Addendum #3-Olin Door Replacements-3/18/14

advertisement
WEST SIDE
DOOR LOCATIONS
(DOOR A & DOOR B)
A
B
DOOR LOCATION PLAN
(BASEMENT FLOOR PLAN)
MAJOR MAINTENANCE FY 15
WESLEYAN
UNIVERSITY
Construction Services
170 Long Lane
Middletown, CT 06457
252 CHURCH STREET
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 3/18/14
P-26-1
WEST SIDE DOORS
TO BE REPLACED WITH
NEW FRP DOORS. ALSO
PROVIDE NEW HARDWARE
AS NOTED.
DOOR ‘A’
DOOR ‘B’
WEST ELEVATION
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 3/18/14
P-26-2
DOOR ‘A’ – EXISTING CONDITIONS
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-3
DOOR ‘B’ – EXISTING CONDITIONS
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-4
Scope of Work (Reference MMFY15 Project Manual for all general project requirements)
(See photo sheets for scope location clarifications)
DOOR ‘A’
•
Contractor shall remove and discard door leaf, hinges, closer and threshold. Salvage “Deliveries Only” sign for reinstallation.
•
Contractor shall salvage lockset and core – return to Owner.
•
Contractor shall repair lower section of rusted HM frames (both sides). Grind out all rusted and deteriorated frame areas. Refasten and anchor base pf
strike side jamb to prevent future movement. Repair base of frame with Bondo or equivalent repair material.
•
Contractor shall install a new FRP door, threshold and associated hardware as identified. Prep existing frame to install new FRP door to replace the
existing HM door. Prior to ordering door, contractor shall field measure frame opening and all hardware prep requirements. Submit shop drawings for
final review and approval. Note: Hardware shall be fastened with thru-bolts as specified.
•
Contractor shall field measure the existing frame opening and hold the tightest dimension at the base of the frame. New door shall be sized based on
using this dimension and adequate clearance shall be provided to account for the continuous hinge and operating clearance at the strike side of the
jamb.
•
Contractor shall prep and level concrete floor to accept new threshold. Repair / replace exist interior VCT floor at threshold. Match existing VCT as
required.
•
Prep, prime and paint interior and exterior of new FRP door. Prep, prime & paint HM frames, including exterior dividing panel between both doors.
Paint shall match existing colors.
•
Contractor shall schedule door installation with Owner. Delivery access must be maintained at all times.
•
Door removal and installation of new door must occur within the same day.
•
Upon completion of the new door installation, ensure proper function and clearance space between new door and existing frame..
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-5
Scope of Work (Reference MMFY15 Project Manual for all general project requirements)
(See photo sheets for scope location clarifications)
DOOR ‘B’
•
Contractor shall remove and discard door leaf, hinges and threshold. Salvage “Fire Panel” sign for reinstallation.
•
Contractor shall maintain and protect existing automatic door closer, electric latch and card reader system.
•
Contractor shall re-install activated electric latch, latch sensor and wiring. Coordinate with ISG (Integrated Security Group), Mike Veronese, 888-474-3672,
and new hardware to ensure compatibility and proper installation.
•
Contractor shall salvage lockset and core – return to Owner.
•
Contractor shall repair lower section of rusted HM frames (both sides). Grind out all rusted and deteriorated frame areas. Refasten and anchor base pf strike
side jamb to prevent future movement. Repair base of frame with Bondo or equivalent repair material.
•
Contractor shall install a new FRP door, threshold and associated hardware as identified. Prep existing frame to install new FRP door to replace the existing
HM door. Prior to ordering door, contractor shall field measure frame opening and all hardware prep requirements. Note: Hardware shall be fastened with
thru-bolts as specified.
•
Contractor shall field measure the existing frame opening and hold the tightest dimension at the base of the frame. New door shall be sized based on using
this dimension and adequate clearance shall be provided to account for the continuous hinge and operating clearance at the strike side of the jamb. Submit
shop drawings for review & approval.
•
Contractor shall prep and level concrete floor to accept new threshold. Repair / replace exist interior VCT floor at threshold. Match existing VCT as required.
•
Prep, prime and paint interior and exterior of new FRP door. Prep, prime & paint HM frames, including exterior dividing panel between both doors. Paint shall
match existing colors.
•
Contractor shall schedule door installation with Owner. Egress must be maintained at all times.
•
Door removal and installation of new door must occur within the same day.
•
Upon completion of the new door installation, ensure proper function and clearance space between new door and existing frame..
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-6
Products (Reference MMFY15 Project Manual for all general project requirements)
Contractor shall field measure, coordinate, furnish and install the following. Verify all field dimensions for proper ordering.
DOOR ‘A’
1. DOORS: 1 ¾” thick FRP door with insulated core (field verify existing door thickness):
• Corrim - Special Lite
• Commercial Door Systems; or
• Approved Equal
2. HINGES: Heavy Duty Continuous MCK 25HD –
3. EXIT DEVICE: Sarg 16-8804-J-ETL704-US4-LHRB-less cylinders - TB
4. CLOSER: NOR CLP7500R – TB – 696
NOTE: Due to existing mounting holes on header stop. A steel plate (approx.) 2 ½”(w) x 8” (L) x 1/8” (d) – may be needed to cover existing holes and
mount new parallel door closer.
5. THRESHOLD: PEM 2286A (or as is needed)
6. DOOR BOTTOM:PEM 345AV
7. PERIMETER WEATHERSTRIPPING: PEM Set 2892GV x 2893GV
8. CORES: (2 ea.) CorbRus 1080-114-A02-606--N25 o-bit –
9. Provide Frame Hinge Fillers
10. Provide Strike Frame Filler
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-7
Products (Reference MMFY15 Project Manual for all general project requirements)
Contractor shall field measure, coordinate, furnish and install the following. Verify all field dimensions for proper ordering.
DOOR ‘B’
1. DOORS: 1 ¾” thick FRP door with insulated core (field verify existing door thickness):
• Corrim - Special Lite
• Commercial Door Systems; or
• Approved Equal
2. HINGES: Heavy Duty Continuous MCK 25HD - G
3. EXIT DEVICE: Sarg 16-8904-J-ETL704-US4-RHRB-less cylinders – TB
(Field measure and prep new door to align with existing strike).
4. CLOSER: Re-install existing – provide ¼ - 20 thru bolts
5. THRESHOLD:PEM 2286A (or as is needed)
6. DOOR BOTTOM:PEM 345AV
7. PERIMETER WEATHERSTRIPPING:PEM Set 2892GV x 2893GV
8. CORES: (2 ea.) CorbRus 1080-114-A02-606--N25 o-bit9. Provide Hinge Frame Fillers
WESLEYAN
UNIVERSITY
252 CHURCH STREET
Construction Services
170 Long Lane
Middletown, CT 06457
OLIN LIBRARY - WEST DOOR REPLACEMENT
SECTION 00020 - EXISTING CONDITION PHOTOS
DATE: 01/20/14
PHOTO. NO.
REVISIONS
ADD#3: 03/1814
P-26-8