Economic Study Process
General
The following outlines the current policy of Cleco Power LLC (Cleco) regarding
Economic Studies as defined in Attachment K of Cleco’s currently filed OPEN ACCESS
Transmission Tariff, OATT.
This policy shall remain in affect until such time Cleco sees fit to modify it, in a nondiscriminatory fashion, due to, among other things, better accommodate the market-place,
eliminate abuses to the process, further explain/clarify the process, or reflect changes to
the OATT itself.
All capitalized terms are defined in the Cleco Power OATT.
Definition
As defined by the Cleco OATT Attachment K, an Economic Study can consist of both a
Facilities Study and System Impact Study which are engineering analyses executed by a
Transmission Provider. More precisely, the Cleco OATT defines these studies as
follows:
System Impact Study – An assessment by the Transmission Provider of (i) adequacy of
the Transmission System to accommodate a request for either Firm Point-to-Point
Transmission Service or Network Integration Transmission Service and (ii) whether any
additional cost may be incurred in order to provide Transmission Service.
Facilities Study - An engineering study conducted by the Transmission Provider to
determine the required modifications to the Transmission Provider’s Transmission
System, including the cost and scheduled completion date for such modifications that will
be required to provide the requested Transmission Service.
Generator Interconnection Studies – An engineering study conducted by the
Transmission Providers to give a high level overview of the proposed site of new
generation. This does not replace or qualify for an actual generator interconnection
study, but rather is to be used to evaluate sites for proposed generation.
Economic Studies will not be used to grant Transmission Service.
Summary of Procedures
Based on a valid transmission Economic Study request, the following summarizes the
process.
Economic Study
 Request for Economic Studies must be received no later than December 31, to be
include in the proposed list for study the following year.







Transmission Provider will post Economic Study request to OASIS node.
Customer must execute Economic Study Agreement, provide a clear scope and
provide all requested data within 30 days upon request to study else it is deemed
withdrawn.
If deemed necessary, stakeholders will vote on the Request for Economic Studies to
determine the top three studies to be studied in sequential order.
The queue for the three chosen Economic Studies will be posted, as well as all
supporting data. There are no masked fields in the Economic Study process. Each
Economic Study will be evaluated as a stand-alone project.
The Economic Study draft reports will be posted on the OASIS as each is completed.
All posted reports are open for customer comment and suggestions.
Results will be discussed at Transmission Provider’s Summit.
Capital Projects, which may or may not include any of the proposed Economic Study
upgrades, for the next two to five years will be posted on the OASIS.
ECONOMIC STUDY AGREEMENT BETWEEN
CLECO POWER LLC
AND
[CUSTOMER]
This Agreement is made and entered into as of ___________________________, between Cleco
Power LLC (“Company”) a corporation organized and existing under the laws of the state of Louisiana
with its principal offices located at Cleco Power LLC. 2030 Donahue Ferry Road; Pineville, Louisiana
71361 and _____________________________(“Customer”), a corporation organized and existing under
the laws of the State of__________________________;
WHEREAS the Company is a public utility subject to the jurisdiction of the Federal Energy
Regulatory Commission (“FERC”) under the Federal Power Act, 16 U.S.C §791 et seq;
WHEREAS, on July 12, 2007 the Company filed with the FERC an OPEN ACCESS
TRANSMISSION Tariff (“OATT”) posted on Cleco’s OASIS.
WHEREAS, Customer is an eligible stakeholder under the Company’s OATT and has submitted a
request(s) for Economic Study via OASIS;
WHEREAS, the Company has determined on a nondiscriminatory basis that an Economic Study is
needed to evaluate the request(s) as provided in Attachment K of its OATT;
NOW, THEREFORE, the Company and Customer agree as follows:
The study to be performed per this agreement will be done in accordance with the provisions of
Attachment K of the Company’s OATT.
The purpose of the study is to evaluate the Customer’s request(s) as described below:
OASIS Request: Amount (MW)
POR
POD
Begin
End
Please identify the specific generating facility supplying the capacity and energy:
Please identify specific transmission issues which a solution is to be studied:
______________________________________________________________________________________
______________________________________________________________________________________
______________________________________________________________________________________
______________________________________________________________________________________
The Company agrees to provide all necessary labor, facilities, transportation, and supervision
necessary to perform the Economic Study for Customer.
The factors to be considered in determining the results of the Economic Studies and proposed
upgrades on the Company’s transmission system will include but not be limited to steady state power flow
study results, NERC, Regional Reliability Council and the Company’s system design criteria, transmission
capacity of the existing system, transmission capacity of the system after the request is added, and
reliability requirements of the Company and Customer.
This Economic Study will not address additions or upgrades to other transmission owner’s
transmission system.
There is no cost associated with the Economic Studies selected by the stakeholders each year at
the Stakeholder Summit.
The results of an Economic Study will not be used to grant Transmission Service, and does not
imply that the upgrades proposed will guarantee Transmission Service.
IN WITNESS WHEREOF, Customer and the Company have caused this Economic Study
Agreement to be executed by their respective authorized officials.
Cleco Power LLC
By:
__________________________________________
Title:
__________________________________________
Date:
__________________________________________
Customer
By:
__________________________________________
Title:
__________________________________________
Date:
__________________________________________