Submission of Working Schedule Specification SP0080302A DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE

advertisement
Submission of Working Schedule
Specification SP0080302A
DISTRICT FIVE CONSTRUCTION
CONTRACT ADMINISTRATION UPDATE
TRAINING
Definitions
2

Calendar Day – Every day shown on the calendar, ending and beginning at midnight

Contract Time – The number of calendar days allowed for completion of the Contract work,
including authorized time extensions.

Precedence Diagram Method (PDM) - A method of constructing a logic network using nodes
to represent the activities and connecting them by lines that show dependencies.

Critical Path Method –A network analysis technique used to predict project duration by
analyzing which sequence of activities (which path) has the least amount of scheduling
flexibility (the least amount of float).

Controlling Item of Work - The activity or work item on the critical path having the least
amount of total float. The controlling item of work will also be referred to as a Critical
Activity.

Delay - Any unanticipated event, action, force or factor which extends the Contractor’s time
of performance of any controlling work item under the Contract. The term “delay” is
intended to cover all such events, actions, forces or factors, whether styled “delay”,
“disruption”, “interference”, “impedance”, “hindrance”, or otherwise, which are beyond the
control of and not caused by the Contractor, or the Contractor’s subcontractors, material
men, suppliers or other agents. This term does not include “extra work”.
Initial CPM Schedule Submittal
 Contract Includes Critical Path Method Schedule Specification?
 Contract has Bonuses or Incentives for Finishing the Project?
 Schedule is in Primavera Project Planner or Suretrak?
 Columns Includes Activity ID, Activity Description, Original Duration,










3
Early Start date, Early Finish Date and Total Float
Schedule Reflects All of the Maintenance of Traffic Plan Phases?
Activities are Broken Out per Phase?
Contract Start and Finish Dates are Correct?
Project Duration is less than or equal to Allowable Contract Time?
Activities Flow in a Logical Order?
Production Rates are Reasonable?
Includes Milestones and Full Scope of Project?
Provides Sufficient Detail to Monitor Contractor’s Work?
Includes Material Procurement and Shop Drawings Submittal and
Reviews?
Accepted Schedule Package has been Scanned?
Initial CPM Schedule Submittal
 Contract Includes Critical Path Method Schedule Specification?
 Contract has Bonuses or Incentives for Finishing the Project?
 Schedule is in Primavera Project Planner or Suretrak?
8-3.2.2
 Columns Includes Activity ID, Activity Description, Original Duration,










4
Early Start date, Early Finish Date and Total Float? 8-3.2.2
Schedule Reflects All of the Maintenance of Traffic Plan Phases? 8-3.2.1
Activities are Broken Out per Phase? 8-3.2.3
Contract Start and Finish Dates are Correct?
Project Duration is less than or equal to Allowable Contract Time?
Activities Flow in a Logical Order?
Production Rates are Reasonable?
Includes Milestones and Full Scope of Project? 8-3.2.3
Provides Sufficient Detail to Monitor Contractor’s Work?
Includes Material Procurement and Shop Drawings Submittal and
Reviews? 8-3.2.1 and 8-2.2.3
Accepted Schedule Package has been Scanned?
5
CPM Schedule Monthly Update
 Still meets Criteria of Initial Submittal Checklist?
 Includes Actual Start and Finish Dates, Added Activities, Changes in





6
Sequence and Days Remaining? 8-3.2.2
Written Narrative addresses Changes from Previous Submittal? 8-3.2.2
Addresses any Agreements, Work Orders or Approved Time
Extensions? 8-3.2.2
Changes in Sequencing had been coordinated with the Contracts
Approved Utility Work Schedules?
If Schedule Indicates an Actual or Potential Delay to the Timely
Completion of The Contract, The Written Narrative Includes a
Discussion of The Problems, Causes, Activities Affected and
Describes The Means and Methods to be Utilized to Complete The
Project Within The Allowable Contract Time?
Does the Contractor’s Schedule show completing The Project within
the Allowable Contract Time? If Not, Negative Float Activities are
addressed in the written Narrative and a Request For Time Extension
is pending or has already been Submitted In Accordance with Spec.
8-7.3.2 ? 8-3.2.2
CPM Schedule Monthly Update Cont.
 Contractor has attended Meetings
Scheduled by the Engineer to resolve any
Problems that may prevent acceptance of
the Schedule? 8-3.2.2
 Is there a need to withhold payment due to
the Contractor’s Failure To Meet The
Requirements for Submittal and
Acceptance of The Updated Schedule? 8-3.2.1
 A Complete Copy of Contractor’s Accepted
Schedule Package (Resident Engineer
Acceptance Letter, Schedule Checklist,
Schedule Printout & Any Backup
Documentation) has been scanned into
FDOT Electronic Document Management
System (Hummingbird) under Job
Correspondence Work Progress
Schedule/CPM
7