Agenda Board of Regents Facilities and Land Management Committee Thursday, June 4, 2009, *3:30 p.m. – 5:00 p.m. Room 109 Butrovich Building University of Alaska Fairbanks Fairbanks, Alaska *Times for meetings are subject to modifications within the June 4-5, 2009 timeframe. Committee Members: Timothy Brady, Committee Chair Carl Marrs, Committee Vice Chair Mary K. Hughes I. Call to Order II. Adoption of Agenda Robert Martin Kirk Wickersham Cynthia Henry, Board Chair MOTION "The Facilities and Land Management Committee adopts the agenda as presented. I. II. III. IV. V. Call to Order Adoption of Agenda Full Board Consent Agenda A. Formal Project Approval for the Toolik Field Station Dining Facility at the University of Alaska Fairbanks B. Schematic Design Approval for the Science Renovation at the University of Alaska Anchorage C. Total Project Cost Increase Approval for the Arctic Health Revitalization Phase 2 at the University of Alaska Fairbanks New Business A. Formal Project Approval for the Kachemak Bay Campus Classroom Building at the University of Alaska Anchorage B. Limited Schematic Design Approval for the Seawolf Sports Arena – Road Upgrade and Site Clearing at the University of Alaska Anchorage Ongoing Issues A. Report on the Utilities Development Plan at the University of Alaska Fairbanks B. Report on the University of Alaska Anchorage Campus Master Plan C. Status Report on University Investments in Capital Facilities, Construction in Progress, and Other Projects D. Update on IT Issues Facilities & Land Management Committee Agenda: Page 1 of 23 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska VI. VII. Future Agenda Items Adjourn This motion is effective June 4, 2009." III. Full Board Consent Agenda A. Formal Project Approval of the Toolik Field Station Dining Facility at the University of Alaska Fairbanks Reference 13 The President recommends that: MOTION “The Facilities and Land Management Committee recommends the Board of Regents approve the combined Formal Project Approval and Schematic Design Approval requests for the University of Alaska Fairbanks Toolik Field Station Dining Facility as presented, and authorizes the university administration to permit NSF to proceed through project completion at no project cost to the university. This motion is effective June 4, 2009.” POLICY CITATION In accordance with Regents’ Policy 05.12.042, Formal Project Approval (FPA) represents approval of the Project including the program justification and need, scope, the Total Project Cost (TPC), and funding plan for the project. It also represents authorization to complete the development of the project through the schematic design, targeting the approved scope and budget, unless otherwise designated by the approval authority. A FPA is required for all projects with an estimated TPC in excess of $2.5 million in order for that project’s inclusion of construction funding to be included in the university’s capital budget request, unless otherwise approved by the Board. The level of approval required shall be based upon TPC as follows: TPC > $4 million will require approval by the Board based on recommendations from the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the F&LMC. TPC > $1 million but ≤ $2 million will require approval by the Chairperson of the F&LMC. Facilities & Land Management Committee Agenda: Page 2 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska TPC ≤ $1 million will require approval by the university’s Chief Finance Officer (CFO) or designee. RATIONALE AND RECOMMENDATION 1. Background The Toolik Field Station is located in the northern foothills of the Brooks Range in northern Alaska on the southeast shore of Toolik Lake, 254 km north of the Arctic Circle adjacent to the Dalton Highway. Toolik Field Station supports 300-400 researchers annually between April through October and more than 100 scientists and students are at Toolik on any given day during midsummer. Toolik Field Station is a unique and valuable center for arctic research because of its history of investment in long-term monitoring of climate, hydrology, biodiversity, and physiological and ecological processes. The land is owned by the Federal Bureau of Land Management and leased to the University of Alaska. All facilities at Toolik Field Station are owned by NSF or UAF. Toolik is operated and administered by the Institute of Arctic Biology at the University of Alaska Fairbanks under a Cooperative Agreement with the National Science Foundation (NSF). The Cooperative Agreement is worth approximately $3M/year. The new facility will be owned by NSF. Toolik Field Station supports year round operations and research and the TFS development plan calls for expanded winter capable operations, laboratories, dormitories, and support facilities within 5 years. 2. Project Scope The highest priority project in the Toolik Development Plan is a new Kitchen and Dining Facility that can serve 160 people in the summer and 60 people during the winter. A conceptual floor plan is attached. The plan accommodates shipping/receiving, food storage, food preparation, restrooms and 575 sf of camp management offices in addition to the dining room. The total area of the facility is approximately 6,000 sf at an estimated total project cost of $4,900,000. The new facility will located adjacent to the existing dining hall. The site is located equidistant from the labs and the dormitories. This will allow scientists reasonable access from where they work and live. The project scope will also include improvements to the water supply and distribution system. The estimated cost of the water system improvements is approximately $400,000. The current water system is not winter capable. Facilities & Land Management Committee Agenda: Page 3 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska It is anticipated that construction will be modular with significant prefabrication done off site to reduce on site labor costs. This will also minimize the disruption of research during the busy summer season. 3. Proposed Cost and Funding Source(s) The NSF has allocated $4.9M from the American Recovery and Reinvestment Act for Toolik facility and infrastructure improvements and $0.4M from other sources for a total of $5.3M. 4. Maintenance and Operating Costs (M&R) UAF performs Operation and maintenance for all facilities at Toolik with funding provided by NSF. UAF and NSF have a cooperative agreement that is currently valued at approximately $3M per year. After construction the new facility will be owned by NSF and they will provide additional funds to UAF for the operation and maintenance. NSF is the primary agency funding research at Toolik and they provide all of the O&M funding, some via the Cooperative Agreement and the remainder from researcher per diem. 5. Consultant(s) Design and construction of the project will be performed by the NSF Arctic Logistics Contractor (CH2M Hill Polar Services) or their subcontractors. UAF Facilities Services will not have a procurement role, but will have a review and monitoring role in the project. 6. Schedule for Completion Design Site Work Construction 7. May 2009-November 2009 August 2009-October 2009 December 2009-October 2010 Action Requested Formal Project Approval and Schematic Design Approval. 8. Supporting Documents (Appendix) Conceptual Floor Plans A one-page budget is normally included, but since NSF is providing all of the funding and project management details of the budget are not available. Facilities & Land Management Committee Agenda: Page 4 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska B. Schematic Design Approval for the Science Renovation at the University of Alaska Anchorage Reference 14 The President recommends that: MOTION “The Facilities and Land Management Committee recommends the Board of Regents approves the Schematic Design request for the University of Alaska Anchorage UAA Science Renovation as presented, and authorizes the University administration to proceed through Construction Document completion not to exceed a Total Project Cost of $11,400,000; and allow for the Phase I demolition and construction work for $3,000,000. This motion is effective June 4, 2009.” POLICY CITATION In accordance with Regents’ Policy 05.12.043, Schematic Design Approval (SDA) represents approval of the location of the facility, its relationship to other facilities, the functional relationship of interior areas, the basic design including construction materials, mechanical, electrical, technology infrastructure, and telecommunications systems, and any other changes to the project since Formal Project Approval. Unless otherwise designated by the approval authority or a Material Change in the project is subsequently identified, SDA also represents approval of the proposed cost of the next phase(s) of the project and authorization to complete the Construction Documents process, to bid and award a contract within the approved budget, and to proceed to completion of project construction. Provided, however, if a Material Change in the project is subsequently identified, such change will be subject to the approval process described below. For the Schematic Design Approval, if there has been no Material Change in the project since the Formal Project Approval, approval levels shall be as follows: TPC > $4 million will require approval by the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the chair of the F&LMC. TPC ≤ $2 million will require approval by the university’s Chief Finance Officer (CFO) or designee. Facilities & Land Management Committee Agenda: Page 5 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska If there has been a Material Change in the project since the Formal Project Approval, the Schematic Design approval levels shall be the same as the Formal Project Approval. RATIONALE AND RECOMMENDATION The existing UAA Science building was originally constructed in 1975. The current programs that are in Science are moving into the new Integrated Science Building in August 2009. Science programs from BMH, and ENG that did not fit into ISB will be moving into Science. The new program will include provide 8 instructional labs, 4 research labs, 27 offices and other support spaces for Physics, Astronomy, Biology, Geology, Life Sciences and Math. BUILDING SITE The existing building is situated along the campus “spine” and connected by walkways to the engineering building toward the west (on the other side of University Drive) and the Parking Garage to the east. Little site development is expected but there will be some minor site modifications required at entries, for utility (electrical service) upgrades, and other minor upgrades to the exterior of the building. EXTERIOR DESIGN OF THE BUILDING This is an existing facility that has a design typical of the 1970’s. The existing building has insulated metal vertical panels with “strip” aluminum windows and is fairly monolithic. The design of the new exterior was primarily focused on a functional upgrade to improve the thermal performance of the exterior building envelope by eliminating window openings where they are either not required for the program, or where program requirements were such that removal of most or all of the existing windows best suits program needs. Removal/replacement of existing windows and infilling areas of exterior wall provides a unique opportunity to improve the appearance of the building, in addition to the functional upgrade. While at complete renovation of the exterior shell of the building is beyond the scope of the project, the new work will significantly improve both the thermal envelope of the building and the aesthetic qualities of it. New building entries on the south, north, and east elevations will be provided with new doors and sidelights, and a new covered canopy provided on the north entry. New building arctic entry vestibules will also be provided at the primary entrance on the north. Some of the exterior panels at the north entry are damaged, so new panels are being provided, which also improve the appearance of the revised entry. The entry design Facilities & Land Management Committee Agenda: Page 6 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska is intended to assist students in “wayfinding” by delineating the building entries, as well as encourage use of the pedestrian walkway “spine” by creating more inviting and visible entries. A new mechanical outside air intake is required. Currently, the air intake is located on the west side of the building under the pedestrian overpass directly adjacent to University Drive, and consequently drawing vehicle exhaust into the building’s mechanical system. The new design proposes a shaft enclosure extending up through the interior of the building and above the roofline; drawing air from above and bringing it down and into the mechanical room, located on the ground level at its current location. This will eliminate the current deficiency of bringing exhaust fumes into the building and will improve the air quality of the building. It also provides an architectural design element that is articulated on the exterior of the building, improving the building appearance. A new exterior entry to the building is being provided on the east side of the building to accommodate field gear storage area serving all of the departments. The articulation of the entry is downplayed because this is not a primary entrance, and we do not want to draw attention to it. PRINCIPAL MATERIALS The primary exterior materials of the exterior of the building will be a combination of re-use of the existing insulated metal panels (mostly on the upper portion of the building), new textured metal insulated metal panels and a proprietary exterior “Swisspearl” Fiber-Reinforced Cementitious Panel System manufactured by Pacific Architectural Products. These materials will be used in a composition that will add visual interest and some variation to the existing monolithic appearance. The general architectural approach for interior construction will be to retain many of the existing interior walls and the existing ceiling suspension grid. The existing ceiling tile and lighting fixtures will be removed and replaced with new tile and lighting. Where necessary for mechanical or electrical work, minor areas of the ceiling grid may be removed and new grid elements installed. Architectural floor finishes will be removed and new finishes provided throughout. Where new walls are required, the new interior wall systems will consist primarily of metal stud assemblies with painted gypsum wallboard finish in most of the office areas, laboratories, and other program areas. Additionally, more highly durable finishes will be used in the common use areas, such as corridors and student gathering areas. Facilities & Land Management Committee Agenda: Page 7 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska New interior door frames will be of aluminum frame construction, to be consistent with some of the newer facilities on campus. Doors will be wood construction with clear wood finish. Where appropriate, interior side lights will be used to share exterior natural light to interior spaces. Where privacy is required, frosted or fritted glass will be used so that both privacy and shared natural light are possible. Interior finishes of program spaces are detailed in the space data sheets included with the building program documents. FUNCTIONAL RELATIONSHIP OF INTERIOR SPACES The building’s existing architecture is based on a modular building layout with a 5’ x 5’ grid throughout the building. This is not uncommon for the time of initial construction, and is similar to other UAA buildings on campus. It makes sense to maintain this module, since there is no technical or program reason for altering it. Therefore, when the program was developed most program elements were designed to fit within a space defined in increments of 5 feet. Fortunately, this provides a very workable building module for the programs that are to fit in the building. The major program elements for the Geology and Physics/Astronomy departments are located on the first floor, along with storage space. The major program elements for Biology and Liberal Studies Integrated Science departments are located on the second floor, along with a Computer Instructional Lab, offices for Math and the aforementioned departments, and other support spaces. The layout also allows for student gathering areas to encourage and facilitate informal learning and study outside of the classroom, and foster a sense of educational community within the facility itself. MAJOR SYSTEMS The existing exterior wall systems consist of insulated metal panels with metal furring on the interior side and gypsum wall board finish. Existing exterior windows are of aluminum frame with 1” insulating glass (2-ply). The windows are arranged as a “band” continuously around the west, south, and east sides of the building. Because of program changes, exterior natural light is not required in all of these spaces. (Natural light is not necessarily desirable in mass quantity in some spaces and explicitly problematic in other spaces.) The physics and astronomy labs in particular are sensitive to light- light is problematic when performing certain lab functions. Reducing the amount of exterior windows to satisfy program requirements also provides the single best opportunity for improving the heat loss performance of the building. Some of the exterior window areas will be removed and infilled with new construction with a higher insulating value. Walls will consist of 6” metal Facilities & Land Management Committee Agenda: Page 8 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska stud framing with R-21 batt insulation within the cavity, and the exterior finish will be a metal panels installed over furring strips with 1 ½” rigid insulation (R-7.5). This additional insulation will improve the energy performance in addition to providing a thermal break for the metals stud. Existing doors and frames are of hollow metal construction and the paint is deteriorating. They will be removed and replaced with new thermally broken aluminum doors and frames. The existing roof is an inverted membrane roof system with concrete pavers. The membrane itself is a built-up asphalt roof system with multiple plies. Destructive testing was not conducted to determine the number of plies. The roof has had some report leaks, but mostly associated with roof penetrations and flashing. The membrane is 30 years old and due for replacement within the next five years. The membrane itself is not in a state of imminent failure, it probably has a few years of life left. However, there are numerous patched areas around the roof, particularly with roof mounted mechanical equipment. These areas are suspect and the mostly likely locations for leaks. Since the roof appears to have some remaining life, the approach will be to retain the existing membrane roof system where possible and simply repair and patch areas where known leaks have occurred. Also, new penetrations will be flashed and areas where any mechanical equipment is removed with be covered with membrane and re-insulated. See additional descriptions of the structural, mechanical, electrical, and hazardous materials systems included within the Schematic Design Narrative. BUILDING CODE REQUIREMENTS The basic building code requirements are as follows: Building Code: Occupancy Classification: Construction Type: Sprinkler system: Corridor Construction: 2006 International Building Code (IBC) B (business, higher education) V-B Combustible, non-rated (Note, building is non-combustible, though not required by code) Not required for B occupancy, but included (Chapter 9). Inclusion of a sprinkler system relaxes other requirements of the code, such as corridor and stair construction and allowable area. Fire-resistive assembly not required, since the building has a sprinkler system. Facilities & Land Management Committee Agenda: Page 9 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska Stair Enclosure: Separation of Occupancy: Fire-resistive assembly not required since the stairs only connect two adjacent floors, and the building has a sprinkler system. No occupancy fire separation assemblies are required since the building’s laboratories do not contain materials in excess of the quantities permitted in B occupancies. BUILDING EFFICIENCY The building on both levels is organized along a double loaded corridor, with program spaces on either side. By most standards, this is considered the most efficient use of space. In particular, it proved to be an appropriate organizational form for the specific program spaces for this facility. The building is approximately 25,000square feet on both levels. Note that there is a difference between this number and the square footage included in the building code analysis. A portion of this building is part of the Campus “spine” system, which connects this facility to the engineering building and the parking garage. The program is based on the area of the building that is actually used for the science department program. The area used in the building code analysis must include the total area. Program spaces (excluding mechanical, electrical, custodial, restrooms, corridors, stairs, and student gathering areas) account for approximately 17,500 square feet. This gives the facility a net to gross ratio of 0.70. Corridor and vertical circulation space accounts for approximately 4,000 square feet (15% of the total building area). CONFORMANCE WITH UAA MASTER PLAN To the extent possible and relevant, the building will comply with the Key Design Guidelines and Standards delineated in the UAA Campus Facilities Master Plan (2004). The building’s placement on site is already defined (existing), but its location and development are generally compliant with the standards. The building is located along the campus spine. This is consistent with the master plan to use the spine as an organizing element of the campus. The building’s entry points will be altered slightly to make them more recognizable and visible to the campus surroundings. The building exterior will be modified using quality materials of known longevity. Roof structure and mechanical equipment will be screened or set back from the roof edge so that they are not visible. The building’s visual appearance will be improved to enhance the quality of the built Facilities & Land Management Committee Agenda: Page 10 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska environment of the campus, a key element of the master plan’s design guidelines. Other technical considerations required by the master plan and addressed in the design include upgrading the structure to current seismic standards and assuring adequate space within the building for HVAC and other equipment. LIFE CYCLE COST/ENERGY MANAGEMENT The primary tool used for analyzing this building’s energy management is the US Green Building Council (USGBC) LEED Program. While the University is not mandated to comply with the USGBC guidelines, it is the best tool to measure the performance of the building based on a national standard. It is a more comprehensive standard than simply addressing a building’s energy efficiency. It addresses environmental responsibility and reducing impact. It focuses on five categories including sustainable site development, water efficiency, energy and atmosphere, materials and resources, and indoor environmental quality. 2. Graphic Description See attached drawings. 3. Proposed Cost and Funding Source(s) FY09 Capital Appropriation Fund #17043-564303 FY09 Capital Appropriation Fund # 17043-564303 FY10 Capital Appropriation Fund # TBD Total Funding for Phase 1 FY11 Capital Appropriation Future Total Funds $1,250,000 $1,064,400 $685,600 $3,000,000 $8,400,000 $11,400,000 In order to fund the design and phase 1 work for the project, funding is coming from REALLOCATION of the following FY09 R&R projects: 1. 2. 3. 4. 5. 6. 7. 8. 9. UAA Roof UAA Fire Panel UAA Gas Extraction UAA HVAC Upgrd UAA EM1&2 Piping UAA Fine Art UAA Roads UAA Recharge Total Allocated $1.9M $300K $800K $700K $1M $1M $500K To SCI Design Phase 1 $ 380,000 $ 30,000 $ 64,400 $ 120,000 $ 105,000 $300,000 $ 200,000 $700,000 $ 200,000 $ 75,000 $ 140,000 ___ __________ $1,250,000 $1,064,400 Facilities & Land Management Committee Agenda: Page 11 of 28 R&R $1,520,000 $ 205,600 $ 680,000 $ 295,000 $ 100,000 $ 800,000 $ 425,000 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska The project will be accomplished in phases. Phase 1 will be the demolition of the interior spaces, and partial replacement of the mechanical and electrical systems and the structural upgrades as funding allows. The building will be left unoccupied until all work is complete. Phase 2 will finish the renovation pending funding. 4. Estimated Total Project Cost See attached budget. 5. Variance Report Cost estimate at Schematic Design exceeded the budget and selected items were reduced in scope: toilets are not being remodeled, existing roof is in good shape and not being replaced, exterior upgrades has been reduced, window replacement was deleted, electrical service will remain but with a new automatic transfer switch, fire sprinkler will be reused and existing plumbing will be reused. There will be a new elevator, new fire alarm system, new DDC controls, new air handling unit and exhaust fans, new light fixtures. The schedule has moved out due to getting Board of Regents Approvals; occupancy was scheduled for Aug 2010. 6. Schedule for Completion Schematic Design Board of Regents Approval of Schematic Design Design Bidding and Award Construction Ph 1 9 months Construction Ph II Nov 08-Apr 09 June 4, 2009 Jun 2009-Oct 2009 Oct 2009-Dec 2009 Dec 2010- Oct 2010 Jun 2010-July 2011 Schedule is dependent on full funding 7. Affirmation Preliminary Administrative Approval was approved on 11/8/08. Formal Project Approval was approved at April 9, 2009 BOR meeting 8. Action Requested Schematic Design Approval by the Chair of the Facilities and Land Management Committee. Facilities & Land Management Committee Agenda: Page 12 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska C. Total Project Cost Increase Approval for the Arctic Health Revitalization Phase 2 at the University of Alaska Fairbanks Reference 15 The President recommends that: MOTION “The Facilities and Land Management Committee recommends that the Board of Regents approve the Total Project Cost Increase request for the University of Alaska Fairbanks Arctic Health Lab Revitalization Phase 2 as presented, and authorizes the university administration to proceed through Construction Document completion and construction not to exceed a Total Project Cost of $12,140,000, contingent upon receipt of additional funding. This motion is effective June 4, 2009.” POLICY CITATION In accordance with Regents’ Policy 05.12.043, Schematic Design Approval (SDA) represents approval of the location of the facility, its relationship to other facilities, the functional relationship of interior areas, the basic design including construction materials, mechanical, electrical, technology infrastructure, and telecommunications systems, and any other changes to the project since Formal Project Approval. Unless otherwise designated by the approval authority or a Material Change in the project is subsequently identified, SDA also represents approval of the proposed cost of the next phase(s) of the project and authorization to complete the Construction Documents process, to bid and award a contract within the approved budget, and to proceed to completion of project construction. Provided, however, if a Material Change in the project is subsequently identified, such change will be subject to the approval process described below. For the Total Project Cost Increase Approval, if there has been no Material Change in the project since the Formal Project Approval, approval levels shall be as follows: TPC>$1 million will require approval by the Board of Regents TPC > $.4 million will require approval by the Facilities and Land Management Committee (F&LMC). TPC > $.2 million but ≤ $4 million will require approval by the Chairperson of the F&LMC. TPC ≤ $.2 million will require approval by the university’s Chief Finance Officer (CFO) or designee. Facilities & Land Management Committee Agenda: Page 13 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska RATIONALE AND RECOMMENDATION 1. Narrative Description HISTORY: Constructed in 1968, the Animal Quarters Wing of the Arctic Health Research Building (AHRB) was built by the federal government to house small and large animals for experiments being performed in other areas of the building. The area currently consists of approximately 15,000 gross square feet of laboratory, small animal holding pens, surgery suites, and storage rooms on three floors. In early 2008, UAF reprogrammed the space based on three new user groups occupying the vacated area: Institute of Arctic Biology Infectious Disease Studies, Fisheries Teaching and Research, and the School of Natural Resources Horticulture Program. Revitalization of the wing will allow four new principal investigators to perform modern research and will also construct two much needed 15-20 student class labs for fisheries and horticulture. The scope of work will address deferred maintenance items, code corrections, and non-deferred maintenance items in the 40-plus year old facility. Deferred maintenance and code corrections items include the complete replacement of heating, ventilation and cooling systems, replacement of laboratory casework and fume hoods, upgrades and replacement of the electrical system, replacing worn floor and wall finishes, and replacement of existing ceiling systems to include lighting. Code violations, cited by the Fire Marshal, include improper lab to corridor wall separations, lack of a fire suppression system, un-braced ceiling systems, non-fire rated cabling above the ceiling, inadequate emergency lighting, and improper chemical storage in labs. Work will include a new wet pipe sprinkler system, upgrades to the fire alarm system in this area, and installation of a new emergency power supply that can operate lights during a power outage. Programmatically, the existing specialized and chopped up floor plan will be demolished and rebuilt with a new layout that is more efficient for the planned user groups yet flexible enough to accommodate different users in the future. On the second floor, two large infectious disease biology labs used for the main research activities will be clustered together with smaller support labs for activities such as tissue cultures and microscopy. On the first floor, two teaching labs will be built for fisheries and horticulture and will also be supported by smaller preparation labs. ADDITIONAL INFORMATION: In 2005, UAF developed a long range R&R plan for the Arctic Health Research Building. The plan indicated Facilities & Land Management Committee Agenda: Page 14 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska that complete renovation of the facility would be 35-40% less than similar new construction, therefore was more beneficial from a capital construction cost perspective. In 2007, the first phase of the revitalization plan was approved by the Board of Regents and constructed over the next year. For Fiscal Year 2009, UAF requested $18.5M to revitalize the next area of the building, commonly called the Animal Wing. The work was to include major building electrical and heat infrastructure upgrades in support of the Animal Wing work and future phases of revitalization. UAF only received $9.0M of the FY09 request for AHRB, meaning work scope was cut from the project. During concept and schematic design, the consulting team (Bezek Durst Seiser) provided an estimate for renovations solely within the Animal Wing. These early estimates demonstrated that UAF could accomplish a major renewal in the wing based on the funding at hand. (Reference December 1, 2008 Schematic Design Approval). In January 2009, UAF received a cost estimate based on 35% design documents that was much higher than the original estimate. UAF identified several scopes of work that were either not immediately required in this phase or could be bid as alternates in order to bring the project within current funding. In late March, UAF issued a preconstruction services contract to the general contracting firm Ghemm Company, based on a CM@Risk Selection Process. Once on board, the contractor provided valuable information on cost of construction, design review issues, and scheduling. UAF, the consultant, and the contractor held a budget reconciliation workshop to resolve budget issues and price out alternates that would allow the project to move forward. At the end of the work shop, and through refinement of the estimate, the project construction estimate had been reduced to a more attainable, yet still partially unfunded level. Overall, nine (9) additive alternates were developed by UAF since 35% design was completed. The alternates include all of the casework, finishes, and trim for multiple rooms that support agricultural science teaching and research programs (SNRAS). Other alternates identified would provide the casework, finishes and trim in multiple small labs for the School of Fisheries and Ocean Sciences (SFOS) and one large lab for the Institute of Arctic Biology (IAB). Freezer farm power and ventilation were also separated as alternates. New electrical service to the building and a new driveway to the proposed head house room are designed, but may be eliminated from the scope of work. The alternates will be awarded on a priority basis with completion of lab space for IAB and SFOS being Facilities & Land Management Committee Agenda: Page 15 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska the highest priority, then labs for SNRAS, and finally the new building electrical feed and driveway. CURRENT CONSTRUCTION COST: Current construction costs for major institutional facilities range from $360 to $500 per square foot for renovation. UAF reviewed projects such as the FMH ER Expansion, AHRB East Wing Revitalization, Fairbanks International Airport (expansion and renovation) and has determined its current project cost estimates appear to be reasonable for the type of work being performed. Fairbanks has yet to see the major drop in construction cost that has been seen in other parts of the state and Lower 48, mostly because fuel and material prices are still high, labor for some trades is still in high demand, and large commercial work in some sectors, including military, remains unfinished. 2. Graphic Description See Supporting Documents Appendix A for a revised graphic description of the project. 3. Proposed Cost and Funding Source(s) Current Funding (previously approved) FY08 UA Revenue Bond (Approved by BOR June 2007) FY09 SB211 State of Alaska Capital Appropriation Previously Approved: $540,000 $9,000,00 $9,540,000 Current Proposed Funding FY10 State of Alaska Capital Appropriation FY09 UAF M&R Funds FY09 University Receipts $1,007,000 $438,000 $250,000 Potential Future Funding FY10 University Receipts Total Project Cost Increase: TOTAL: $905,000 $2,600,000 $12,140,000 Current Proposed Funding: The FY10 State of Alaska Capital Appropriation authorized by the legislature will provide $2.007M for UAF Renewal and Renovation projects. UAF’s Arctic Health Research Building Deferred Renewal project was a priority project in the University’s FY09 capital request and was also included in the FY10 request. The distribution of the FY10 appropriation is planned to be split between Waste Line Repairs ($1.0M) and the Arctic Health Lab Revitalization Phase 2 ($1.007M). Facilities & Land Management Committee Agenda: Page 16 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska FY09 Maintenance and Repair funds ($438K) would be used to make heating line repairs and the campus would also allocate some FY09 University Receipts ($250K) to accomplish department priorities. By reallocating these funds, the Arctic Health project will provide a positive impact to the research and teaching capacity of three large programs at UAF: School of Fisheries and Ocean Sciences, School of Natural Resources and Agricultural Sciences, and Institute of Arctic Biology. Potential Future Funding: As part of this project, UAF is also requesting approval to award up to an additional $905,000 to complete the remaining alternates for this project, if funding can be secured through university receipts such as departmental, grants, or federal stimulus funding. 4. Variance Report The design documents for the project are 95% complete and UAF has selected a Construction Manager at Risk to provide pre-construction and possibly construction services. The Board of Regents gave approval to design in June 2008 and approval to construct in December 2008. The consultants estimates, which established the budgets for the June and December 2008 board approvals were inaccurate, as shown by their more recent 35% and 65% design estimates. UAF is seeking a total project cost increase of up to $2.6M to allow the entire project to be completed if full funding is secured. The project is critical to the strategic goal of increasing research space because it takes vacated space and converts it to highly modernized labs for multiple programs and initiatives. UAF has reduced the base bid scope of work and developed multiple alternates in an attempt to complete the project within current funds on hand. The current Base Bid work needs an additional $1,145,000 to allow a construction contract to be awarded. To award the alternates, an additional $1,455,000 is required. As stated above, UAF will allocate $1.007M of FY10 State of Alaska Capital funds to the project. In addition to the state funding allocation, the campus is allocating additional funds ($688,000) to offset the total project cost shortfall and “buy back” some of the key alternates for the Institute of Arctic Biology and School of Fisheries and Ocean Sciences that are needed to increase academic and research capacity in the building. With this approval, if additional funding is secured, the other alternates would be awarded in priority order (up to a maximum of $905,000). 5. Schedule for Completion Construction Documents: Construction Begins: Facilities & Land Management Committee Agenda: Page 17 of 28 June 1, 2009 June 15, 2009 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska Construction Complete: June 2010 6. Affirmation Prior approvals are listed in the Board of Regents meeting minutes on the following dates: Formal Project Approval: Schematic Design Approval: June 2008 December 2008 7. Action Requested Total Project Cost Increase, for the Arctic Health Lab Revitalization Phase 2 project, from the original amount of $9,540,000 to a total project cost of $12,140,000, an increase of $2,600,000. 8. IV. Supporting Documents One Page Budget Floor Plan Layout New Business A. Formal Project Approval for the Kachemak Bay Campus Classroom Building at the University of Alaska Anchorage Reference 16 The President recommends that: MOTION “The Facilities and Land Management Committee approves the Formal Project Approval request for the University of Alaska Anchorage Kachemak Bay Campus Classroom Building as presented, and authorizes the university administration to proceed through schematic design (SD) not to exceed a Total Project Cost of $2,700,000. This motion is effective June 4, 2009.” POLICY CITATION In accordance with Regents’ Policy 05.12.042, Formal Project Approval (FPA) represents approval of the Project including the program justification and need, scope, the Total Project Cost (TPC), and funding plan for the project. It also represents authorization to complete the development of the project through the schematic design, targeting the approved scope and budget, unless otherwise designated by the approval authority. A FPA is required for all projects with an estimated TPC in excess of $2.5 million in order for that project’s inclusion of construction funding to be included in the university’s capital budget request, unless otherwise Facilities & Land Management Committee Agenda: Page 18 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska approved by the Board. The level of approval required shall be based upon TPC as follows: TPC > $4 million will require approval by the Board based on recommendations from the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the F&LMC. TPC > $1 million but ≤ $2 million will require approval by the Chairperson of the F&LMC. TPC ≤ $1 million will require approval by the university’s Chief Finance Officer (CFO) or designee. RATIONALE AND RECOMMENDATION 1. Background UA was allocated $2.5 million in FY08 by the legislature to acquire and renovate Homer City Hall, the intent was that UA (for KBC) would acquire city hall and renovate it with the FY08 appropriated funding. KBC would vacate leased space at West Campus and move into City Hall. However, Homer city residents voted down a bond issue in Feb. 2008 preventing the City of Homer from acquiring needed capital to build a new City Hall. In order to move forward in consolidating the campus and utilizing the already allocated funds, is this project is for a separate building located at the KBC East Campus. KBC is currently physically split between two campus locations in downtown Homer separated by approximately two miles. The FY08 $2.5M would have enabled the consolidation of all faculty offices, classrooms and instruction on one campus. Currently the West Campus building is leased on a year-to-year basis from the City of Homer for $56,000 annually. West Campus is costly to operate. The city which leases it to UA has indicated that they may no longer support any further repairs to the building. The new facility will be located on the southern portion of the KBC property. The site plan for the main campus was developed during the 2008 KBC master planning study. Failure of the procurement of “Homer City Hall” necessitates development of additional square footage on University owned property to replace the West Campus space. In order to use the $2.5 million in FY08 funds for this new project, legislative authority was requested to reallocate the funds to support this construction. Facilities & Land Management Committee Agenda: Page 19 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska 2. Project Scope Project scope is to provide a 6,800 sf two story building, with classrooms and offices as shown in attached space summary, floor plan and site plan. The building will be designed so that it could be built in modules offsite and delivered to the project in order to bring cost per sf down as the funding for this project is limited. The attached drawing is a concept only and will be developed further during schematic design. The warehouse space (called exterior storage on the plan) will be deleted from the scope and this space will be used for 3 additional offices, copy/supply room and additional space for the learning resource center while staying within the budget. The West Campus has 9 faculty offices and the concept plan showed only 6 faculty offices. The stairs will be brought in close to the building and we plan on having a bid alternate of adding a small amount of additional spaces which will be identified at schematic design. An Architect will be selected by a Request for Proposal and if performance is acceptable they will continue with the project design when Formal Project Approval is given. 3. Proposed Cost and Funding Source(s) This should describe the cost and funding source(s) for the next phase of the project and for eventual completion of the project: FY08 Capital Appropriation Fund 107043-564275 FY 08/09 KPC Operating Fund 106210-22714 $2,500,000 $200,000 $2,700,000 4. Estimated Total Project Cost See attached budget. 5. Maintenance and Operating Costs (M&R) Cost to operate the new building is estimated at $4/sf = $27,200 annually. Maintenance costs are estimated at 1.5% of construction cost ($1,900.000)= $28,500 The Kachemak Bay Campus will use the funds that they presently use to lease the West Campus from the City of Homer, $50,000 per year, to pay for operating and maintenance costs on the new facility so that there will be no increase to the Campus operating budget for this project. Facilities & Land Management Committee Agenda: Page 20 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska 6. Consultant(s) McCool Carlson Green has produced the concept design. 7. Other Cost Considerations None. 8. Schedule for Completion Reallocate funds Select Architect Design Bidding & Award Construction Occupancy 30 days 45 days 160 days 50 days 170 days 4/20/09 - 6/01/09 6/02/09 - 8/03/09 8/ 4/09 – 3/15/10 3/16/09 – 5/24/10 5/25/10 – 1/13/11 1/14/11 9. Action Requested Approval requested. 10. Supporting Documents The budget does not allow for new furniture, existing furniture will be moved to the new building. Parking and landscaping will be added as required. Technology will be determined during design development; classroom should have smart technology. B. Limited Schematic Design Approval for the Seawolf Sports Arena – Road Upgrade and Site Clearing at the University of Alaska Anchorage Reference 17 The President recommends that: MOTION “The Facilities and Land Management Committee approves the Limited Schematic Design Approval request for the University of Alaska Anchorage Seawolf Sports Arena – Road Upgrade and Site Clearing as presented, and authorizes the university administration to proceed through Construction Document completion not to exceed a construction amount of $3,000,000 for this phase of work. This motion is effective June 4, 2009.” POLICY CITATION In accordance with Regents’ Policy 05.12.043, Schematic Design Approval (SDA) represents approval of the location of the facility, its relationship to other facilities, the functional relationship of interior areas, the basic design including construction materials, mechanical, electrical, technology infrastructure, and telecommunications systems, and any other changes to the project since Formal Project Approval. Facilities & Land Management Committee Agenda: Page 21 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska Unless otherwise designated by the approval authority or a Material Change in the project is subsequently identified, SDA also represents approval of the proposed cost of the next phase(s) of the project and authorization to complete the Construction Documents process, to bid and award a contract within the approved budget, and to proceed to completion of project construction. Provided, however, if a Material Change in the project is subsequently identified, such change will be subject to the approval process described below. For the Schematic Design Approval, if there has been no Material Change in the project since the Formal Project Approval, approval levels shall be as follows: TPC > $4 million will require approval by the Facilities and Land Management Committee (F&LMC). TPC > $2 million but ≤ $4 million will require approval by the chair of the F&LMC. TPC ≤ $2 million will require approval by the university’s Chief Finance Officer (CFO) or designee. If there has been a Material Change in the project since the Formal Project Approval, the Schematic Design approval levels shall be the same as the Formal Project Approval. RATIONALE AND RECOMMENDATION 1. Narrative Description This project supports the construction of the Seawolf Sports Arena projected to start in 2010 by completing critical site preparation activities the summer of 2009 that include: Site Clearing: the construction access drive, future roads and future parking lot areas will be cleared and graded to allow for installation of job site trailers and other support facilities. This area will become the major “on site” material storage and staging areas during the construction of the arena. East Providence Loop Upgrades (north segment): in cooperation with Providence Alaska Medical Center (PAMC), UAA will improve East Providence Loop to 3 lanes from Providence Drive to South Providence Loop. The improved road will be located partially on UAA property and partially on PAMC property. This road will provide access to both UAA and PAMC properties for their customers and the general public. Both Facilities & Land Management Committee Agenda: Page 22 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska UAA and PAMC have provided letters indicating their support of this shared access (letters attached). Improvements will include a 3-lane road, sidewalks along the west side and new landscaping where existing landscaping is disturbed. Pathways and landscaping on the east side will be completed concurrent with the construction of the Arena. 2. Graphic Description See Attached: 1. Arena concept site plan dated March 20, 2009 2. C1.0 Site Plan for 2009 improvements 3. L100 Landscaping plan for 2009 improvements 3. Proposed Cost and Funding Source(s) FY09 appropriation made $15M of $80M available for design and site work for this project. This road upgrade and site clearing work is estimated to be $3M. 4. Estimated Total Project Cost See Attached 5. Variance Report None 6. Schedule for Completion Road Upgrade and Site clearing: DD Submittal: CD Submittal: Bidding Period: Contract Award: Construction Complete: May 25, 2009 June 22, 2009 June 30 – July 20, 2009 August 15, 2009 October 15, 2009 7. Affirmation This project is in compliance with the UA Facilities Policy; the following approvals have been obtained. Preliminary Project Approval Master Plan amendment for Site Location Formal Project Approval August 1, 2008 February 24, 2009 February 24, 2009 Facilities & Land Management Committee Agenda: Page 23 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska V. Ongoing Issues A. Report on Utility Development Plan at the University of Alaska Fairbanks BACKGROUND The Utility Development Plan, which was completed in October, 2006, was a comprehensive utilities planning effort involving the administrations of University of Alaska (UA) and University of Alaska Fairbanks (UAF) in addition to UAF’s Facilities Services. The plan contained recommendations for utilities to support current and future campus needs with better reliability. The plan identified the following fundamental issues: Campus buildings and utility consumption growth beyond existing capacity Aging Utility infrastructure Fuel supply/price risks UAF financial constraints RECOMMENDATIONS FROM 2006 In order to reliably serve all campus utility needs over the next twenty years, UAF must: Invest substantially in utility system capital asset renewal and utility infrastructure improvements almost immediately. The best long term utility strategy is renewal and expansion of the Atkinson Power Plant using coal as the preferred fuel. This strategy is the best strategic, operational and financial fit for UAF. Subsequent to the completion of the Utilities Development Plan, UAF sought solutions to increasing its commitment to sustainability and the use of renewable energy sources. Although wind, solar, and geothermal sources were considered, biomass appeared to be the only viable option for renewable energy for now and in the immediate future. The boiler technology that was selected (circulating fluidized bed or CFB) for coal boilers is also suitable for mixed coal and biomass combustion. There is significant potential for sustainable biomass sources in the Fairbanks area, but there is no commercial source today. Facilities & Land Management Committee Agenda: Page 24 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska The US Department of Energy is currently performing a feasibility study for a combined biomass and coal power plant for UAF. The study is also investigating a biomass gasification system that could be used by the UAF Alaska Center for Energy and Power for research purposes. The possible research subjects include determining the gasification properties of local biomass sources and the properties for biomass to liquids. The products of this research could be used to fuel the UAF vehicle fleet and possibly Fairbanks North Star Borough (FNSB) buses. The study is scheduled to be completed by August, 2009. The study will include cost estimates that can be used for funding requests. A rough order of magnitude cost for this power plant expansion is $130M. STATUS OF UAF UTILITIES RENEWAL EFFORTS The 2006 Utilities Development Plan contained a list of critical renewal projects. The total amount of renewal was estimated at $65M in 2006 dollars. Approximately $6.1M of funding has been obtained for utilities renewal projects, which is less than 10% of the required amount for renewal. The following is a list of projects completed or in progress and their status: Project Convert Boiler No. 4 to Natural Gas New Air Compressors Cost $0.2M $0.2M New turbine controls and control room $0.6M Critical Electrical Distribution Renewal Phase 1A $5.2M Comments Project is complete 1 of 3 new compressors is installed, additional funding needed for 2 additional compressors Funds are encumbered and work is scheduled to be completed in July, 2009 Initial Phase of a $35M project. This phase, scheduled for completion during summer 2009, constructs utilidors. Future phases will construct functional electrical facility and system. The current pace of spending for addressing critical renewal items would predict completion in over 20 years. Although UAF utilities are not in poor shape where a major failure is imminent, the probability of a major utility failure increases with every year that renewal work is not done. A major utility failure could have significant financial ramifications and in the worst case could impact UAF’s mission by forcing closure of facilities. Decision makers in our past have left a durable, robust utility system that has provided over 40 years of reliable service. It is hoped that similar Facilities & Land Management Committee Agenda: Page 25 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska decisions and commitments can be made to ensure UAF has a reliable utility system in the next 40 years. B. Report on the University of Alaska Anchorage Master Plan Reference 18 PURPOSE Since the UAA Campus Master Plan was drafted in 2003, a number of significant decisions have been made, four building projects have been undertaken, and a number of personnel and policy changes have occurred. The purpose of the master plan update effort is to respond to all of these changes with amendments to the text and graphics of the campus master plan that was approved by the Board of Regents in 2004. The intention is to present to the Board of Regents for their information a revised master plan that provides a sound and current basis for future decisions affecting the fabric of the Anchorage campus. The master Plan will be presented for BOR Approval in the September 2009 meeting. RECENT CHANGES The goals, objectives and principles that formed the basis of the campus master plan that was adopted in 2004 rest on an extensive series of consultations in 2003. UAA held a series of 45 meetings with various constituencies that have an interest in future campus facilities. The foundation of the plan is not concerned with individual projects and improvements, but with the underpinnings of the whole institution, and so will remain unaltered in the 2008 update. Changes that have occurred are both physical and organizational. Physical changes that have occurred or are expected to occur in the near future include the following: ANSEP Building completed and occupied; Integrated Science Building and adjacent parking garage nearing completion; Health Sciences Campus Master Plan completed, and ground broken for the first new building, HSB Ph 1 Temp parking established; Siting and preliminary design for the new Sports Center completed; Implementation of the campus core loop road begun; Extension of a loop road from APU connecting via Elmore (formerly Bragaw) to Providence East, passing north of UAA residence halls on Sharon Gagnon Lane. Organizational and policy changes include: Facilities & Land Management Committee Agenda: Page 26 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska Changes in Senior Administration at the university; Publication of an updated Strategic Plan and Academic Plans for the University; Changes in enrollment projections; Several Infrastructure studies conducted by the University Changes in the State economy and thus of campus improvement funding prospects; Changes in regional political leadership that may reopen arguments for northward extension of Elmore (formerly Bragaw) to Northern Lights Boulevard with consequent severance of the campus. University Signage Plan approved by the Municipality of Anchorage Municipality of Anchorage Title 21 Revisions Revised Regents Facility Policy as it pertains to Master Plans ISSUES TO BE ADDRESSED As stated above, no changes will be made to the goals, objectives and principles that form the basis of the campus master plan. It has been reorganized to better conform to paragraph B and associate 12 points of the Regents Policy P05.12.030. Campus Master Plans. Both projects and priorities among proposed facilities have changed since 2004, so the siting and phasing of these projected improvements must be re-evaluated. Also, the availability of sites for future improvements and possible expansion of the campus should be considered. UPDATES PROPOSED The aerial photograph and all plans of the campus in the 2004 master plan will be updated to reflect changes that have occurred or have been confirmed as of this date. Thus the approved amendments for the Health Sciences campus and Sports Arena area will be shown although none of the buildings has yet been constructed. In order to clarify the potential for siting new development and redevelopment on campus, two new plans have been prepared. These depict remaining tracts of developable land, and large sites that could be assembled from previously developed land, comprising surface parking lots, obsolete structures and under-developed sites. These complement plans prepared in 2003 that show wetlands and proposed conservation areas. Facilities & Land Management Committee Agenda: Page 27 of 28 Agenda Facilities & Land Management Committee June 4, 2009 Fairbanks, Alaska The new development capacity plans aided in preparation of new plans showing potential siting of new and expanded facilities in three periods: 2008-2018, 2018-2028, and after 2028. With these changes under review by UAA staff, our consultants will check the text of the 2004 master plan and will amend any inconsistencies with the updated graphics. They will assure conformance with current Regent’s Policy 05.12.030.B and assure this Master Plan will meet the Municipality requirement under Title 21. This Update is being provided for your information. UAA will seek you approval at the Board of Regents Meeting in September 2009. C. Status Report on University Investments in Capital Facilities, Construction in Progress, and Other Projects Reference 19 Kit Duke, Chief Facilities Officer, and campus facilities representatives will update the committee regarding the ongoing investment in capital facilities and answer questions regarding the status report on active construction projects approved by the Board of Regents, implementation of recommendations by the external consultants, functional use survey, space utilization analysis, and other recent activity of note. This is an information and discussion item; no action is required. D. Update on IT Issues Reference 20 Chief Information Technology Officer Smith will provide an update on the status of online security remediation based on the external security review. He will also provide an in depth report on the conditions and historical context for online security across the University of Alaska system. New laws, both federal and state, and new threats, both internal and external, combined with growing dependencies on technology for every aspect of life create challenges to securely and effectively conduct the business of the university. VI. Future Agenda Items VII. Adjourn Facilities & Land Management Committee Agenda: Page 28 of 28