THE DUFFY SCHOOL ADDITION & RENOVATION Penn State AE Senior Capstone Project Jeremy Drummond Construction Option Advisor: anumba **Rendering of building supplied by Gary Gardner with Owner Permission April 14th, 2014 JEREMY DRUMMOND│ CONSTRUCTION OPTION PRESENTATION OUTLINE: THE DUFFY SCHOOL ADDITION & RENOVATION INTRODUCTION ANALYSIS 1 │ ROOFTOP SOLAR PANELS ANALYSIS 3 │PREFABRICATED EXTERIOR WALL PANELS I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS PROJECT OVERVIEW IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS ` VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS ANALYSIS 2 │HISTORICAL REQUIREMENTS http://www.solar.excluss.com/solarequipment/solar-panels/ http://cptmfg.com/portfolio/pew s.php Googlemaps.com Taken by Jeremy Drummond April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PROJECT BACKGROUND THE DUFFY SCHOOL ADDITION & RENOVATION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW PROJECT BACKGROUND III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Building History: Marcella. L Duffy School 1870 Expansion 1950 Closed 2008 Building Use: Affordable Senior Citizen Apartments 53 New Units Gym, Entertainment Center, Library, Doctors Office, Kitchen, Etc. General Building Information Building Name Location Function Size Height Cost Construction Delivery The Duffy School Addition and Renovation Florence, NJ Residential 70,593 GSF 3 Stories $9.3 Million GMP April ‘14- April '15 Design-Bid-Build April 14, 2015 THE DUFFY SCHOOL ADDITION & RENOVATION JEREMY DRUMMOND│ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS PROBLEM IDENTIFICATION COMPONENTS FEASIBILITY ANALYSIS Analysis #1 Implementing Rooftop Solar Panels ELECTRICAL BREADTH IMPLEMENTATION & RECOMMENDATION IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION ENERGY COSTS THE DUFFY SCHOOL ADDITION & RENOVATION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: VIRTUAL MOCKUPS PROBLEM IDENTIFICATION Problem Identification: Proposed Solution: Affordable Apartments Apartment Amenities Payment Method? Rooftop Solar Panels Research Goal: COMPONENTS Different types of photovoltaic systems Sunlight Properties Cost vs. Schedule FEASIBILITY ANALYSIS ELECTRICAL BREADTH IMPLEMENTATION & RECOMMENDATION IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS http://www.solar.excluss.com/solar-equipment/solarpanels/ April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION THE DUFFY SCHOOL ADDITION & RENOVATION SOLAR PANEL COMPONENTS PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: VIRTUAL MOCKUPS PROBLEM IDENTIFICATION COMPONENTS FEASIBILITY ANALYSIS ELECTRICAL BREADTH IMPLEMENTATION & RECOMMENDATION System: Placement: Grid-tied system 4 rows of 9 panels (36 panels) SunPower X21- 345 Panel UltraLITE Model ELU14000 Centralized Inverter IronRidge XR1000 New Addition EPDM Roof Inverter Location AC panel and utility tie in located in RM IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS Created by Jeremy Drummond VII. ACKNOWLEDGEMENTS April 14, 2015 PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS PROBLEM IDENTIFICATION COMPONENTS FEASIBILITY ANALYSIS ELECTRICAL BREADTH IMPLEMENTATION & RECOMMENDATION IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS Cost: Prices Installation Total- $69,270 Solar Panel Cost Solar Panel Installation Schedule: Installation Process Longest Task Total- 18.5 Days THE DUFFY SCHOOL ADDITION & RENOVATION FEASIBILITY ANALYSIS JEREMY DRUMMOND │ CONSTRUCTION OPTION Item Mount Rack Solar Panels Inverter Circuit Breaker #12 AWG #8 AWG 3/4" Conduit 1/2" Conduit Qty. 36 4 36 1 1 20 6 1153 42 Unit Ea. Per 9 Mounts Ea. Ea. Ea. LF LF LF LF Hours 1.25 0.75 1 4 1.5 0.5 0.5 0.03 0.25 Total 45 3 36 4 1.5 10 3 34.6 10.5 147.6 Item Mount Rack Solar Panels Inverter Circuit Breaker #12 AWG #8 AWG 3/4" Conduit 1/2" Conduit Solar Panel Installation Cost Qty. Unit Total Cost $0.11 $322.54 $426.25 12420 4 36 Watt Ea. Ea. $1,366.20 $1,290.16 $15,345.00 $5,153.88 $912.05 $47.69 $89.23 $3.57 $2.44 1 1 20 6 1153 42 Ea. Ea. LF LF LF LF $5,153.88 $912.05 $953.80 $535.38 $4,116.21 $102.48 $3.18 12420 Watt $39,495.60 $69,270.76 VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS PROBLEM IDENTIFICATION COMPONENTS FEASIBILITY ANALYSIS ELECTRICAL BREADTH IMPLEMENTATION & RECOMMENDATION IV. ANALYSIS #2: HISTORICAL REQUIREMENTS Power Usage: THE DUFFY SCHOOL ADDITION & RENOVATION ELECTRICAL BREADTH Shading: Receptacles Lighting Dryer Washer Refrigerator Fireplace Exercise Equipment V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW Payback Period: III. ANALYSIS #1: ROOFTOP SOLAR PANELS Total Cost- $69,270 COMPONENTS 36 Panels FEASIBILITY ANALYSIS kWh ELECTRICAL BREADTH Electrical Rate IMPLEMENTATION & RECOMMENDATION Federal Incentive IV. ANALYSIS #2: HCash ISTORICAL REQUIREMENTS PROBLEM IDENTIFICATION Payback Period: Total Cost- $69,270 36 Panels 60480 kWh per day Output Electrical Rate- $0.12 ELECTRICAL BREADTH THE DUFFY SCHOOL ADDITION & RENOVATION Payback Period: Annual Energy Value- $3,559 Annual System Output11 Years V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS April 14, 2015 PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW Schedule Impact: Schedule Implications: 18.5 Days COMPONENTS IMPLEMENTATION & RECOMMENDATION IV. ANALYSIS #2: HISTORICAL REQUIREMENTS Cost Impact: Occupant Satisfaction Profit after 11 years NJ Green Checklist $69,270 Design Phase: Implement Early V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Implement Rooftop Solar Panels Potential Value Added: PROBLEM IDENTIFICATION ELECTRICAL BREADTH Recommendation: III. ANALYSIS #1: ROOFTOP SOLAR PANELS FEASIBILITY ANALYSIS THE DUFFY SCHOOL ADDITION & RENOVATION SOLAR PANEL IMPLEMENTATION JEREMY DRUMMOND │ CONSTRUCTION OPTION Design-Review meetings between project participants & end users Changes can be costly to implement later in the project lifecycle Construction Phase: During interior finishes April 14, 2015 THE DUFFY SCHOOL ADDITION & RENOVATION JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN Analysis #2 Historical Requirements MECHANICAL BREADTH ANALYSIS PANEL IMPLEMENTATION CONCLUSION & RECOMMENDATIONS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION REQUIREMENTS THE DUFFY SCHOOL ADDITION & RENOVATION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS REQUIREMENTS HISTORICAL CONSULTANT CONCLUSION & RECOMMENDATIONS Requirements: Chalkboards Trim Tin Ceilings Border Panels V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Provided by Gary Gardner Construction Provided by Gary Gardner Construction April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION THE DUFFY SCHOOL ADDITION & RENOVATION HISTORICAL CONSULTANT PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS REQUIREMENTS HISTORICAL CONSULTANT Consultant: Issue #1: Keystone Preservation Group Location Previous Projects Cost??? Current Storage Item Movement On-Site Containers CONCLUSION & RECOMMENDATIONS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Created by Jeremy Drummond Taken by Jeremy Drummond April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: HISTORICAL CONSULTANT Issue #2: Issue #3: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS THE DUFFY SCHOOL ADDITION & RENOVATION Window Procurement Schedule Delays Consultant Installation Issues Labeling Consultant REQUIREMENTS HISTORICAL CONSULTANT CONCLUSION & RECOMMENDATIONS V. ANALYSIS #3: PREFAB EXTERIOR WALLS Taken by Jeremy Drummond VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Provided by Keystone Preservation Group Provided by Gary Gardner Construction April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION IMPLEMENTATION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS NALYSIS #2: #2: H HISTORICAL ISTORICALRR EQUIREMENTS EQUIREMENTS REQUIREMENTS HISTORICAL ISTORICALCONSULTANT CONSULTANT CONCLUSION ONCLUSION& &RRECOMMENDATIONS ECOMMENDATIONS V. ANALYSIS #3: PREFAB EXTERIOR W PANELS ALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Final Conclusions: Schedule Impact: 27 Days Comparison Summary Item Fee Comparision Summary Item Fee Consultant Firm No Firm $35,000 x +$2,000 Consultant Firm No Firm $35,000 x x $37,000 Save 27 Days x $35,000 $37,000 Architectural xBreadth $37,000 General Conditions Cost Impact: THE DUFFY SCHOOL ADDITION & RENOVATION General Conditions Schedule Schedule Total Total Save 27 Days Save $2,000 x $35,000 $37,000 Save $2,000 On-Site Storage Container Material Procurement Labeling Recommendation: Recommend hiring The Keystone Preservation Group to do historical consulting for The Duffy School. April 14, 2015 THE DUFFY SCHOOL ADDITION & RENOVATION JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS Analysis #3 Prefabricated Exterior Wall Panels CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN PANEL IMPLEMENTATION CONCLUSION & RECOMMENDATIONS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: Opportunity Identification: FAÇADE COMPARISON Proposed Facade: Original Façade: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS Time & Labor Intensive Site Congestion Weather Delays Critical Path THE DUFFY SCHOOL ADDITION & RENOVATION 9” Insulated Precast Panel Embedded Thin Brick Cost = $32/SF Erection = 8 panels/ day 3.5” Brick on Wood Stud Cost Schedule CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN PANEL IMPLEMENTATION CONCLUSION & RECOMMENDATIONS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Research Goals: Identify alternative panel Reduce schedule & cost Reduce site congestion & trade coordination on site Provided by Gary Gardner Construction Slenderwall.com April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION THE DUFFY SCHOOL ADDITION & RENOVATION PANEL DESIGN PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN PANEL IMPLEMENTATION Panel Design: Consistency & Transportation Span Building Height Maximum width 12’ Total 16 precast panels North East Created by Jeremy Drummond Created by Jeremy Drummond Panel Installation Durations 4 different panel types South CONCLUSION & RECOMMENDATIONS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Created by Jeremy Drummond Elevation Panel QTY. Duration Adjusted Duration South 6 .75 Days 1 Day North East Total 6 4 16 .75 Days .5 Days 2 Days 1 Day .75 Days 2.75 Days April 14, 2015 PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW THE DUFFY SCHOOL ADDITION & RENOVATION PANEL IMPLEMENTATION JEREMY DRUMMOND │ CONSTRUCTION OPTION Cost Implications: Building Enclosure Construction Cost Comparison Cost Comparison Summary Material Total (SF) Prefabricated Panels Cost/SF Total Traditional Brick Cost/SF Total Site Layout: III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN PANEL IMPLEMENTATION Item Prefabricated Panels Total Cost Traditional Brick Total Cost Exterior Face Wall Interior Components 6,200 $32.00 $198,400 $10.47 $64,914 6,200 $18.73 $116,126 $18.73 $116,126 Insulation Caulking Transportation Erection Equipment 6,200 1,190 x $1.65 $2.18 Included $10,230 $2,594.20 Included $2.89 x x $17,918 X X x Included Included x $35,026 $54.56 $327,350 $32.09 $233,984 Cost of Assembly General Conditions Cost $327,350 $233,984 $466,630 $487,156 Total $793,980 $721,140 CONCLUSION & RECOMMENDATIONS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Difference + $72,840 Total Created by Jeremy Drummond April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW PANEL IMPLEMENTATION Final Conclusions: Cost Implications: Implement = Additional $6/SF III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS Interior Components Same Vapor Barrier, Sheathing & Backup PANEL IMPLEMENTATION 16 Architectural Precast Panels Schedule Reduction = 15 Days Implementation Cost = $72,840 Recommendation: CURRENT VS. PREFABRICATED FAÇADE PANEL DESIGN THE DUFFY SCHOOL ADDITION & RENOVATION General Conditions Savings Not in owner’s best interest to pursue 15 Days = $20,526 CONCLUSION & RECOMMENDATIONS Increased cost and planning for implementation outweigh savings in schedule and building performance VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Created by Jeremy Drummond April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION PRESENTATION OUTLINE: CONCLUSIONS ANALYSIS 1 │ ROOFTOP SOLAR PANELS I. INTRODUCTION Implement Rooftop Solar Panels II. PROJECT OVERVIEW Save Cost Help Occupants III. ANALYSIS #1: VIRTUAL MOCKUPS IV. ANALYSIS #2: FAÇADE PREFABRICATION V. ANALYSIS #3: REVALUATING COMP. SLAB THE DUFFY SCHOOL ADDITION & RENOVATION ANALYSIS 2│ HISTORICAL REQUIREMENTS Would hire an historical consultant firm Reduced Schedule & Planning Increased upfront Cost ANALYSIS 3 │ PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS VII. ACKNOWLEDGEMENTS Would not recommend the prefabrication of the building’s facade Provided by Gary Gardner Construction Increased Cost & Planning Reduced Schedule April 14, 2015 JEREMY DRUMMOND│ CONSTRUCTION OPTION PRESENTATION OUTLINE: I. INTRODUCTION II. PROJECT OVERVIEW III. ANALYSIS #1: ROOFTOP SOLAR PANELS IV. ANALYSIS #2: HISTORICAL REQUIREMENTS V. ANALYSIS #3: PREFAB EXTERIOR WALLS VI. FINAL RECOMMENDATIONS Architectural Engineering Faculty: Dr. Chimay Anumba (Advisor) ACKNOWLEDGEMENTS Special Thanks to: THE DUFFY SCHOOL ADDITION & RENOVATION Industry Acknowledgements: My Family & Friends Alex Medvesky - Gary F. Gardner Dominic DeSantis- Gary F. Gardner Janine Owens- Conifer LLC. PACE Industry Members VII. ACKNOWLEDGEMENTS April 14, 2015 JEREMY DRUMMOND │ CONSTRUCTION OPTION THANK YOU THE DUFFY SCHOOL ADDITION & RENOVATION Questions & Comments Provided by Gary Gardner Construction Provided by Gary Gardner Construction April 14, 2015