Senior Sophister: Structures Project ACADEMIC YEAR 2006- 2007 THE HYATT REGENCY WALKWAY COLLAPSE Group No.3 Group No. 3 : John Duffin John Deenihan Claire O Farrell Declan Farrell Lecturer : Dr. D. Dwyer Date : 25th October, 2006 Hyatt Regency Walkway Collapse 1 The Hyatt Regency Walkway Collapse Introduction: In July 1980 the most luxurious and modern hotel in Kansas city was completed and ready for recreational purposes after over four years from conception to completion. The Hyatt Regency complex consisted of three connecting structures, a slim reinforced concrete tower on the northern end containing guests bedrooms and suites, a thirty four meter by forty four meter (34m x 44m) atrium with a steel and artificial grass roof fifteen meters (15m) above ground floor level, the southern end of the complex consisted of a four storey reinforced concrete ‘function block’, containing all essential services. The northern tower had individual access to the function block via three pedestrian bridges suspended from the steel trusses of the atrium roof. The bridge on the second floor (west side of the atrium) was connected to the bridge on the forth floor by a system of thirty two millimetre (32mm) steel hanger rods at nine meter (9m) centres. The hanger rods were originally supposed to span directly from the steel truss roof down through both the fourth and second floor bridges, suspending them using a single bolt on either side of the box beam (as is evident in fig.1). Thus the hanger rods suspended from the steel truss would support the weights of both bridges, while the box beams would support the loads applied on that individual walkway. On the eastern side of the atrium was an individual bridge serving the third floor, this was supported in an identical manner. The main purpose of the bridges was to enable people to pass between the tower and function block without having to pass through an often busy atrium. Bridge Design: Gillum-Colaco International (GCE) was responsible for the design of all structural engineering components of the building including the walkways. The original design (as visible in fig. 1) was to have the walkway supported by two wide flange beams, one on each side. This was then hung from a box beam. Each box beam was supported by a washer and nut which was threaded onto the supporting rod. This type of connection had virtually no moment so the connection was modelled as a hinge. Fig. 1: Originally Proposed Box Beam Hanger Detail Group No.3 Hyatt Regency Walkway Collapse 2 Havens Ltd, were the contractors who were responsible for the fabrication and erection of the steel truss and supported bridges. Havens manufacturing department proposed a different connection method (fig. 2). This was a double hanger rod connection to the box beam; this enabled the contractor to fit each bridge in position without having to thread the entire hanger rod to fit the washer and nut. Each support rod of the fourth floor walkway was attached to the atriums cross beams and suspended by a washer and nut (as shown in fig 2). The two tie rods were fifty millimetres (50mm) and one hundred and fifty millimetres (150mm) respectively from the outer edge of the box beam. Fig. 2: Amended Box Beam Hanger Detail The amended shop drawings were stamped ‘approved’ by the architects and ‘reviewed’ by the structural engineers without recalculating the moments and applied forces of the new connection. The new connection supported the forth floor bridge via shorter hanger rods between the box beam and the truss roof, the second floor was now suspended via a shorter tie rod which passed through the second and fourth floor box beams but was not directly connected to the hanger rod connected to the steel truss. Thus the forth floor box beams had to support the load of two walkways rather than the one originally designed for. The third floor bridge was constructed as originally designed. Failure: At 7:05 p.m. on Friday, July 17, 1981, the atrium was filled with over sixteen hundred people; most were dancing to a tea dance competition when a sharp thunderbolt sound was heard. Sixty three people had concentrated on the southern half of the eastern walkway and were dancing to the rhythm of the music. This vibration caused the fourth floor box beam to split at the welds and the hanger rods pulled free. As the second floor bridge was suspended by the forth floor bridge both collapsed and 114 people were killed with over 200 injured. Extensive testing carried out by E.O. Pfrang and R.M. Marshall determined that the actual dead load of the bridges was 8% higher than originally calculated but even with the 63 people dancing on the bridge this would not have caused the collapse. It was thus evident that the weak element of the structure was the box beams. Tests carried out on replica samples and some actual undamaged samples proved that the ultimate strength of the welds and box beams was less than the applied load (i.e. twice the originally calculated dead load) from the two Group No.3 Hyatt Regency Walkway Collapse 3 suspended floors. This caused the bolt to first bend the lower flange of the beam then pull free from the box beam completely. This process started at midspan of the bridge under the hanger rod and the remaining tie rods were incapable of supporting the additional loads thus the entire structure collapsed. The modification made to the walkway was not only under designed but it also lacked redundancy (i.e. its capability of transferring loads to another structural member in times of local failure, thus preventing major structural failure). Fig. 3: Compared Box Beam Hanger Details Fig. 4: Actual Box Beam After Collapse Responsibilities: The National Bureau of Standards analysed the findings E.O. Pfrang and R.M. Marshall and publish a list of findings, some of which are briefly abbreviated here: The walkways collapsed under substantially less load than was specified by the Kansas City Building Code. The fourth floor box beam connections were the candidates for the initiation of the walkway collapse. All box beam connections both originally designed or actual connections did not meet with the Kansas City Building Code. Neither the quality of workmanship nor quality of material used played a significant role in initiating the collapse. Group No.3 Hyatt Regency Walkway Collapse 4 The National Bureau of Standards determined that the originally designed connections ‘might’ have prevented the collapse, even though they were below Kansas City Building Code standards. The Missouri licensing board and the Missouri Court of Appeals found the fault to be with the structural design engineers because they did not recognise the essential differences between the original and modified connection drawings. No recalculation for amended load takedowns was ever produced, thus the constructed walkway was both uncertified and illegal. The Missouri licensing board claimed that a huge error had been made on behalf of the structural design engineers, because no final review of the design would have allowed them to notice the extra loading on the rods. As a result of these errors all the GCE engineers who signed off on the walkway design lost their engineering licences in the states of Texas and Missouri. GCE also lost the right to be an engineering firm. Conclusions: Engineers are responsible for all aspects of a project which involve their computing and management skills, they have a responsibility to the public and all individuals involved in the project which is in question for both the construction and service life of the structure. All aspects of the design must be carefully designed and calculated to ensure maximum safety and reliability of the works is achieved. No compromise may be made on safety as it endangers civilians who are involved at any stage of the works or service life. In the case of The Hyatt Regency, the associated engineering firm neglected to fulfil their legal duties when they designed a structure (i.e. the walkways) that was not to compliant with the Kansas Building Code, but also when they neglected to notice the major difference in box beam connection proposed. No attempt was made to recalculate the applied loads of the new connections, thus the structural design firm was completely liable for the death of 114 people. References: http://en.wikipedia.org/wiki/Hyatt_Regency_walkway_collapse http://ethics.tamu.edu/ethics/hyatt/hyatt1.htm http://www.answers.com/topic/hyatt-regency-walkway-collapse Why Buildings Fall Down: How Structures Fail, Matthys Levy, Mario Salvadori, Publisher: W. W. Norton & Company; Reprint edition (1994), Pages 221-230. Group 3: John Deenihan John Duffin Claire O Farrell Declan Farrell Group No.3 Hyatt Regency Walkway Collapse 5