Tay Bridge Disaster Group 7.ppt

advertisement

Tay Bridge Disaster

Group 7

Tay Bridge

Completed in February 1878

Designed by Thomas Bouch

The Span was 2 miles(3,264 meters )

Longest spanning bridge in the world at time of completion

Took six years to build

Cost in excess of £300,000

Collapse

In 1879 there was a great storm with gale force winds topping 70mph

The Tay Bridge collapsed in the gale

A train was crossing the bridge at the time resulting in death of 75 people

Mode Of Collapse

Mode Of Collapse

Mode Of Collapse

Mode Of Collapse

Mode Of Collapse

Aftermath

An inquiry team was set up

They delivered their report in six months

Inquiry Report

The supervision of the bridge after its completion was unsatisfactory

Trains were frequently run through the high girder at much higher speeds than at the recommended rate of 25 mph

Inquiry Report

The fall of the bridge was probably due to the giving way of the crossbracing and its fastenings

The imperfections in the columns might also have contributed to the same result

The report blamed Bouch for the collapse

Other Theories

The train could have come off the rails assisting the bridge to collapse

Dynamic effects and fatigue could have been a contributory factor although they are weakly supported by evidence

Conclusion

From this information it appears the bridge collapse was due to the fact the cross-bracing wasn’t strong enough to resist the lateral loads from the gale force winds

Lessons Learnt

Bouch’s bridges were examined and reinforced

Designs using cast iron was barred

Steel was approved for future use in bridge design

A Royal commission on wind pressure on railway structures was set up in 1881

References

 http://www.open2.net/forensic_engi neering www.bradford.ac.uk/acad/civeng/ marketing/ civeng/failtay1.htm

Download