BAE – STRUCTURAL OPTION conclusion breadth depth goals proposal overview introduction DAVID GEIGER DULLES TOWN CENTER BUILDING ONE DULLES, VIRGINIA SENIOR THESIS PRESENTATION 14 APRIL 2009 Proposal Summary DULLES, VIRGINIA SENIOR THESIS 2009 Building Overview DULLES TOWN CENTER BUILDING ONE Goals Depth Study • Structural System Redesign Breadth Study • Cost Comparison • Schedule Comparison • 7th Floor Acoustics Conclusions DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion INTRODUCTION DULLES TOWN CENTER BUILDING ONE • (7) Stories of office space above grade • (1) Sub-grade floor Houses building services and amenities SENIOR THESIS 2009 7 Story Commercial/Office Building DULLES, VIRGINIA Square Footage: 202,110 gross floor area Site Area: 12.37 acres Project Duration • Fall 2000 – Spring 2002 Project Delivery Method • Design-Bid-Build DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion OVERVIEW 21000 Atlantic Boulevard Dulles, Virginia 20101 25 miles northwest of Washington, D.C. 5 minutes from Dulles International Airport introduction DULLES, VIRGINIA SENIOR THESIS 2009 Location: DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION conclusion breadth depth goals proposal overview OVERVIEW SENIOR THESIS 2009 Architect: depth Structural Engineer: Civil Engineer: General Contractor: KCF-SHG Inc. DAVID GEIGER – STRUCURAL OPTION introduction overview proposal DULLES, VIRGINIA Owner: MEP Engineer: conclusion DULLES TOWN CENTER BUILDING ONE Project Team breadth goals OVERVIEW • • • • • • 7” one-way slab on post-tensioned beam system F’c = 5000 psi ½” DIA. 7 wire, low-relaxation strand 48”x 17” post-tensioned beams 3-day curing time before post-tensioning 40’ spans DULLES, VIRGINIA SENIOR THESIS 2009 Existing Floor System DULLES TOWN CENTER BUILDING ONE Existing Columns • • • • Cast-in-place 24”x 24” f’c = 5000 psi (Floors C-2) f’c = 4000 psi (Floors 4-PH) DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion OVERVIEW SENIOR THESIS 2009 • Frames in east-west direction depth • Frames in north-south direction DAVID GEIGER – STRUCURAL OPTION introduction overview DULLES, VIRGINIA Ordinary reinforced concrete moment frames in both directions • Post-tensioned beams • Reinforced columns • Slab drops breadth conclusion DULLES TOWN CENTER BUILDING ONE Existing Lateral System goals proposal OVERVIEW 5” slab on grade reinforced with 6x6 – W2.0xW2.0 WWF Strap beams ranging from 24”x 36” to 48”x 48” 24” foundation wall Pile caps Cast-in-place caissons with diameters ranging from 30” to 75” depth breadth conclusion DULLES, VIRGINIA South Elevation SENIOR THESIS 2009 • • • • • DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION introduction overview Existing Foundation goals proposal OVERVIEW DULLES TOWN CENTER BUILDING ONE To conduct a comparison between the existing concrete system and a steel redesign to determine which building material resulted in more benefits, both in regards to time and money SENIOR THESIS 2009 Proposal Summary DULLES, VIRGINIA • Gravity System o Composite metal deck system • Lateral System o Ordinary steel moment frames • Foundation System o Resist overturning o Reduce number of caissons, if possible DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion PROPOSAL DULLES TOWN CENTER BUILDING ONE Design Goals Respect the current column layout to maintain large spans and open floor plans Limit total floor depth to preserve floor-to-ceiling heights of 9’ and prevent additional façade costs SENIOR THESIS 2009 DULLES, VIRGINIA Establish a design that quickens construction and decreases total project costs Preserve a suitable working environment within the 7th floor office space Become more familiar with steel design and construction DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion GOALS Composite metal deck Benefits • Speed of steel construction • No shoring breadth conclusion DULLES, VIRGINIA Design governed by fire rating Drawbacks • Maximum clear span of 17’ • Infill beam needed • Larger slab depth DAVID GEIGER – STRUCURAL OPTION introduction Vulcraft Product Catalog depth proposal Chapter 4, ASCE 7-05 DULLES TOWN CENTER BUILDING ONE SENIOR THESIS 2009 Floor System goals overview DEPTH Infill beams Benefits • Can span 40’ • Lighter than concrete breadth conclusion DULLES, VIRGINIA Design governed by ΔLL Drawbacks • Larger beam depth • Needs fireproofing In order to keep floor-to-ceiling heights at 9’, need to camber DAVID GEIGER – STRUCURAL OPTION introduction 13th Ed. AISC Steel Manual depth proposal Chapter 4, ASCE 7-05 DULLES TOWN CENTER BUILDING ONE SENIOR THESIS 2009 Floor System goals overview DEPTH SENIOR THESIS 2009 DULLES, VIRGINIA Reduces overall cost of infill beams compared to no camber depth breadth conclusion DULLES TOWN CENTER BUILDING ONE Typical floor layout of cambered beams DAVID GEIGER – STRUCURAL OPTION introduction overview Camber goals proposal DEPTH DULLES TOWN CENTER BUILDING ONE Ordinary steel moment frames in both the east-west and north-south directions Beam to column connections are fixed by providing flange welds Benefits • Lighter framing • Better in tension • Can span the necessary 40’ Drawbacks • Beam depth • Expensive connections SENIOR THESIS 2009 Lateral System DULLES, VIRGINIA DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH Wind • ASCE 7-05, Chapter 6 o Method 2 o Serviceability controlled strength in east-west direction DULLES, VIRGINIA SENIOR THESIS 2009 Lateral System Design Loads DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH Seismic • ASCE 7-05, Chapter 12 o Equivalent Lateral Force Procedure o Controls strength in north-south direction DULLES, VIRGINIA SENIOR THESIS 2009 Lateral System Design Loads DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH breadth depth goals proposal overview Lateral System Layout North-South introduction SENIOR THESIS 2009 East-West DAVID GEIGER – STRUCURAL OPTION conclusion DEPTH DULLES TOWN CENTER BUILDING ONE DULLES, VIRGINIA DULLES TOWN CENTER BUILDING ONE Lateral System Design Loads Inherent Torsion • Mt = V(e) Accidental • Mt,a = V (e + .05L) SENIOR THESIS 2009 DULLES, VIRGINIA Minimal effects due to symmetry • Maximum shear caused by torsion less than 1 kip per frame DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH DULLES TOWN CENTER BUILDING ONE Preliminary hand calculations • Design loads from ASCE 7-05 procedures • Portal Frame Analysis for Moments o Exterior, façade-supporting beam • deflection of L/500 controlled • used conjugate beam method o Column, interior • Table 6-1, AISC Steel Manual • Interaction equation • Iteration until OK SENIOR THESIS 2009 Lateral System Member Design DULLES, VIRGINIA DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH DULLES TOWN CENTER BUILDING ONE RAM Analysis • Design loads from ASCE 7-05 o Beams • drift controlled design • repetition of members o Column • used Eq. H1-1a, interaction equation • drift controlled design • repetition of members SENIOR THESIS 2009 Lateral System Member Design DULLES, VIRGINIA DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH DULLES TOWN CENTER BUILDING ONE Serviceability Wind • h/400 • h/500 for members supporting precast or curtain wall façade SENIOR THESIS 2009 DULLES, VIRGINIA Seismic • .020hsx • amplification factor o δx = (Cd x δxe)/I Drifts taken from RAM using ASCE 7-05 lateral loads Serviceability controls design in the east-west direction only DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion DEPTH Floor Depth DULLES, VIRGINIA Due to serviceability standards, beams as large as W18x130’s were needed for typical floor framing SENIOR THESIS 2009 introduction DULLES TOWN CENTER BUILDING ONE Preserving ceiling-to-floor height of 9’ not achieved, must use 8’-8” DAVID GEIGER – STRUCURAL OPTION conclusion breadth depth goals proposal overview DEPTH Overturning moment calculated in both directions introduction DULLES, VIRGINIA SENIOR THESIS 2009 Foundation DULLES TOWN CENTER BUILDING ONE North-south direction good by inspection East-west direction checked for overturning • .9D + 1.6W Mresisting > Moverturning DAVID GEIGER – STRUCURAL OPTION conclusion breadth depth goals proposal overview DEPTH Intermediate caissons removed 84 C.Y. of concrete saved Loads on caissons checked using cantilever method and compared to existing loads on plans • Live load reduction • 1.2D + 1.6W + L + .5Lr depth breadth conclusion 1 2 SENIOR THESIS 2009 Foundation DAVID GEIGER – STRUCURAL OPTION introduction overview DULLES, VIRGINIA goals proposal DULLES TOWN CENTER BUILDING ONE DEPTH Existing Concrete System • R.S. Means • Multiple crews used for forming and post-tensioning • Construction zones: 5 • Column construction per floor: 30 days • Slab and beam construction per floor: 10 days • Post-tensioning per floor: 25 days • Total construction time: 258 days DULLES, VIRGINIA SENIOR THESIS 2009 Schedule Analysis DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion BREADTH Steel Redesign • R.S. Means • Single crews used • Construction zones: 3 • Framing construction per floor: 15 days • Deck and detailing: 45 days • SOD preparation and placement: 18 days • Total construction time: 96 days DULLES, VIRGINIA SENIOR THESIS 2009 Schedule Analysis DULLES TOWN CENTER BUILDING ONE DAVID GEIGER – STRUCURAL OPTION introduction overview proposal goals depth breadth conclusion BREADTH Cost Analysis Existing System • R.S. Means DULLES, VIRGINIA SENIOR THESIS 2009 introduction DULLES TOWN CENTER BUILDING ONE conclusion Overall estimated savings of approximately $1.8 million Moment connection costs not included DAVID GEIGER – STRUCURAL OPTION Steel Redesign • R.S. Means breadth depth goals proposal overview BREADTH DULLES, VIRGINIA SENIOR THESIS 2009 introduction DULLES TOWN CENTER BUILDING ONE Breadth Comparison Cost and Schedule comparison conclusion breadth * * Moment connection costs not included DAVID GEIGER – STRUCURAL OPTION depth goals proposal overview BREADTH DULLES, VIRGINIA Acoustic Study Checked for sound infiltration in the 7th floor office space due to the reduction in depth of the floor slab SENIOR THESIS 2009 introduction DULLES TOWN CENTER BUILDING ONE Existing PH Floor Existing Roof DAVID GEIGER – STRUCURAL OPTION conclusion breadth depth goals proposal overview BREADTH DULLES, VIRGINIA SENIOR THESIS 2009 introduction DULLES TOWN CENTER BUILDING ONE Acoustics Study Redesigned Roof breadth conclusion Result: No sound penetration found in either case DAVID GEIGER – STRUCURAL OPTION Redesigned PH Floor depth goals proposal overview BREADTH Were goals met? Respect the current column layout to maintain large spans and open floor plans Limit total floor depth to prevent additional façade costs and preserve floor-to-ceiling heights of 9’ Establish a design that quickens construction and decreases total project costs conclusion breadth depth proposal YES SENIOR THESIS 2009 DULLES, VIRGINIA YES/NO YES Preserve a suitable working environment within the 7th floor office space YES To become more familiar with steel design YES DAVID GEIGER – STRUCURAL OPTION introduction DULLES TOWN CENTER BUILDING ONE goals overview CONCLUSION Schedule Analysis • reduced schedule by an estimated 162 days • benefits owner with sooner building opening Cost Analysis • Material costs went up, but overall costs went down • Estimated an approximate savings of $1.8 million conclusion breadth depth proposal Gravity/Lateral system redesign • Applicable to DTC One • Minimal change to architecture Acoustic Analysis • No new sound penetration caused by the thinner slab Redesign of DTC One in steel is feasible SENIOR THESIS 2009 Recommendation DULLES, VIRGINIA DAVID GEIGER – STRUCURAL OPTION introduction DULLES TOWN CENTER BUILDING ONE goals overview CONCLUSION depth Industry Professionals: Michael Sladki – Cates Engineering, Ltd. Walter Rabe – Schanbel Engineering, LLC Colleagues: Dr. Linda Hanagan – Penn State University Benjamin Follett – The Bat Cave Jeremy McGrath – The Bat Cave And a special thanks to my family and friends for all of their love and support. SENIOR THESIS 2009 Owner Representatives: Frank Gambino – Lerner Enterprises, Inc. Kelly Burnette – Lerner Enterprises, Inc. DAVID GEIGER – STRUCURAL OPTION introduction overview proposal DULLES, VIRGINIA I would like to thank the following people for assisting me in this thesis research process: Advisor: conclusion DULLES TOWN CENTER BUILDING ONE Acknowledgements breadth goals CONCLUSION breadth depth goals proposal overview introduction SENIOR THESIS 2009 Questions? DAVID GEIGER – STRUCURAL OPTION conclusion CONCLUSION DULLES TOWN CENTER BUILDING ONE DULLES, VIRGINIA