Straumann USA 60 Minuteman Road Andover, MA Kevin Kaufman Mechanical Option The Pennsylvania State University Architectural Engineering Presentation Outline Straumann USA INTRODUCTION Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis • Conclusions Kevin Kaufman Mechanical Option Existing conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Building Background Straumann USA Introduction EXISTING CONDITIONS Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Manufacturing Area Manufacturing storage and support areas Dental training and operatory Administrative offices Original Project Introduction EXISTING CONDITIONS Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Straumann USA Renovation of 153,000ft2 Complete airside upgrade No central plant changes Construction May 2004 – May 2005 Cost $10.6 million Straumann USA Mechanical Systems Introduction EXISTING CONDITIONS Design Objectives Mechanical Alternatives 9 VAV AHU’s 1 CAV AHU 2 natural gas boilers (11.3 MBH) 3 centrifugal chillers (750, 500, 350 tons) 2 cooling towers (750, 680 tons) Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option 1st Floor Mezzanine Design Objectives Straumann USA Introduction Existing Conditions Educational experience DESIGN OBJECTIVES Reduce annual energy costs Mechanical Alternatives Provide a lower 20 year LCC Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option System Comparisons Introduction Existing Conditions Airside Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Conclusions Kevin Kaufman Mechanical Option VAV vs DOAS Waterside Chillers Construction Breadth Life Cycle Cost Analysis Straumann USA Direct-fire Absorption Electric Centrifugal Waterside Free Cooling Series Parallel Straumann USA VAV System Advantages Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Single system for ventilation and space cooling Full air side economizing available Lower pumping costs than DOAS DOAS System Advantages Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Reduced fan energy costs Smaller air-handling units require less space and are cheaper Decouples sensible and latent loads Straumann USA DOAS Rooftop Unit Zones Introduction Reduced from 10 to 8 zones Existing Conditions Design Objectives Ventilation Air Supply Air VAV (CFM) DOAS (CFM) 35,144 510,400 15,104 143,742 % Reduction by DOAS 57.0% 71.8% MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option RTU-1 RTU-2 RTU-3 RTU-4 RTU-5 RTU-6 RTU-7 RTU-8 Straumann USA DOAS Design Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Radiant panel capacity – 54 Btu/ft2 Space DPT – 55°F Water MWT – 56.5°F Electrical Breadth Radiant Panel (Sterling) Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Ventilation rate – ASHRAE 62.1 Design Temperatures Winter – 7.7°F Summer – 90.8°F/73.7°F Annual Energy Cost Comparison Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Component Air System Fans Cooling Heating Pumps Cooling Tower Fans HVAC Sub-Total Lights Electric Equipment Non-HVAC Sub-Total Grand Total Straumann VAV $72,647 $64,415 $42,958 $17,916 $8,961 $206,897 $68,570 $423,845 $492,415 $699,312 Cost Straumann DOAS/VAV $50,727 $62,839 $20,298 $24,035 $8,752 $166,651 $68,570 $423,845 $492,415 $659,066 DOAS Savings $21,920 $1,576 $22,660 ($6,120) $209 $40,245 $0 $0 $0 $40,245 Direct-fire Absorption Chiller Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Reduce electric load and demand Natural gas available on site Possibility for simultaneous heating and cooling Absorption Chiller (Carrier) Chiller Annual Energy Comparison Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Cost Electric Centrifugal Chiller Straumann Straumann VAV DOAS/VAV Component Air System Fans $72,647 $50,727 Cooling $64,415 $62,839 Heating $42,958 $20,298 Pumps $17,916 $24,035 Cooling Tower Fans $8,961 $8,752 HVAC Sub-Total $206,897 $166,651 Lights $68,570 $68,570 Electric Equipment $423,845 $423,845 Non-HVAC Sub-Total $492,415 $492,415 Grand Total $699,312 $659,066 Direct-fired Absorbtion Chiller Straumann Straumann VAV DOAS/VAV $72,647 $50,727 $107,264 $92,452 $42,958 $20,298 $21,720 $28,737 $13,779 $9,055 $258,368 $201,270 $68,570 $68,570 $423,845 $423,845 $492,415 $492,415 $750,783 $693,685 Waterside Free Cooling - Parallel Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Reject heat without a chiller Must be able to reject entire load Waterside Free Cooling - Parallel Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Reject heat without a chiller Must be able to reject entire load Waterside Free Cooling - Parallel Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Reject heat without a chiller Must be able to reject entire load Waterside Free Cooling - Series Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Partially or completely rejects heat from chilled water Operates more hours than parallel Requires more complex controls Waterside Free Cooling - Series Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Partially or completely rejects heat from chilled water Operates more hours than parallel Requires more complex controls Waterside Free Cooling - Series Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Partially or completely rejects heat from chilled water Operates more hours than parallel Requires more complex controls Waterside Free Cooling - Series Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Partially or completely rejects heat from chilled water Operates more hours than parallel Requires more complex controls Waterside Free Cooling - Results Introduction Existing Conditions Design Objectives Ton Hours Free Cooling Parallel Series (55) Series (51) Life Cycle Cost Analysis 591 591 591 0 33036 11470 769711 770465 769014 -754 698 800.0 Cooling Load (tons) Construction Breadth Ton Hours Series Total Energy Savings Compared to Cooling (kW) Parallel (kW) Cooling Load vs Wet Bulb Temperature MECHANICAL ALTERNATIVES Electrical Breadth Straumann USA 600.0 400.0 200.0 Conclusions 0.0 0.0 Kevin Kaufman Mechanical Option 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 Wet Bulb Temperature (F) Chiller No Cooling Series Cooling (51) Free Cooling Chiller 2 Electrical Breadth Introduction Existing Conditions Design Objectives Mechanical Alternatives ELECTRICAL BREADTH Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Straumann USA Branch Circuit Summary of Alterations Item Breaker Panel Id Action taken Wire Szie Description Size 5 Single Phase 5HL2 VAV Boxes #14 15 Ciructs Removed 4 Single Phase 5HL2 FPB'S #14 15 Circuits Removed 4 Three Phase 5HL2 FPB'S #8 30-40 Circuits Removed 4 Single Phase 5HL3 VAV Boxes #14 15 Ciructs Removed 3 Single Phase 5HL3 FPB'S #14 15 Circuits Removed 2 Three Phase 5HL3 FPB'S #8 30 Circuits Removed 6 Single Phase 5HL4 VAV Boxes #14 15 Ciructs Removed 1 Single Phase 5HL4 FPB'S #14 15 Circuit Removed 2 Three Phase 5HL4 FPB'S #8 30 Circuits Removed 6 Three Phase 2MCC-1 VAV Units #10 - 1/0 20-150 Circuits Removed 4 Three Phase 2MCC-1 DOAS Units #12 20 Circuits Added Freeze 6 Three Phase 10MCC-1 Protection #12 Circuits Removed Pump Conduit Size 1/2" 1/2" 1-1/4" 1/2" 1/2" 1-1/4" 1/2" 1/2" 1-1/4" 3/4" - 2" 3/4" 3/4" Straumann USA Electrical Breadth Introduction Existing Conditions Design Objectives Mechanical Alternatives ELECTRICAL BREADTH Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Panel Id 5HL1 5HL2 5HL3 5HL4 2MCC-1 10MCC-1 Wire Size 2 sets of 500 MCM Feeder Summary of Alterations VAV Breaker Size Conduit Size Wire Size 800A 3-1/2" 500 MCM 500 MCM 4/0 2 sets of 500 MCM 400A 400A 225 4" 4" 2-1/3" 800A 3-1/2" #1 100A 3" 2 sets of 500 MCM DOAS/VAV Breaker Size Conduit Size 800A 3-1/2" 300 MCM 3/0 #3 2 sets of 250 MCM 300 200 100 3-1/2" 3" 1-1/2" 500 3-1/2" #10 25 3/4" Construction Breadth Straumann USA Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth CONSRUCTION BREADTH Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option VAV Electric Costs Electric Panels $29,010 Breakers $15,313 Wiring $33,537 Conduit $249,455 Total $327,314 VAV Rooftop Units CFM Cost RTU-1 33,000 $24,000 RTU-2 33,000 $24,000 RTU-3 6,400 $10,400 RTU-4 33,000 $24,000 RTU-5 24,000 $17,700 RTU-6 24,000 $17,700 RTU-7 33,000 $24,000 RTU-8 33,000 $24,000 RTU-9 33,000 $24,000 RTU-10 33,000 $24,000 Total $213,800 DOAS Electric Costs Electric Panels $14,525 Breakers $5,860 Wiring $14,770 Conduit $108,056 Total $143,211 DOAS Rooftop Units CFM Cost RTU-1 4,273 $11,513 RTU-2 3,328 $9,675 RTU-3 1,052 $6,550 RTU-4 3,089 $9,444 RTU-5 33,000 $24,000 RTU-6 33,000 $24,000 RTU-7 33,000 $24,000 RTU-8 33,000 $24,000 Total $133,181 Straumann USA Construction Breadth Introduction First Cost Summary Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth CONSRUCTION BREADTH Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option DOAS VAV AHU Radiant Panel Diffuser Ductwork VAV/FPB Mechanical Subtotal $133,181 $602,778 $17,520 $23,616 $0 $777,094 $213,800 $0 $99,595 $34,316 $116,239 $463,950 DOAS Additional First Cost ($80,619) $602,778 ($82,075) ($10,700) ($116,239) $313,144 Electrical $143,211 $327,314 ($184,103) Total First Cost $920,305 $791,264 $129,042 Initial Chiller Cost 500 Tons (2) 300 Tons (1) Total Electric Centrifugal $191,000 $130,400 $512,400 Direct-fire Absorption $392,000 $245,000 $1,029,000 Straumann USA Life Cycle Cost Analysis Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth LIFE CYCLE COST ANALYSIS Conclusions Kevin Kaufman Mechanical Option Air System LCC Air System 20 Year Life Cycle Cost VAV DOAS $8,812,317 $8,479,052 Chiller Type Electric Absorption Life Cycle Cost Savings First Cost Annual Cost Payback $0 $333,265 $791,264 $920,305 $699,312 $659,006 N/A 3.7 years Chiller and Air System LCC Air 20 Year Life First Cost System Cycle Cost VAV $9,324,717 $1,303,664 DOAS $8,991,452 $1,432,705 VAV $10,431,686 $1,820,264 DOAS $9,905,818 $1,949,305 Annual Cost $699,312 $659,006 $750,783 $693,685 Payback N/A 3.7 years No Payback No Payback Straumann USA Conclusions Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis CONCLUSIONS Kevin Kaufman Mechanical Option DOAS has a higher initial cost but has a lower annual operating cost and can be paid back in 3.7 years. Absorption chillers increase annual operating costs. Series waterside free cooling adds a few additional hours of free cooling but will add more complex controls. Straumann USA Acknowledgements Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option AE Department Mechanical Faculty Bruce Chappell William McGee Paul Petrilli Straumann USA Brickstone Companies Justin Bem Markus Benzenhofer Questions? Chiller Heater Feasibility Straumann USA Introduction Existing Conditions Design Objectives MECHANICAL ALTERNATIVES Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Heating requirements: 3222 hrs Simultaneous heating/cooling available: 733 hrs Capable of meeting heating load: 507 hrs (16%) Straumann USA Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Costs/ft2 Electric Absorption Component Straumann VAV Straumann DOAS Straumann VAV Straumann DOAS Air System Fans $0.47 $0.33 $0.47 $0.33 Cooling $0.42 $0.41 $0.70 $0.60 Heating $0.28 $0.13 $0.28 $0.13 Pumps $0.12 $0.16 $0.14 $0.19 Cooling Tower Fans $0.06 $0.06 $0.09 $0.06 HVAC Sub-Total $1.35 $1.09 $1.69 $1.32 Lights $0.45 $0.45 $0.45 $0.45 Electric Equipment $2.77 $2.77 $2.77 $2.77 Non-HVAC Sub-Total $3.22 $3.22 $3.22 $3.22 Grand Total $4.57 $4.31 $4.91 $4.53 Component Air System Fans Cooling Heating Pumps Cooling Tower Fans HVAC Sub-Total Lights Electric Equipment Non-HVAC Sub-Total Grand Total Energy (MMBTU) Direct-fired Absorbtion Chiller Electric Centrifugal Chiller Straumann Straumann Straumann VAV Straumann VAV DOAS/VAV DOAS/VAV 1,564 1,229 1,250 356 156 4,554 1,509 9,326 10,835 15,389 1,093 1,202 616 455 155 3,521 1,509 9,326 10,835 14,356 1,564 5,838 1,250 439 246 9,337 1,509 9,326 10,835 20,172 1,093 5,072 616 542 146 7,468 1,509 9,326 10,835 18,303 Straumann USA Introduction Existing Conditions Number of Hours per Wet Bulb Range 2500 Design Objectives Electrical Breadth Construction Breadth Life Cycle Cost Analysis Conclusions Kevin Kaufman Mechanical Option Number of Hours Mechanical Alternatives 2000 1500 1000 500 0 WB < 30 30 < WB < 40 40 < WB < 50 50 < WB < 60 60 < WB < 70 Wet Bulb Temperature (F) WB > 70 Straumann USA Introduction Existing Conditions Design Objectives Mechanical Alternatives Electrical Breadth Heat Exchanger in Parallel No Cooling Free Cooling Chiller Cooling Total Conclusions Kevin Kaufman Mechanical Option 5051 2 3707 8760 0 591 904743 905334 Fan Energy Chiller Energy Additional (kW) (kW) Pump (kW) 0 50 103773 103822 0 0 665889 665889 Total Energy (kW) 0 0 0 0 0 50 769662 769711 Additional Pump (kW) Total Energy (kW) 0 0 934 0 934 0 50 15635 754780 770465 Additional Pump (kW) Total Energy (kW) 0 0 324 0 324 0 50 14184 754780 769014 Heat Exchanger in Series (55F) No Cooling Free Cooling Series Cooling Chiller Cooling Total Construction Breadth Life Cycle Cost Analysis Hours Ton Hours Hours Ton Hours 5051 2 108 3599 8760 0 591 33036 871707 905334 Fan Energy Chiller Energy (kW) (kW) 0 50 3222 103773 107044 0 0 11480 651008 662487 Heat Exchanger in Series (51F) No Cooling Free Cooling Series Cooling Chiller Cooling Total Hours Ton Hours 5051 2 38 3669 8760 0 591 11470 893274 905334 Fan Energy Chiller Energy (kW) (kW) 0 50 1134 103773 104956 0 0 12726 651008 663734