Reliable Power Demand Response Working Group AESO ‘As Is’ and Needs Assessment Reliable Markets Reliable People Jerry Mossing Director, Operations Planning Paul Barry Director, Market Services Purpose • Provide information to the Demand Response Work Group (DRWG) that helps the group understand : – what operational situations that may require resources to manage, – What resources are currently available, – How these resources are used, and – Experience to date • Opportunity for the DRWG to ask questions and provide feedback. 2 AESO Operations Concern • There is a strong possibility that sometime in the next several years; – transmission constraints may increase, • Delays in north south, south west, etc. – supply shortfall events may be more frequent, • LTA metrics indicate decreasing supply margin however no trigger action at this time – wind’s fast down-ramps exceeding system ramp up capability. • MOF implementation underway. Approximately 11,000 MW in the queue. – Each of these operating situations: • will be managed using procedures that ultimately end in manual load curtailment procedures. (e.g. OPP 5xx, OPP 801, etc.) • contains a gap between the point where supply runs out and manual (involuntary) load curtailment is necessary. The gap is demand response. 3 AESO Operations • Price responsive loads acting independently have an impact to the energy market – Independent action by a significant amount of load in response to System Marginal Price (SMP) has a direct impact to AIES supply demand balance. – Regulating reserve volumes may mask some of the effect but most often a generator dispatch is required. – System Marginal Price changes with generator dispatch – The cycle may repeat, depending on many factors including volumes and prices in the merit order 4 Current Load Response Operating Situation Supply Shortfall ENMO & ASMO PRL Transmission Constraint (Downstream or Load pocket) Wind Fast Ramp Down High Import LSS Loss of One Generator SUPL Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS Large Loss of Generation (Alberta or in WECC) UFLS UFLS Time 5 Current Load Response Operating Situation Supply Shortfall ENMO & ASMO PRL Transmission Constraint (Downstream or Load pocket) •No requirement to be in the merit order Wind Fast Ramp Down •Independent action by load(s) has a direct impact High Import to the supply/demand balance and will cause Loss of One Generator generator dispatch and SMP will change Large Loss of Generation •E.g. An (Alberta or unintended in WECC) consequence - 50 MW need for supply could result in 300 MW load response LSS Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS UFLS SUPL UFLS Time 6 Current Load Response Operating Situation Supply Shortfall ENMO & ASMO PRL Transmission Constraint (Downstream or Load pocket) processes Wind• Manual Fast Ramp Down involving phone calls and paper. High•Doesn’t Importscale to large number of participants Loss•No of measurable One Generator response other in real time Large•The Loss of Generation program exists but no (Alberta in kW) WECC) MW or (only LSS Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS UFLS SUPL UFLS Time 7 Current Load Response Operating Situation ENMO & ASMO Supply Shortfall PRL Transmission Constraint (Downstream or Load pocket) – emergency Wind• Inter-ties Fast Ramp Down energy agreements • Many steps, not many MW High•LSS, Import DOS are likely price responsive loads Loss•3% of One Generator voltage reduction, pleas, non-essential loads = Largefluff Loss of Generation LSS Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS UFLS SUPL UFLS (Alberta or in WECC) Time 8 Current Load Response Operating Situation ENMO & ASMO Supply Shortfall PRL Transmission Constraint (Downstream or Load pocket) •AESO directs DFO curtailment Windvolume Fastas Ramp Down a percentage of load. •DFO procedures identify load breakers to trip. TFOs carry out the procedures as they have 24/7 control. SCADA required to be effective in 10 minutes. Load curtailments may be rotated between breakers during longer duration events. •The breakers used in these procedures must be coordinated with UFLS (so as to preserve load in some of the UFLS blocks) •This is typically when the terms rotating outages or brown outs are used, even for short duration events. High Import LSS Loss of One Generator SUPL Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS Large Loss of Generation (Alberta or in WECC) UFLS UFLS Time 9 Current Load Response •Under frequency event caused by BC tie line trip during high BC import •Also used when Alberta is Operating Situation ENMO & ASMO islanded •Automatic action, load breakers PRL Supply areShortfall tripped by relay (either UF or tie trip) •Allows operating criteria to be Transmission Constraint met while enabling high BC (Downstream or Load pocket)firm imports though preventing load loss for N-1. loads may be price Wind•LSS Fast Ramp Down responsive. High Import LSS Loss of One Generator SUPL Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS Large Loss of Generation (Alberta or in WECC) UFLS UFLS Time 10 Current Load Response •Safety net for extremely large loss of generation •This is the last automatic action to keep the system up before Operating Situation ENMO & ASMO generators trip to protect their equipment. PRL •WECC requirement Supply Shortfall •The breakers used in these procedures must be coordinated Transmission with manual Constraint load shed (Downstream or Load procedures (so as pocket) to preserve some load in the manual load shed blocks) Wind Fast Ramp Down High Import LSS Loss of One Generator SUPL Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS Large Loss of Generation (Alberta or in WECC) UFLS UFLS Time 11 Current Load Response •Contingency Reserves •WECC requirement •No concurrent use •Technical requirements well Operating Situation ENMO defined, including performance requirement Supply Shortfall & ASMO PRL Transmission Constraint (Downstream or Load pocket) Wind Fast Ramp Down High Import LSS Loss of One Generator SUPL Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS Large Loss of Generation (Alberta or in WECC) UFLS UFLS Time 12 Current Load Response Operating Situation Supply Shortfall ENMO & ASMO PRL Transmission Constraint (Downstream or Load pocket) Wind Fast Ramp Down High Import LSS Procedures Last Resort Involuntary Curtailment VLCP Inter-ties SUPL LSS Fluff DOS Involuntary EOS Trigger DTS Curtailment Involuntary Curtailment ILRAS UFLS •The possibility exists that in the next few years supply shortfall, Loss of One Generator SUPL transmission constraints and wind power ramps will result in more frequent curtailment. Large Loss involuntary of Generation •No reasonable mechanism or program exists to fills this gap. (Alberta or in WECC) •Demand response programs that establish loads who can voluntarily curtail load prior to involuntary curtailments seems a reasonable approach to Time preserve reliability and FEOC? •Can a comprehensive demand response program be implemented in time? When exactly is the need? Whose job is it? UFLS 13 Reliable Power Demand Response Commercial Experience Reliable Markets Reliable People AESO Commercial Experiences • Load Participation – 20MW for supplemental reserves – 120MW for under frequency mitigation – An incremental 100MW expressed interest recently in providing an under frequency mitigation service • Majority of dealings with pulp and paper related customers • AESO yet to contract with a Demand Aggregator • Up to 240MW for ILRAS during supply shortfall events • * VLCP – created by way of EUB Negotiated Settlement in 2000 to balance supply/demand – no longer used • * DOS – alleviates abnormal conditions (* not AESO Commercial dealings) 15 Questions/Comments on Implementation 16 Reliable Power Thank you! Reliable Markets Reliable People