Cleaning Up Carabuela: What to do with Number Two Team 7 Ian Compton Adam DeYoung Josh Scheenstra Nathan Williams Engineering 339/340 Senior Design Project Calvin College December 12, 2012 ©2012 Team 7, Calvin College i Executive Summary Initial Project Summary The focus of this project is to provide sanitary wastewater management practices for a small village in Ecuador. The village, Carabuela, is made up of about 500 homes and is located in the Andes Mountains. Carabuela currently has a defective treatment system that is releasing untreated or poorly treated waste into a nearby river. The waste collection system is in an unknown condition and will be evaluated and redesigned as needed. Partnering Organization The project was proposed through Calvin College by the global healthcare/ministries organization called HCJB (Heralding Christ Jesus’ Blessing). HCJB operates largely out of Ecuador and does substantial work with community development projects. They have partnered with Calvin College for a while and are working with the team to help bring more sanitary conditions to the village of Carabuela. Collection system The village has an existing collection system that services approximately half of the homes. The condition and location of the system is currently unknown and will need to be evaluated. Depending on the state of the collection system, a completely new system will be designed or only broken-down portions. Treatment Facility The treatment facility is the largest part of the design. The two main requirements of the facility are that it must be a passive process and it must have low costs. The current preliminary design is a set of bar screens, followed by a set of anaerobic ponds in parallel, and an infiltration bed to discharge the treated effluent to the groundwater. This process will operate passively and require minimal maintenance and installment costs. Irrigation Distribution A feasibility study to use the treated effluent for irrigation will be done after gathering more pertinent information regarding Carabuela. Travel Requirements Team Carabuela will be traveling to Ecuador in January for 10 days to gather information about Carabuela. This trip will entail evaluating conditions of the current collection system, surveying topography, testing soil types, locating available land, working directly with HCJB, and communicating with the local people to establish a relationship and understand the cultural parameters affecting any possible designs. Costs The costs for the trip include airfare, room and board, food, equipment rental, and ground transportation. The estimated cost per person for this trip then is $1700; $1000 for airfare and a $700 contingency fund for daily expenses. This is based on a cost estimate of about $55/day given by HCJB. ii Next Steps The next steps of the project are to refine the initial treatment design and begin validating assumptions made in the collection system model. This will mainly come through the information gathered from the trip to Carabuela. iii Table of Contents Executive Summary....................................................................................................................................... ii Table of Contents ......................................................................................................................................... iv Table of Figures ............................................................................................................................................ vi Table of Tables ............................................................................................................................................ vii 1. Introduction .............................................................................................................................................. 1 1.1 The Team: Cleaning Up Carabuela .................................................................................................... 1 1.2 Project Background ............................................................................................................................. 2 2. Problem Statement .................................................................................................................................. 2 3. Partnering Organization ............................................................................................................................ 2 3.1 HCJB .................................................................................................................................................... 2 3.2 The Village and Context ...................................................................................................................... 2 4. Existing Conditions .................................................................................................................................... 5 4.1 The Treatment Plant ........................................................................................................................... 5 4.2 The Collection System ......................................................................................................................... 6 4.3 Village Demographics.......................................................................................................................... 6 5. Design Constraints .................................................................................................................................... 7 5.1 Flows and Loads .................................................................................................................................. 7 5.2 Effluent Standards............................................................................................................................... 8 5.3 Location ............................................................................................................................................... 8 5.4 Costs .................................................................................................................................................... 8 6. Design Norms ............................................................................................................................................ 9 6.1 Cultural Appropriateness .................................................................................................................... 9 6.2 Caring .................................................................................................................................................. 9 6.3 Stewardship ........................................................................................................................................ 9 6.4 Transparency....................................................................................................................................... 9 7. Design...................................................................................................................................................... 10 7.1 Collection System ........................................................................................................................ 10 7.1.1 Preliminary Design 1.1 ........................................................................................................ 10 iv 7.1.2 Preliminary Design 1.2 ........................................................................................................ 12 7.1.3 Materials Standards ................................................................................................................... 19 7.2 Treatment ................................................................................................................................... 19 7.2.1 Treatment Options ................................................................................................................... 19 7.2.2 Treatment Decision Matrix ........................................................................................................ 25 7.2.3 Selected Treatment Design Alternatives ................................................................................... 27 7.3 Effluent .............................................................................................................................................. 30 7.3.1 Effluent Targets .......................................................................................................................... 30 7.3.2 Irrigation Feasibility ................................................................................................................... 31 8. Construction and Maintenance .............................................................................................................. 31 9. Costs ........................................................................................................................................................ 31 9.1 Team Costs .................................................................................................................................. 31 9.2 Project Costs ............................................................................................................................... 32 9.2.1 Treatment System Cost ....................................................................................................... 32 9.2.2 Collection System Costs ...................................................................................................... 32 9.2.3 Design Costs ........................................................................................................................ 33 9.2.4 Cost Summary ..................................................................................................................... 33 10. Work Plan .............................................................................................................................................. 34 10.1 Interim............................................................................................................................................. 34 10.2 Trip .................................................................................................................................................. 34 11. Works Cited ........................................................................................................................................... 35 v Table of Figures Figure 1 : Map of Ecuador with a star on Carabuela .................................................................................... 3 Figure 2 : Overview Map of Carabuela ......................................................................................................... 4 Figure 3: Average Yearly Temperatures in Quito, Ecuador........................................................................... 5 Figure 4: Average Yearly Rainfall in Quito, Ecuador ..................................................................................... 5 Figure 5: Current Treatment Facility ............................................................................................................ 6 Figure 6: Preliminary Sewer Design 1.1 AutoCAD Approximate Pipe Layout for Entire System ................ 11 Figure 7 : Preliminary Sewer Design 1.2 SWMM Map with Manhole Invert Elevations and Pipe Slope .... 13 Figure 8 : Preliminary Sewer Design 1.2 SWMM Maximum Velocities ...................................................... 15 Figure 9 : Preliminary Sewer Design 1.2 SWMM Surface and Pipe Profile View of the Longest Reach (Southern Most Point to Discharge) ........................................................................................................... 16 Figure 10 : Preliminary Sewer Design 1.2 SWMM Model Conduit Peak Flows .......................................... 17 Figure 11 : Preliminary Sewer Design 1.2 SWMM Model Conduit Capacity (Ratio of Depth to Full Depth) .................................................................................................................................................................... 18 Figure 12: Manually Cleaned Bar Screen Structure Plan and Profile Views ............................................... 20 Figure 13: Typical Septic Tank Design ......................................................................................................... 22 Figure 14: Typical Bio-Filtration Setup ........................................................................................................ 23 Figure 15: Constructed Wetlands ............................................................................................................... 24 Figure 16: Infiltration Bed ........................................................................................................................... 25 Figure 17 : Waste Stabilization Pond Layout .............................................................................................. 27 vi Table of Tables Table 1 : Major Constituents of Typical Domestic Wastewater ................................................................... 7 Table 2 : Current and Projected Sanitary Flows ............................................................................................ 8 Table 3 : Preliminary Design 1.1 Pipe Lengths and Diameters ................................................................... 10 Table 4 : Collection System Flow Calculations ............................................................................................ 12 Table 5 : Sewer Size and Minimum Slope to Maintain a 2ft/s Flow Velocity ............................................. 14 Table 6 : Piping Materials............................................................................................................................ 19 Table 7: Horizontal Flow Grit Chamber Design Criteria .............................................................................. 20 Table 8 : Decision Matrix............................................................................................................................. 26 Table 9 : Waste Stabilization Pond Design Parameters .............................................................................. 28 Table 10 : Pond Sizing ................................................................................................................................. 28 Table 11: Recommended Rates of Wastewater Application for Trench and Bed Bottom Areasa .............. 29 Table 12 : Fresh Water Discharge Effluent Standards in Ecuador .............................................................. 30 Table 13 : Michigan Department of Environmental quality Standards for discharge into Ground Water . 30 Table 14 : Breakdown of Trip Costs ............................................................................................................ 32 Table 15 : Initial Estimated Wastewater Treatment Facility Costs ............................................................. 32 Table 16 : Initial Estimated Wastewater Collection System Costs.............................................................. 33 Table 17 : Initial estimated Design Costs .................................................................................................... 33 Table 18 : Total Cost Estimate .................................................................................................................... 34 vii 1. Introduction 1.1 The Team: Cleaning Up Carabuela Team Carabuela is composed of civil/environmental engineering students; each member brings a variety of experiences, interests, skills, and backgrounds to the design project. Nathan Williams Nathan was born and raised in Howell, Michigan. He is a senior at Calvin College expecting to graduate in May 2013 with a Bachelor of Science in Engineering degree. He is interested particularly in the environmental field but would like to work with water quality or quantity. He interned in the summer of 2012 at the City of Kentwood, working with the municipal engineering department. Adam DeYoung Adam was born and raised in Hudsonville, Michigan. He has a desire to use his skills acquired in Calvin College’s Engineering program to provide clean water and quality water wherever God will tell him to go. He has previously been involved with Varsity Athletics in Basketball and Track and Field at Calvin College. He has been involved in youth ministry for three years through a summer camp in Montana and Young Life in a local high school. This past summer, 2012, Adam worked as an intern at Vriesman & Korhorn Civil Engineers completing a Global Positioning System (GPS) survey, a witnessing project, and supervised new utility construction. His gained experience using the GPS will be put to use when the team travels to Ecuador. He desires to serve others with his engineering, by providing for their needs, and sharing the Gospel. Ian Compton Ian is a senior civil engineering student from Duanesburg, New York. He had the great opportunity to work with HCJB Global, the partnering mission organization of this project, in the summer of 2012. He worked specifically with the community development team in Quito on various clean water projects throughout Ecuador. He is privileged to have the opportunity to work with HCJB again. He is mostly interested in the hydraulic and environmental aspects of the project. Joshua Scheenstra Joshua Scheenstra is a senior at Calvin College who was born and raised in Kenya. His family has served as missionaries to an unreached people group for the past 26 years. He has participated in numerous community development projects in developing countries and many of them had to do with providing clean water. He has interned for Tulare Irrigation District the past three summers in California’s central valley. He is mostly interested in the hydraulics and structural aspects of civil engineering. 1 1.2 Project Background The village of Carabuela Ecuador is a small, underprivileged community of approximately 500 homes tucked in the Andes Mountains approximately 100 kilometers north of the capital city, Quito. The mission organization HCJB Global (Heralding Christ Jesus Blessings) is an international organization focused on community development in developing countries and has established large presence in Ecuador, and specifically in Carabuela. Recently, HCJB implemented a water distribution system in the village but also realized the village’s desperate need for a wastewater collection system and treatment facility. Currently, there only exists a partial collection system and all of the effluent is discharged into the local stream untreated. To solve this problem, Team Carabuela, is partnering with HCJB to design the wastewater collection system and treatment facilities for them to implement in the near future. 2. Problem Statement The goal of this project is to design a new wastewater collection and treatment system for Carabuela, Ecuador. In addition to improving sanitation, the main constraints of the project are cost, ease of design and a passive treatment facility that requires no power consumption. Keeping costs low is of high importance for the village and the organization. The design must also be able to operate passively in order to keep maintenance and labor requirements low. 3. Partnering Organization 3.1 HCJB Team Carabuela is partnering with the international mission organization HCJB Global. HCJB works with healthcare provision, community development, and multimedia ministry. They operate on almost every continent with a strong base in Ecuador and the entire Latin America. HCJB has been very active in Ecuador with both their radio and healthcare ministries. Especially from an engineering standpoint, HCJB has worked on many projects, from clean drinking water to treating wastewater. Students from Calvin College have often partnered with HCJB in the past to provide clean water needs to various villages or organizations in Ecuador and around the world. 3.2 The Village and Context The village we are working with is called Carabuela. Carabuela is a village of about 500 homes a few hours driving distance north of the capital city, Quito. Ecuador is located in South America and straddles the equator. Ecuador is divided into three main geographic regions: La Costa (the Coast), La Sierra (the Highlands), and La Amazonia (the East). La Costa is made up of the coastal western side of Ecuador, La Sierra is comprised of the Andes Mountain range through central Ecuador and La Amazonia is made up mostly of rain forest. 2 N a s Map not to scale Figure 1 : Map of Ecuador with a star on Carabuela1 Carabuela is located in La Sierra in the Andes Mountains and has a relatively mild and dry climate because of its altitude. A simplified overview of Carabuela can be seen in Figure 2. In this figure, the contour of the village is shown along with roads, and the stream running through the village. Because Carabuela is in the same climate zone as Quito, they have similar temperature and precipitation ranges. To see average yearly temperature and rainfall, see Figure 3 and Figure 4, respectively. 1 http://mappery.com/map-of/Ecuador-Map-2 3 Figure 2 : Overview Map of Carabuela2 Ecuador gained its independence from Spain in 1820 and has been plagued with political instability throughout most of the 19th and 20th centuries. It is currently a republic and has been holding democratic elections since the late 1970s. Economically, Ecuador is growing and has stabilized considerably over the past few decades. Almost half of its exports are crude oil related and the rest is made up mostly of agricultural products, such as bananas and coca3. Ecuador has also improved in the health care and infrastructure development areas over the past few decades; however, rural areas, such as the area surrounding Carabuela, are still in need of much improvement. 2 3 HCJB https://www.cia.gov/library/publications/the-world-factbook/geos/ec.html 4 Figure 3: Average Yearly Temperatures in Quito, Ecuador4 Figure 4: Average Yearly Rainfall in Quito, Ecuador 5 4. Existing Conditions 4.1 The Treatment Plant The initial treatment plant for the approximately 200 homes that were connected to the collection system was a septic tank and leach field (Figure 5). The leach field was undersized and became saturated6. Untreated wastewater is now discharged into the river by the school (Figure 5). This treatment system failed and an adequately sized treatment system is needed. The septic tank could be used with a rebuilt treatment field to treat a portion of the wastewater but most of the wastewater needs to be diverted elsewhere. The location of the current drainage field is 4 From World Weather and Climate Information From World Weather and Climate Information 6 Obtained from Bruce Rydbeck, October 2012, HCJB 5 5 concerning because of its close proximity to the river and presumably the groundwater table as seen in Figure 5. The size and status of the septic tank and drain field can be verified upon visiting the site. Figure 5: Current Treatment Facility7 4.2 The Collection System The initial information provided by HCJB on the collection system is very limited. The given information stated that an existing collection system is attached to approximately 200 of the 500 homes and was built around 2005 or 2006, but the condition and definite location is unknown. HCJB further stated that the 200 homes are roughly located on the east side of the village between the central hill and the PanAmerican Highway. The only specific pipe information given was that one known 20cm diameter concrete pipe runs perpendicular to the highway. The water consumption for the village was also given from which a total treated water flow of 265600 L/day was calculated. The infiltration flow rate given was 1 to 2 liters/second for the entire system. Not further information was provided. 4.3 Village Demographics The 508 homes in the village were modeled with a growth rate of 3% per year. The growth rate was provided by HCJB as an initial constraint. 7 Provided by HCJB 6 5. Design Constraints 5.1 Flows and Loads In order to correctly design a suitable treatment facility for Carabuela, the concentration and amount of wastewater constituents was crucial to understand. Due to the lack of specific information regarding waste loads in Ecuador or developing countries in general, an estimate was made according to Table 1. We assumed a strong waste concentration. This confirms other research relating to waste in developing countries as well as previous design teams that have worked in Ecuador with HCJB. Table 1 : Major Constituents of Typical Domestic Wastewater8 Constituent Total solids Dissolved solids (TDS)19 Suspended solids Nitrogen (as N) Phosphorus (as P) Chloride1 Alkalinity (as CaCO3) Grease BOD510 (mg/L) Strong 1200 850 350 85 20 100 200 150 300 (mg/L) Medium 700 500 200 40 10 50 100 100 200 (mg/L) Weak 350 250 100 20 6 30 50 50 100 The water usage is 332 m3/day for the 508 homes, but only about 200 homes are connected to the sewer line.11 The water usage for just the homes that are connected would then be around 133 m 3/day. Sanitary flow typically ranges from 50% to 100% of the water usage.12 Sanitary flow ranges greatly from city to city and there is no data for the flow in Carabuela so a safe estimate of 80% of the water usage was used for comparing treatment options. Sanitary flows into the collection system vary throughout the day, so it is important to be able to predict and design for peak flows. The peaking factor is related to population and tends to become less pronounced at higher populations. The peaking factor can be 8 UN Department of Technical Cooperation for Development (1985) The amounts of TDS and chloride should be increased by the concentrations of these constituents in the carriage water. 10 BOD5 is the biochemical oxygen demand at 20°C over 5 days and is a measure of the biodegradable organic matter in the wastewater. 9 11 12 Obtained from Bruce Rydbeck of HCJB in October 2012 Reynolds, Tom D., and Paul A. Richards. Unit Operations and Processes in Environmental Engineering. 2nd ed. Boston: PWS Publishing Company, 1996: 96. 7 calculated using πΈπ· πΈπ¨ = π Equation 1, where P is the population in thousands and Qp/QA is π·π.π the peak hourly flow divided by the average hourly flow. πΈπ· πΈπ¨ = π Equation 1 : Sanitary Flow Peaking Factor13 π·π.π Table 2 : Current and Projected Sanitary Flows Year Average Sanitary Flow (L/day) 2012 265.6 2032 (Projected) 479.7 Peaking Factor 4.15 3.69 Peak Hourly Sanitary Flow (L/day) 1102 1770 The sanitary flows in Table 2 exclude storm water since there is a minimal time period where storm water will dictate the amount of wastewater that can be treated. The projected flows are based on a project design life of 20 years with a population growth rate of 3%.14 5.2 Effluent Standards The effluent quality standards given by HCJB were quite vague. The standards for the design were to be comparable to similar projects. In order to find a suitable target, case studies and national standards were researched. For specific values, see Table 12 and Error! Reference source not found. in section 7. 5.3 Location The village location itself is also a constraint that we have considered in relation to the proposed design solution. Carabuela is in a mountainous and somewhat arid region. This limits the amount of land available for the implementation of the design solution as well as the amount of water available to the village for irrigation. 5.4 Costs It is imperative to the design system’s costs as low as possible. This is a major constraint for our team and HCJB as well as the village itself. We were given a maximum target cost of $50,000 (US) for the 13 14 Reynolds, Tom D., and Paul A. Richards. Unit Operations and Processes in Environmental Engineering: 98. Obtained from Bruce Rdbeck of HCJB in October 2012 8 treatment facility and collection system (excluding labor costs). This dollar figure came from our HCJB contact in Ecuador. 6. Design Norms 6.1 Cultural Appropriateness The cultural appropriateness is of utmost concern in our proposed design. It was very important to prioritize the differing culture and societal standards of Carabuela, Ecuador as opposed to Grand Rapids, Michigan. Before travelling to the village, our designs could only be considered as tentative until they could be evaluated in their proper context. As Christians, it was important to us not to try and impose a type of cultural norm on the treatment design or the village. 6.2 Caring At its most basic level, the purpose of the design project and proposed solution is to be able to help people that need it. The village of Carabuela is currently living in unsanitary and unsustainable conditions. The driving force of this project is to be able to provide a basic need to people without the ability to provide it for themselves. It was important for our team to keep this in mind in order to stay grounded and focus on helping people in need. 6.3 Stewardship The design norm of stewardship is a crucial element to our design constraints and proposed solution. An idea implicit within our design criteria is that the treated wastewater effluent must be safe for the environment and potential contact with humans downstream. This idea is fundamental to our beliefs as Christians that the earth has been charged to humans to be taken care of. Stewardship is also important to the types of materials used in the design as well. Ideally, these materials will maximize the effectiveness of the design while still not polluting the earth or having a negative effect for many years. 6.4 Transparency It was important that our design be transparent, especially during the designing process itself. Treatment designs must be clear and easy to comprehend under ordinary circumstances; however, it is so much more imperative that this is the case when working across vast geographic and linguistic barriers. Our communication with our engineering contact in Ecuador was infrequent at best due to availability constraints. This made it very important that our communication with him was very concise and clear. Many of the resources that we came in contact with were written in Spanish. This was also something our group had to keep in mind when translating technical information into English. 9 7. Design 7.1 Collection System 7.1.1 Preliminary Design 1.1 Because the initial information was so limited, the preliminary design for the collection system was based on numerous assumptions. The entire system to collect from all 508 homes was initially modeled with sewage pipes running down each street and laid out in AutoCAD. The design can be seen below in Figure 6. The main assumption made was that no system already exists. The assumption was made to get an assessment of what the total length of pipe will be needed if the entire system has to be replaced. The initial design yielded a total pipe length of 11500m. The estimated pipe diameters and lengths can be seen below in Table 3. The pipe diameters and locations were chosen to have the smaller pipes on the outskirts and the larger pipes for the main sewers where the largest flows are found. The primary purpose of the preliminary design 1.1 was to find out what total pipe lengths would be to estimate the initial cost. Because the location of the existing system was too vague, the initial cost plan used this design layout of the entire system and did not take into account the possible 200 homes already connected. After further information is collected, a much more accurate assessment will be made. Table 3 : Preliminary Design 1.1 Pipe Lengths and Diameters 6” Concrete Pipe 8” Concrete Pipe 10” Concrete Pipe Total Length (ft) 3326.4 3125.7 5051.3 11503.4 10 Figure 6: Preliminary Sewer Design 1.1 AutoCAD Approximate Pipe Layout for Entire System 11 7.1.2 Preliminary Design 1.2 After completing the general layout in Preliminary Design 1.1, a much more accurate and specific model was created in Preliminary Design 1.2. This design’s purpose was to model the area on the east side of the village where the probable location of the existing collection system resides. The computer software used for this design was SWMM (Storm Water Management Model), which is a universally recognized storm water and wastewater simulation program. Although the actual location of the system was unknown, it was assumed that the pipes ran along the major streets and collected from all the homes in the most populated part of the area between the hill and the Pan-American Highway. Figure 7 shows the SWMM system layout. Table 4 shows the flow calculations for the model. (NOTE: Because SWMM only used US Customary units all units were converted to that, and after the final model is finished all the results will be converted back to SI units) The flow calculations in Table 4 were based on the water consumption and infiltration flows given by HCJB. Assuming that the average household hosts 5 members the total population connected to the system was calculated. Additionally, the peak factor as a function of population was calculated using Curve G given in the ASCE Manuals and Reports on Engineering Practice- No. 60. The peak factor multiplied by the average discharge yielded the peak discharge for the entire system and when divided by the number of homes it gave the peak discharge per home. Finally, the peak discharge per home was multiplied by the number of homes contributing to each node in the SWMM system and modeled as inflow in that location. Table 4 : Collection System Flow Calculations Discharge Collection System Flow Calculations US Customary Units SI Units 35 gal/cap/day 0.133 m3/cap/day Infiltration 22824.49 gal/day 90 m3/day Infiltration 0.035315 cfs 0.001 m3/s # of Homes Population Total Population Peak Factor Average Discharge 229 homes 5 persons/home 1145 total persons 3.761 Curve G 62899.49 gpd 229 5 1145 3.761 241.7125 homes persons/home total persons Curve G m3/day Peak Discharge Peak Discharge Per Home 0.366 0.001598 0.0105 4.59504E05 cms cms cfs cfs 12 Figure 7 : Preliminary Sewer Design 1.2 SWMM Map with Manhole Invert Elevations and Pipe Slope 13 Several key design parameters were assumed for Preliminary Design 1.2. First, to ensure that the pipes conveyed all of the waste adequately, a minimum velocity of 2ft/s was assumed (Practice No. 60). To attain the minimum velocity, a minimum slope was required for each pipe. The minimum slopes for various diameters required to ensure a 2ft/s velocity are shown below in Table 5 (Practice No. 60) and the slopes of each pipe are seen above in Figure 7. Figure 7 also shows the invert elevations based on the contour map of the village provided by HCJB. To prevent velocities from getting too high on the villages steep slopes, a maximum velocity of 10ft/s was also assumed (Practice 60). Figure 8 shows the designs initial velocities in the pipes. This initial design shows some possible problems in the system that need to be addressed once final pipe locations and slopes are confirmed. Primarily, the main possible problem is the areas where velocities may not reach the minimum 2ft/s or may exceed 10ft/s. Table 5 : Sewer Size and Minimum Slope to Maintain a 2ft/s Flow Velocity Sewer Size (in) 8 10 12 15 18 21 24 30 36 Minimum Slope (ft/100ft) 0.40 0.28 0.22 0.15 0.12 0.10 0.08 0.058 0.046 14 Figure 8 : Preliminary Sewer Design 1.2 SWMM Maximum Velocities Second, the minimum cover necessary was assumed to be 3 ft. Because the area is never inflicted with freezing temperatures, no consideration was needed for the possibility of the water freezing in the pipes. Additionally, because none of the houses have basements where bathrooms or other water utilities exist, no consideration was taken to place the pipes below house basement levels. The minimum cover of 3 feet was chosen to ensure that the pipes are always protected from vehicle loads in the roads and possible erosion that would expose the pipes. The pipe and soil profile view can be seen below in Figure 9. Further study will be done of the optimal depth once more information can be gathered from the trip to Carabuela in January. 15 Figure 9 : Preliminary Sewer Design 1.2 SWMM Surface and Pipe Profile View of the Longest Reach (Southern Most Point to Discharge) 16 Finally, a pipe diameter of 8 inches was chosen initially based on the smallest available pipe sizes. Sewers in the United States rarely use pipes smaller than 8 inches but after further information is gained on the trip to Ecuador, 6 inch pipes may be substituted later. The main criteria for the conduit flows were that the pipes should never surcharge and should be able to adequately handle all the flows. Figure 10 below shows the peak flows in each pipe. Figure 11 shows the each pipe’s capacity, or the ratio of maximum depth to full depth. The pipe capacity confirms that none of the pipes ever become surcharged because none of the values exceed 1. Figure 10 : Preliminary Sewer Design 1.2 SWMM Model Conduit Peak Flows 17 Figure 11 : Preliminary Sewer Design 1.2 SWMM Model Conduit Capacity (Ratio of Depth to Full Depth) 18 7.1.3 Materials Standards The piping materials that are commonly used in the U.S. for sewer design are shown below in Table 6. These materials are also commonly used around the world and will most likely be found in Ecuador. Table 6 : Piping Materials15 Pipe Material Asbestos cement Ductile iron Reinforced concrete Pre-stressed concrete Polyvinyl chloride Vitrified clay Description Rigid yet light-weight; moderate resistance to corrosion Very leak-proof; susceptible to acid corrosion High availability; vulnerable to corrosion if waste stream contains hydrogen sulfide or in high-sulfate environment Well-suited to long transmission mains; vulnerable to corrosion Lightweight and strong plastic material; resistant to corrosion Commonly used in past; resistant to corrosion; quite brittle and susceptible to leakage 7.2 Treatment One of our main constraints is to design a passive process. This limited our treatment options considerably and automatically ruled out most of the processes used in the United States. Passive treatment can be very cost effective and easier to maintain than more mechanical processes if designed correctly. The passive treatment options we then considered can be seen below. 7.2.1 Treatment Options 7.2.1.1 Bar Screens Bar Screens are used for preliminary treatment. The effluent from the collection system flows through a metal screen that filters out large objects such as rags and floatables. This prevents clogging downstream and protects equipment. The closer the bars are together on the screen, the more contaminates are removed, however, this increases the need to rake and remove the contaminates from the screen. In most U.S wastewater treatment plants, bar screens are mechanically raked but our system would require manual raking in order to be passive treatment. Bar screens are very simple and have a very small footprint, which makes it an essential part of the design. A secondary flow path is needed to maintain flow while cleaning the primary flow path as shown in Figure 12. 15 Source: From Metcalf & Eddy, Inc. [6-8] Figure 12: Manually Cleaned Bar Screen Structure Plan and Profile Views16 7.2.1.2 Grit Removal Grit is defined as sand, gravel, food waste and other heavy solid materials. Removal of grit prevents excess accumulation in pipelines or waste lagoons. Grit removal also decreases the amount of manual labor needed to maintain subsequent waste lagoons. A passive grit removal technique that could be employed is a horizontal flow grit chamber. This uses weirs and control devices to maintain a constant flow of 0.3 m/s. The length of the chamber depends on the items shown in Table 7. Table 7: Horizontal Flow Grit Chamber Design Criteria17 Item Detention Time Horizontal velocity Settling velocity 50-mesh 100-mesh Head loss (% of channel depth) Inlet and outlet length allowance 16 17 Range Metric (English) 45-90 s 0.24-.0.4 m/s (0.8-1.3 ft/s) Typical Metric (English) 60 s 0.3 m/s (1.0 ft/s) 2.8-3.1 m/min (9.2-10.2 ft/min) 0.6-0.9 m/min (2.0-3.0 ft/min) 30-40% 25-50% 2.9 m/min (9.6 ft/min) 0.8 m/min (2.5 ft/min) 36% 30% Drawn by Ian Compton Wastewater Technology Fact Sheet: Screening and Grit Removal. Washington, D.C.: U.S. Environmental Protection Agency, Office of Water, 2003. Internet resource. 8 20 7.2.1.3 Waste Stabilization Ponds Waste Stabilization Ponds (or WSP’s) use the sun and natural processes to treat raw sewage. The three types of ponds considered for the design are anaerobic, facultative, and maturation. All are open bodies of water that require little to no human supervision or interaction18. The ponds are used to settle out suspended solids in wastewater as well as lower the total BOD. As the waste stream enters the pond, the liquid velocity goes to zero which causes most of the suspended solids to settle out. Bacteria in the pond then break down organic constituents in the waste. These ponds are often good treatment options when considering passive treatment methods, if the necessary amount of land is available. Ponds like these rely on a specified residence time that is required to reduce targeted waste constituents by a certain amount. The residence time is a function of how quickly the bacteria can break down waste and can vary with temperature. Ponds can be connected in series or in parallel in order to give a level of redundancy or increased residence time. Waste stabilization ponds need to be routinely cleaned in order to remove accumulated solids. WSPs, when sized correctly, can achieve 80% BOD removal19. WSPs also have a fairly large footprint, which could become a problem if areas of level ground are limited in Carabuela. 7.2.1.4 Septic tanks Septic tanks are similar to anaerobic ponds in that they separate the solids from the liquids and biologically degrade the waste20. A septic tank, however, is a watertight tank underground as shown in Figure 13. The tank allows waste to be broken down by bacteria and also relies on a certain residence time in order to optimize effectiveness. A septic tank is currently being used in Carabuela, but it is considerably undersized for the amount of wastewater being produced (Figure 13). Septic tanks also require routine removal of accumulated solids. 18 Kayombo, Sixtus. Development of a Holistic Ecological Model for Design of Facultative Waste Stabilization Ponds in Tropical Climates. Copenhagen: Royal Danish School of Pharmacy, Department of Analytical and Pharmaceutical Chemistry, Section of Environmental Chemistry, 2001. 6 19 Mara, D. Domestic Wastewater Treatment in Developing Countries. London: Earthscan Publications, 2004. 109 Internet resource 20 From Onsite Wastewater Treatment and Disposal Systems, EPA Design Manual 21 Figure 13: Typical Septic Tank Design21 7.2.1.5 Bio-filtration Bio-filtration relies on a gravity feed of the waste stream through a bed of filter media as seen in the middle of Figure 14. This is often sand of various grain sizes, but can be different forms of activated carbon or even man-made material. Filters of this type are used as secondary treatment after much of the solids is removed. The filters then often contain a layer of biofilm which helps further reduce BOD content in waste streams. However, some biofilm is flushed out with the water and trickling filters. Scum layers form periodically on the top of bio-filters and need to be routinely backwashed and/or scraped off in order to maintain optimal working conditions. The scum may contain disease-causing pathogens, but can be safely scraped off and buried.22 21 22 Drawn by Ian Compton From Onsite Wastewater Treatment and Disposal Systems, EPA Design Manual 22 Figure 14: Typical Bio-Filtration Setup23 7.2.1.6 Constructed Wetlands Since Carabuela has a natural river that flows through the town, this natural feature could be utilized for wastewater treatment in the form of a constructed wetland. This treatment option is useful for irrigation purposes because of the removal of pathogens.24 Currently, constructed wetlands have imprecise design and operation criteria. It is hard to quantify how well the wastewater would be treated. Topographic relief may also prevent this approach. A portion of the river could be lined with plants as shown below in Figure 15 . 23 24 Drawn by Ian Compton Kayombo, S., and T.S.A Mbwette. Waste Stabilization Ponds and Constructed Wetlands Design Manual UNEP-IETC. 44 23 Figure 15: Constructed Wetlands25 7.2.1.7 Ground Infiltration26 Ground infiltration is a process in which a treated discharge stream is allowed to percolate through the ground. This effectively uses the soil as a type of filter media. This process relies heavily on the type of soils in the area and the elevation of the water table. At least three feet of dry soil is required to maximize pollutant removal and prevent ground water contamination. Infiltration usually takes place as ground application or as an underground set of perforated pipes. With ground application, an effluent stream is discharged onto a gravel bed that overlays the intended infiltration area as seen in Figure 16. With underground infiltration, a pipe or pipes are laid along the bottom of an excavated trench or bed and then packed with gravel before backfilling. These methods also require routine maintenance in order to scrape off a biofilm “mat” that forms on top of the filter media and can clog the infiltration capacity. This can be lessened with the use of dosing multiple infiltration beds one at a time. This allows a period of drying for a field and can help prevent a mat from building up. 25 26 Drawn by Ian Compton From Onsite Wastewater Treatment and Disposal Systems, EPA Design Manual 24 Figure 16: Infiltration Bed27 7.2.2 Treatment Decision Matrix With many treatment options it was necessary to implement a decision matrix. The matrix seen in Table 8 is divided into preliminary treatment options and primary treatment options. Five characteristics are used to evaluate each treatment process. 1) Passive a) This was a constraint from HCJB and is critical for our design. Most treatments are either passive or not. Three of the treatment options were in between because mechanisms are needed part of the time to different degrees. 2) Maintenance a) The facility will be maintained by villagers who may not be experienced with wastewater treatment processes. The only maintenance will be in the form of manual labor. Therefor the decision of the numerical value was based on frequency and amount of labor needed. 27 Drawn by Ian Compton 25 3) Footprint a) The treatment facility needs to fit in a particular location in Carabuela. The current size of the land available is unknown yet the matrix is giving treatment options with a smaller footprint preference. 4) Cost a) The main cost of the treatment facility will be the materials that need to be brought into the village. Manual labor will be provided for construction. Therefrom the amount of piping drives the cost characteristic 5) Quality a) The wastewater needs to be treated effectively. The options presented all provide sufficient treatment. However the value of quality was based on how quickly and now much wastewater could be treated. The characteristics were weighted to give particular characteristics a greater importance. Each of the treatment options was given a rating in a characteristic from worst, 1, to greatest, 10. Three treatment options stood out from the rest of the options. These are the most desired treatments to implement. However, the different combinations of the options will dramatically increase the effectiveness of the system. Several system combinations will be looked at. Table 8 : Decision Matrix Characteristic Weight Preliminary Bar Screens Grit removal Primary Waste Stabilization Ponds Trickling filter Septic Tank Constructed Wetlands Ground Infiltration Passive Maintenance Footprint Cost 10 6 7 Quality 8 Total 6 370 10 5 8 8 10 10 8 5 4 3 306 226 10 5 8 10 10 6 4 4 8 8 3 7 6 4 8 10 5 6 4 8 8 9 7 8 8 285 217 236 256 316 26 7.2.3 Selected Treatment Design Alternatives 7.2.3.1 Waste Stabilization Ponds The most important design parameters for waste stabilization pond design are temperature, net evaporation, flow, and BOD inflow. Table 9 shows the parameters used to size the ponds. The flow used is the 20 year projected flow. We used an estimate of 30 gcd28 for BOD concentration, which results in a wastewater BOD of 287 mg/L. Net evaporation rate data was hard to find so a conservative estimate was used. A pan test needs to be conducted to more accurately define the net evaporation rate. The target reduction of the fecal coliform per 100 ml of wastewater is <10 4.29 This will allow the treated effluent to be used for restricted irrigation based on WHO standards. Figure 17Figure 2 shows the potential layout for the waste stabilization ponds. There are two sets of anaerobic, facultative, and maturation ponds connected in parallel. The ponds connected in parallel provide redundancy so that a pond can be shut down for desludging while the system remains operational. The additional ponds also provide the desired removal of fecal coliform to provide an effluent suitable for irrigation purposes. The pond sizing required to produce an effluent of 1767 fecal coliform per 100 ml of wastewater is given in Table 10. This effluent would be clean enough for restricted irrigation. In order to achieve a cleaner effluent the ponds would need to be larger or have the influent pretreated. The area of land available will be determined upon visiting the site. The preferred placement of the ponds would be at a higher elevation so that the treated effluent can be conveyed to irrigation fields without installing pumps. Figure 17 : Waste Stabilization Pond Layout 28 29 http://www.unep.or.jp/Ietc/Publications/Water_Sanitation/ponds_and_wetlands/Design_Manual.pdf. 20 WHO, . Guidelines for the Safe Use of Wastewater, Excreta and Greywater, Volume 1: Policy and Regulatory Aspects. Geneva: World Health Organization, 2006. Internet resource. 27 27 Table 9 : Waste Stabilization Pond Design Parameters Parameter temperature (C°)30 net evaporation rate (mm/day) flow (L/day) BOD5 (mg/L) Volumetric Loading (gm/day/m3)31 Anaerobic Pond Depth (m) Facultative Pond Depth (m) Maturation Pond Depth (m) Surface Loading (kg/hectare-day) Fecal Coliform/100 ml of Wastewater Value 16 4.2 479700 287 200 3 1.5 1 262 10,000,000 Table 10 : Pond Sizing Quantity Retention Time (days) Size (m2) Anaerobic 2 1.43 127 Facultative 2 8.54 1512 Maturation 2 4.47 1186 6 14.44 5650 Pond Total 7.2.3.2 Infiltration Beds A set of infiltration is also proposed as a discharge mechanism for the treated effluent. This will discharge the effluent to the ground water, as long as there are suitable soils and a low enough water table. This process will deliver a treated effluent that should be of suitable quality to release into the environment and not damage wildlife or pollute water sources. Not many design specifications can be finalized before a visit to the village. This is because infiltration relies heavily on the soil type in the area. Different soil types allow for different rates of application to the beds. Some recommended rates can be seen in Table 11. 30 31 www.weather.com http://www.unep.or.jp/Ietc/Publications/Water_Sanitation/ponds_and_wetlands/Design_Manual.pdf. 21 28 Table 11: Recommended Rates of Wastewater Application for Trench and Bed Bottom Areas a32 Soil Texture Gravel, coarse sand Coarse to medium sand Fine sand, loamy sand Sandy loam, loam Loam, porous silt loam Silty clay loam, clay loamd Percolation Rate (min/in) <1 1–5 6 – 15 16 – 30 31 – 60 61 - 120 Application Rateb (gpd/ft2) Not suitablec 1.2 0.8 0.6 0.45 0.2e a May be suitable for sidewall infiltration rates Rates based on septic tank effluent from a domestic waste source. A factor of safety may be desirable for wastes of significantly different character. c Soils with percolation rates <1 min/in can be used if the soil is replaced with a suitably thick (>2ft) layer of loamy sand or sand. d Soils with expandable clay b 7.2.3.3 Residuals33 Periodically, bio-solids must be removed and disposed of properly in order to keep the treatment process in an optimal condition. In the preliminary design, the main source of residuals will be from the bar screens and waste stabilization ponds. Waste stabilization ponds will need to be routinely cleaned about once a year. The solids removed will have high concentrations of BOD, suspended solids, grease, hair, grit and disease-causing pathogens.34 This requires care in their disposal in order to maintain healthy conditions. In the United States, the largest volume of residuals comes from septic tanks. This is called septage and is handled in a variety of ways. Septage can be dewatered and spread over land; both on and under the surface, buried in trenches, applied to a landfill, burned, composted, digested (both aerobically and anaerobically), or treated with chemicals. In this design, many of the facilities and infrastructure used in the United States are lacking. This limits options for residual removal in Carabuela. For this design, we recommend composting the removed residuals. This option does not require much equipment and can be done locally with little of the offensive odors associated with other methods. This is also much safer than some options and contains less risk of contaminating ground water. Composting requires adding a “bulking agent” to the waste in order to help aerate the waste and prevent stagnation. This requires periodic mixing of the waste with an organic agent such as wood chips or shavings. These agents are readily available in the area and are easy to create. After a suitable amount of time, most of the pathogens in the waste will be destroyed and the compost will be acceptable to add to soil. 32 From Onsite Wastewater Treatment and Disposal Systems, EPA Design Manual From Onsite Wastewater Treatment and Disposal Systems, EPA Design Manual 34 Table 9-1, Onsite Wastewater Treatment and Disposal Systems 33 29 7.3 Effluent 7.3.1 Effluent Targets Due to comparatively lax wastewater effluent standards in Ecuador, finding suitable effluent quality standards for the region were difficult to find. However, we did find Ecuadorian standards as listed in Table 12. These standards are considerably weak and are even comparable to weak waste stream influents. Table 12 : Fresh Water Discharge Effluent Standards in Ecuador 35 Contaminant BOD5 Total Suspended Solids Nitrogen Phosphorous pH Fecal Coliform Bacteria Standard Concentration 100 mg/L 100 mg/L 10 mg/L 10 mg/L 5–9 Removal >99.9% or 0 eggs/L for use in agriculture After looking into effluent standards by the EPA, Michigan Department of Quality, and the World Health Organization, we compiled a set of standards as seen in Table 13. Table 13 : Michigan Department of Environmental quality Standards for discharge into Ground Water Contaminant CBOD TSS Total Phosphorous Total Inorganic Nitrogen pH Sodium Chloride Concentration 25 mg/L monthly average; 40 as 7-day average 30 mg/L monthly average; 45 as 7-day average 5 mg/L 10 mg/L 6.5 - 9 150 mg/L 250 mg/L 35 From Ecuadorian Congress: NORMA DE CALIDAD AMBIENTAL Y DE DESCARGA DE EFLUENTES : RECURSO AGUA LIBRO VI ANEXO 1 30 7.3.2 Irrigation Feasibility Until more information is gathered, we cannot confirm the feasibility of using the treated effluent as an irrigation source. This is due mainly to the lack of information regarding the layout of the village. If most of the agricultural fields are downhill of the village, it may be quite possible to have a gravity feed to the effluent to the farmland. However, if most of the fields are at a higher elevation than the treatment facility, then it may no longer be feasible for the village to use the effluent stream as an irrigation source. This part of the project will be put on hold until information can be gathered from the village. 8. Construction and Maintenance Construction of the project will be completed by HCJB, if chosen to be implemented. Labor then will be provided by either the organization or the village itself. It still remains unknown what type of equipment HCJB has at their disposal in order to build the proposed treatment facility. The infiltration bed especially requires delicate construction methods so as not to damage the soils or disturb its permeability. Maintenance is projected to be relatively low. The proposed treatment process is designed to be a passive process only requiring routine maintenance and cleaning. Dosing of the infiltration bed will need to be changed periodically to perform optimally. This can perhaps be done on a daily or weekly basis. The bar screens will need to be raked on a need basis. Routine cleaning will have to be performed on the ponds yearly. This will require draining the pond (one at a time) and removing the accumulated solid residuals. The infiltration bed will also require periodical maintenance if a biofilm mat begins to develop on the surface of the soil media. 9. Costs 9.1 Team Costs Team 7 requests $6100 as its total budget for the academic year. This amount is not feasible based on the class’s budget so we are requesting the initial allotted $500 with whatever extra can be added if funds permit. To attain the rest of the funds, our team is applying for the Innotec grant and raising our own support. Currently, we have raised $2300 of our own support so far. Table 14 shows all the costs for the team. 31 Table 14 : Breakdown of Trip Costs Trip Costs (9 days) Per Day Airfare (round trip) Based on Hotwire.com Daily Costs ($/day) As given by HCJB Per Person $55 Totals: Total for Team $1,050 $4,200 $495 $1,980 $1,695 $6,180 9.2 Project Costs The project costs are divided into three parts: design work, collection system costs, and treatment system costs. No labor or excavation costs were included because our client requested them to be left out. 9.2.1 Treatment System Cost The estimated initial treatment costs are shown in Table 15. These are based on the EPA cost curves of a lagoon construction costs. Table 15 : Initial Estimated Wastewater Treatment Facility Costs 3-Phase Treatment Plan View Area (Pond) Anaerobic Depth Volume SI Volume English Retention Rate (m2) 254 (m) 3 (m3) 762 (ft3) 26910 (Days) 1.43 Facultative maturation 3024 2372 1.5 1 4536 2372 160190 83766 8.54 4.47 Totals: 5650 8000 282517.3 14.44 Cost (1979 US $) $2,200.00 $20,000.0 0 $4,500.00 $26,700.0 0 Cost (2012 US $) $4,510.00 $41,000.0 0 $9,225.00 $54,735.0 0 9.2.2 Collection System Costs Initial estimated collection system costs are shown in Table 16. Values are very high right now because this is for the entire village and approximately half is already in place so a good amount of the costs are already covered. Because we don’t know which part or where it is this is the overall cost of what the whole village would be. 32 Table 16 : Initial Estimated Wastewater Collection System Costs Initial Pipe Costs (PVC and Concrete) 10" Pipe 8" Pipe Length (m) 5051.3 3125.7 Concrete Pipe $20.10 $17.40 Cost ($/m) Cost ($): PVC Pipe Cost ($/m) Cost ($): 6" Pipe 3326.4 $15.60 $101,531 (Cheapest)=> $47.37 $54,387 $51,892 Total Cost ($) $207,810 $33.36 $24.87 $239,280 $104,273 $82,728 Total Cost ($) $426,281 9.2.3 Design Costs The team is made up of for engineers. Each will generate an average of 8 hours in a week. The rate for work is an industry standard for covering the overhead costs of an engineering firm. The total costs are over 14 weeks, the first semester as seen in Table 17. Table 17 : Initial estimated Design Costs Number of Hours Per Week 8 8 8 8 Hourly Cost 100 100 100 100 Weekly Cost $800.00 $800.00 $800.00 $800.00 Total Total Costs $11,200.00 $11,200.00 $11,200.00 $11,200.00 $44,800.00 9.2.4 Cost Summary The project is large and we currently have no data parting to a possible distribution of the effluent to surrounding farmland. Adding that portion would increase the project cost substantially. Table 18 shows out total costs. A contingency factor is within the extremely conservative design of the collection system and the treatment facility. Yet we added a 15% contingency to the total because we are at such an early stage of the design process. 33 Table 18 : Total Cost Estimate Item Trip Design Treatment Facility Collection System Total With 15% Contingency Cost $6,200 $44,800 $54,700 $207,800 $360,525 The total cost of our Project is currently $360,525. This is not including the potential distribution of the effluent, but it includes a 15% contingency. 10. Work Plan 10.1 Interim The team will make final preparations for the trip to Carabuela at the end of January. This will involve gathering of all necessary equipment and questions that need to be addressed. The main piece of equipment that is still needed is a GPS unit for surveying the current wastewater collection system and possible placement of new sewer lines. HCJB is planning on buying a new GPS unit. They could have it sent to our team to bring with to practice with it and make sure it is compatible with the team’s laptops. HCJB also has a theodolite to check the slope of the sewer drains. The major questions that need to be addressed during the team’s visit are: What and how much land is available for treatment? What types of crops are grown in the area? What on-site treatment is currently implemented? Where is the water table high? What is the infiltration rate of the soil? How are the household connections to the collection system regulated? A more finalized itinerary will be made as well during interim break. 10.2 Trip The team will travel to Ecuador for the days of January 19-27. HCJB Engineer Cesar Cortez will accompany the team to Carabuela till Engineer Bruce Rydbeck returns on the 22nd. Bruce will accompany the team on January 24-26. Visiting engineers Andrew and Laura Price Rescola may also accompany the team for several days. The team plans to hand over a copy of this report to HCJB to be translated into Spanish and given to the community. This will provide value to collaboration between the team and the village. The expected costs of the trip are in section 9.1 and the team will plan accordingly. 34 11. Works Cited “Gravity Sanitary Sewer Design and Construction”. ASCE Manuals and Reports on Engineering PracticeNo. 60. Kayombo, Sixtus. Development of a Holistic Ecological Model for Design of Facultative Waste Stabilization Ponds in Tropical Climates. Copenhagen: Royal Danish School of Pharmacy, Department of Analytical and Pharmaceutical Chemistry, Section of Environmental Chemistry, 2001. Kayombo, S., and T.S.A Mbwette. Waste Stabilization Ponds and Constructed Wetlands Design Manual UNEP-IETC. Mara, D. Domestic Wastewater Treatment in Developing Countries. London: Earthscan Publications, 2004. Internet resource Onsite Wastewater Treatment and Disposal Systems: Design Manual. Washington, D.C: U.S. Environmental Protection Agency, Office of Water Program Operations, 1980. Print. Reynolds, Tom D., and Paul A. Richards. Unit Operations and Processes in Environmental Engineering. 2nd ed. Boston: PWS Publishing Company, 1996: 96. UN Department of Technical Cooperation for Development. (1985) The use of non-conventional water resources in developing countries. Natural Water Resources Series No. 14. United Nations DTCD, New York. Wastewater Technology Fact Sheet: Screening and Grit Removal. Washington, D.C.: U.S. Environmental Protection Agency, Office of Water, 2003. Internet resource WHO, . Guidelines for the Safe Use of Wastewater, Excreta and Greywater, Volume 1: Policy and Regulatory Aspects. Geneva: World Health Organization, 2006. Internet resource. World Weather and Climate Information. N.p., 2010-2011. Web. 7 Dec. 2012. <http://www.weatherand-climate.com/average-monthly-Rainfall-Temperature-Sunshine,Quito,Ecuador>. 35