TIM BEARDMORE 3/7/2014 Project Overview Procurement/Design Equipment Selection Construction Total Project SY: 2,800,000 SY Total SY complete 2010: Total SY compete 2011: Total SY complete 2012: 380,993 SY 1,380,061 SY 1,038,946 SY Four Construction Joint Venture Team Members •Integrated Management Team in all Disciplines •Treated All Partners as Equals •Weekly and as Needed PM, AM and Field Meetings •Visibility and Availability of Leadership to all $1.1B design-build UDOT project in Utah County, Utah Fixed-price, best-design procurement approach UDOT Ultimate Infrastructure Configuration (UIC) UDOT required project completion date by fall 2014 Minimize number and duration of roadway closures Focused on all Scoring Criteria Scope 60% Provided 10 Miles more than Base Project 2 Miles more than Competitors MOT 20% Maintained More Capacity During Construction Then Before Project Started ABC Bridges Advanced Traveler Information Systems Schedule/Interim Milestones 20% 35 Month Schedule – 9 Months Shorter than Competition Delivered Northern 5 Miles 6 months early Pavement design objectives & criteria Traffic loads Existing pavement and embankment PCCP overlay design PCCP new alignment design Transverse joint design Longitudinal joint design Design during construction Official design procedure: 1993 AASHTO/UDOT Design features: Mainline 10 traffic lanes, including HOV Ramps Cross streets Design life: 30-years (minimal maintenance) per UDOT RFP Performance criteria: Initial smoothness Terminal smoothness Existing pavement/embankment/subgrade: HMA (several layers of overlays) Untreated aggregate base Embankment material: slag, other Subgrade support along a long project was characterized using soil classification & structural deflection testing. Geotechnical boring logs (RB&G Engineering) provided to PRC indicated the presence of slag embankment in some areas, while other areas were built upon silty sands and gravels with low embankments. PRC utilized Falling Weight Deflectometer (FWD) data provided by UDOT to structurally characterize the subgrade materials along the Project. The FWD data, combined with known layer thicknesses from the geotechnical exploration, was analyzed through a process known as back calculation to develop the key subgrade inputs for pavement design Concrete pavement: modulus of subgrade reaction, or k-value. Flexible pavement: resilient modulus for flexible pavements). 1993 AASHTO Pavement Design Guide methodology to back calculate subgrade resilient moduli along the project length. Back calculation was performed considering the existing 11-in AC thickness over 6-in UTBC, over embankment/subgrade. By cross-referencing the back calculated subgrade resilient modulus profile with geotechnical boring logs, project length was divided into three foundation stiffness areas along the project length. Categorized as “Strong” and “Weak” “Strong” subgrade has Mr = 25,000 psi. “Weak” subgrade has Mr = 12,500 psi. Back calculated elastic moduli adjusted to appropriate design input lab values at optimum moisture content. “Strong” subgrade has design Mr = 9,250 psi. “Weak” subgrade has design Mr = 4,625 psi. Table 1. PRC PJCP Designs for I-15 CORE Base Type Subgrade Support Description 6.5 miles ‘Strong’ Slag Embank PJCP ‘Widening’ 6.5 miles ‘Strong’ Slag Embank 600’ North of Geneva Road Bridge to SR 75 PJCP ‘Reconstruct in Weak Subgrade Area’ 11.2 miles ‘Weak’ Fine grain Emb SR 75 to Spanish Fork Main Street PJCP ‘Reconstruct in Strong Subgrade Area’ 4.1 miles ‘Strong’ Slag Embank Location Description Lehi Main Street to 600’ North of Geneva Road Bridge PJCP ‘Whitetopping’ over existing HMA Lehi Main Street to 600’ North of Geneva Road Bridge ??-in PCCP Top HMA K-Value Top OGB/GB K-Value HMA: 7-in Exist or 3-in New 6-in UTBC Exist or 6-in OGB 12-in GB New Subgrade K-Value “Strong” = 203psi/in “Weak” = 94 psi/in Embankment/Subgrade Cores indicated 9 to 13-in thickness. Some deterioration of HMA Significant cores show stripping, disintegration Some layer debonding Back calculated modulus along project indicated reasonable in situ modulus for support of PCCP Inputs Traffic: 95 million heaviest trafficked lane Subgrade: Segment design k-value Base HMA: 3-in Subbase OGB: 6-in Tied PCC shoulders Joint spacing: 15-ft PCC mean strength: 720-psi 40-year PCCP Mainline Concrete Overlay Designs Location Along Project Project Centerline Length JPCP Thickness Base Layer Whitetopping Overlay – Lehi Main Street to 600’ North of Geneva Road 6.5 miles 12.0 in 7 in Existing Widening Adjacent to Whitetopping – Lehi Main Street to 600’ North of Geneva Road 6.5 miles 12.0 in 3 in ACB Subbase Layer Design Life Design ESALs 6 in UTBC 40 Years 95.5M 6 in OGB 12 in GB 40 Years 95.5M 40-year PCCP Mainline Reconstruction and Ramp Designs Location Along Project Project Centerline Length JPCP Thickness Base Layer Subbase Layer Design Life Design ESALs 40 Years 95.5M Reconstruction – 600’ North of Geneva Road to SR 75 11.2 miles 12.5 in 3 in ACB 6 in OGB 12 in GB Reconstruction – SR 75 to Spanish Fork Main Street 4.6 miles 12.0 in 3 in ACB 6 in OGB 12 in GB 40 Years 95.5M N/A 10 in 3 in ACB 6 in OGB 12 in GB 40 Years 32.5M Ramps 1.5-in diameter dowels 5 / wheelpath, 12-in spacing Table 9. M-E PDG results for 40-year PJCP Reconstruction 12-in PJCP, 3-in HMA, 6-in OGB, 12-in GB, weak subgrade Performance Criteria Distress Target Reliability Distress Reliability AcceptTarget Predicted Predicted able Terminal IRI (in/mi) 172 95 103.2 97.5 Pass Transverse Cracking (% slabs cracked) 15 95 0 99.999 Pass Mean Joint Faulting (in) 0.12 95 0.032 99.87 Pass Equipment selection was based upon meeting the project goals of delivering a high quality pavement product in less than 3 years under heavy traffic in tight work areas. 1 - GP 4000 with IDBI (In-The-Pan Dowel Bar Inserter)-4 Track 2 - GP 2800 with IDBI- 4 Track 1- GP 2800-2 Track 3 - Commander III’s 2 with a zero clearance kit 1 with a v-mold kit (variable width) 3 – 9500 Trimmer/Placer (set up for a concrete placer) 4 – Texture/Cure 600 4 – Leica PaveSmart 3D CONVENTIONAL SET UP: Sell grade Survey Drill through asphalt to set pins Set Pins Set Wire Measure Each Pin Eyeball the wire line Check wire prior to paving LEICA PAVESMART Set up in a controlled environment (office) Sell grade Check control, Import the design into the paver Paving the day after selling grade Know where you are at all times Safer working conditions Paving in Organized Chaos Total Scope SY of pavement Schedule Traffic Planning Tools Special Equipment Machine selection Detailed paving passes Smoothness Quality Considerations Paving in inclement weather (hot/cold) April 1, 2010 started temporary widening for phase I construction. PRC has until Dec 30, 2012 to complete the project. PRC’s decisions on pave passes were based on schedule considerations and on MOT plans rather than on paving efficiencies. It is a different mindset. Started paving September 15, 2010 MOT was worth 20% of the scoring criteria when UDOT evaluated proposals for I-15: CORE UDOT was determined to minimize impacts to the traveling public during the project This determination forced the Construction Joint Venture to think outside of the box in construction techniques Many construction means and methods were driven by schedule and MOT rather than production efficiencies. Paver selection (including IDBI’s) and survey selection was driven by space limitations due to phasing, truck access, working in tight quarters, and not having enough room for staging Extensive Paving Plans. Detailed out all paving passes Daily meetings amongst the paving group to cover new issues that arose that day. Coordination with Other discipline work going on. • • • • • • • Side slopes being finished Noise Wall Posts being drilled, set, concreted in place Noise wall panels Sharing the same haul road Barrier Curb and Gutter Drillers for sign foundation Verification of Mix Designs Inspection of Aggregate Sources Inspection of Batch Plants Sampling and Testing of Stock Piles (Daily) Sampling and Testing of Concrete in Front of Paver Inspection of Dowel and Tie Bar Insertion Ensuring Paving Equipment is in Good Condition (inc. Vibrators) Inspection of the Finishing Operation Check on the Texturing Measurement of the Curing Compound Application Hot Paved w/ the big pavers at night Increased efforts to keep asphalt cool Cold 3000 blankets for 5 miles Increased monitoring Surface thermometers Maturity meters From procurement through execution, UDOT was committed to delivering the best value while taking all steps possible to minimize impacts to the traveling public. Best value approach and acceptance of MEPDG design yielded a 40 yr pavement design, 10 years higher than the specified 30 yr requirement. Schedule and MOT constraints made the construction team research and procure equipment that allowed them to step outside of the traditional mindset Steeves, Kelly ACPA Paving Powerpoint Paving Presentation. 2012 Barnes, Tuhr. Risley, Scott. Tolbert, Brian. Wood, Darren. I-15 Case Study: Powerpoint. 2013