Document 15188752

advertisement

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

• Masonic Villages of Pennsylvania

• Valley Care Association in 1999

• 60 personal care apartments

• 227 unit retirement living building

• Increase occupancy to 128 beds

• 66,000 SF of New Construction

• 40,000 SF of Renovations

• Importance of masonry

- Courtesy of Google Maps

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

• Mortar Mixing Procedures

• Freestanding vs. Hydro-Mobile Scaffolding

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

- Courtesy of WMF, Inc.

• Mortar Mixing Procedures

• Freestanding vs. Hydro-Mobile Scaffolding

• Adjusting Critical Path Elements!!!

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

- Courtesy of RLPS, LTD.

• Adjusting Critical Path Elements!!!

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Floor 1

Floor 2

Floor 3

Total

Wing A

0 Days

6 Days

10 Days

16 Days

Wing B

-

0 Days

10 Days

10 Days

Total

0 Days

6 Days

20 Days

26 Days

26 Days!

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

• Not Designed for Masonry Construction!!!

• 116 Different Dimensional Components

• 64 Do Not Match up in Desirable Increments

• Analyzed Savings:

• Material Waste

• Time

• Manpower

1,3

6,22

10,32

20,34

29,63

46,47

Evenly Matching Units

.

2,39

7,11

12,14

23,24

31,35

48,52

• 1 Cut / CMU

4,16

8,15

17,61

25,26

36,37

49,59

5,18

9,13

19,44

28,57

38,45

54,58

21

27

30

33

40

Wall #

Walls With Usable Scraps

Length of

Scrap

Wall # Length of

Cut Block

9

5

4

9

5

=>

=>

=>

=>

=>

60

50

55

56

64

3

2

2

8

3

Total:

Total

Waste of

CMU/row

1”

2”

6”

3”

2”

14”

• 1 Cut / CMU

• 2 Cuts / CMU + Waste

Walls With Usable Scraps

Wall #

41

42

43

51

53

62

Length of Cut

Block

12

12

12

12

10

10

Total Waste of

CMU/row

4”

4”

4”

4”

6”

6”

Total: 36”

• 1 Cut / CMU

• 2 Cuts / CMU + Waste

• 1 Cut / CMU + Waste

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Cost of Material Waste:

• Summed up the total inches of waste

• Multiplied by the number of CMU courses

• Computed an equivalent number of “wasted”

CMU’s

• Found a final dollar value of material

$1,031

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Cost of Time:

• Calculated the total amount of cuts

• Assumed:

• 4 min cycle

• Labor rate of $28 / hr.

• Schedule delay of 24.4 hours

• 30 man crew

Cost of Manpower:

• 4 additional laborers

Labor cost of 24.4 hour activity delay:

$20,496

Cost of additional manpower for a 59 day duration:

$52,864

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Total Cost Reduction

$74,394

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

• Façade Redesign

• Embossed Brick-Faced CMU’s

• Eliminates the need for brick veneer

• Veneer:

• 39,047 SF

• $453,800 - Courtesy of Westbrook Block

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Added Project Costs:

• Brick Block CMU’s

• Dyed Masonry

• Spray Foam Insulation

VE Changes

No Brick Veneer

Brick Block CMU’s

Dyed Masonry

Cost / SF Total Cost Cost Difference

$0.00

$0 +$453,800

$9.51

$0.41

$371,300

$16,000

-$58,900

-$16,000

Spray Foam Insulation $4.32

$168,700 -$129,700

Total Savings: +$249,200

- Cost Data Extracted From RS Means Facilities Construction Cost Data 2011

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

RValue of Current Façade

Brick Veneer =

2” Rigid Insulation =

Mass Enhanced =

Total R-Value =

R-3.2

R-10

R-0.5

R-13.7

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

- Courtesy of Apple Gate

Spray Foam Insulation:

R-3.8/in x 5-1/8 in

CMU:

=

=

R-19.5

R-2.5

Average Total R-Value:

(19.5 x 79.7%) + (2.5 x 20.3%) = R-16.0

R-16.0 > R-13.7

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

• LEED 2009 for Healthcare:

New Construction and Major Renovations

• LEED Silver

• 55 Points

• LEED Gold (60 – 79 Points)

3 Categories:

• Sustainable Sites

• Energy and Atmosphere

• Materials and Resources

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

 Points to be Pursued

 Points Already Earned / Not Practical

Sustainable Sites:

• Credit 6.1: Stormwater Management – Quantity

• Credit 6.2: Stormwater Management – Quality

• Credit 7.1: Heat Island Effect (Non-Roof) +1

Energy and Atmosphere:

• Credit 1: Optimize Energy Performance +1

Materials and Resources:

• Credit 1: Building Wall Reuse

• Credit 2: Waste Management

• Credit 3: Resource Reuse

• Credit 4: Recycled Content

• Credit 5: Regional Materials

+5 LEED Points

+1

+2

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Analysis #1: Masonry Acceleration

• Remove Floor Planks From Critical Path

• 26 Day Savings

Analysis #2: Façade Dimensioning

• Adjust Perimeter Dimensions on a Scale of Inches

• Cost Reduction:

• Material Waste $1,031

• Time

• Manpower

• Total Savings:

$20,496

$52,864

$74,394

Analysis #3: Value Engineered Façade

• Embossed Brick-Faced CMU’s

• Additional Expenses

• Net Savings: $249,200

Analysis #4: Masonry Sustainability

• 5 Points From LEED Gold

• 3 Categories:

• Sustainable Sites

• Energy and Atmosphere

• Materials and Resources

Industry

• Weber Murphy Fox, Inc.

• Masonic Villages of Pennsylvania

Academic

• Penn State AE Faculty

• Dr. Craig Dubler

• Professor Jim Faust

Special Thanks

• Tony Grace, Project Manager

• Kim Jeffreys, Project Executive

• Patty Downey, Project Coordinator

• Steve Burdick, Site Superintendent

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Appendix

Elevation View Plan View

Design Criteria:

Hollow Core Floor Plank:

Beam Self-Weight:

50 psf.

3 psf.

Resident Room Live Load: 40 psf.

Factored Load = [1.2(50 psf.+3 psf.)] + (1.6 x 40 psf.) = 127.6 psf.

Tributary Area (A t

P u

) = 25.5 ft. x 15 ft. = 382.5 ft 2

= 127.6 psf. x 382.5 ft 2 = 48.8 Kip

V u

M u

= 48.8 Kip/2 = 24.4 Kip

= 48.8 Kip x 10 ft. = 488 K-ft.

No Brace Points: C b

= 1.14

M u

’ = M u

/C b

= 488/1.14 = 428.1

W14x90 most efficient

(See Figure 42)

Shape exceed limit for flexure

Use W16x89

Project Overview

Analysis #1: Masonry Acceleration

Adjusting the Critical Path

Savings Potential

Analysis #2: Façade Dimensioning

Evenly Sized Elements

Analyzing Dimensional Mismatches

Material Waste, Time, and Manpower

Analysis #3: Value Engineered Façade

Net Savings of the New Façade System

Mechanical Breadth

Analysis #4: Masonry Sustainability

Analyses Summary

Acknowledgements

Appendix

Elevation View Plan View

Live Load Deflection:

I w = 40 psf. x 15 = 600 plf = 0.05 k/in

L = 25.5 ft. x 12 in/ft. = 306 in x

= 1,300 in 4

MAX

MAX

< 5wL/384EI

= [5(0.05 k/in)(306 in)

L/360 = 306 in/360 = 0.85

MAX

< L/360

0.15 < 0.85 OK

4 ] / [384(29,000 ksi)(1,300 in 4 )] = 0.15

Download