12.05.2014 Progress Report

advertisement

MIS3535

Progress Report

Project Team #: Flanagan 2 – Doyle 3

Team Members: PMs: Stephanie Kilroy, Arren Soroko, Sandra Brown, John

Illuminati, Evan Bedor, Melissa Aguilar-Ramirez; BAs: Tyler DiBetta, Trang Nguyen,

Michael Paszkiewicz

Reporting Period From: 11.01.2014 To: 11.07.2014

Overall Project Status:

On Track / At Risk

Deliverables:

Work Completed:

Task Name Date Completed

1.

Project Schedule

2.

Problem Statement

3.

Project Charter

09.10.2014

09.10.2014

09.10.2014

4.

Work Breakdown Structure 09.10.2014

5.

Interview #1 Questions

6.

Risk Management Plan

09.11.2014

09.17.2014

7.

Communications Plan

8.

Quality Management Plan

9.

Change Management Plan

10.

Interview #2 Questions

11.

Scope Document

12.

Interview Questions #3

13.

Project Charter

09.17.2014

09.17.2014

09.17.2014

09.23.2014

09.24.2014

10.06.2014

10.08.2014

Summary Notes

Shows all tasks and resources assigned

Defines the problem to be solved

States that the project exists and has authorization from the PMs to begin work

Organizes the team’s work into manageable sections

Questions were very broad

Identifies risks and how they will be dealt with

Defines communication goals and strategies

Documents the information required to

effectively manage project quality

Tracks any changes made to the project

Questions were more specific

BAs combined individual scopes

Questions were much better

Statement of scope, objectives, and participants in the project

1

MIS3535

14.

Scope Revision

15.

List of Stakeholders

16.

Organization Chart

17.

RACI Chart

18.

Revised Budget

19.

Critical Path

20.

Prototype #1

21.

Use Case

22.

Prototype #2

23.

Persona/Story

24.

Revised RM Plan

25.

Business Rules

26.

Prototype #3

10.08.2014

10.13.2014

10.13.2014

10.13.2014

10.22.2014

10.29.2014

10.29.2014

10.29.2014

11.05.2014

11.05.2014

11.12.2014

11.12.2014

11.12.2014

27.

Data Schema 11.12.2014

28.

Revised Comm. Mgmt. Plan 11.19.2014

29.

Revised Change Mgmt. Plan 11.19.2014

30.

Prototype #4

31.

Prototype #5

11.19.2014

12.03.2014

Revised scope based on professor’s comments and critique.

Lists all of the stakeholders & their roles

Diagram showing structure of team and relationships & links between members

Shows who is Responsible, Accountable,

Consulted, and/or Informed for tasks

An updated version of the budget; still needs to be implemented into Project

Integrated project into MS Project, used to determine critical path

First draft of the Justinmind; focused on front-end rather than back-end

Defines how users can use the prototype

Some front-end changes as well as working on making it functional

Layout of what the presentation will be like, and a persona to have a character in mind for the presentation

The plan is now 1 page and meets all of the requirements

Specifies all of the rules that must be followed for the project

The prototype’s design looks great.

They are still working on the functional aspects and making sure that it meets and professor’s requirements and business rules.

States all of the data masters and attributes for each of them within the prototype.

Meets the requirements for the document. Will make some revisions based on class critique.

Still needs a lot of work to be done on it. Will be further revised based on class critique.

The design looks fantastic. Still some functional issues to work on, but that shouldn’t be an issue.

This is the finished prototype, and it looks excellent and works well.

2

MIS3535

32.

BA Presentation

33.

Finished PM Deliverables

Work in Progress:

1.

Task Name

1.

Work Schedule to begin:

Task Name

12.03.2014

12.05.2014

The presentation went well, and even got praise from Tony Loftus.

We made final revisions to the deliverables that we will include in the

binder.

Planned End Date Resources Assigned

Planned Start Date

Project Issues

Descriptions

1.

None; we are in good shape

Project Risks:

Description

1.

None at this point

Actions

Actions

Meetings

Meetings that have taken place:

Description

1.

Kickoff Meeting #1

2.

Kickoff Meeting #2

3.

Weekly Meeting

4.

Weekly Meeting

5.

Weekly Meeting

6.

Weekly Meeting

7.

Weekly Meeting

8.

Weekly Meeting

9.

Justinmind Help

10.

Weekly Meeting

11.

Weekly Meeting

12.

Weekly Meeting

13.

Weekly Meeting

14.

Presentation Practice

15.

Presentation Practice

Date / Time Attendees

09.08.2014 @ 4pm Sandi, Melissa, Mike, & Trang

09.10.2014 @ 11am Arren, John, Melissa, Mike, & Tyler

09.19.2014 @ 4pm All PMs and BAs

09.26.2014 @ 4pm All PMs and BAs

10.03.2014 @ 4pm All PMs and BAs

10.10.2014 @ 4pm All PMs and BAs

10.20.2014 @ 4pm Arren, Evan, John, Stephanie, & all BAs

10.24.2014 @ 4pm All PMs and BAs

10.27.2014 @ 11am John, Arren, & all BAs

10.31.2014 @ 4pm All PMs and BAs

11.07.2014 @ 4pm All PMs and BAs, except Tyler

11.14.2014 @ 4pm PMs: John, Evan, Stephanie, Melissa;

BAs: Trang, Michael

11.21.2014 @ 4pm All PMs and BAs

12.02.2014 @ 2pm PMs: Sandi, Steph, Evan, John

All BAs

12.03.2014 @ 4pm PMs: Sandi, Steph, Arren, John

All BAs

3

MIS3535

Planned Meetings:

1.

Description Date / Time Attendees

4

Download