The Bridge ► The Quebec Bridge collapsed on the 29th of August 1907. ► It was to span 550m across the St Laurence River. ► The bridge was designed as a cantilever bridge. ► Difficulties were noted in riveting the bottom chord splices, due to deformation of the faced ends of the middle ribs. The Bridge ► These deformations were ignored and construction continued. ► The central, suspended span began to be constructed in July. ► Early August the end details of the lower compression chords began to show signs of buckling. The Bridge ► 6th August: two of the lower chords of the south arm cantilever were bent ► 12th August: the splice between two lower chords was also bent. ► 27th august:A chord of the south anchor arm, which had showed a deflection of 1.5cm only a week before, showed a deflection of 5cm. ► On the 29th of August two of the compression chords on the south anchor arm suddenly failed. ► This failure spread through the south anchor of the bridge and eventually to the partially constructed central span ► Within 15 minutes the entire superstructure had collapsed into the river beneath Design of Bridge ► The design of the bridge was quite a difficult one due its location. ► As the St Laurence was a shipping lane the Quebec Bridge required a single span of approx. 500m and height above the river of 45m Design of Bridge ► Along with a 22m width required to accommodate railway tracks, streetcar tracks and two roadways led to a particularly large and heavy central span. ► In the case of any cantilever bridge the weight of the central span is key to the design. ► Steel plate cylinders were to be used as the main compression members. These were to be prefabricated off site. Technical Factors in the Collapse ► Cooper (Chief Engineer), recommended that the span be increased to 550m. ► This was to speed up construction and prevent piers being subject to heavy ice flows during winter ► The main factor responsible for the failure was an incorrect initial calculation of the weight of the bridge ► Construction was started assuming the initial estimated weights were correct. Technical Factors in the Collapse ► The bridges actual weight was almost 3 million kilograms greater than the design value. ► It was decided that this excess weight was catered for in the safety tolerances. ► During the construction phase inadequate riveting of some of the bridges key weight bearing lower chord members in the south anchor left some key elements unstable. ► This was at least partially due to lack of understanding of the instability of latticed compress ional members during construction, i.e. asymmetries during construction lead to increased likelihood of failure. ► Finally the lack of action taken when deformations far exceeded expected values was a big contributor to the final disaster Human Factors in the Collapse ► Theodore Cooper, was appointed as chief consulting engineer in 1900. ► He had signalled that the Quebec Bridge would be his final project. ► Pride in this project inhibited the appointment of a second consultant engineer to review technical aspects of the design and in particular the high unit stresses in the bridge members. Human Factors in the Collapse ► The appointment of the Phoenix Bridge Company has been questioned since the disaster. ► Pressure was brought to bear on Theodore Cooper, the consultant engineer, to accept their tender. ► No tests had been done to revise the weights under the new specifications drawn up by Cooper to compensate for the increased bridge length. ► Work went ahead using outdated assumed weights. ► Cooper did not intervene, he accepted the theoretical figures provided by the Phoenix Bridge Company. Human Factors in the Collapse ► Construction went ahead using proposal drawings only. These were approximations and the design was as yet incomplete. ► During construction the Chief Consulting Engineer, Cooper, never actually visited the construction sight. ► He instead appointed a recently graduated inexperienced engineer, Norman McLure, to oversee the construction. ► The distances involved made communications slow in emergencies. Lessons Learned ► Key to a successful construction project is ensuring sufficient funds are in place to see the project through. ► If the tenders do not meet the specifications in terms of cost then the project should be reassessed and a revised tender issued. Lessons Learned ► It is extremely important to have a concrete set of design drawings available at the outset of a project. ► The Quebec Bridge Disaster prompted research into the understanding of latticed compression members in a major bridge structure, as there was little understanding beforehand ► It is important to have more than one means of checking design drawings and construction details. ► The design principles of smaller scale bridges cannot be applied to larger scale bridges ► It exposed the importance of the Chief Consulting Engineer being present on site.