Business Practice Revision BPR BPR021 Number Business Practice Section(s) Requiring Revision (include Section BPR Title Authorization to Plan New Business Practice No., Title, and Protocol Version) Impact Analysis Required No (Yes or No) MMU Report Required (Yes or No) Requested Resolution (Normal or Urgent) No Urgent Revision Description Reason for Revision MOPC directed SPP Engineering to develop the Authorization to Plan process and incorporate the process into a Business Practice Tariff Implications or Changes (Yes or No; If yes include a summary Possibly; Include ATPs into the SPP OATT. of impact and/or specific changes) Criteria Implications or Changes (Yes or No; If yes include a summary No of impact and/or specific changes) Credit Implications (Yes or No, and summary of impact) Name E-mail Address Company Company Address No Sponsor Katherine Prewitt kprewitt@spp.org Southwest Power Pool 415 North McKinley, STE 140, Little Rock, AR 72205 Page 1 of 3 Business Practice Revision Phone Number Fax Number (501) 614-3514 Proposed Business Practice Language Revision AUTHORIZATION TO PLAN An Authorization to Plan (ATP) is issued to those projects identified in the Integrated Transmission Process (ITP) that are needed beyond the financial commitment window. SPP will post a document on the SPP website that lists all projects that have been issued an ATP. The process flow diagram for issuing an ATP is located in Appendix A. Once ATPs have been issued from SPP’s Board of Director approved projects, SPP will include all applicable ATPs into the models for the Aggregate Study (ATSS) and Generator Interconnection (GI) study processes. ATPs will be modeled as described by the following conditions: An ATP project will be modeled if the in-service date is prior to (or equal to) the model date. An ATP project will not be modeled if the in-service date is later than the model date. An ATP project will not be modeled if no in-service date has been assigned to that project. SPP will consider those ATP projects that do not fall within any of the modeling horizons as possible solutions in future studies, but will not be limited to just those ATP projects as solutions. The authority for SPP to issue an ATP is derived from approval by the SPP Board of Directors or when such upgrade is otherwise required pursuant to the tariff. Page 2 of 3 Business Practice Revision APPENDIX A: ATP Process Flow Diagram Board Approved ITP 10, 20 Projects List of Proposed Projects Re-evaluation of ATP’s: (ITP 10, 20 Projects) Is project in financial commitment window? Project Tracking Process NTC Issued Yes No ATP’s Issued on all projects that did not receive an NTC Post a list of all ATP projects on web and notify MOPC of posting Does ATP fall within any applicable Modeling Horizon? Yes Project gets put into next interval of Models Sub process for annual Model build No Project will be considered as solutions in Future Studies Page 3 of 3