Fairfax High School Renovation and Addition M F

advertisement
Fairfax High School
Renovation and Addition
Washington, DC
MICHAEL FUNK
Construction Management
Fairfax High School
Renovation and Addition
Presentation Outline
Project Overview
Analysis 1 – LEED® Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation Excavation
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Project Overview
Total Cost:
Project Overview
$ 45 Million
Analysis 1 – LEED®
Guide
Size:
Analysis 2 – Phasing Layout
Duration:
Analysis 3 – Foundation
Conclusions
Q&A
410,000 Sq. Ft.
2 Stories
30 Months
Original: March 2005 – September 2007
Building Function:
High School
Facilities:
Classrooms, Computer Lab, Gymnasium,
Stage and Dressing Rooms, Dance Studio,
Weight and Aerobics Rooms, Arts / Crafts,
Music Room
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Project Overview
Construction:
Project Overview
School must remain in session throughout the project duration
Analysis 1 – LEED®
Guide
During school:
Analysis 2 – Phasing Layout
Summer:
Analysis 3 – Foundation
Conclusions
Q&A
50 to 60 workers
150 workers
Project Site:
Fairly Open Construction Site
Given 60 parking spaces
Trash sorted by concrete/CMU and steel despite there being
no recycling requirements
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Project Overview
Traditional Delivery Method
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
Project Team:
Owner:
City of Fairfax School Board
Program Manager:
BeeryRio Architecture & Interiors
General Contractor:
Grunley Construction Company
Architects/ Engineers:
Strickler Associates, Ehlert/Bryan, Adtek Engineers
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
PROJECT ORGANIZATIONAL CHART
FAIRFAX HIGH SCHOOL
STAFFING PLAN
City of Fairfax
School Board
GRUNLEY SUPPORT TEAM
Accounting & Human Resources
Estimating
Procurement
Information Technologies
Corporate Scheduling
Corporate Safety
Corporate Quality Assurance
LEED Certification
Field Operations & Training
Off-Site
Organization
CHIP SCOTT
PROJECT EXECUTIVE
GREG MCHUGH
BERNARD SCHULZE
PROJECT MANAGER
GENERAL SUPERINTENDENT
SCHEDULER
COST ENGINEER
SAFETY
DIRECTOR
ASSISTANT
SUPERINTENDENTS
COORDINATORS
FOREMEN
ASSISTANT PMS
TRADESMEN
Self-Performed Work
Subcontractors’ Home and Field Organizations
Michael Funk
Construction Management
On-Site
Organization
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Analysis 1 – LEED Guide
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
LEED Guide
Problem
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
•
•
•
‘Going green’ trend continues to increase
LEED points can be hard to obtain
Focus gets lost on the project
Existing Research
•
Setting early “green” goals is critical
Analysis 3 – Foundation
Conclusions
Q&A
Goal
•
•
Michael Funk
Construction Management
Identify LEED® points that are attainable based on project
type
Develop a guide that can be distributed to project team to
aid in obtaining these points
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
LEED Guide
Research Steps:
•
•
Project Overview
Analysis 1 – LEED®
Guide
•
•
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
•
•
Literature review to become more familiar with LEED®
Identify and interview different owners on different LEED® Rated
projects
Surveyed owners and project managers
Develop an outline for a guide that will benefit owners and project
managers from the start of a project
Developed a spreadsheet format for each LEED ® point
Had several project managers test out the guide, obtained
Conclusions
Q&A
Michael Funk
Construction Management
feedback, and developed a final version
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
LEED Guide
Excel Spreadsheet:
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Specification Section
Description
Responsible Party
Material Cost
Location
Comments
Submission Deadline
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
LEED Guide
Spec
Section
LEED LOG
08110
05310
10605
04065
07210
07620
07900
08800
07814
07900
0990
09900
09900
10270
07210
07900
09100
09250
09280
09510
09770
Description
Standard Steel Doors and
Frames
Steel Deck and Plate
Hardware Cloth
Stone Mortar
Building Insulation Product Data - STONE
Sheet Metal Flashing and
Trim - Stonework
Joint Sealants - Stone
Control Joints
Glass and Glazing Transom Glass
Interior Intumescent
Fireproofing
Joint Sealants - Partition
Opening Perimeter Joints
Temporary Cafeteria Paint
Temporary Cafeteria Epoxy Paint
Paint
Access Flooring
Building Insulation Product Data - DRYWALL
Joint Sealants - Partition
Perimeter and Control
Joints
Drywall Metal Support
Assemblies, Metal Support
Assemblies
Gypsum Board Temporary Cafeteria,
Whole Project
Plaster Restoration
Acoustical Ceilings,
Fasteners
Glass Fiber-Reinforced
Wall Panels
Resp Party
Material Cost
Location
Comments
Due By
AG Mauro
AIW
AIW
Atlantic
Sent:
Sent:
Sent:
Sent:
6/29/05
6/29/05
6/29/05
6/29/05
Received:
Received:
Received:
Received:
7/8/2005
7/8/2005
7/8/2005
7/8/2005
Atlantic
Sent: 6/29/05
Received:
7/8/2005
Atlantic
Sent: 6/29/05
Received:
7/8/2005
Sent: 6/29/05
Received:
7/8/2005
Received: 6/29/05
-
Atlantic
Glass Manufacturer: Oldcastle Glass - Telford, PA
Wood from existing/salvaged transoms
AV Smoot
Sent: 6/29/05
Ballard
Sent: 6/29/05
Received:
7/8/2005
Ballard
Sent: 6/29/05
Received:
7/8/2005
Ballard
Sent: 6/29/05
Received:
Ballard
Ballard
Bettinger-West
Sent: 6/29/05
Sent: 6/29/05
Sent: 6/29/05
Received:
Received:
Received:
7/8/2005
7/8/2005
7/8/2005
Coakley
8000.00
Inwood, WV
Sent: 6/29/05
Received: 7/11/05
-
Coakley
n/a
n/a
Sent: 6/29/05
Received: 7/11/05
-
Coakley
120000.00
Baltimore, MD
Sent: 6/29/05
Received: 7/11/05
-
Coakley
Coakley
Baltimore, MD
Baltimore, MD
Cloquet, MN
Stony Point, NY
Sent: 6/29/05
Sent: 6/29/05
Received: 7/11/05
Received: 7/11/05
-
Coakley
54000.00
141000.00
5000.00
18000.00
Sent: 6/29/05
Received: 7/11/05
-
Coakley
n/a
n/a
Sent: 6/29/05
Received: 7/11/05
-
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Analysis 2 – Phasing
Layout
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Phasing
Functionality of the school caused for a unique schedule
Project Overview
Analysis 1 – LEED®
Guide
Four Phases and Fourteen Areas
Analysis 2 – Phasing Layout
Phase 1
Nine areas covered
54% of the $1.2 million contingency used
Heavily front-end loaded
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Phasing
Initial Layout:
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
Phase 1 – 9 Areas
Phase 2 – 6 Areas
Area A
Area B
Area D
Area E
Area I
Area J
Area L
Area M
Area N
Area A
Area C
Area D
Area G
Area I
Area E
Phase 3 – 4 Areas
Phase 4 – 2 Areas
Area F
Area I
Area K
Area J
Area H
Academy Work
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Phasing
Re-Designed Layout:
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
Phase 1 – 4 Areas
Phase 2 – 4 Areas
Area A
Area B
Area M
Area N
Area C
Area D
Area E
Area H
Phase 3 – 3 Areas
Phase 4 – 4 Areas
Area F
Area G
Area I
Area J
Area K
Area L
Academy Work
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Phasing
New layout provides a more balanced schedule
Project Overview
Analysis 1 – LEED®
Guide
Phase 3 is lighter to allow for make-up time if any previous
Phases get behind
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Places the work in a nice flow based on what work is
being done and the school remaining open
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Analysis 3 – Foundation Placement
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Foundation
Project Overview
Analysis 1 – LEED®
Guide
Bulk Excavation (current) versus Trench Excavation
Goal:
Reduce labor costs, schedule, and the amount of material used
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Trench excavation eliminates the need for forming and reduces the
amount of material removed and the amount of fill
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Foundation
Table 1 - Cost Difference Summary
Trench
Bulk
Item
Excavation Excavation Difference
Material (BCY)
483.545
1310.465
826.92
Material (LCY)
531.9
1441.51
909.61
Total Costs
$13,946.96 $60,158.80 $46,211.84
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Foundation
Table 3 - Schedule / Excavator
Demand Impact
Item
Equipment
Labor (hrs/BCY) Total BCY
Trench Excavation
1 C.Y. Hydraulic Backhoe
0.04
483.55
Bulk Excavation
1 C.Y. Hydraulic Backhoe
0.027
1310.47
Difference:
Total hrs
19.34
35.38
Total Days
2.4
4.4
16.04
2
*Assume 8 hour work day
** Productivity rates taken from R.S. Means 2006
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Foundation
Outcome
Project Overview
Analysis 1 – LEED®
Guide
•
•
Increased safety measures must be taken
Trench Method Saves
– $46,211
•
•
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
–
–
2 days off schedule
826 BCY reduction in spoils
•
•
Michael Funk
Construction Management
Reduced spoils
Removal of formwork labor
and materials
Reduced by roughly 77%
Reduced site disturbance
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Conclusions
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Conclusions
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
LEED® Guide
Developed spreadsheet design to aid in obtaining various points
Phasing Layout
Adjusted the existing phasing to ease the schedule
Foundation Placement
Trench foundation placement method is a feasible alternative
•
Reduces quantities of spoils and associated costs
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Conclusions
Project Overview
Acknowledgements:
Analysis 1 – LEED®
Guide
Penn State Architectural Engineering Faculty
Analysis 2 – Phasing Layout
Grunley Construction Company
Analysis 3 – Foundation
Conclusions
Q&A
All of the LEED® Rated project personnel
Fellow AE students and LP friends
Most importantly: Mom, Dad, and Molly
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Fairfax High School
Renovation and Addition
Questions/Suggestions?
Project Overview
Analysis 1 – LEED®
Guide
Analysis 2 – Phasing Layout
Analysis 3 – Foundation
Conclusions
Q&A
Michael Funk
Construction Management
AE Senior Thesis 2007
Pennsylvania State University
Download