CASE STUDY – Stanly County Deck Girder Bridge Tom Koch, PE - NC DOT, Structure Design Unit Richard Potts, PE - Standard Concrete Products, Georgia Division Mark Foster - Lee Construction Company of the Carolinas Janos Gergely, PhD, PE - UNC Charlotte, Civil Engineering Acknowledgements •FHWA – Innovative Bridge Research and Construction Program •Brian Hanks, NCDOT •Kevin Bailey, STV-Ralph Whitehead •Reid Castrodale, Carolina Stalite •LARSA Inc. Presentation Outline •Design and development (T. Koch) •Deck girder fabrication (R. Potts) •Bridge construction (M. Foster) •Analysis and testing (J. Gergely) Design and development Tom Koch, PE NCDOT, Structure Design Unit Design and development B-3700 Stanley County Precast Deck Bulb Tee 110’ Single Span Design and development PVI= 17+15 El =485.10 L=820’ -1.34% +7.00% Design and development •Deck Bulb tees - Come in standard shapes •Used most extensively in Cold -weather states with a short concrete pouring season (AK, WA, ND, SD, OR) Design and development Project Schedule Original Design •63” MBT’s , skew = 115 degrees •Original Schedule Let Date : May 2005 , to be finished June 2006 •DBT Final Schedule -•Let: May 15 2005 •Availability: June 27, 2005 •Completion: November 1, 2005 (about a 4 month Construction schedule) Design and development Design and development 6’-6 Deck Bulb Tee 32 -- 0.6” Straight strands Original Design: 63” MBT w/ 36 0.6” strands Design and development Design and development Design and development Deck Bulb Tee Features F’c initial = 5500 Psi F’c final(28 day) = 9000 psi Calcium Nitrite Corrosion Inhibitor Concrete mix for girders was required to contain either Fly Ash, Slag or Silica Fume Diaphragms, connector plates, embedded angles were galvanized Final Girder Weight -- about 138 Kips Design and development Costs Compared the cost to 60” Plate gdr. and a 63” MBT for a similar one span bridge, 3600 - 4000 sq ft •Sq. Ft Costs : Plate gdr. = $84.56 63” MBT = Type III DBT = $90.24 $118.48 Line item bid for Gdrs. = $301 K Total Design and development Lessons Learned •Cracks in flanges due to integral abutment detailing -- details will need to be improved if using for integrals •DBT’s are an extremely efficient shape (high Length/Depth) •DBT use is more ideal for crest vertical curves rather than sags •Diamond grind rather than Asphalt overlay •Construction schedule of 4 months could have been easily reduced by at least a month to 6 weeks •To speed acceleration even more, detail more precast elements substructure, rails PRETOPPED TYPE III GIRDER FABRICATION AND ERECTION Richard C. Potts, PE Standard Concrete Products Deck girder fabrication Description Stanley County NCDOT B-3700 SR 1214 Over Long Creek 5 Pre-Topped Type III Girders 107’- 4” Deck girder fabrication Superstructure Typical Section Deck girder fabrication Contract Drawing Beam Detail Deck girder fabrication Bed Modification Deck girder fabrication Decks Form In Position Deck girder fabrication Deck Form Pulled Away Deck girder fabrication Deck Forms/Girder Pallet Deck girder fabrication Type III Tied Deck girder fabrication Type III Cast/ Forms Removed Deck girder fabrication Deck Forms In Place Deck girder fabrication Shear Key Block Outs Deck girder fabrication Deck Steel Bottom Mat Installation Deck girder fabrication Deck Steel Complete Deck girder fabrication Deck Steel/Barrier Rail Steel Deck girder fabrication Embedded Angle Top Flange Connection Deck girder fabrication Poured Deck Deck girder fabrication Deck Forms Removed Deck girder fabrication Girder Cut Out Deck girder fabrication Deck/Girder Joint Deck girder fabrication Girder Lifting Deck girder fabrication Girder Transport Deck girder fabrication Girder Storage Deck girder fabrication End View Deck girder fabrication Camber 1 1/2 hours After Detentioning - 3 1/2” - 4” Deck girder fabrication Deck View Deck girder fabrication Connection Block-out Deck girder fabrication Deck Joint Connection Angle Mating Keyway Deck girder fabrication Pre-topped Type III Span Setup Deck girder fabrication Girder Erection August 18 Erection Began 8:00 AM Girders Were Set In 3.5 Hours With Rain Showers Deck girder fabrication Girder Leveling and Slope Adjustment Girders Are Tilted With Ratchets And Stabilized With Wood Blocking Deck girder fabrication Metal Diaphragms Deck girder fabrication Welded Connection Deck girder fabrication Erection Complete August 18 Time Frame . July 5 : Break Ground (substructure, rip-rap, temporary access bridge) . August 18 : Beams Set Erection Time 3.5 Hours . August 24 : Diaphragms and Shear Keys Complete Bridge Construction •Mark H. Foster, Project Manager •Lee Construction Company of the Carolinas, Inc Charlotte, North Carolina Bridge construction Let: May 17, 2005 Available: June 27, 2005 Complete By: Nov. 1, 2005 Bridge construction Schedule Bridge construction Clearing, Demolition Bridge construction Substructure, Temporary Bridge Bridge construction Girder Erection Bridge construction Girder Erection Bridge construction Diaphragm Installation Bridge construction Girder Erection Bridge construction Shear Key Connection Bridge construction Backwall Formwork Bridge construction Barrier Rail, Approaches Bridge construction Base, Paving, Handrail Bridge construction Ready for Traffic 5 October: final surface. 13 October: pavement markings installed. 26 October: punchlist complete, open for traffic. Analysis and Testing •Janos Gergely, PhD. PE •The University of North Carolina at Charlotte, Civil Engineering Department Analysis and testing Bridge Details 106’-0” BEARING-TO-BEARING SPAN, INTEGRAL END WALL TWO LANE BRIDGE, 30’-0” CLEAR ROADWAY HL-93 DESIGN LOAD Analysis and testing Analytical Study “LARSA 2000 4th DIMENSION FOR BRIDGES” SOFTWARE WAS USED TO ESTIMATE THE FORCES AND STRESSES IN THE CONNECTIONS AND DIAPHRAGMS “ANSYS 10.0” WAS USED TO DEVELOP A MORE REFINED BRIDGE MODEL, WHICH WAS LATER USED IN A PARAMETRIC STUDY Analysis and testing Model Comparison Stress at Midspan (Prestress + Dead) 2.50 2.00 1.50 1.00 0.50 0.00 Displacement Comparison Top of Girder Bottom of Girder LARSA™ 0.1658 2.8005 ANSYS™ 0.1745 2.7890 NCDOT 0.1910 2.7250 *All Values are Com pression Displacement (in.) Stress (ksi) 3.00 3.50 3.00 2.50 2.00 1.50 1.00 0.50 0.00 Deflection Dead ↓ Prestress ↑ Prestress + Dead ↑ LARSA™ 1.302 2.980 1.678 ANSYS™ 1.235 2.915 1.680 NCDOT 1.300 2.889 1.589 Analysis and testing FEA Results - Girders Displacement (in.) 0.1500 Normal Stress (psi) 400.0 300.0 200.0 100.0 0.1000 0.0500 0.0000 0.0 Girder 2 Girder 3 Girder 4 Girder 5 LARSA™ 0.0660 0.0720 0.0620 0.0420 102.0 ANSYS™ 0.1000 0.1190 0.0890 0.0510 80.0 Load Test 0.0900 0.0500 0.0700 0.0500 Girder 1 Girder 2 Girder 3 Girder 4 Girder 5 LARSA™ 143.0 209.0 237.0 203.0 134.0 ANSYS™ 130.0 222.0 294.0 195.0 Load Test 70.0 253.0 270.0 118.0 Analysis and testing FEA Results – Connection Plates 4000 3000 7000 2000 1000 0 Ansys Load Test Path 1 Path 2 Path 4 1960.8 2011.4 2188.7 2964 4060 933.8 Comp. Stress Syy (psi) Tensile Stress Syy (psi) 5000 6000 5000 4000 3000 2000 1000 0 Path 1 Path 2 Path 4 Ansys 4668 4747 4601 Load Test 6307 3602 4744 Analysis and testing Bridge Load Testing Instrument types Instrument Locations Loading Vehicles Test Procedure Testing Types: - Quasi-static - Dynamic Analysis and testing 1E 1W 2E 2W 3E 3W 4E 4W 5E 5W Test Data ASD LRFD Interior Exterior Interior Exterior Interior Exterior 0.52 0.77 0.58 0.60 0.78 0.26 0.73 0.33 0.75 0.37 1.08 1.16 0.70 0.65 0.69 0.47 0.50 0.95 0.48 0.85 0.67 0.65 0.54 0.74 Distribution Factors Analysis and testing Diaphragm Forces Analysis and testing Girder Deformation Analysis and testing Impact Factors DYNAMIC QUASI-STATIC Analysis and testing Connection Evaluation Analysis and testing Connection Evaluation Tension Force 16000 14000 Force (lbs) 12000 Tension #1 10000 Tension #2 8000 Tension #3 6000 Tension #4 4000 2000 0 0 0.2 0.4 0.6 Displacement (in) 0.8 1 Analysis and testing Connection Evaluation 30000 Shear Force Force (lbs) 25000 20000 Shear #1 15000 Shear #2 Shear #3 10000 5000 0 0 0.5 1 Displacement (in) 1.5 CONCLUSIONS ECONOMICAL SHAPE EASE OF FABRICATION RAPID CONSTRUCTION DESIGN ASSUMPTIONS CONFIRMED THROUGH LOAD TESTING: – DISTRIBUTION FACTORS – IMPACT FACTORS – DEFORMATION AND STRESS LEVELS – CONNECTION CAPACITY