March 5 2015 Open Planning Meeting Agenda Presentation posted on 2-19-15 Updated:2015-02-19 12:17 CS

advertisement
Public Service Company of New Mexico
Public Transmission Planning Meeting
March 5, 2015
Albuquerque, NM
Agenda
•
•
•
•
•
•
•
•
•
Introduction
Agenda Additions
Stakeholder Process
PNM 10-Year Plan Development
Regional Activities
Summary of Current Interconnection Study Activity
Order 1000 Stakeholder Process Status
Other Items
Next Meeting
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
2
Introduction
• Public Stakeholder Meetings
– Order 890 Objective to improve transparency
– Involvement of all affected stakeholders
• Coordinated with WECC processes
– Reliability – System performance evaluations, reliability standards
and coordination.
– TEPPC – Planning Policy and Economic Evaluations
• Formalized Stakeholder Input through WestConnect STP
Agreement
• OATT Appendix K defines each utility’s planning process.
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
3
PNM Bi-Annual Meetings
• March Meeting
– Study Plan
– Solicit Stakeholder Input to Plan
• November
– 10-Year Plan Review
– Solicit Stakeholder input on plan and follow-up
to be included in next planning cycle
• Others as needed
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
4
PNM Study Plan Objectives
• Support Data Base Development for PNM
and Regional Studies
– 2017 (2-yr), 2020 (5-yr), 2025 (10-yr)
• Maintain Reliability
• Define Transmission for Native, Network
and Point-Point Customers
• Incorporate Plans Developed Through
FERC Processes, NM IRP and Regional
Planning Analysis
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
5
Study Scope
• Review transmission adequacy with network
customer updates to designated network resources
and load.
• Determine if new system improvements or
adjustments to existing improvements are needed
to serve expected obligations.
• Develop operational mitigations or system
improvements to maintain system reliability and
associated cost estimates and schedule.
• Incorporate assessments of economic congestion if
applicable.
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
6
Methodology
• Powerflow Assessments
–
–
–
–
All lines in service
Single circuit or transformer contingencies
Double circuit contingencies
Breaker failure contingencies
• Short Circuit Analysis
• Stability Analysis
– Dynamic Stability
– Voltage Stability
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
7
Key Assumptions
• Load forecast
– Slow growth
– Effects of energy efficiency, demand response and load side distributed renewables
• Generation modeled
– In-Service
– Under Construction with expected ISD
• Wind resources
– Capacity for summer peak based on historical – low contribution
– Sensitivity cases for high wind periods
• Committed projects will be included as part
of base case assumptions
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
8
Modeling Criteria for PNM Planning Area
• NERC/WECC Reliability Criteria (included with
Study Plan)
– Line loading criteria
– Base Case and Post-contingency voltage criteria
– Minimum voltage stability margin
– Minimum/Maximum transient voltage and
frequency
• Violations of performance criteria is basis for most
system improvements.
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
9
Final 10 Year Plan Facilities
• Facilities defined in this planning cycle for Native
and Network Customer Load Growth and Point to
Point Transmission Service
• Committed projects from other studies:
– Previous Planning Cycle
– Transmission associated with an approved IRP
• Studies performed pursuant to NM IRP rule.
– Transmission for Generator Interconnections with
notice to proceed
• Studies per FERC requirements
– New Point-Point Requests with notice to proceed
• Studies per FERC requirements
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
10
Project Additions for 2017
• Completed
– Rio Puerco-Progress 115 kV Line (2014)
• Under Construction
–
–
–
–
–
Richmond Switching Station (2016)
Rio Puerco 345 kV Station Additions (2015)
Rio Puerco-Progress 115 kV Line (2015)
Rio Puerco SVC (2015)
Yah-Ta-Hey 345/115 kV Transformer Addition (2016)
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
11
2017 Base Case
Northern New Mexico
Rio Puerco Expansion
and SVC (ISD 2015)
Northern
New Mexico
Completed
Project
Planned
Project
Yah-Ta-Hey Transformer
(ISD 2016)
Richmond Station
(ISD 2016)
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
12
2017 Base Case
Southern New Mexico
Southern
New Mexico
Alamogordo Replacement Capacitor Installation
(ISD 2015)
Completed
Project
Planned
Project
PNM Open Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
13
Planned Project Modeled for 2020
• 2017 Projects plus:
– Alamogordo Voltage Support Phase 2
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
14
2020 Base Case Additions
Southern
New Mexico
Alamogordo Replacement Capacitor Installation
(ISD 2015)
 Alamogordo Voltage Support Phase 2
(ISD 2018 +)
Completed
Project
Planned
Project
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
15
Planned Projects Modeled for 2025
• 2020 Projects
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
16
AGING INFASTRUCTURE
PROJECTS
• Spare 345/115 kV Transformer
• Spare 345 kV Line Reactor
• Equipment will be energized to support
system but can be relocated if needed.
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
17
Additional Information
• See November, 2014 meeting presentation for
additional project details.
– https://www.oasis.oati.com/PNM/PNMdocs/Open_P
lanning_MTG_11-06-14_Presentation.pdf
• 2014 Rio Puerco and Jicarilla follow-up:
– Requested WECC approval to update Path 48 Definition
and Rating in January – in 60 day review period.
– Received WECC approval for required modifications to
WECC RAS PNM-1 in January.
PNM Open Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
18
Timeline
• February 19 - Draft Study Plan distributed to stakeholders
• March 1 - Network Customer ten-year projected network load
and network resources are due to PNM
• March 5 - Stakeholder Meeting to discuss study plan.
• March 30 - Finalize detailed Study Plan and Base Cases
• March thru July – Complete analysis, develop improvements
including descriptions, one-line and cost estimates
• November 5, 2015 - Stakeholder meeting to review transmission
plan and follow-up for next study cycle
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
19
Stakeholder Discussion
• Loads and Resources required from
Stakeholders.
• Study Plan Discussion
• Comments/suggestions by March 19, 2015
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
20
Regional Projects
•
High-Plains Express
–
•
SunZia
–
–
•
Completing WECC rating process in March
Centennial West Clean Line Project
–
•
Project modified to single 345 kV line from Gladstone area to Ojo switching station.
Completed WECC Project Coordination Review Group report.
Southline Project
–
•
Some limited activity to complete preparation for next phase of studies.
Lucky Corridor
–
–
•
Received EIS Record of Decision on January
Targeting a 2020 in-service date
Tres Amigas
–
•
Phase II Completed – no Stakeholder activity in 2014.
Development agreement with Western Area Power Administration
Western Spirit Clean Line Project
–
Stakeholder relationships established with Tribal entities, PNM, and private landowners
– Initiating WECC Project Coordination Review Process
PNM Open Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
21
Map of
Transmission
HPX
SunZia
Tres Amigas
Lucky Corridor
Southline
Centennial West
Alt
Western Spirit
PNM Open Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
22
Interconnection Cluster Activity
Summary
• Fourth Definitive Cluster closed February 16, 2014
– Three requests – 415 MW
– Initial System Impact Studies completed
– Some restudies required and a Facilities Study process
started
• Fifth Definitive Cluster closed November 13, 2014
– Three requests – 148 MW
– Starting System Impact Studies
• Fifth Preliminary Cluster open through March 15,
2015
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
23
Order 1000
• Initiated an abbreviated 2015 Order 1000 Planning Cycle
• New Planning Management Committee and various subcommittee
formed.
– PMC is currently holding two meetings a month.
– Planning Subcommittee will be holding regular meetings to work through planning
analysis.
– Cost Allocation Subcommittee expected to start meetings in March.
• Most non-jurisdictional transmission owners have not signed the new
PPA. Awaiting FERC ruling on compliance filing.
• Targeting completion of a 2024 peak summer base case in March.
• New planning consultant hired through RFP process and on-board.
– Energy Strategies
PNM Public Transmission Planning Meeting
March 5, 2015 Albuquerque, NM
24
2015 Order 1000 Schedule
PNM Open Transmission Planning Meeting
March 6, 2014 Albuquerque, NM
25
Questions or Comments
Don Maez
Donald.Maez@PNM.com
505-241-4577
PNM Public Transmission Planning Meeting
March 5, 2015
Albuquerque, NM