Simulation and Analysis of a Pratt & Whitney Turbine Module Manufacturing Cell Christopher L. Gunther Rensselaer Polytechnic Institute DSES-6620 Simulation Modeling and Analysis Final Presentation 21 December 2000 Hartford, Connecticut Rensselaer Polytechnic Institute Executive Summary • Goal: Simulate Manufacturing Cell #6 – Build a ProModel simulation of the system – Determine the limit production load of the cell – Identify potential areas for improvement • Baseline model with current production level – Verify/validate simulation model – Understand the process and resource utilization • Difficult due to long cycle times, shifts, and operators • Production run results for 7 production levels analyzed – – – – Current three-month requirement of 35 parts correlates well Cell reaches saturation point at around 44 parts/three months More VTL machines can improve throughput (long operation times) More operators needed (manual machine and move time) Rensselaer Polytechnic Institute Current Process Layout Standard Work Sheet Name: Frank Gill, Steve Ali, Shaun Vickers FPI - Op. 1330 Cell 3901 Shot Peen - Op. 1350 Cell 3530 Wash - Op. 1360 Cell 3530 Mark - Op. 1380 Cell 3102 Improved Production Process - 52L002 Business Unit:210 Cell:3106 16 Scope of Operati ons:Turn - 1030 to M ark - 1380 VTL - A VTL - B Op. 1030 Op. 1040 Setup=0.00 Manual=41.08 1 Setup=0.00 Manual=74.02 Date: 08/07/00 Broach Op. 1080 2 Setup=0.00 Manual=68.26 5 B Typhoon Wash VTL - D Op. 1060, 1170 Set up=0 . 0 0 M an ual=9 5 . 19 Set up=0 . 0 0 M an ual=3 3 . 6 8 Op. 1280 15 A 4 VTL - C 10 Setup=0.00 Manual=105.83 3 Op. 1050 Sunstrand 5 Axis Op. 1130, 1200 Setup=0.00 Manual=27.76 Setup=0.00 Manual=30.90 12 Deburr 13 Op. 1090, 1240 6 Balance VTL - E Op. 1250, 1260 1270 14 Pre-Spin process only 8 9 Abrasive Brush Turbo - Op. 1100 Cell 3107 Mark - Op. 1120 Cell 3107 7 Operators Quality Check Grind - Op. 1150 Cell 3107 11 Safety Precaution Standard Work in Process (SWIP) Machine Loss of Control Grind - Op. 1195 Cell 3107 Standard Work in Process Takt Time (minutes) Cycle Time Number of Operators Part travel distanc e in feet 2 2605.7 3037.47 2 0 Rensselaer Polytechnic Institute Machine Capacity by Process - Improved Part Number Department Number / Name 52L002 3106 Part Name Required Daily Output Hub, Turbine Stage 2 Available Time (minutes) 0.4 TAKT Time (minutes) 912 Walk Time Manual Int/Ext Time Manual Internal Time Task # Description Of Task Machine PCS. / Load 1030 Turn VTL-A 1 0.00 1040 Turn VTL-B 1 0.00 265.43 191.41 1050 Turn VTL-C 1060 Turn 1080 1090 52.15 11.07 2605.7 Manual External Time 41.08 Auto Time Cell Change Operator Over Time Number Takt Time (Min) Takt Time (Mean) Takt Time (Max) 73.10 0.00 B 651.43 390.86 333.66 74.02 250.76 0.00 A 651.43 390.86 333.66 1 0.00 438.73 332.90 105.83 494.86 0.00 A VTL-D 1 0.00 284.54 189.35 95.19 380.51 0.00 B Broach Broach 1 3.26 86.26 18.00 68.26 410.14 0.00 A Deburr Bench 1 0.00 36.93 0.00 36.93 0.00 0.00 B 1100 Abrasive Brush CNC Brush 1 0.00 2.00 2.00 0.00 5.00 5.00 2605.71 1563.43 1334.63 1120 Mark Dot-Peen 1 0.00 6.82 0.00 6.82 0.00 0.00 2605.71 1563.43 1334.63 1130 Mill Sundstrand 1 0.00 44.44 16.68 27.76 138.01 0.00 1150 Grind Heald 1 0.00 75.46 33.35 42.11 33.35 0.00 A 2605.71 1563.43 1334.63 651.43 390.86 333.66 651.43 390.86 333.66 2605.71 1563.43 1334.63 2605.71 1563.43 1334.63 2605.71 1563.43 1334.63 1170 Turn VTL-D 1 0.00 59.23 25.55 33.68 25.55 0.00 1195 Grind Pfauter 1 0.00 53.14 33.08 20.06 96.35 0.00 1200 Mill Sundstrand 1 1.48 59.95 29.05 30.90 128.51 0.00 A 2605.71 1563.43 1334.63 1240 Deburr Bench 1 0.00 189.52 0.00 189.52 0.00 0.00 B 2605.71 1563.43 1334.63 1250 Balance Balance 1 0.00 22.09 0.00 22.09 0.00 22.09 B 2605.71 1563.43 1334.63 1260 Balance if necessary Balance 1 0.00 6.57 2.49 4.08 2.49 6.57 B 2605.71 1563.43 1334.63 1270 Balance if necessary Balance 1 0.00 22.48 3.05 19.43 3.06 22.48 B 2605.71 1563.43 1334.63 1280 Wash Proceco 0 0.00 7.43 2.54 4.89 2.54 0.00 B 2605.71 1563.43 1334.63 1330 FPI FPI 0 0.00 0.00 0.00 0.00 0.00 0.00 2605.71 1563.43 1334.63 1350 Shot Peen Shot-Peen 0 0.00 24.63 1.00 23.63 75.75 10.00 2605.71 1563.43 1334.63 1360 Wash Proceco 0 0.00 10.92 5.65 5.27 5.65 0.00 2605.71 1563.43 1334.63 1380 Mark Dot-Peen 0 0.00 6.82 0.00 6.82 0.00 15.12 2605.71 1563.43 1334.63 4.74 1755.54 897.17 858.37 2125.63 81.26 B 2605.71 1563.43 1334.63 2605.71 1563.43 1334.63 2988.74 Cycle Time Created by: Frank Gill (5-15-2000) Rensselaer Polytechnic Institute Determination of Cell Capability P re d ic te d v s . A c tu a l P a rts P ro d u c e d Simulation Parts Produce d 48 43 38 35 33 A v e r a g e Ex its 95% Low 28 9 5 % H ig h 23 18 20 40 60 80 100 P r e d ic t e d P a r t s P r o d u c e d 10 replications 100 replications 3 Month Req't Mean Current Predicted 35 Min Mean Max 21 35 41 50 75 100 Simulation Average Exits Std. Dev. 95% Low 95% High 33.7 7.3 28.48 38.92 19.69 32.09 36.84 42.1 44.39 44.87 4.24 6.32 4.82 4.03 1.77 1.59 18.82 30.8 35.85 41.28 44.03 44.55 20.56 33.38 37.83 42.92 44.75 45.19 Rensselaer Polytechnic Institute Simulation Results M a c h in e % Utiliz a tio n 100 90 VT L A 80 VT L B 70 VT L C B ro a c h D e b u rr 50 A b r a s i ve B r u s h 40 5 - A xi s M i l l G rin d 30 B a la n c e Wash 20 F P I/P e e n /M a r k 10 0 18 23 28 33 38 43 48 E n tity S ta te s - P a rt 5 2 L 0 0 2 S i m u l a ti o n P a r ts P r o d u c e d (3 m o n th s) 90 80 70 60 Pe rce nt, % % Utiliza tion VT L D 60 50 % in M o ve L o g ic % W a it fo r R e s o u rc e 40 % in O p e ra t io n % B lo c k e d 30 20 10 0 18 23 28 33 38 S im u la tio n E x its (3 m o n th s ) 43 48 Rensselaer Polytechnic Institute ProModel Simulation • Manufacturing Cell #6 layout copied • Machines and operations labeled – Operator manual internal and external time – Machine automatic time – Setup time • Uncertainty introduced into the model – 5% normal distributions used on all times – Random operator downtime • Gray boxes are queues with counters • Two operators with idle and downtime locations • Global variable created to count exits • DEMO! Rensselaer Polytechnic Institute