Business Practice Revision

advertisement
Business Practice Revision
BPR
BPR008
Number
Business Practice
Section(s) Requiring
Revision (include Section
BPR
Title
BP1.14 - Current Hour Service
Revision to BP 1.14
No., Title, and Protocol Version)
Impact Analysis
Required
No
(Yes or No)
MMU Report Required
(Yes or No)
Requested Resolution
(Normal or Urgent)
Revision Description
Reason for Revision
No
Normal
The BP does not state that Current Hour requests are required to be
Pre-Confirmed.
Add the requirement that Current Hour service requests be PreConfirmed
Tariff Implications or
Changes (Yes or No; If
yes include a summary No
of impact and/or
specific changes)
Criteria Implications or
Changes (Yes or No; If
yes include a summary No
of impact and/or
specific changes)
Credit Implications
(Yes or No, and
summary of impact)
Name
E-mail Address
Company
Company Address
No
Sponsor
Jimmy Womack
jwomack@spp.org
SPP
Page 1 of 2
Business Practice Revision
Phone Number
Fax Number
501-614-3244
Proposed Business Practice Language Revision
2.14 Current Hour Transmission Service
Current-hour transmission service is non-firm hourly or secondary transmission service to be
utilized within the current hour or within the next hour but submitted less than 30 minutes prior to
the start of the hour. The following describes SPP’s business practice concerning the provision of
current-hour transmission service.
Business Practice
Requests for current-hour transmission service:

Must be made on the OASIS.

Are limited to a single hour.

Must be made for a full hour even if the intent is to schedule the service for a partial hour.

Must be scheduled and tagged and are subject to applicable scheduling timing
requirements and approvals.

Are not to be used by the transmission customer to request service for transmission
usage after the fact.

Must be PreConfirmed
Explanation / Rationale