Report to Environmental Scrutiny Committee Highway Maintenance / Traffic and Transportation/ Street Lighting Improvement Plan. Progress Update, October 2002. Improving the Condition of Pavements INDICATOR Community Perception Stabilise claims paid out Repairing dangerous roads and pavements within 24 hours 2001/2 BASELINE -39% £2.1m 97% OBJECTIVE R1Target planned maintenance resources to high risk areas R2 Seek Cabinet Agreement to using bitmac as standard except in designated areas R3 Determine designated areas excluded from bitmac policy R4 Improve the Inspection regime R5 Merge the highway client and DLO R6 Establish a consultancy with a Sue.Parkinson/219513082 2002/3 TARGET -39% £2.1m 97% ACTION 2002/3 ACTUAL TO DATE No re-survey yet undertaken On target 98% TIMESCALE POSITION OCTOBER 2002 Analyse GIS Plans for “hot spots” March/April 2002 Achieved Obtain Cabinet view to policy change in principle Produce cabinet report seeking a resolution Seek cabinet approval to designated areas Introduce new computer system incorporating hand held devices Increase Inspector numbers April 2002 Achieved May 2002 Achieved June 2002 Not Achieved. April 2002 Achieved During 2002 Not yet Achieved. Re- define inspector roles Trial various methods of actioning repairs Devise and consult on staffing April 2002 During 2002 Achieved Partly achieved. May 2002 Achieved July 2002. Determine facilities required Design and Construct building Prepare Brief June 2002 December 2002 July 2002 Achieved. Finance confirmed. On target Achieved COMMENTS Further work required to designate specific areas Attempts at recruitment made but no suitable applicants Trials undertaken but not yet reviewed OBJECTIVE construction company to introduce fresh thinking, prior to seeking tenders for an operational partner R7 Introduce a Rapid Repair Service R8 Establish closer liaison with Environmental Services via an Officer Partnership Board R9 Revise Risk Management Process Sue.Parkinson/219513082 ACTION TIMESCALE Advertise for expressions of interest October 2002 Shortlist Seek tenders Evaluate and appoint Carry out further trials Consider implications of trials on Code of Practice Implement/publicise Rapid Repair service Agree Constitution First Meeting January 2003 August 2003 Change claims handling process Implement SBS Improve communication with claims handling agents POSITION OCTOBER 2002 April. May 2002 May/June 2002 Not now considered to be required as firms interviewed during the BVreview Achieved On target On target for October 2002 Achieved Not Yet achieved August 2002 Not yet achieved April 2002 May 2002 Achieved Achieved Ongoing August 2002 Ongoing Progressing Achieved Progressing COMMENTS Accord plc appointed October 2002 The Response Time to Non Urgent Works Orders INDICATOR Non dangerous defects repaired within 2 weeks OBJECTIVE R10 Revise practices 2001/2 BASELINE 65% 2002/3 TARGET 70% ACTION Purchase infra red patching system Staff training on system Launch Operation 2002/3 ACTUAL TO DATE 70% TIMESCALE April 2002 June 2002 July 2002 POSITION OCTOBER 2002 Achieved Achieved Achieved COMMENTS Coverage in Salford Advertiser Results of a A six week review A 58% time and cost saving on repairing a pothole 50mm deep A 17% time and cost saving on a pothole 25mm deep. 14 tonne of dense bitumen used in 26 days. Used to be 118 tonne. 104 tonne less of excavated carriage way to be disposed of, reducing disposal and land fill tax cost 88% of old carriageway surface retained and recycled £30,000 per year has been freed up to fund more improvements Improve clarity of information produced through SBS Consider response implications of the Code of Practice Sue.Parkinson/219513082 April 2002 Achieved July 2002 Achieved Reducing the Number of People Killed or Seriously Injured on Roads INDICATOR 2001 BASELINE Number of KSI’s 110 OBJECTIVE R11 Seek resources through a PSA bid 2002 TARGET <95 ACTION 2002 ACTUAL TO DATE 43 Jan - June 2002 . Was 44 Same period 2001. TIMESCALE Prepare background to bid Present to Cabinet Submit bid February 2002 February 2002 March 2002 POSITION OCTOBER 2002 Achieved Achieved Achieved. COMMENTS Bid was successful The Provision of Customer Information INDICATOR 2001/2 BASELINE Highway Routing information for disabled people OBJECTIVE R12 Improve information for disabled people in conjunction with the Disability Access Forum R13 Improve public communication through the web site R14 Produce alley gating guide No information 2002/3 TARGET Full information ACTION 2002/3 ACTUAL TO DATE No Information TIMESCALE POSITION OCTOBER 2002 Disability Access Forum to identify suitable ways of publicising routes By June 2002 Date Not achieved but work is progressing Post on the web site a schedule of major utility works being carried out within the City May 2002 Achieved Complete consultation on the guide September 2002 On target Reducing Opportunites to Commit Crime Sue.Parkinson/219513082 COMMENTS Trupti Patel ( Traffic Officer) is formulating a joint document with Access Officer Judith Irving. Manchester City Council’s document may be used as a base version INDICATOR 2001/2 BASELINE The number of alley gating projects completed OBJECTIVE R15 Progress further alley gating projects in conjunction with community committees 2 2002/3 TARGET 4 2002/3 ACTUAL TO DATE On target ACTION TIMESCALE Programme of work to be determined in conjunction with partners On going POSITION OCTOBER 2002 Progressing COMMENTS The Highway Maintenance Manager is currently dealing with 2 requests for closures Improving Facilities for Disabled People INDICATOR 2001/2 BASELINE The percentage of pedestrian crossings with facilities for disabled people OBJECTIVE R16 LTP monies to be redirected at this PI 59% Previous definition 2002/3 TARGET 59% Based on previous definition ACTION Procure a survey of work required and phasing options Sue.Parkinson/219513082 2002/3 ACTUAL TO DATE 59% Based on previous definition TIMESCALE April 2003 POSITION OCTOBER 2002 Achieved COMMENTS Ahead of schedule. A phased improvement plan will shortly be developed. Improving Ease of Use of Footpaths INDICATOR 2001/2 BASELINE Percentage of footpaths easy to use 50% OBJECTIVE R17 That measures are taken to improve this PI 2002/3 TARGET 65% ACTION 2002/3 ACTUAL TO DATE On target TIMESCALE Ordering of new footpath signs Commence installation March 2002 June 2002 POSITION OCTOBER 2002 Achieved Installation progressing COMMENTS Approximately 10 of 40 signposts installed so far Improving the Condition of Street Lighting Columns INDICATOR 2001/2 BASELINE The percentage street lighting columns in need of urgent replacement 10% OBJECTIVE R18 Produce a business case for funding 2002/3 TARGET 11% ACTION 2002/3 ACTUAL TO DATE Est 11% TIMESCALE POSITION OCTOBER 2002 Survey street lighting stock June 2002 Partially Achieve Consult with Unison April 2002 Achieved Sue.Parkinson/219513082 COMMENTS Will now be a part of the PFI work Improving the Management of the Service INDICATOR 2001/2 BASELINE Improve quality of Highway Information Records Degree of compliance with Code of Practice for Highway Maintenance OBJECTIVE R20 Improve Highway records R21 Further progress position against the Highway Maintenance Code of Practice 2002/3 TARGET 2002/3 ACTUAL TO DATE Satisfactory Move towards Good On target for long term objective 55% full 27% partial 18% none 58% full 30% partial 12%none On target ACTION TIMESCALE RESPONSIBLE OFFICER POSITION OCTOBER 2002 Complete National Street gazetteer level June 2002 Achieved Carry out study of existing record systems compatibility with SBS Further progress the implementation of the SBS system Further progress April 2002 and ongoing On target Sue.Parkinson/219513082 On target ongoing Progressing COMMENTS Increasing the level of Investment in the Highway INDICATOR 2001/2 BASELINE Increase baseline expenditure Maintain levels of capital investment Obtain capital investment from external partnership OBJECTIVE R22 Ensure joint working with Regeneration Teams R23 Director of Corporate Services to instigate a process that models the SSA allocation to verify it R24 Explore long term Strategic partnership arrangements 2002/3 TARGET 2002/3 ACTUAL TO DATE 100% 100% 100% 100% 100% 100% Nil Nil Nil ACTION TIMESCALE POSITION OCTOBER 2002 Seek clarification of the bidding process Put forward ideas to include in bids May 2002 June 2002 onwards Achieved Progressing Review process with Director of Corporate Services May 2002 Achieved Consultation, brief preparations etc. September 2002 On target Advertise for expression s of interest October 2002 On target Sue.Parkinson/219513082 COMMENTS Awaiting City Council decision about size and scoping. Working group is set up. An advertisement seeking private sector proposals for partnership models is due to be placed at end October 2002