Cleco Power LLC System Impact Study for Transmission Reservation Request OASIS Request 73408113 The purpose of this study is to determine the availability of transfer capability across Cleco Power LLC’s transmission system. This study will determine the ability to accommodate OASIS Request 73408113 for 8.4 MW of Network Transmission Service beginning January 1, 2010 up to 45 MW of Network Transmission Service ending on January 1, 2019. This study was performed using the base case models identified in the table below. The studies were run using Siemens® PSS/e version 30 and MUST version 8.3 programs. Power flow models were developed to reflect anticipated operational conditions, including load, generation, extended outages and confirmed firm transactions, from January 1, 2010 through January 1, 2019. Modifications to the base cases were made to reflect the latest information available. Changes that were made include the following: 1. Existing network resource generation in the source balancing authority was re-dispatched to allow for the transaction. 2. Customer’s resources were re-dispatched to allow the transaction. 3. Cleco load was scaled to reflect the latest load forecast. 4. Confirmed firm transmission reservations were modeled for the year 2010. 5. Active OASIS transmission service request with prior queue position were added. If the flow on a monitored facility exceeds 100% of its emergency rating under normal and single contingency conditions with the transfer in place, the loading on the facility will be compared with the loading prior to the transfer. If the transfer causes an increase in flow greater than 3.0%, the facility is expected to require improvement. Furthermore, if the transfer results in transmission bus voltage levels falling below criteria under single contingency conditions, then voltage support facility additions must be constructed. With confirmed transactions, the ATC analysis indicates that the transaction is limited by the following facilities with an impact greater than 3.0%. These limiting elements must be upgraded to eliminate the transfer constraints they cause. Study Results ATC values were calculated for the study period and are listed below along with the limiting and contingency element. Due to the closely interconnected nature with neighboring systems, violations identified in directly interconnected transmission systems (“Affected System”) will require an Affected System impact study with the identified Affected System(s) prior to the granting of transmission service. Identified Affected System: None Issued by: Cleco Power Transmission Planning Department Issued on: November 25, 2009 1 This study includes the following active OASIS transmission service requests with prior queue position: 71847922, 71956063, 72310136, 72805097, 72981623, 1352934, 73436331, 73408102 Month/Year 2010 2011 2014 2019 Limiting Element None None International Paper to Mansfield 138 kV International Paper to Mansfield 138 kV Contingency Element ATC (MW) 0 6 Dolet Hills to S.W.Shreveport 345 kV Dolet Hills to S.W.Shreveport 345 kV The following transmission bus voltage levels fall below planning criteria (0.92 p.u. under N-1) as a direct result of the transaction for certain single contingencies. Affected busses and their worst offending single contingency are provided below. Year 2010 2011 2014 2019 Bus Voltage Violations None None I.P. Mansfield 138 kV I.P. Mansfield 138 kV Contingency Element Bus Voltage (P.U.) Gravel Point Rd to Wallace Lake 138 kV Gravel Point Rd to Wallace Lake 138 kV 0.8910 0.8780 Upgrade Cost Estimates Upgrade cost estimates are planning estimates for transmission facilities owned by Cleco and are listed below. A facility study will provide detailed cost estimates and solutions for the required upgrades on the limiting elements. Facility study results may be different due to transmission system configuration changes and/or prior OASIS requests in the facilities study phase. Facilities owned by others will require a system impact study and a facility study to obtain estimates of costs of required upgrades on the systems owned by others. Limiting Elements International Paper to Mansfield 138 kV International Paper 138 kV Substation Voltage Planning Estimate for Upgrade Year Needed $1,000,000 $2,000,000 2013 2013 Proposed Upgrade Installation of a 6 reactor in series with the Mansfield to I.P.Mansfield 138 kV transmission line and can be placed in-service when needed will reduce the flow below 100% for an outage of the Dolet Hills to S.W. Shreveport 345 kV transmission line at a cost of $1,000,000. In addition, 45 MVAR’s of capacitance will be needed at the new Gravel Point 138 kV substation to improve the voltage at IP Mansfield and Gravel Point 138 kV substation for the loss of the Gravel Point Road to Wallace Lake 138 kV line at a cost of $2,000,000. Hence, the total planning estimated cost for these upgrades is $3,000,000. Issued by: Cleco Power Transmission Planning Department Issued on: November 25, 2009 2 Summary of System Impact Study Results: OASIS Period Request 73408113 January 1, 2010 – January 1, 2019 Cases Used 2010 Summer Peak 2011 Summer Peak 2014 Summer Peak 2019 Summer Peak Capacity ATC (MW) Available 45.0 Yes 45.0 Yes 0.0 No 6.0 Yes The requested transfer capability is available for the transactions specified in the study as stated below, OASIS Request 73408113: January 1, 2010 through January 1, 2011 45.0 MW Total: 45.0 MW January 1, 2011 through January 1, 2014 45.0 MW Total: 45.0 MW January 1, 2014 through January 1, 2019 Total: 0.0 MW 0.0 MW Total: 6.0 MW 6.0 MW January 1, 2019 through January 1, 2020 These results are based upon the most recent information available at the time of the study. TTC and ATC values obtained in the study are for Cleco Power’s transmission system and are subject to change as a result of any modifications to the assumptions utilized in the study. Issued by: Cleco Power Transmission Planning Department Issued on: November 25, 2009 3 Cleco Power LLC Motor Start Study for Transmission Reservation Request OASIS Request 73408113 The purpose of this study is to determine the ability to start motor loads on the Cleco Power LLC’s transmission system. This study will determine the ability to accommodate OASIS Request 73408113. This study will investigate starting the largest rated motor at the plant with the Balance of Plant load already online. The largest motor studied is a 2,500 HP motor in 2010 up to two 5,000 HP motors installed by 2013. This study was performed using the base case models identified in the table below. The studies were run using Siemens® PSS/e version 30 program. Power flow models were developed to reflect anticipated operational conditions, including load, generation, extended outages and confirmed firm transactions, from January 1, 2010 through January 1, 2019. Modifications to the base cases were made to reflect the latest information available. Changes that were made include the following: 1. Existing network resource generation in the source balancing authority was re-dispatched to allow for the transaction. 2. Customer’s resources were re-dispatched to allow the transaction. 3. Cleco load was scaled to reflect the latest load forecast. 4. Confirmed firm transmission reservations were modeled for the year 2010. 5. Active OASIS transmission service request with prior queue position were added. If the flow on a monitored facility exceeds 100% of its emergency rating under normal and single contingency conditions while the motor is operating, the facility is expected to require improvement. Furthermore, if starting the motor results in transmission bus voltage levels falling below criteria under single contingency conditions, then voltage support facility additions must be constructed. Study Results This study includes the following active OASIS transmission service requests with prior queue position: 71847922, 71956063, 72310136, 72805097, 72981623, 1352934, 73436331, 73408102 Starting currents were calculated for the largest motor installed for each study year and are listed below. Month/Year 2010 2011 2014 2019 Motor Starting MVA Largest Motor Started 2,500 HP 2,500 HP 5,000 HP 5,000 HP Issued by: Cleco Power Transmission Planning Department Issued on: November 25, 2009 MW MVAr 2.188 2.188 4.376 4.376 14.322 14.322 28.645 28.645 4 The following transmission bus voltage levels and line flows occur during motor start. Motor Starting bus voltage and Transmission line load Year 2010 2011 2014 2019 M # Balance of Plant Load Motor 1 1 2 1 2 1 2 MW,MVAr 6.47, 4.01 11.25, 6.97 13.17, 8.17 33.66, 20.86 37.51, 23.25 35.66, 22.10 39.51, 24.49 HP 2,500 2,500 2,500 5,000 5,000 5,000 5,000 Grav Pt Rd 138kV No contingency kV 0.9782 0.9752 0.9744 0.9487 0.9468 0.9448 0.9429 %Ld1 31 29 29 34 35 34 36 Grav Pt Rd 138kV GPR-WLake out kV 0.9543 0.9440 0.9407 0.8433 0.8336 0.8296 0.8193 %Ld 11 13 14 34 37 36 39 Grav Pt Rd 138kV IPM-Man out kV 0.9643 0.9628 0.9617 0.9247 0.9220 0.9216 0.9188 %Ld 24 29 30 62 65 64 67 Upgrade Cost Estimates Upgrade cost estimates are planning estimates for transmission facilities owned by Cleco and are listed below. A facility study will provide detailed cost estimates and solutions for the required upgrades on the limiting elements. Facility study results may be different due to transmission system configuration changes and/or prior OASIS requests in the facilities study phase. Facilities owned by others will require a system impact study and a facility study to obtain estimates of costs of required upgrades on the systems owned by others. Limiting Elements Planning Estimate for Upgrade Year Needed None Summary of Motor Start Study Results: OASIS Period Request 73408113 January 1, 2010 – January 1, 2019 Cases Used 2010 Summer Peak 2011 Summer Peak 2014 Summer Peak 2019 Summer Peak Capacity (HP) 2,500 2,500 5,000 5,000 Results Acceptable Acceptable Acceptable Acceptable These results are based upon the most recent information available at the time of the study. TTC and ATC values obtained in the study are for Cleco Power’s transmission system and are subject to change as a result of any modifications to the assumptions utilized in the study. 1 International Paper to Mansfield 138 kV transmission line load Issued by: Cleco Power Transmission Planning Department Issued on: November 25, 2009 5