PowerPoint Presentation Matching your Textbook to Part B Guidelines.

advertisement
For each of the items under A through H be sure to have:
1)
Heading
2)
Introductory paragraph
3)
Some explanation, discussion, and/or analysis
4)
And document all non-original work.
•2
Table 4-1. Project Charter for the DNA-Sequencing
Instrument Completion Project
•Information Technology Project
Management, Seventh Edition
•3
Table 4-1. Project Charter (cont.)
•Information Technology Project
Management, Seventh Edition
•4
Defining Scope
• Project scope statements should include at least
a product scope description, product user
acceptance criteria, and detailed information on
all project deliverables. It is also helpful to
document other scope-related information, such
as the project boundaries, constraints, and
assumptions. The project scope statement
should also reference supporting documents,
such as product specifications
• As time progresses, the scope of a project should
become more clear and specific
•5
Table 5-3: Further Defining Project Scope
6
Figure 5-4. Sample Intranet WBS
Organized by Phase
7
Figure 5-5. Intranet WBS and Gantt Chart in
Microsoft Project
8
Figure 6-5. Gantt Chart for Project X
9
Figure 6-4. Sample PDM Network Diagram
10
PERT Formula and Example
• PERT weighted average =
optimistic time + 4X most likely time + pessimistic time
6
• Example:
PERT weighted average =
8 workdays + 4 X 10 workdays + 24 workdays
= 12 days
6
where optimistic time= 8 days
most likely time = 10 days, and
pessimistic time = 24 days
Therefore, you’d use 12 days on the network diagram instead of
10 when using PERT for the above example
•11
Figure 7-4. Surveyor Pro Project Cost Baseline
12
Earned Value Calculations for a One-Year
Project After Five Months
•13
Figure 9-3. Sample Organizational Chart for a
Large IT Project
14
Figure 9-4. Work Definition and
Assignment Process
15
Responsibility Assignment Matrices
• A responsibility assignment matrix (RAM) is a
matrix that maps the work of the project as
described in the WBS to the people
responsible for performing the work as
described in the OBS
• Can be created in different ways to meet
unique project needs
•16
Figure 9-5. Sample Responsibility Assignment
Matrix (RAM)
17
Communications Management
Plan Contents
1. Stakeholder communications requirements
2. Information to be communicated, including format, content,
and level of detail
3. Who will receive the information and who will produce it
4. Suggested methods or technologies for conveying the
information
5. Frequency of communication
6. Escalation procedures for resolving issues
7. Revision procedures for updating the communications
management plan
8. A glossary of common terminology
•18
Table 10-1. Sample Stakeholder Analysis for
Project Communications
19
Contract Statement of Work (SOW)
• A statement of work is a description of the
work required for the procurement
• If a SOW is used as part of a contract to
describe only the work required for that
particular contract, it is called a contract
statement of work
• A SOW is a type of scope statement
• A good SOW gives bidders a better
understanding of the buyer’s expectations
•20
Figure 12-3. Statement of Work (SOW)
Template
21
Procurement Documents
• Request for Proposals: Used to solicit
proposals from prospective sellers
– A proposal is a document prepared by a seller when there
are different approaches for meeting buyer needs
• Requests for Quotes: Used to solicit quotes or
bids from prospective suppliers
– A bid, also called a tender or quote (short for quotation), is a
document prepared by sellers providing pricing for standard
items that have been clearly defined by the buyer
•22
Figure 12-4. Request for Proposal (RFP)
Template
23
Download