ADDENDUM #2
To:
Bidders of Record
Project:
Bid Package 6
Annual Major Maintenance FY 15
Date:
April 7, 2014
SPECIAL NOTE: Addendum #2 information shall supersede the information contained in the
Contract Documents
This Addendum forms a part of the Contract Documents and modifies the original Bidding
Documents dated January 20, 2014. Acknowledge receipt of this Addendum in the space provided on
the Bid Form. Failure to do so may subject the Bidder to disqualification.
Date: April 9, 2014 @ 4:00 pm
Location: Meet at Cady Building, 170 Long Lane, Middletown, CT 06457 – Conference Rm. A
Bids due: April 23, 2014 @ 1:00PM
Post bid interview/bid review: Week of April 29, 2014
Selection of successful bidders: Week of May 5, 2014
Construction Start Date: May 27, 2014
Substantial Completion Date: July 11, 2014
Project Completion Date: July 25, 2014
Addendum #2 Documents include:
MM FY15 Project Manual Divisions 0 – 16
MM FY15 Project Specifications Attachments, Exhibits, Stair Detail
Proposal Form
Scope of Work
Revised EPDM specification
Fall Protection Devices specification
Roof Plans
A package is in the process of being developed for repairs/replacement of roofing surfaces at Hall –
Atwater inner roof and making water tight the exterior roof perimeter coping stone.