Wesleyan University SCOPE OF WORK BID PACKAGE #24 VAN VLECK OBSERVATORY ON FOSS HILL LARGE DOME INTERIOR STRIPPING, STAINING & PAINTING PART 1 – GENERAL 1.1 RELATED DOCUMENTS 1. Drawings, photos and general provisions of the Contract, including General and Supplementary Conditions and all other Specification Sections referenced, apply to this section. 1.2 HAZARDOUS MATERIAL COORDINATION 1. All painted surfaces shall be treated as positive for lead containing paint. Federal, State, Local and OSHA requirements are to be strictly adhered to for all lead abatement. Contractor shall wrap lead waste in 6-mil plastic, transport and store lead waste on Owner’s site in a location to be designated. Owner shall dispose of lead waste. 2. All contractor personnel working on the project shall be certified by the U.S. Environmental Protection Agency (EPA) for lead based paint activities. 3. All Contractors shall provide current blood test results for ALL employees working on Wesleyan properties in the performance of demolition, window installations, and painting activities before the start of any work. 1.3 SCHEDULE 1. General Project Schedule 1. Start Work: July 1, 2013 2. Project Complete: August 20, 2013 1.4 GENERAL PROJECT REQUIREMENTS 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Contractor shall adhere to the project manual. Contractor to assume all paint is lead containing. Coordinate all work with Owner’s Representative. Building and surrounding dormitories will be occupied. Reference construction schedule for start and completion dates. The contractor will be responsible for daily clean up. Project site must be kept clean and free from tripping hazards. Conduct construction waste management activities in accordance with the State of Connecticut EPA, Middletown Municipal Code and all other applicable laws and ordinances. Removal of debris is to be disposed of in contractor supplied dumpsters at a centralized location. Coordinate all work with work of other trades. Contractor to comply with all State and Federal Codes, City of Middletown Ordinances, OSHA requirements and Wesleyan University General Project Requirements and Closeout Procedures. Provide as-built condition drawings. After review of site, contractors are responsible for any required temporary protection during the work. Contractor shall maintain dust protection between work area and occupied space. Any overtime required to complete project MUST be brought to Owner’s attention prior to submission of bid. Major Maintenance FY 2013/2014 Project No. 2014000000 00200- 24 - 1 6/11/2013 Wesleyan University 13. Coordinate the use of motorized lifts with Owner. Contractor shall protect turf, concrete walks and pavement as required. Damaged turf, concrete walks and pavement shall be repaired by the contractor at no cost to the Owner. 14. This is an occupied building. Doors to facilities must be kept locked at all times; any propped doors will be closed by Wesleyan University facility operations staff or public safety, no complaints or exceptions. If doors are to be propped the door shall be watched by a representative of this contractor. 1.5 SPECIFIC PROJECT REQUIREMENTS 1. The maximum weight limit on the Otis elevator floor is 3000 pounds. 2. Scaffolding, workers and related equipment must be distributed evenly across the floor. Contractor shall submit mobilization plan identifying weight of all equipment, scaffolding, materials and personnel. 3. Contractor shall cover and protect wood floor prior to the start of work. 4. Contractor shall cover and protect all existing equipment, light fixtures, wall mounted equipment, cabinet/control board, ladder and telescope. Wrap entire telescope and weight system with poly. Ensure lens covers for both ends of telescope are installed prior to wrapping. Owner must be present when contractor is ready to cover and protect these items. 5. Contractor shall protect horizontal surface of rail system and wheels, pulley systems, cables, cable weights, and gears prior to performing the work. 6. Contractor shall take extreme caution to protect the telescope when working in and around the dome. 7. Contractor shall remove existing window treatments to complete the work. Reinstall upon completion of the project. Utilize existing fasteners and brackets, or provide new as required for reinstallation. 8. Contractor shall protect equipment in the basement space below the elevated floor prior to the start of work. 9. Scheduling of work shall be coordinated with the owner to best accommodate the needs of the observatory. 1.6 SCOPE OF WORK 1. This is an academic building and is occupied year round. All work and work hours shall be coordinated with the Owner. Use of semi-transparent or solid stain shall be determined as the work progresses. 2. Contractor shall apply paint remover paste to all curved dome wood surfaces. Contractor shall allow paste to dwell overnight or as required to remove the paint and all previous coatings. Peel Away paper may be required to be used to remove difficult sections or areas of paint. Contractor shall remove softened / lifted paint using a scraper, taping knife or squeegee, taking care not to damage or scar the wood surface. Re-apply paint remover as required to lift stubborn sections or areas. The intent of the stripping process is to remove all paint and previous coatings as required to create a suitable wood surface substrate to properly accept the new stain product. Contractor shall apply stripping product in accordance with all manufacturer application requirements. 3. Upon completion of the stripping process, Contractor shall thoroughly rinse the stripped surface with water or denatured alcohol to remove any remaining residue. Contractor must rinse the stripped surfaces a minimum of two times. 4. Contractor shall install pre-finished bead board over the existing vertical section of bead board at the base of the dome around the entire circumference of the dome. Pre-finished bead board groove profile and spacing shall match existing. Pre-finished color shall match new stain color. Submit bead board samples to Owner for approval. Major Maintenance FY 2013/2014 Project No. 2014000000 00200- 24 - 2 6/11/2013 Wesleyan University 5. Contractor shall notify the Owner upon completion of the stripping and rinsing process to review and accept the dome wood substrate. Once approved, Contractor may proceed with applying the stain product. 6. Contractor shall thoroughly prep and repair all surfaces scheduled to be painted. A. Contractor shall apply stain to the curved dome bead board wood surface to obtain the desired outcome. B. Contractor shall apply one (1) coat of primer and two (2) coats of paint on all interior concrete walls/ceiling including but not limited to all tin walled areas, horizontal surfaces and doors. Painting of walls shall extend down to the finished floor beneath the elevator platform. C. Contractor shall apply one (1) coat of primer and two (2) coats of paint on the steel dome framing structure, includes continuous wood blocking. Contractor shall repair and prime all rust spots and shall protect all gears that operate the dome. D. Contractor shall apply one (1) coat of primer and two (2) coats of paint on the telescope pier. Contractor shall repair and prime all rust spots and shall protect all gears and control cabinets. E. Contractor shall apply one (1) coat of DTM to all metal pipe railings. Match exist black railing color and sheen. Do not paint diamond mesh railing infill panels. F. Contractor shall apply one (1) coat of primer and two (2) coats of paint on all walls and the ceiling of the stairway leading to the basement floor of the observatory. Maintain wood trim, treads, risers and door – clean with Murphy’s oil soap. Contractor shall apply two (2) coats wood preservative on plywood door at basement level. 7. Contractor shall not paint dome iron rail track and wheels, cables, cable weights, elevator rails, unpainted pulleys, etc. 8. Contractor shall clean existing varnished window and door trim surfaces with Murphy’s oil soap. PAINT REMOVER – INTERIOR WOOD DOME SURFACE A. Manufacturer: Dumond Chemicals, Inc. www.dumondchemicals.com Product: Smart Strip™ Pro Paint Remover. PAINT / STAIN FINISH SCHEDULE A. Interior Wood Dome Surface: Manufacturer: Sherwin Williams Semi Transparent Stain Color: SW3508 Covered Bridge or SW3511 Cedar Bark. Provide samples and mock-up as required for final selection by Owner. B. Interior Walls, Tin Walled Areas, Horizontal Surfaces and Doors: Manufacturer: Sherwin Williams Color: SW7683 Buff; satin finish C. Steel Dome Framing Structure: Manufacturer: Sherwin Williams Color: SW6179 Artichoke or TBD; semigloss finish. Provide samples of semigloss and satin finish and mock-up as required for final selection by Owner. Major Maintenance FY 2013/2014 Project No. 2014000000 00200- 24 - 3 6/11/2013 Wesleyan University D. Telescope Support Pier, Railings Manufacturer: Sherwin Williams Color: DTM Stove Pipe Black; semigloss finish 9. Contractor shall submit draw downs of all colors specified. Major Maintenance FY 2013/2014 Project No. 2014000000 00200- 24 - 4 6/11/2013