Faculty Jury Presentation (PowerPoint)

advertisement
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
Johnathan Peno
Mechanical Option
Final Thesis Presentation
Johnathan Peno
Mechanical Option
Spring 2011
Advisor: Dr. Treado
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
Size:
194,000 SF
• Existing Conditions
Construction Period:
Spring 2011 - Fall 2013
• System Evaluation
Occupancy Type:
Lab, Education, Office
• Ventilation Load Reduction
Project Budget:
$140M
• Electrical System Integration
Construction Budget:
$105M
• Conclusions
Project Delivery Method:
Design-Bid-Build
Architect:
Ayers Saint Gross
Mechanical Engineer:
Owner:
Mueller Associates
The University of Delaware
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
 Building Overview
• Existing Conditions
N
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
N
Presentation Outline
• Introduction
• Building Overview
 Existing Conditions
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Water/Steam Side
• CHW to Building from ECUP (1350 tons)
• Building Cooling
• HX to Lab Process CHW
• Steam-Water HX Fed by Campus Steam Loop (19,000 PPH)
• Heat/Preheat Needs
• Domestic HW
• Electric Standby Chiller for Critical Spaces
• Condenser Heat in Preheat/Reheat Loop
• Fluid Coolers on Roof
N
Presentation Outline
• Introduction
• Building Overview
 Existing Conditions
• System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Air Side
10 Total Air Handling Units
• AHU 1, 2 & 10 = Recirculating
• Rest = 100% Outdoor Air
• Enthalpy Wheel/Heat Pipe
• VAV with terminal reheat (HW coils)
• Building Direct Digital Control System
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
 System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
Mechanical Option
Newark, DE
System Evaluation
• Building Overview
• Existing Conditions
Johnathan Peno
• Lab Buildings = High Ventilation Loads
N
• Instructional Laboratories
• Less Stringent Environmental Constraints
• Labs & Non-Labs on Same AHUs ( 3 & 4 )
• Goals:
• Reduce Ventilation Energy Consumption
• Maintain Occupant Safety
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
 System Evaluation
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
Mechanical Option
Newark, DE
System Evaluation
• Building Overview
• Existing Conditions
Johnathan Peno
• Lab Buildings = High Ventilation Loads
• Instructional Laboratories
• Lower Hood Densities
• Less Stringent Environmental Constraints
• Labs & Non-Labs on Same AHUs ( 3 & 4 )
• Goals:
• Reduce Ventilation Energy Consumption
• Maintain Occupant Safety
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Redesign Approach 1
 Approach 1
• Separate Spaces
• Demand Based ACH
• Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
3 Step Process to Reduce Building Ventilation Loads
• Separate Lab and Non-Lab Spaces
• Lower Air Change Rates
• Implement Chilled Beam System
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Step 1) Separate Lab & Non-Labs
• Approach 1
N
AHU 3 (Lab & Non)
AHU 4 (Lab & Non)
AIR SUPPLIED TO NON-LAB SPACES
Separate Spaces
• Demand Based ACH
25000
• Passive Chilled Beams
20000
• Approach 2
• Electrical System Integration
2,106
OUTDOOR AIR
15000
SUPPLY AIR
(CFM)
RECIRC AIR
24,440
22,342
10000
AHU 4 (Labs only)
5000
• Conclusions
AHU 3 (Non only)
0
0
1
Base Design
2
Redesign 2
Mechanical Option
Newark, DE
Approximate Hourly ACH Reduction
Lab Ventilation Rates of DCV vs. Set 12/6ACH
• Ventilation Load Reduction
• Conclusions
DCV
6
Set
12/6ACH
4
2
AM
0
AM
• Electrical System Integration
Redesign: Adjust ACH Rate Based on Demand
8
4:
00
• Approach 2
Current Design: 12/6 ACH (Occ/UnOcc)
10
AM
• Passive Chilled Beams
12
2:
00
Demand Based ACH
Minimum Air Change Rates In Labs
14
12
:0
0
• Separate Spaces
Lab Occupant Safety:
ACH (air changes per hour)
 Approach 1
AM
8:
00
AM
10
:0
0
AM
12
:0
0
PM
2:
00
PM
4:
00
PM
6:
00
PM
8:
00
PM
10
:0
0
PM
• Introduction
Johnathan Peno
6:
00
Presentation Outline
Interdisciplinary Science &
Engineering Building (ISEB)
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
System Diagram
• Ventilation Load Reduction
• Approach 1
• Separate Spaces
Step 2) Implement Demand Based ACH Control
System
Demand Based ACH
• Room Sensors
• Passive Chilled Beams
• Data Routers
• Approach 2
• Electrical System Integration
• Conclusions
• Sensor Suite
• DDC System
Illustration Provided by Aircuity
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Separate Spaces
• Demand Based ACH
Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Passive Chilled Beam
Step 3) Lab Passive Chilled Beam System
• 12ACH  Ventilation Load Dictates
• Lower ACH  Cooling Load May Dictate
• Implement Parallel Cooling System instead of bringing in
excess OA
Photo: Halton Passive
Chilled Beam
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Separate Spaces
• Demand Based ACH
Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
CFD Analysis
Goal:
Feasibility of Passive Chilled Beam System
Design Variables:
• Diffuser Pattern
• Chilled Beam Layout
Model:
Turbulence Model: Standard K-e
Differencing Scheme: Hybrid
Johnathan Peno
Mechanical Option
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Separate Spaces
• Demand Based ACH
Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
Diffuser Pattern
Vertical vs. Horizontal
Johnathan Peno
Mechanical Option
Vertical Patterns
Horizontal Patterns
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Separate Spaces
• Demand Based ACH
Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Row Layout
Newark, DE
Chilled Beam Layout
Row vs. Perimeter
Perimeter Layout
Presentation Outline
• Introduction
• Ventilation Load Reduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
CFD Analysis Conclusion
• Approach 1
• Separate Spaces
Perimeter Beam + Horizontal Pattern
• Demand Based ACH
Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
• Effectively Cooled Room to Design 72F
• Acceptable Temp. Gradient
(Standard 55 +/- 3oC)
Ave. Room
Temp=71.78oF
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
Interdisciplinary Science &
Engineering Building (ISEB)
• Passive Chilled Beams
• Approach 2
• Electrical System Integration
• Conclusions
Mechanical Option
Newark, DE
Approach 1 Conclusions
• Separate Spaces
• Demand Based ACH
Johnathan Peno
Chilled Water
Steam
Electricity
Payback Period
Approach 1
-2%
-15%
-1%
4.1
1.2
.
.
w/ Chilled Beams
w/o Chilled Beams
X
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Design
• Savings
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Design
• Savings
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Design
• Savings
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Design
• Savings
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
Design
• Savings
• Electrical System Integration
• Conclusions
GreenHeck Low Profile Cabinet Centrifugal Fan
N
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Approach 1
• Approach 2
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2
• Transfer air from Non-Labs to Labs as Make-Up
Air In lieu of O.A.
Design
• Savings
• Electrical System Integration
• Conclusions
GreenHeck Low Profile Cabinet Centrifugal Fan
N
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
• Approach 2
Mechanical Option
Newark, DE
• Ventilation Load Reduction
• Approach 1
Johnathan Peno
Chilled Water
Steam
Savings
24,898 ton-hrs
256 Mbtu
Chilled Water
Steam
Electricity
Payback Period
Approach 2
-2%
-5%
0%
3.3
• Design
Savings
• Electrical System Integration
• Conclusions
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Electrical System Integration
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Existing Electrical
• 34.5 kV service entrance feeders
 Existing Conditions
• Approach 1
• Approach 2
• Conclusions
• Dual primary-secondary doubled ended unit substation
• (2) medium voltage fused switches, Indoor substation
• Transformers Step 34.5 kV  480Y/277 V
• 3000A main-tie-main distribution section.
Existing Conditions
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Electrical System Integration
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
Electrical Integration
• 1000A Busway serving Instructional Wing
 Existing Conditions
• Approach 1
• Approach 2
• Conclusions
• 480/277  208/120 Xformer
• 400A MDP (Ground Floor)
• New 100A , 32 pole Equipment Panels
Johnathan Peno
Mechanical Option
Existing Conditions
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Electrical System Integration
• Existing Conditions
 Approach 1
• Approach 2
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 1 Additions
Fan Coil Unit
• Blower Motors
• Electric Heaters
MDP
DRGC
Location
Size
Previous Load
Added Load
New Amp Draw
Elec Rm 115
400 Amps
110,082 VA
26,704
379 Amps
Okay?
Yes
Future Growth
5%
Electrical Equipment Affected
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Electrical System Integration
• Existing Conditions
• Approach 1
 Approach 2
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Approach 2 Additions
Transfer Fan Motors
Fan Coil Units
• Blower Motors
• Electric Heaters
MDP
DRGC
Location
Size
Previous Load
Added Load
New Amp Draw
Elec Rm 115
400 Amps
110,082 VA
29,767
388 Amps
Okay?
Yes
Future Growth
3%
Electrical Equipment Affected
Presentation Outline
• Introduction
• Ventilation Load Reduction
Interdisciplinary Science &
Engineering Building (ISEB)
Johnathan Peno
Mechanical Option
Newark, DE
Recommendations
• Electrical System Integration
• Conclusions
 Recommendations
• Acknowledgements
• Questions
Approach 1 ( minus Chilled Beams)
• Most Economical (1.2 years)
• Highest Level of Occupant Safety (IEQ)
- Thanks to Room Sensors
Presentation Outline
• Introduction
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
Acknowledgements
Family
Friends
• Recommendations
AE Department
 Acknowledgements
Mueller Associates
• Questions
AIG Architects
University of Delaware
Johnathan Peno
Mechanical Option
Presentation Outline
• Introduction
Interdisciplinary Science &
Engineering Building (ISEB)
Newark, DE
• Ventilation Load Reduction
• Electrical System Integration
• Conclusions
• Recommendations
• Acknowledgements
 Questions
Questions?
Johnathan Peno
Mechanical Option
Download