Jun/Jul 2006
Sept 2006
Oct 2006
May 2007
Oct 2008
 Community & stakeholder involvement. This is being managed
through the development of a media strategy, communications and
consultation planner. The Community Forum and Pendleton Steering
Group are involved in preparing the strategy and planner.
 Appointment of main developer partner. The timing of the
appointment is dependant on the decision of the PFI Expression of
Interest and the preferred option that is approved as these define the
brief of the development partner.
 Opportunities have been identified in the Communication and
Consultation Planner and the Media Strategy.
30
Project: TESCO – Shopping City
Pledge: Creating prosperity in Salford/ Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Land adjacent to Pendleton Way
P J Openshaw, Urban Vision
779 6126
New food store to support the centre and enhance retail facilities in
the area.
 7th April agreement over scheme between Gubbay /Tesco.
Agreement with Council for comment. Scheme detail still awaited.
 Detailed discussion has commenced with Robert Gubbay in
relation to the land and financial transactions associated with the
sale of the Pendleton way car parks to enable the extension of the
shopping centre to proceed.
 Detailed discussions with GMPTE and Bus operators are
continuing.
 The relocation church site has been assembled without a
contested CPO as all interests were acquired beforehand. This will
Hopefully enable the New Chuch to start on site by Dec 2006
subject to the resolution of the flat element of the scheme.The
scheme has planning consent.
 The relocation site for the new RC Primary school requires the
acquisition of the remaining 8 interests. A statement of reasons for
the proposed CPO will be served by 1st June and all that can be
done is being done to try to secure an uncontested CPO, which
would enable an early start with the School which has planning
consent.
 The key to driving forward the overall project is securing a scheme
which has support to enable a planning application to be
made.Officers are pressing Tescos and Gubbay to deliver such a
scheme for comment.
Funding sources
Private
Priorities and Milestones
 New Church on site
 Statement of reasons for CPO
 Agreement over Tesco and Shopping City proposal
Risks and barriers
Communication
Opportunities
Timescales
Dec 2006
June 2006
May 2006
 Failure to agree any of the above.
Yes
31
Project: Seedley and Langworthy
Pledge: All 7
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
2006/07
Seedley Village
Gill Finley, Regeneration Manager
212 4471
To secure the comprehensive regeneration of the Seedley and Langworthy area
through 5 themes:

Physical regeneration

Strengthening the community

Crime and community safety

Children and young people

Employment, learning and enterprise
Seedley and Langworthy
 Urban Splash held a pre lanch to the local community at the end of March 2006.
10 properties were sold.
 Properties went on general public sale on 8th April 2006 and all phase 1 has now
been sold.
 Renovation work to 10 properties has begun on Co-operative Street, work is
expected to be completed by October 2006. All 10 properties have been chosen
by Homeswappers.
 Budget provision approved for Phase 2 Langworthy Road shops
refurbishments. Programme for start on site being negotiated with partner
contractor.
 CPO for 132 - 174 Langworthy Road (shops) confirmed. Mixed use
development including residential expected to start on site Autumn 2006.
 CPO for Langworthy South East confirmed March 2006.
 Seedley West Phases 3 & 4 Block Improvement Scheme
commenced on site January 2006, expected completion September 2006.
Funding sources
SRB5, NWDA, ERDF, HMRF
Priorities and Milestones
Timescales
September 2006
 Seedley West block improvements completion
September 2006
 Completion of Co-operative Street Homeswap properties
May 2006
 Preparation for National In Bloom competition
Risks and barriers
 Properties are purchased and renovated for homeswaps are unpopular.
 Unforeseen structural problems within the proposed refurbishments.
 Management of areas with increasing vacant properties.
 Need to secure resources for future project activity.
 Retaining Staff on short-term contracts.
 Potential delays in obtaining permissions for alleyways to be closed.
 Potential for delays due to contractor timescales.
Communication
Opportunities

May - In Bloom 2006 begins
32
Project: Dock 9
Pledge: Creating prosperity in Salford / Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Salford Quays – Dock 9 – north bank
Dave Jolley. Urban Vision 0161 – 779 4831
Progress to Date
 Further progress on site dependent on outcome of BBC bid. Decision
expected June 2006.
 Detroit Bridge refurbishment (£0.25m) completed.
 Planning and Transportation Regulatory Panel approved Extension
of time limit on the outline planning permission for Dock 9 in March
2006.
 Mixed use development off Michigan avenue approved by planning
panel March 2006.
 Planning application submitted for the erection of 4 towers on
opposite side of The Quays loop road to the NV buildings. 600
apartments, retail on ground floor. Retail and traffic studies
requested. Highways Agency have directed no decision be made
pending traffic assessment.
 Detailed planning permission for 153 apartments adj. NV site. New
planning permission granted for 203 apartments plus ground floor
restaurants in 2 blocks (20 floors and 9 floors).
 Planning permission granted to mixed-use development at Michigan
Avenue 15th December Planning Panel.
Funding sources
Private Sector
Continuing the development of the Quays.
Priorities and Milestones
 Masterplan for remaining development
being reviewed. Preliminary meeting has
taken place with the architects.
 Broadway Link completed.
Risks and barriers

Communication
Opportunities

Timescales
On-going
Dec 2012 linked to implementation of phase
3 of outline pp.
The scheme is fully privately funded and thus is dependent on market
conditions / demand.
Announcement and completion of each phase (eg NV Buildings).
33
Project: Clippers Quay
Pledge: Enhancing life in Salford/ Creating prosperity in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Salford Quays – Clippers Quay
Dave Jolley, Development Services; 0161 – 779 4831
Mixed-use development with primarily residential and commercial
flavour (office) and food and drink.
Residential to comprise mix of dwelling types from 1 to 3 bed.
Strong design requirement – aim is landmark building.
 Planning application submitted for approx 290 studio residential
units (Abito) on former pub site approved by Planning Panel April
2006.
Funding sources
Private Sector
Priorities and Milestones
Timescales
End 2006
 Begin on site
Risks and barriers
 Acquisition of leasehold interests by the developer.
 The scheme is fully privately funded and thus is dependent on
market conditions / demand.
Communication
 The first redevelopment scheme for part of Salford Quays (The
Opportunities
former cinema was one of the first buildings built at Salford
Quays).
 Announcement and completion of each phase.
34
Swinton
LIVIA
 Agreement in principle has been obtained to lease council land to the Forestry
Commission (FC) under the Newlands Programme.
 Coalfield Community Funding of £225k has been secured for the Clifton area,
directly linked to the Newlands work on the LIVIA site.
 The Single Programme Proposal Form (SPPF) has been submitted to the NWDA
and if approved up to £365,000 should be released for 2006/07.
35
Project: Newlands - Lower Irwell Valley Improvement Area (LIVIA)
Pledge: Enhancing life in Salford
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
The LIVIA area is entirely within the Pendlebury ward boundary.
Tim Jones, Environment and Projects, Housing and Planning
Services. Tel: - 793 3655
email: - tim.jones@salford.gov.uk
 Over 200 hectares identified for reclamation in the Irwell Valley.
 Site suffers from significant contamination from a wide range of
past industrial uses.
 Focus of the programme will be to assess contamination, treat it
where possible and restore the land for soft-end and recreational
after uses.
 Agreement in principle has been obtained to lease council land to
the Forestry Commission (FC) under the Newlands Programme.
Lease agreements must be secured before FC can draw down
Newlands funding.
 The Forestry Commission is anticipating entering into a 99-year
lease with landowners. It was originally expected that they would
enter in to a 20 year lease, as Newlands funding secures
management and maintenance funding for 20 years. However, the
FC is prepared to enter in to the additional period on an ‘at risk’
basis.
 Coalfield Community Funding of £225k has been secured for the
Clifton area, directly linked to the Newlands work on the LIVIA site.
Groundwork Salford, Manchester and Trafford have taken lead
responsibility for the delivery of this programme on behalf of the
council. Phase I of works at Queensmere Dam to support the work
of Swinton and Pendlebury Angling Club has been completed.
 The Single Programme Proposal Form (SPPF) has been submitted
to the NWDA and if approved up to £365,000 should be released
for 2006/07.
Up to £4m capital over a 5 year period, (dependent on hectares
brought under lease agreements). Approximately £1.5m will provide
at least 15 years management and maintenance. Approximately £0.5
m has already been spent on site investigation work, planning, design,
legal issues, consultation work etc.
Match funding has been secured from a number of sources including
the following: - Coalfield Communities fund, Environment Agency
landfill tax credits, S106 agreements, council capital receipts, Home
Office ‘Gate-It’ funding.
Need to ensure linkage with other major regeneration initiatives
including e.g. Manchester Bolton & Bury Canal restoration, Central
Salford and New Deal for Communities.
Priorities and Milestones
 Identify and agree 3 year Capital programme.
 Agree Lease arrangements between FC and land-owners.
Funding released subject to NWDA appraisal process
Timescales
On approval.
On-going.
2006/07
36
Risks and barriers
Communication
Opportunities
NWDA funding.
Securing agreement from all landowners for Forestry Commission to
manage land under a ‘pie-crust’ lease for at least 20 years.
Securing additional and match funding.
Land contamination issues are severe and may be difficult to treat with
funding levels provided.
Flood risk issues.
Vandalism and anti-social behaviour problems present a challenge.
Communication and consultation issues are an essential element of
the whole programme. As the programme develops there will be
many opportunities for positive publicity. Occasional progress notes
are circulated for information to a number of Members and Officers.
37
FUNDING PROGRAMMES
Programme: Single Regeneration Budget Round 5
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure –
Spending on target
Key Outputs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
City Wide
Sue Ford, Strategy and Resources
ext 3443
April 1999
End Date
March 2006
To ensure the comprehensive regeneration of Seedley and Langworthy. To
reintegrate Seedley and Langworthy and other target areas into the social
and economic fabric of the City through 2 supporting programmes of:

Social inclusion measures.

Economic development opportunities.
30
Key Projects
 Salford Money line
 Local Labour Initiative
 Linear Coridor development
 Partnership capacity Building
 Seedley and Langworthy Living
Environment Programme
 Seedley & Langworthy Trust
 Good practice in community involvement
 SPARKY
Annual Target Spend Profile Spend to end
Actual Spend to March
2005/06 £
Dec 2005 £
2006 £
3.26million
800,000
Figures being verified
Output Targets 2005/06
Output to 2006
80 jobs created
34 jobs created
70 people obtaining qualifications 85 people obtaining qualifications
300 Businesses advised
420 businesses advised
20 new business start ups
6 new business start ups
200 dwellings where security is
29 dwellings where security is
upgraded
upgraded
195 dwellings created/improved
15 community safety initiatives
12 community safety initiatives
5 Youth crime prevention
2 youth crime prevention initiatives
initiatives.




Final year delivery plan (£3.256 m) 2005/06 approved by NWDA.
Forward strategies for projects completed.
Evaluation underway – Quaternion Consulting.
End of scheme evaluation draft report due in May 2006, final report
anticipated end June 2006.
 Stakeholders end of scheme conference to be held 6th July 2006.
 Final year of SRB 5 – close monitoring is needed to achieve full SRB
programme spend of £25m.
 Regularly reviewed throughout year.
38
Programme: Housing Market Renewal Fund
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Key Outputs
Central Salford
Kevin Scarlett, Housing Services Division Ext 8702
2/10/03
End Date
2013
To re-structure the housing market in Central Salford.
Neighbourhood
Key Projects
During initial phase, HMR grant focuses
Based
on site assembly particularly in
Programme with
Broughton and Seedley and Langworthy;
some bespoke
alongside improving homes in Seedley
projects in
and Langworthy, Broughton and
Sustaining
Claremont. Thematic projects include
Neighbourhoods
warden schemes and environmental
theme.
improvements.
Annual Target Spend
Profile Spend End
Actual Spend End
2005/06 £
march 2006 £
March 2006 £
22.222 million
2.222 million
20.222 million
Output Targets (2005/06)
- 550 Homes constructed
- 364 Homes demolished
- 416 Homes acquired
- 5804 Homes subject to additional
management measures
- 467Homes subject to non-housing work
- 25 Households assisted with relocation
- 6 Homes subject to intervention by RSLs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
Outputs Achieved to End March
2006
416 Homes constructed
513 Homes demolished
271 Homes acquired
5855 Homes subject to additional
management measures
6904 Homes subject to non –
housing work
39 houses assisted with
relocation
44 homes subject to intervention
by RSL’s
 Achieving spend and output targets and balancing expenditure across
interventions.
 Review of programme and progress towards meeting aims/objectives and
performance targets set out in the prospectus.
 Scheme Update to secure funds for 2006/07 and 2007/08 submitted to
ODPM in October 2005.
 ODPM decision on scheme update expected April 2006.
 Integration of HMR within Central Salford Vision and Regeneration
Framework.
 Integrated Secretariat team recruited, joint office due to be established in
July 2006.
 2006/07 appraisal of programme elements underway, approval expected
end of April 2006.
 Delivering significant spend of £24.075 million in 2005/06.
 Alignment with Central Salford Vision and Regeneration Framework.
 All linked to delivery of neighbourhood level programmes within each of 8
neighbourhoods across Central Salford.
 Integrated secretariat team to include Marketing and Communications post.
39
Programme: Neighbourhood Renewal Fund
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Key Outputs
Citywide with focus on 10% most deprived wards
Paul McKenna, Strategy & Resources ext 3421
April 2001
End Date March 2008
To use the NRF to help meet the wider Neighbourhood Renewal Agenda,
measured through the city’s progress against Government Floor Targets for
Education, Employment, Crime, Health and Housing.
In
2006/07 allocation process moved to a commissioning model.
2006/07:
SDP's identified key priorities and are now working with partners
to deliver interventions.
51
Annual Target Spend
Profile Spend to end
Actual Spend to end
2005/06
March 2006
March 2006
£9,343,379 £9,202,000
Figures being verified
Annual Target Spend
2006/07
£9,308,000
Annual Output Targets
NRF is outcome focussed
rather than output. As a
condition of funding all
activity feeds directly into
meeting the Government
Floor Targets.
Actual Output
Expected end of Q1.
In 2006/07 the NRF is
supporting a range of
activities that focus on
raising attainment against
floor targets through a
partnership approach to
tackling unemployment, poor
educational attainment,
health inequalities and high
crime rates.
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
 2006/7 Allocation –
Agreed projects currently developing action plans and milestones.
Signing of all contracts nearing completion
Barriers:
 Measuring proportional effect of NRF funded projects against progress in
the national floor targets.
Individual press releases by appropriate projects. LSP newsletter/ website.
40
Programme: North West Objective 2 Programme – Priority 1 ‘Business and Ideas’
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Key Outputs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
City Wide
Dee Carroll – Strategy & Resources ext 3016
January 2000
End Date
Dec 2005
To create and protect jobs and income by investing in new
entrepreneurial businesses, innovation, and e-commerce, and by
improving the business performance of existing SMEs. This will be
delivered through 5 key themes:
 Creation & establishment of entrepreneurial business starts.
 Increasing the competitiveness of established SMEs.
 Developing the regional knowledge economy: supporting
business innovation & networking.
 Investment in premises for new & expanding SMEs.
2
Key Projects
 Digital World
 Business Expansion Grants
Target 2000/06
Profile Spend to end
Actual Spend to end
Programme Spend £
Dec 05 £
Dec 05£
2.585 million
2,350,000
2,585,000
Annual Output Targets
Actual Output
7,500 sq.m of premises provided
36,000sq. m of floorspace
20 business grants processed
provided
28 business grants approved
23,972 sq. m refurbished
88 jobs created, 346 jobs
safeguarded
 Digital World at Salford Quays completed.
 Business Expansion project completed.
 Opening of Digital World. Companies awarded grant.
41
Programme: North West Objective 2 Programme Priority 2 ‘Improving People & Communities’
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/ Objectives/
Themes
Number of
Projects
Expenditure
Key Outputs
Barton, Blackfriars, Broughton, Langworthy, Little Hulton, Ordsall, Pendleton,
Weaste and Seedley, Winton (Walkden North, transitional)
Dee Carroll, Strategy and Resources ext 3016
January 2000
End Date
December 2008
To create local employment and enterprise opportunities, remove barriers to
participation and progression, improve employability and to increase participation
in the labour market, build the capacity and cohesiveness of groups and
communities and improve the local physical environment. This will be delivered
through 5 key themes:
 Developing Enterprise & Employment in Communities.
 Improving Access to Employment.
 Developing an Inclusive Information Society.
 Connecting Communities.
 Building Economically Sustainable Communities.
24
Key Projects
 SALT
 Money Line
 Job Shop Plus
 ICT in the Community
 Neighbourhood Wardens
 Cornerstone
 Langworthy Road Improvements
 Salford Sports Village
Target 2000/06
Target Programme Spend
Actual Spend to end
Programme Spend £
Dec 2005
Dec 2005
£9 Million
£8.5m
£8.5m
Annual Output Targets
Actual Output (Dec 05)
(Dec 05)
81 Community Enterprises
457 Community Enterprises assisted
assisted
19 Community Enterprises established
34 Community Enterprises
109 Micro Enterprises established
established
42,556 Residents assisted towards employment
28 Micro Enterprises
5,144 People securing employment
established
306 People given self employment support
7,467 People assisted
13 Learning/Employment Centres
towards employment
2282 Learning beneficiaries securing a positive
2,179 People securing
outcome
employment
5467 People provided with learning support
64 New jobs in community
1278 Women accessing employment opportunities
& micro enterprises
3010 Women accessing training and development
5 Environmental Initiatives
opportunities
supported
54 Women participating in management
6 Community Safety
1478 Sq mts new premises
Initiatives supported
36,011 People assisted towards employment
2.15 Hectares land
3,250 People securing employment
improved
77 New jobs in community & micro enterprises
7.6 km Route ways
2 Good practice networks established
improved
13 Community ICT facilities
120 Web content and maintenance projects
52,891 Residents benefiting from IS delivered
information
50 Environmental Initiatives supported
73 Community Safety Initiatives supported
180 Development of community devised and
implemented solutions to problems
4.72 Hectares land improved
4.441 km Route ways improved
42
Priorities and
Milestones
Risks/barriers
Communication
Opportunities

To claim quarterly as per Programme forecast expenditure profiles.
 Project managers failing to return info within the required deadlines.
Project approvals and profiles.
43
Programme: North West European Objective 2 Programme Priority 2 ‘Manchester Salford
Sustaining Neighbourhoods Initiative’
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/ Objectives/
Themes
Central Salford wards
Dee Carroll, Strategy and Resources ext 3016
Number of
Projects
3
Expenditure
Key Outputs
Priorities and
Milestones
Risks/barriers
Communication
Opportunities
October 2004
End Date
December 2008
The Programme seeks to support the process of transformation in a limited
number of Priority 2 wards surrounding the regional centre, maximising the
opportunity afforded to the area its designation as the first Housing Renewal
Pathfinder. The Action Plan seeks to utilise ERDF resources to add value to
the Housing Market Renewal in order to create sustainable neighbourhoods
through:
o Targeted streetscape and environmental enhancements
o Alleyway treatments and alley-gating
o Associated neighbourhood planning and ward co-ordination
 Transport Corridor Improvements
 Streetscape Environmental Improvements
 Neighbourhood Planning
Target Spend 2000 /
Target Spend December
Actual Spend to end
2008 £
2008
Dec 05
£2.6 million
£2.6 million
£32,000
Annual Output Targets (End March
Actual Output (end March 2006)
2006)
19 Marketing Initiatives supported
Neighbourhood Management
18 Environmental Initiatives supported application submitted for approval Feb
8 Community Safety Initiatives
06.
supported
0.5 Hectares land improved
Streetscape approved September 2005
2.68 km Route ways improved
- work on site has started.
13 Facilitate community participation
in maintaining local environment
Transportation Corridor Improvements
3 re-use of redundant buildings and
approved October 2005 - work on site
derelict land
has started
1 Linkages to wider community
sustainability
1st claims was submitted in December
7 Community organisations supported 2005.
2 residents securing employment
 Sub regional ERDF Action Plan bid to match HMRF programme approved in
Oct 04 for £1.219m.
 2 Projects now approved
 Neighbourhood Planning still going through Appraisal process
 To claim quarterly as per Programme forecast expenditure profiles.
 Project managers failing to return info within the required deadlines.
 Projects failing to gain approval
 Delays in implementation
Project approvals and profiles.
Key Projects
44
Programme: North West Objective 2 Programme – Priority 3 ‘Irwell Corridor Economic
Development Zones’
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Key Outputs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
Blackfriars/Broughton
Dee Carroll – Strategy & Resources ext 3016
Jan 2000
End Date
Dec 2008
To develop employment sites and realise the economic potential of
natural, built, cultural or industrial heritage assets to create significant
number of jobs, that are accessible to residents from ‘communities in
need’. This will be delivered through 3 themes:
 Developing Strategic Employment Opportunities.
 Maximising the economic potential of the Region’s Natural,
Cultural Assets.
 Connecting with communities in need.
2
Key Projects
 Manchester Bolton Bury Canal.
 Salford Central Station.
2006 / 2008 Target
Profile Spend to end
Actual Spend to end
Spend £
Dec 2008 £
March £
£3.6 million
£3.6m
To be confirmed
MBBC - No claims can be made prior to securing land from Granada.
SCC – 2nd interim claim made.
Annual Output Targets
Actual Output
Re-profile underway for 2005 delivery
Salford Central Station:
Phase 1 on site:
 Agreement to Phase 1 scheme by
June 06
GMPTE/City Council/Network
Phase 1 completed
Rail/SRA/Train Operating Company.
June 07
MBB Canal:
May 2006
 Start on site of phase 1
Post 2006
 Securing NWDA approval to project
outline for future phases of the canal
 Delays in letting contracts.
 Delays in securing land ownership.
 Project Approvals.
 Highlight water based regeneration & development in Salford.
45
Programme: Knowledge Capital (M: KC)
Area Covered
Lead Officer & Contact
Details
Start Date
Aims/
Objectives/Themes

Number of Projects
Key Outputs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
Citywide (Arc of Opportunity covers parts of Central Salford)
Karen Charnley, Economic Development Section
793 3408
Sept 04
End Date
N/A
Overall aim is to create 100,000 new jobs
The initiative has four themes:

Enterprise and Innovation (Developing the Knowledge Interface);
Environment and Infrastructure (Secure a High Quality and Highly
Attractive Physical, Social and Cultural Environment);

Education and Inclusion (Secure Inclusivity -focused on education and
skills enhancement);

Influence (Providing thought-leadership in building “knowledge
capital” and promoting Manchester: Knowledge Capital).
M:KC Exec
Key Projects
Salford Innovation Park
Team currently
within Salford
Central + Crescent Station
devl Science
Media Link (i.e. Adelphi)
City initiative
Arc of Opportunity studies
S Construction Partnership
Annual Output Targets
Actual Output
Indicators currently being developed
The M:KC initiative now has three major programmes of activity:
 Science City
 Green Energy Revolution
 City Growth Strategy

SCC is now seeking to develop projects to contribute to the above
programmes.

SCC continued liaison with M:KC Executive Team and M:KC Partnership.

Continued partnership support and resources for MKC is required in order
for it to meet its objectives.

Lack of available funds to deliver key priority projects.

Good communications opportunities exist with M:KC, M:KC Team have
Marketing Strategy and Manager
46
Programme: Fairshares Transforming Your Space
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Key Outputs
Priorities and
Milestones
Risks and barriers
Communication
Opportunities
City Wide
Sue Ford, Strategy and Resources
Ext 3443
August 2003
End Date
March 2007
To fund local environmental initiatives aimed at enhancing the quality of life of
local communities; improving the appearance and amenities of local
environments and; increasing development of sustainable community assets.
Total programme approved £1,337,542.
8
Key Projects
 Chimney Pot Park
 Mandley Park
 City Park and Play Activity in 5 parks
 Strengthening Communities –
improvements at 5 community centres
 Ordsall Community Café
 Oakwood Park
 Beechfarm Playing Fields
 Princes Park
Annual TYS Target
Actual Spend to end
Target Spend 2006/07
Spend 2005/06 £
March 2006 £
£676,820
£649,848
£326,736
Annual Output Targets 2006/07
Actual Output
- Chimney Pot Park to be complete
- Oakwood Park to be complete
- All projects to be financially
complete by 31st March 2007.
 Chimney Pot Park – Landscape Architects appointed and site
investigation underway.
 Mandley Park – Completed and open to the public.
 City Parks and Play Activities Improvements:
o Albert Park – Completed and open to the public. Additional multigames area now installed and open.
o Lightoaks Park – All works completed and open to the public.
o Winton Park – Completed and open to the public. Sure Start
contributed £85k to the project.
o Eccles Recreational Ground – Completed and open to the public.
Additional multi-games area now installed and open.
o St. Mary’s Park – Completed and open to the public.
 Strengthening Communities – All five Community Centres are complete
and open to the public. The project is now financially complete
 Ordsall Community Café phase one completed and open to the public.
Funding has been secured to complete the final phase of the
refurbishment.
 Oakwood Park plans underway.
 Beechfarm Playing Fields – Completed and open to the public.
 Princes Park – Completed and open to the public. Additional access
path now completed.
Physical works need to be completed by 31st September 2006. Delays in spend
would impact on NOF funding if physical works are not completed.
o Launch of projects once complete.
47
Programme: SHIFT (Salford’s Health Investment For Tomorrow)
Area Covered
Lead Officer &
Contact Details
Aims / Objectives /
Themes
Salford community and hospital NHS services
Stephen Whittaker
0161 212 4125
Stephen.Whittaker@salford-pct.nhs.uk
The SHIFT programme will bring primary care health and other public
services closer to patients and the communities of Salford.
The five SHIFT projects are:
 Redevelopment of Hope hospital in a £130 million PFI contract
and a further £30 million modernisation investment.
 Construction of six new Health and Social Care (LIFT) centres
located across Salford (see separate report)
 Change Management & Delivery: Redesign of health services to
provide integrated primary and hospital care with services
provided in the most suitable location: in hospital, in the
community or at home. Six project areas are Planned Care,
Unscheduled Care, Diagnostics, Children’s Services, Long Term
Conditions and Practice Based Commissioning
 NHS National Programme for IT IN Salford (now NHS
Connecting for Health) IN Salford
 An integrated NHS Workforce IN Salford
Progress to Date
 Hope Hospital: Announcement of ‘Preferred Bidder’.
 NHS National Programme for IT: ‘Choose & Book’ is first system to
be implemented IN Salford (December 2005). This will put patients
in control when arranging an initial outpatient appointment.
 Change Management & Delivery: Six project plans approved (May
2005); Anticoagulation service redesign completed.
 Workforce: new work experience schemes for Salford residents
implemented at Hope Hospital .
 Approval of project plans for 6 project areas, each with 2 year
timetable Spring 2005.
Funding sources
NHS / Salford PCT
Priorities and Milestones
LIFT Centres: see separate report
Redevelopment of Hope Hospital
 Submit full business case
 Consultation with stakeholders
Timescales
Autumn 06
Autumn 05 –
Summer 06
Change Management & Delivery
 Approval of project plans for 6 project areas, each with 2 year
timetable
2005 – 2008
NHS National Programme for IT (NPFIT)
 Local NHS patient information records transfer to new national
system (NHS Care Record Service)
June 2006 (Hope
Hospital)

Electronic prescriptions IN Salford
Risks and barriers


2007
National Programme for IT (NPFIT): implementation delays
with possible knock-on effect for other SHIFT projects
National Programme for IT (NPFIT): affordability and
complexity of programme at national level
48
Communication
Opportunities





Hope Hospital: announcement of Preferred Bidder decision
Hope Hospital: design consultation with staff, public, patients
etc
National Programme for IT: national NHS Choose & Book
campaign
WWW.SHIFTPROGRAMME.CO.UK website
SHIFT programme newsletter published at milestone events
during programme
49
Programme: LIFT
Area Covered
Lead Officer &
Contact Details
Aims/
Objectives/Themes
Progress to Date
Funding sources
Six Health and Social Care Centres across Salford
Alan Westwood, Customer Services and Finance
793 3200
Provision of new community and health buildings
 Charlestown
 Lower Kersal
 Walkden
 Swinton
 Pendleton
 Eccles
 Charlestown scheme completed September 2005 – operational
October 2005.
 Lower Kersal scheme construction commenced October 2005
(planned completion Autumn 2006).
 Planning permission granted for Pendleton, Eccles and Walkden
developments.
 Financial Close planned for Eccles, Pendleton, Walkden schemes,
June-August 2006.
 Proposals for Swinton to be reviewed, with anticipated financial
close in autumn 2006.
PCT / NHS
Priorities and Milestones
Timescales
Spring 2006
 Phase 1C (Eccles, Swinton, Pendleton and Walkden) Planning
approval.
Summer 2006
 Phase 1C financial close
Summer 2006
 All remaining schemes on site.
Risks and barriers
 Slippage and cost increases across the MAST LIFT programmes.
Communication
Opportunities
Opportunities as each scheme reaches financial close, during
construction phase and on completion/opening.
50
Programme: Urban Regeneration Company (URC)
Area Covered
Lead Officer &
Contact Details
Start Date
Aims/
Objectives/Themes
Number of Projects
Expenditure
Central Salford
Cath Inchbold, Head of Service, Regeneration Strategy and Coordination
Ext 3796
2004
End Date
10 – 20 year programme
The URC will actively promote the whole area to the private sector
and radically improve the image and perception of Central Salford.
The key objectives are:

Preparing to develop and market the area

Major infrastructure improvement

Exploiting the economic growth potential

Linking opportunities to local people
Detailed
Key priority
 Vision and regeneration
programme areas
framework under development
to be
 Salford Central station area.
developed
 Chapel Street realignment,
transformation.
 Greengate
 Pendleton
 Irwell Corridor
 BBC Relocation
Annual Target Spend
Profile Spend to
Actual Spend to
2005/06 £
end March 06 £
end March 06 £
Revenue – 879,000
Capital – Under
Discussion
Key Outputs
Annual Output Targets
Actual Output
Priorities and
Milestones
 Bid submitted to the BBC. Response expected June 2006
 Chris Farrow the new URC Chief Executive has now started.
 The URC Board agreed the Central Salford Vision during w/c
15th April.
 2005/06 business plan and budget to be completed June 2006
 Work on key projects e.g Greengate, Central Station area and
Crescent Station, on-going.
 Private sector Board representatives appointed.
 Alignment with HMR Scheme Update achieved
Risks and barriers
Communication
Opportunities
 NWDA/EP funding not on the scale expected.
 Opportunities maximised around consultation on draft Vision and
Regeneration Framework.
51
Area Covered
Citywide
Title
Salford Construction Partnership
Lead Officer
David Timperley, Economic Development Section
Contract Details
0161 745 7844
Start Date
April 2004
End Date
March 2006
Aims/Objectives/Themes
Maximise local benefit through inward investment and
development e.g. HMRF & PFI’s in the city to generate local
employment and training opportunities for local people.
Number of Projects
Salford Construction Partnership
Key Outputs
1. 10 Construction Employers/Partners to sign up to the
Salford Construction Partnership Protocol Agreement
2. Deliver joint offer to provide support with supply of
labour, recruitment, job creation, support & training
 12 construction employers have signed Salford
Construction Partnership Protocol Agreement
 332 Salford residents supported into construction
employment via SCP partners
 158 Salford residents supported into construction
related apprenticeships
 247 Salford residents registered on SCP database/skills
register
 Secured ESF funding to deliver 5 eight week basis
construction skills training via partners from Jan 06
 Secured NRF funding to recruit dedicated team to coordinate the activities of the Salford Construction
Partnership from April 06
Lack of mainstream/continued funding
Priorities and Milestones
Risks and Barriers
Communication Opportunities
Good communication and involvement with agencies and
employers involved in the Salford Construction Partnership
52