Cell Layout and Performance Term Project Modeling Analysis of Manufacturing Systems Bryan Baker April 12, 2001 1 Description The term project report that I am proposing is to analyze the performance of a manufacturing cell in the Pratt & Whitney Turbine Module Center. Since the cell is moving to East Hartford, the opportunity is available to change the layout in order to maximize performance. Its previous layout was more geared toward cellular manufacturing, however some performance was lacking due to some dated equipment. The analysis will include verification of layout type best suited for the desired throughput of product in order to meet customer demand. Some of the different types of layouts that can be focused on include Product Layout, Process Layout, and cellular layout, or Group Technology. Characteristic Product Process Group Throughput time Low High Low WIP Low High Low Skill Level Choice High Med-High Product Flexibility Low High Med-High Machine Utilization High Med-Low Med-High Worker Utilization High High High Unit Production Cost Low High Low To simplify the problem and the model significantly, only three of the higher volume parts that are manufactured by the cell will be looked at to determine optimal layout and cell efficiency. Buffer location Major issues in design of cells comes about is the allocation of function and products to cells, this in turn actually determines the overall structure of the cell. Which determines which cells will be connected by flows of parts and products. 3 Theoretical Modeling Cell Unit A - Grinding Dept Operation (min) Blade1 (52L472) Blade2 (53L822) Blade3 (54L422) Wt. Average 15.000 2.000 3.000 15.000 2.000 3.000 15.000 2.000 3.000 3.800 3.890 3.890 3.890 3.800 3.890 3.890 3.800 3.810 3.890 3.890 3.830 3.500 3.500 3.500 3.500 3.500 3.467 1.380 1.380 1.380 1.600 1.800 1.733 2.000 1.380 1.200 1.350 2.000 1.380 1.200 1.400 Cycle time 2.000 1.380 1.200 1.417 51.497 3.000 3.000 3.000 3.000 7.651 7.320 0.000 9.437 2.000 2.000 2.000 2.000 0.780 0.780 0.000 0.520 0.870 0.000 0.000 0.290 Cycle time 15.247 2754-A WIRE EDM"V" NOTCHES 15.000 2754-A CMM INSPECT EDM NOTCHES 2.000 2754-A FILL TURBINE BLADE WITH 3.000 POLYETHYLE 2754-A GRIND ROOT FACES 3.830 2754-A GRIND MATE FACES 3.890 2754-A GRIND CC & CV ROOT SERRATION 3.890 2754-A GRIND BOTTOM OF ROOT AND 3.800 AIRFOIL T 2754-A GRIND SEALS 3.500 2754-A Forced air to remove excess coolant 3.400 (DRY) 2754-A BUFF EDGES OF ROOT SERRATIONS 1.380 AND 2754-A IN-LINE INSPECTION OF MACHINED 1.800 FEA 2754-A BAKE TO REMOVE POLY FILL 2.000 2754-A BREAK EDGES, ROOT BOTTOM 1.380 2754-A INSPECT & MARK , 1.200 2754-A INSPECTION CODE 5 1.500 Cell Unit C – Hole Drilling 2754-C FILL TURBINE BLADE WITH POLYETHYLE 2754-C LASER DRILL (63) AIRFOIL HOLES PER 2754-C BAKE TO REMOVE BACKING MATERIAL F 2754-C AIRFLOW LASER DRILLED HOLES PER PO 2754-C REMOVE RAISED EDGES FROM LASER DRI Cell Unit D - Finishing 2754-D PRECIPITATION HEAT TREAT PER PWA 1 2754-D REMOVE OXIDE ON END OF ROOT 2754-D SHOT PEEN BLADE ROOT PER NMOP-0016 2754-D X-RAY BLADE 2754-D WELD COVER TO BLADE PER SPEC. PWA 2754-D WATERFLOW BLADE FOR OBSTRUCTIONS 2754-D AIRFLOW ALL AIRFOIL HOLES 2754-D FINAL INSPECTION 9.910 9.910 9.910 9.910 0.410 0.684 0.410 0.684 0.410 0.684 0.410 0.684 0.880 1.300 0.880 1.300 0.880 1.300 0.880 1.300 0.590 0.590 0.590 0.590 0.780 0.800 0.780 0.700 0.780 0.800 Cycle time 0.780 0.767 15.321 To understand how to start assigning machines and product in order to produce an estimate for layout, demand of the product must be known. From this, cycle time, and machine requirements can then be determined. Demands for the particular three blades in review are as follows: Part Blade 1 Blade 2 Blade 3 Avg. Weekly demand 320 230 290 Working time will be estimated at 8 hours per shift,2 shifts per day, 5 days per week, with only 2 fifteen-minute breaks per shift. This gives total available minutes per week of approximately 4500. Calculating cycle time based on the demand yields: c Deviation +/- (10%) 32 23 29 4500 5.011 min 898 Using the average processing time as seen in the first table, the lower bound on number of workstations needed to perform each operation in order to meet the demand can be calculated. The lower bound provided that all the operations could be done on the same machines would simply be calculated as processing time divided by cycle time shown in the table below. Cell Unit A- Grinding C – Hole Drilling D - Finishing Processing time (min) 51.497 15.247 15.3211 Cycle time Lower Bound 15.41 15.41 15.41 10.276 3.0427 3.057 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 WIRE EDM"V" NOTCHES CMM INSPECT EDM NOTCHES FILL TURBINE BLADE WITH POLYETHYLE GRIND ROOT FACES GRIND MATE FACES GRIND CC & CV ROOT SERRATION GRIND BOTTOM OF ROOT AND AIRFOIL T GRIND SEALS Forced air to remove excess coolant (DRY) BUFF EDGES OF ROOT SERRATIONS AND IN-LINE INSPECTION OF MACHINED FEA BAKE TO REMOVE POLY FILL BREAK EDGES, ROOT BOTTOM INSPECT & MARK , INSPECTION CODE 5 FILL TURBINE BLADE WITH POLYETHYLE LASER DRILL (63) AIRFOIL HOLES PER BAKE TO REMOVE BACKING MATERIAL F AIRFLOW LASER DRILLED HOLES PER PO REMOVE RAISED EDGES FROM LASER DRI PRECIPITATION HEAT TREAT PER PWA 1 REMOVE OXIDE ON END OF ROOT SHOT PEEN BLADE ROOT PER NMOP-0016 X-RAY BLADE WELD COVER TO BLADE PER SPEC. PWA WATERFLOW BLADE FOR OBSTRUCTIONS AIRFLOW ALL AIRFOIL HOLES FINAL INSPECTION Machine lower bound Average processing 3 Shifts 2 shifts 1 shift time 15.00 2 3 6 2.00 1 1 1 3.00 1 1 2 3.81 3.89 3.89 3.83 1 1 1 1 1 1 1 1 2 2 2 2 3.50 3.47 1 1 1 1 2 2 1.38 1 1 1 1.73 1 1 1 2.00 1.38 1.20 1.42 48.15 3.00 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 9.44 2 2 4 2.00 1 1 1 0.52 1 1 1 0.29 1 1 1 15.25 9.91 2 2 4 0.41 0.68 1 1 1 1 1 1 0.88 1.30 1 1 1 1 1 1 0.59 1 1 1 0.78 0.77 1 1 1 1 1 1 Assigning operations to workstations then becomes a simple task, since most of the operations can only be run on one piece of equipment. The only operations where multiple machines are needed are operation 1, operation 17, and operation 21. The assignment of parts to these machines becomes pretty simple also, since there are only three parts to go through operation 1, 2 parts to go through operation 17, and all three parts to go through operation 21. The assignment will be as follows: Operation 1 Operation 17 Operation 21 Part 1 EDM 1 Laser 1 PHT 1 Part2 EDM 2 Laser 2 PHT2 Part3 EDM 3 PHT3 4 Simulation Modeling Unit A Unit C Unit D Throughput and machine usage improvements due to buffer locations and cell layout improvement. Throughput – No buffer (part 1,2,3) 248,177,117 132,113 265,196,184 Throughput – With buffers (part 1,2,3) 220,222,220 448,446 445,447,444 Buffer Locations Demand EDM, Polyfill Laser, Polyfill PHT, Polyfill 320,230,290 320,230,290 320,230,290 Machine usage before 50% 23% 65% Machine usage - after 75% 97% 98% 5 Discussion The production cell to produce the demanded quantity of product is still best configured in a cellular type layout. It actually ends up to be more of a combination between Product Layout and Process Layout. The layout may also change a bit if other parts were looked at. The best configuration for the Grinding Unit, however, is the only part of the cell that was still struggling to meet demand. Since the demand was actually targeted lower than the maximum, then it may be possible to use over time to take care of some of these issues. Possibly since there were some issues with blockage of PolyFill, the parts could be done on the machine in the Hole Drilling unit. The travel distance would go up but since travel time was modeled to be relatively high, this may not matter. The Hole Drilling Unit and the Finishing Unit succeeded immensely in improving efficiency simply by strategically adding large buffers to the higher processing time or bottleneck operations. With production levels capable of much more than the demand, it may be wise to scale back in order to more effectively use the equipment. Unfortunately there were many operations which could not be performed on other equipment.