LIQUIDATED AND ASCERTAINED DAMAGES (LAD) AND REQUIREMENTS OF MITIGATION YONG MEI LEE UNIVERSITI TEKNOLOGI MALAYSIA PSZ 19: 16 (Pind. 1/97) UNIVERSITI TEKNOLOGI MALAYSIA BORANG PENGESAHAN STATUS TESIS ♦ JUDUL: LIQUIDATED AND ASCERTAINED DAMAGES (LAD) AND REQUIREMENTS OF MITIGATION SESI PENGAJIAN : 2005 / 2006 Saya YONG MEI LEE ___________________________ (HURUF BESAR) mengaku membenarkan tesis (PSM / Sarjana / Doktor Falsafah)* ini disimpan di Perpustakaan Universiti Teknologi Malaysia dengan syarat-syarat kegunaan seperti berikut: 1. Tesis adalah hakmilik Universiti Teknologi Malaysia. 2. Perpustakaan Universiti Teknologi Malaysia dibenarkan membuat salinan untuk tujuan pengajian sahaja. 3. Perpustakaan dibenarkan membuat salinan tesis ini sebagai bahan pertukaran antara institusi pengajian tinggi. 4. ** Sila tandakan (9) 9 SULIT (Mengandungi maklumat yang berdarjah keselamatan atau kepentingan Malaysia seperti yang termaktub di dalam AKTA RAHSIA RASMI 1972) TERHAD (Mengandungi maklumat TERHAD yand telah Ditentukan oleh oprganisasi/ badan di mana Penyelidikan dijalankana) TIDAK TERHAD Disahkan oleh __________________________________________ (TANDATANGAN PENULIS) Alamat Tetap: 22, Jalan Saga SD8/2E, Bandar Sri Damansara, 52200 Kuala Lumpur. Tarikh: ____________________ CATATAN: __________________________________________________ (TANDATANGAN PENYELIA) Assoc. Prof. Dr. Rosli Abdul Rashid Nama Penyelia Tarikh: ______________________ * Potong yang tidak berkenaan. ** Jika tesis ini SULIT atau TERHAD, sila lampirkan surat daripada pihak berkuasa/organisasi berkenaan dengan menyatakan sekali sebab dan tempoh tesis ini perlu dikelaskan sebagai SULIT atau TERHAD. Tesis dimaksudkan sebagai tesis bagi Ijazah Doktor Falsafah dan Sarjana secara penyelidikan, atau disertasi bagi pengajian secara kerja kursus dan penyelidikan, atau Laporan Projek Sarjana Muda (PSM). “We hereby declare that we have read this thesis and in our opinion this thesis is sufficient in terms of scope and quality for the award of the degree of Master of Science in Construction Contract Management.” Signature : ................................................................. Name of Supervisor I : ................................................................. Date : ................................................................. Signature : ................................................................. Name of Supervisor II : ................................................................. Date : ................................................................. LIQUIDATED AND ASCERTAINED DAMAGES (LAD) AND REQUIREMENTS OF MITIGATION YONG MEI LEE A thesis submitted in fulfilment of the requirements for the award of the degree of Master of Science in Construction Contract Management Faculty of Built Environment Universiti Teknologi Malaysia MARCH, 2006 ii DECLARATION I declare that this thesis entitled “Liquidated and Ascertained Damages (LAD) And Requirements of Mitigation” is the result of my own research except as cited in the references. The thesis has not been accepted for any degree and is not concurrently submitted in candidature of any other degree. Signature : ................................................................. Name : ................................................................. Date : ................................................................. iii Specially dedicated to my family for your love and support “With love and appreciation” iv ACKNOWLEDGEMENT I would like to express my thankfulness to those who have helped me in completing this thesis. First and foremost, I would like to express my sincere appreciation to my supervisor, Associate Professor Dr. Rosli Abdul Rashid, for his encouragement, support, guidance and dedication in assisting me to succeed in writing out this thesis. Special thanks to En. Jamaludin Yaakob for his concerns, comments and professional advices. Besides that, I would also like to acknowledge Associate Professional Dr. Maizon Hashim, En. Norazam Othman for their support and motivation. My appreciation also goes to all my classmates, Nor Jalilah Idris, Ling Tek Lee, Dennis Oon Soon Lee; my friends Sze Nee, Voon Chiet and Wan Siang for their great support, opinion and willingness to share their knowledge towards the completion of my research. Finally, I would like to extend my truthful appreciation to all my family members, especially my father, the late Yong Weng Lok and my beloved mother, Mdm. Kok Nyok Moi for her love and support. Yong Mei Lee March, 2006 v ABSTRACT When a project is late in completion due to contractor’s fault, the employer is entitled to a contractual remedy by enforcing the Liquidated and Ascertained Damages (LAD) provisions. However, contractors often seek to challenge the enforceability of LAD by alleging that the employers suffer no loss and that they are under a duty to mitigate their losses. Therefore, the objectives of the research are to determine the requirements of mitigation and the extent of the employer’s duty to mitigate his losses when enforcing his right under the LAD clause. The objectives of this research are achieved by analysing relevant laws governing LAD and mitigation. The governing laws include relevant statutes, judicial decisions, and the Contracts Act 1950. The research found that although the requirements is silent in standard forms of contract, an employer is bound to comply with the requirements of mitigation in enforcing LAD by taking all reasonable steps to mitigate his losses. Furthermore, employer’s duty to mitigate his losses is governed by the principles of mitigation. He is only bound to take all reasonable steps in order to comply with the requirements and does not has to embark on hazardous or uncertain courses of action that will cause him incur substantial expense or inconvenience, damage his reputation, or breach any contracts, in order to mitigate. The reasonable actions to mitigate will be determined on a case-to-case basis. In short, this research is expected to grab the attention of employers in enforcing LAD, so that they can safeguard their claims. vi ABSTRAK Apabila sesuatu projek mengalami kelewatan disebabkan kegagalan kontraktor, majikan akan menuntut gantirugi tertentu dengan mengenakan klausa Ganti Rugi Tertentu (Liquidated and Ascertained Damages, LAD). Walau bagaimanapun, kontraktor sentiasa mencabar pengenaan klausa tersebut dengan menyatakan bahawa pihak klien tidak mengalami kerugian dan mereka adalah dikehendaki mengurangkan kerugian yang dialami. Oleh yang demikian, kajian ini dijalankan untuk mengenalpasti keperluan pengurangan kerugian dan sejauh manakah klien perlu bertindak untuk mengurangkan kerugian yang dialami semasa mengenakan haknya dibawah klausa LAD. Objektif kajian ini dicapai dengan menganalisa undang-undang yang mengawal LAD dan pengurangan. Undang- undang kawalan yang berkaitan termasuklah statut, keputusan mahkamah dan Akta Kontrak 1950. Kajian ini mendapati walaupun kehendak tersebut adalah tidak dinyatakan, klien adalah terikat untuk mematuhi kehendak pengurangan semasa mengenakan LAD dengan mengambil langkah-langkah yang munasabah bagi mengurangkan kerugiannya. Tambahan pula, hak klien untuk mengurangkan kerugiannya adalah dikawal oleh dasar pengurangan. Klien hanya terikat untuk mengambil langkah-langkah munasabah bagi mematuhi kehendak tersebut dan tidak perlu bertindak sehingga menyebabkannya mengalami kerugian lanjutan atau ketidaksenangan, menjejaskan reputasinya, atau memungkiri mana-mana kontrak dalam usaha mengurangkan kerugian. Kemunasabahan tindakan mengurangkan kerugian ditentukan berdasarkan kes-kes yang tersendiri. untuk Secara ringkasnya, kajian ini dijangka akan menarik perhatian klien semasa mengenakan LAD, supaya mereka dapat mempertahankan tuntutan mereka. vii TABLE OF CONTENTS CHAPTER TITLE PAGE TITLE i DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF CASES xii LIST OF FIGURES xvi LIST OF ABBREVIATIONS xvii LIST OF APPENDICES xviii CHAPTER 1 INTRODUCTION 1.1 Background Of Study 1 1.2 Problem Statement 6 1.3 Objectives Of The Study 8 1.4 Scope And Limitations Of The Study 8 1.5 Significance Of The Study 9 1.6 Research Methodology 9 1.6.1 Stage 1: Identifying Research Issue 10 1.6.2 Stage 2: Literature Review 10 1.6.3 Stage 3: Data And Information Collection 10 1.6.4 Stage 4: Research Analysis 11 viii 1.6.5 Stage 5: Conclusion And Recommendations 11 1.7 Research Flow Chart 12 1.8 Conclusion 13 1.8.1 Chapter 1: Introduction 13 1.8.2 Chapter 2: Liquidated And Ascertained Damages (LAD) 13 1.8.3 Chapter 3: Mitigation 14 1.8.4 Chapter 4: Requirements of Mitigation and The Extent of Mitigation in Enforcing LAD Provisions 1.8.5 14 Chapter 5: Conclusion And Recommendations 14 CHAPTER 2 LIQUIDATED AND ASCERTAINED DAMAGES (LAD) 2.1 Introduction 15 2.2 Breach Of Contract 17 2.2.1 19 2.3 2.4 2.5 Remedies For Breach Of Contract Damages 20 2.3.1 General Principles of Damages 21 2.3.2 Types Of Damages 22 2.3.3 Statutory Provisions 24 2.3.4 Recovery Of Damages 26 2.3.4.1 Remoteness Of Damage 27 2.3.4.2 Measure Of Damage 29 2.3.5 Proof Of Damages 30 Liquidated And Ascertained Damages (LAD) 32 2.4.1 Express Contractual Provisions 32 2.4.2 Definition Of LAD 34 2.4.3 Merit Of The LAD Provision 35 2.4.4 Advantages Of LAD Provision 37 Component Costs Of LAD 38 2.5.1 39 Loss Of Income ix 2.6 2.5.2 Financing Loss 40 2.5.3 Business Disruption Loss 40 2.5.4 Management Costs 41 2.5.5 Professional Fees 41 LAD And Penalties 41 2.6.1 Distinction Between LAD And Penalties 42 2.6.2 Pleading Cases In Distinguishing LAD And Penalties 2.7 44 Liquidated And Ascertained Damages: The Malaysian Position 46 2.7.1 Applicable Statutory Provision 46 2.7.2 Interpretation Of Section 75 Of Contracts Act 1950 2.7.3 Recovery Of Liquidated And Ascertained Damages (LAD) 2.8 47 Conclusion 51 53 CHAPTER 3 MITIGATION 3.1 Introduction 54 3.2 Definition Of Mitigation 55 3.3 General Rules And Principles Of Mitigation 55 3.4 Mitigation In Malaysian Position 57 3.5 The Duty To Mitigate 59 3.6 Limitation Of Mitigation Upon Recovery Of Damages 63 3.7 Mitigation In Building Contracts 64 3.8 Significance Aspects In Relation To Mitigation 65 3.9 Conclusion 67 x CHAPTER 4 REQUIREMENTS OF MITIGATION AND THE EXTENT OF MITIGATION IN ENFORCING LAD PROVISIONS 4.1 Introduction 4.2 Requirements Of Mitigation in Enforcing LAD Provisions 70 4.2.1 Malaysian Law 70 4.2.2 English Law 71 4.2.3 English Commercial Law 74 4.2.4 Requirements Of Mitigation In Building Contracts 4.3 75 To What Extent That Employer Has To Mitigate His Losses In Enforcing LAD Provisions 78 4.3.1 The Extent In Loss Mitigation 78 4.3.2 4.3.3 4.4 69 Reasonableness In Taking The Duty To Mitigate 79 Bottom Line Of Mitigation 80 Conclusion 81 CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 5.1 Introduction 83 5.2 Research’s Findings 83 5.2.1 Objective 1: To Determine The Requirements Of Mitigation In Enforcing The LAD Provisions in Construction Contracts 5.2.2 84 Objective 2: To Determine The Extent That Employer Has To Mitigate His Losses In Enforcing LAD Provisions 85 5.3 Research’s Constraints 86 5.4 Suggestions For Further Research 86 5.5 Conclusion 87 xi REFERENCES 89 APPENDICES A General Procedure in Recovery of Liquidated Damages 96 B Clause 40 of the JKR Forms 203A (Rev 10/83) 99 C Clause 22.0 of the PAM 1998 Forms 100 D Clause 26 of the CIDB Form (2000 Edition) 102 E Section 74-76 of Contracts Act 1950 104 F Section 3, 5 of Civil Law Act 1956 110 G Case 1: Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh [2003] 5 MLJ 116 114 H Case 2: Payzu Ltd. v Saunders [1919] 2 K.B. 581 123 I Case 3: Selva Kumar a/l Murugiah v Thiaragajah a/l Retnasamy [1955] 1 MLJ 817 127 xii LIST OF CASES CASE PAGE AMEV-UDC Finance Ltd. v Austin [1986] 162 CLR 170, 193 ………15 Balfour Beatty Construction (Scotland) Ltd v Scottish Power plc [1994] 71 BLR 20 ………………………………………………28 Ban Hong Joo Mine Ltd. v Chen & Yap Ltd [1969] 2 MLJ 83 ………19 Bhai Panna Singh v Bhai Arjun Singh [AIR 1929 PC 179] ......47, 48, 49, 53 Boyo v Lambeth London Borough Council [1994] ICR 727 Brace v Clader [1895] 2 Q.B. 253 ………77 ………………………………………60 British Westinghouse Electric Co. v Underground Electric Railway Co. of London [1912] AC 673 Chiam Keng v Wan Min [1924] 5 FMSLR 4 ………...…….19, 56, 78 ………………………..4 Choo Yin Loo v Visuvalingam Pillay [1930] 7 FMSLR 135 Chou Choon Neoh v Spottiswoode [1869] 1 Ky. 216 Chulas v Kolson [1867] Leic.462 ……4, 19 ………………73 ………………………………………73 Chung Syn Kheng Electrical Co Bhd. v Regional Construction Sdn Bhd. [1987] 2 MLJ 763 ……………………………………4, 49 Dennis v Sennyah [1963] MLJ 95 ..……………………………………..23 Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd. [1915] AC 79 ..……………………………………....4, 16, 42 Fateh Chand v Balkrishan Dass AIR 1963 supreme court 1405 Frank & Collingwood Ltd v. Gates [1983] 1 Con LR 21 .……….5 …..…………..22 Gebruder Metel Mann GmbH & Co. KG v NBR (London) Ltd. [1984] 1 Lloyd’s Rep 614 ..……………………………………..62 xiii Government of Malaysia v Thelma Fernandez [1967] 1 MLJ 194 ............5 Government of Pakistan v Seng Peng Sawmills Sdn Bhd. [1979] 1 MLJ 219 ……………………………………………..66 Hadley v Baxendale [1854] 9 Ex 341 ………4, 24, 26, 27, 28, 30, 50, 51, 52 Hong Leong Co Ltd v Pearlson Enterprise Ltd (No 2 ) [1968] 1 MLJ 262 ………..…………………………....23, 57, 58 Hopkins v Norcross plc [1993] 1 All ER 565) ..……………………77 Hua Khiow Steamship Co. Ltd. v Chop Guan Hin [1930] 1 MC 175, 1 JLR 33 .………………………..…………….4 Hutchinson v Harris [1978] 10 BLR 19 ……………………………..65 Joo Leong Timber Merchant v Dr. Jaswant Singh A/L Jagat Singh [2003] 5 MLJ 116 .……………………...5, 76, 77, 82, 84, 87, 88 Kabatasan Timber Extraction Co. v Chong Fah Shing [1969] 2 MLJ 6 ..………………………………………….5, 59 Kemble v Farren [1829] 6 Bing 141 ...…………………………....44 Khoo Hooi Leong v Khoo Chong Yeok [1930] A. C. 346 ...……………73 Khoo Tiang Bee v Tan Beng Guat [1877] 1 Ky. 423 ……………...73 Kilbourne v Tan Tiang Guee [1972] 2 MLJ 94 ...……………………23 Kleinwort Benson Ltd v Birmingham City Council [1996] 4 All ER 733 …77 Kon Thean Soong v Tan Eng Nam [1982] 1 MLJ 323 ..…………….75 Kueh Sing Khay v Lim Boon Chuan [1950] SCR 23 ...……………67 Larut Matang Supermarket Sdn. Bhd. v Liew Fook Yung [1995] 1 MLJ 379 ..…………………………………………….17 Law v Redditch Local Board [1892] 1 QB 127 ...……………………43 Linggi Plantation Ltd v Jagatheesan [1972] 1 MLJ 89 ...4, 17, 47, 48, 49, 53 Malayan Credit Ltd. v Mohammed Kassim [1965] 2 MLJ 134 ...……..5 Maredelanto Compania Naviera SA v Bergbau-Handel GmbH; 'The Mihalis Angelos' [1970] 3 WLR 601 ……………………...77 Morello Sdn Bhd v Jaques (International) Sdn Bhd. [1995] 1 MLJ 577 (also reported at [1995] 2 CLJ 23, [1995] 1 AR 873 and [1995] 1 MAC 153) ……………………..67 Pacific Electrical Co Ltd v Seng Hup Electrical Co (S) Pte Ltd. [1978] 1 MLJ 162 ……………………………………………..66 Paradine v Jane [1647] Aleyn 26 ………………………………………1 xiv Pasuma Pharmacal Corp v McAlister & Co Ltd. [1965] 1 MLJ 221 ………………………………………65, 79, 81 Payzu Ltd. v Saunders [1919] 2 K.B. 581 ……...60, 61, 62, 66, 79, 81, 84, 87 Penang Port Commission v Kanawagi s/o Seperumaniam [1996] 3 MLJ 427 ………………………………………………76 Pilkington v Wood [1953] 2 Ch 770; [1953] 3 WLR 522 …..66, 68, 80, 82, 85 Public Works Commissioner v Hills [1906] AC 368 Robinson v Harman [1848] 1 Ex 850 ...…………….45 …………………………...19, 28 Rockingham Country v Luten Bridge Co. [1929] US Ct of App ……….65 SEA Housing Corporation Sdn. Bhd. v Lee Poh Choo [1982] 1 MLJ 324 ……………………………………....30 Selva Kumar a/l Murugiah v Thiaragajah a/l Retnasamy [1955] 1 MLJ 817 ……………………3, 24, 50, 52, 53, 87 Selvanayagam v University of the West Indies [1983] 1 WLR 585 …………………………………..64, 81 Smith Construction Co. Ltd. v Phit Kirivata [1955] MLJ 8 ………………19 Song Toh Chu v Chan Kiat Neo [1973] 2 MLJ 206 ………………………17 SS Maniam v The State of Perak [1975] MLJ 75 ………………..4, 47, 48 Stanor Electric Ltd v R Mansell Ltd. [1988] CILL 399 ………………44 Syarikat Batu Sinar Sdn. Bhd. & Ors v UMBC Finance Bhd. & Ors. [1990] 3 MLJ 468 ………………………………………73 Syed Jaafar bin Syed Ibrahim v Maju Mehar Singh Travel & Tours Sdn. Bhd. [1999] 4 MLJ 413 ………………………………31 Tan Hock Chan v Kho Teck Seng [1980] 1 MLJ 308 ………………19 Tansa Enterprise Sdn Bhd v Temenang Engineering Sdn Bhd. [1994] 2 MLJ 353 ………………………………………………58 Techno Land Improvements Ltd v British Leyland (UK) Ltd [1979] EGD 519 ………………………………………76, 77, 84 Tham Cheow Toh v Associated Metal Smelters Ltd [1972] 1 MLJ 171 ..28, 28 Toeh Kee Keong v Tambun mining Co. Ltd [1968] 1 MLJ 39 ………28 T & S Contractors Ltd v Architectural Design Associated QBD (Official Referee's Business) 16 October 1992 ………………77 Victoria (Laundry Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528 ………………………………………………26 xv Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 ...4, 24, 25, 48, 49, 53 Wee Wood Industries Sdn. Bhd. v Guannex Leasing Sdn. Bhd [1990] 2 CLR 1060 ……………………………………………….4 West v Versil Ltd & Ors Court of Appeal (Civil Division) ………………77 Westwood v Secretary of State for Employment [1985] AC 20 ………77 William Tompkinson & Sons Ltd. v Parochial Church Council of St. Michael [1990] 6 Const. LJ 319 ………………………………64 Woon Hoe Kan & Sons Sdn. Bhd. v Bandar Raya Development Bhd. [1972] 1 MLJ 75 ………………………………………………17 WT Malouf Pty Ltd v Brinds Ltd [1981] 52 FLR 442 ………………..4 Yerkey v Jones [1940] 63 CLR 649 ………………………………………19 xvi LIST OF FIGURES FUGURE NO. TITLE PAGE 1.7 Research Flow Chart 12 xvii LIST OF ABBREVIATIONS AC - Appeal Cases AIR - All India Reports Bing - Bingham Reports BLR - British Law Reports Con LR - Construction Law Reports Ex - Exchequer Reports FMSLR - Federated Malay States Law Reports ICE - Institute of Civil Engineering JLR - Johore Law Reports KB (or QB) - King’s (or Queen’s) Bench LAD - Liquidated and Ascertained Damages Lloyd’s Rep - Lloyd’s List Law Reports MC - Malayan Cases MLJ - Malayan Law Journal PAM - Pertubuhan Arkitek Malaysia PC - Privy Council PCC - Privy Council Cases PWD - Public Work Department SCR - Supreme Court Reports SIA - Singapore Institute of Architects SO - Superintending Officer UTM - Universiti Teknologi Malaysia WLR - Weekly Law Reports xviii LIST OF APPENDICES APPENDIX TITLE PAGE A General Procedure in Recovery of Liquidated Damages 96 B Clause 40 of the JKR Forms 203A (Rev 10/83) 99 C Clause 22.0 of the PAM 1998 Forms 100 D Clause 26 of the CIDB Form (2000 Edition) 102 E Section 74-76 of Contracts Act 1950 104 F Section 3, 5 of Civil Law Act 1956 110 G Case 1: Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh [2003] 5 MLJ 116 114 H Case 2: Payzu Ltd. v Saunders [1919] 2 K.B. 581 123 I Case 3: Selva Kumar a/l Murugiah v Thiaragajah a/l Retnasamy [1955] 1 MLJ 817 127 CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 Background of Study A contract is an agreement enforceable by law. 1 When two or more persons enter into a contract, their intention is normally to carry out the terms of contract as promised. 2 As a general principle, once a party enters into a contract, he must perform his obligations strictly according to the terms of contract. 3 He is liable to answer for any of the obligations, which he has failed to discharge and it is no defence to an action for incomplete performance that the party has done everything that can be reasonably undertaken if the end result falls short of that required of the contract. 4 There are only two parties to a building contract: the employer and the contractor but due to the customary divisions of duties within the building process, several other persons are named. 5 Some of these are professional advisers to the em1 Section 2(h) of Contracts Act 1950. Alsagoff, Syed Ahamad. (2003). Principles of the Law of Contract in Malaysia. Malyaisa: Malaysia Law Journal Sdn. Bhd., pp.1 3 Chow, Kok Fong. (1988). An Outline of the Law and Practice of Construction Contract Claims. Singapore: Longman Singapore Publishers Pte. Ltd., pp.27 4 Paradine v Jane [1647] Aleyn 26 5 Turner, D.F. (1971). Building Contracts: A Practical Guide. London: George Godwin Ltd., pp.9 2 2 ployer, who are also given defined responsibilities and powers under the contract, some of which may be quasi-judicial. 6 A breach of contract is essentially a non performance of a contractual obligation under conditions for which no legal excuse for the non performance exists. 7 The ordinary remedy for breach of contract is an action for damages; the innocent party is entitled to claim for a financial amount, which would compensate him for the loss incurred as a result of the breach committed by the other party. In the example of late completion, the usual redress afforded the employer would be to award him liquidated damages calculated according to a rate stipulated in the contract. 8 In exceptional cases, where a breach takes on a very serious nature so that it adversely affects some fundamental aspect of the contract, the innocent party may under common law, bring the contract to the end. 9 Liquidated damages may as a provision in a contract, and therefore agreed between the parties to the contract at the time if entering into it, which aims to determine in advance the extent of the liability for some future, specified breach. 10 Construction contracts frequently contain a “liquidated damages” clause in favour of the owner. This typical liquidated damages clause provides that if the contractor fails to complete the work by the agreed completion date, he will be required to pay the owner a stipulated amount for each day thereafter until completion. 11 For example, clause 40 12 of PWD Forms 203A (Rev 10/83), and clause 22 of PAM 98 13 provides a provision of Damages for Non-completion. Briefly, the provi- 6 Ibid. Chow, Kok Fong. (1988). An Outline of the Law and Practice of Construction Contract Claims. Singapore: Longman Singapore Publishers Pte. Ltd., pp.28 8 Ibid, pp.29 9 Ibid. 10 Turner, D.F. (1971). Building Contracts: A Practical Guide. London: George Godwin Ltd., pp.17 11 Kenny, P. (2001, March). Liquidated Damages: how much of a threat can they be? Heavy construction News. Toronto: Mar 2001 vol.45. Iss.3. Pg.32. URL:http://proquest.umi.com/pqdweb?did37477610&sid-8&Fmt-3&clientld.21690&RQT-309&VName-PQD 12 If the Contractor fails to complete the Works by the “Date for Completion” stated in the Appendix or within any extended time under Clause 43 hereof and the S.O. certificates in writing that in his opinion the same ought reasonably so to have been completed the Contractor shall pay or allow the Government a sum calculated at the rates stated in the Appendix as Liquidated and Ascertained Damages for the period during which the said Works shall so remain and have remained incomplete and the S.O. may deduct such damages from any monies due to the Contractor. 7 3 sion indicates that in the event of late completion, the contractor shall pay to the employer the LAD a specified amount per day of delay until the completion date. The employer may deduct such sum from any monies payable to the Contractor under this Contract. In addition, the LAD is considered as the actual loss that will be suffered in breach f contract and the contractor agrees to pay the said sum without the need of proving damages by the employer. Statutory provision for liquidated damages in Malaysia is found in Section 75 of the Contracts Act 1950. 14 “When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contact reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for”. The Federal Court in Selvakumar a/l Murugiah v Thiagarajah a/l Retnasamy 15 held that the employer is required to prove his actual loss suffered in accordance with the general principles of proof of damages. The Federal Court, in interpreting Section 75 held that the plaintiff who is claiming for actual damages in an action for breach of contract must still prove the actual damages or reasonable com13 22.1 If the Contractor fails to complete the Works by the Date for Completion of within any extended time fixed under Clause 23.0 or sub-clause 32.1 (iii) and the Architect certifies in writing that in his opinion the same ought reasonably so to have been completed, then the Contractor shall pay to the Employer a sum calculated at the rate stated in the Appendix as Liquidated and Ascertained Damages (LAD) for the Date for Completion or any extended date where applicable to the date of Practical Completion. The Employer may deduct such sum as a debt from any monies due or to become due to the Contractor under this Contract. 22.2 The Liquidated and Ascertained Damages stated in the Appendix is to be deemed to be as the actual loss which the Employer will suffer in the event that the contractor as in breach of the Clause thereof. The Contractor by entering into this Contract agrees to pay to the Employer the said amount(s) if the same become due without the need of the Employer to prove his actual damage or loss. 14 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd., pp.195 15 [1995] 2 MLJ 817 4 pensation in accordance with the settled principles in the English landmark case of Hadley v Baxendale. 16 Any failure to prove such damages will result in the refusal of the court to award such damages. The Contracts Act s75 provides an instance in which Malaysian law departs significantly from the line of English common law. 17 Under common law, a liquidated damages clause must comply with the ‘penalty’ principle establish by Lord Dunedin in the landmark case of Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd. 18 that: “The essence of liquidated damages is a genuine covenanted pre-estimate of loss.” What is meant by the term ‘genuine pre-estimate’ was further explained in WT Malouf Pty Ltd v Brinds Ltd 19 as: “A genuine pre-estimate means a pre-estimate which is objectively of that character: that is to say, a figure which may properly be called so in the light of the contract and the inherent circumstances. It will not be enough merely that the parties honestly believed it to be so.” The court in Malaysia have concluded that the distinction between liquidated damages and penalties does not apply, the situation being governed by section 75 of the Contracts Act which has been held to have erased this distinction. 20 16 [1854] 9 Ex 341 Robinson, N.M., et.al. (1996). Construction Law in Singapore and Malaysia 2nd ed. Singapore: the Butterworth Group of Companies., pp.244 18 [1915] AC 79 19 [1981] 52 FLR 442 20 See e.g. Choo Yin Loo v SK Visuvalingam Pillay [1930] 7 FMSLR 135, The Hua Khiow Steamship Co. Ltd. v Chop Guan Hin [1930] 1 MC 175, 1 JLR 33; SS Maniam v The State of Perak [1957] MLJ 75; Wearne Bros (M) Ltd. v Jackson [1966] 2 MLJ 155; Linggi Plantation Ltd v Jagatheesan [1972] 1 MLJ 89, [1971] 2 PCC 749, reversing [1969] 2 MLJ 253, which in turn reversed [1967] 1 MLJ 177; and Wee Wood Industries Sdn. Bhd. v Guannex Leasing Sdn. Bhd. [1990] 2 CLR 1060. See also the Bruneian Case of Chung Syn Kheng Electrical Co Bhd. v Regional Construction Sdn Bhd. [1987] 2 MLJ 763 which, however, is not, with respect, wholly unambiguous. Cf Chiam Keng v Wan Min 17 5 In addition, there is a general duty requiring that reasonable steps to be taken to mitigate losses flowing a breach particularly in the case of anticipatory breach. 21 The party who has failed to mitigate the losses cannot later recover any such loss flowing from his neglect. 22 This is a long established principle applied in Kabatasan Timber Extraction Co. v Chong Fah Shing. 23 The Federal Court held that, it was the duty of the respondent to take reasonable steps to mitigate the damages caused by the appellant when he failed to deliver logs to the mill but left them some 500 feet away. This principle also applied in Joo Leong Timber Merchant v Dr. Jaswant Singh a/l Jagat Singh. 24 The respondent counterclaimed for loss of rental income against appellant’s claim for the balance sum due for the completed building works was dismissed by the High Court due to respondent’s failure to show that he had taken all reasonable steps to mitigate his damage. Construction contracting is extremely time sensitive and timely completion of a project is frequently seen as major criteria of a project success. 25 Owners lose opportunity and profits waiting for completion of late projects. 26 Hence, a liquidated damages provision provides a straight forward method of calculating damages recoverable by an owner in the event of late completion. However, the recent position seems to put more burdens to employer in his effort to impose LAD. The recent case, Joo Leong Timber Merchant v Dr. Jaswant Singh A/L Jagat Singh 27 , employer is now liable to take mitigation in enforcing LAD although it is silent in the provision of LAD in the forms of contract. Failure in taking mitigation will cause the employer fail in recovering the LAD. [1924] 5 FMSLR 4 at 14. But cf Malayan Credit Ltd. v Mohammed Kassim [1965] 2 MLJ 134 and Government of Malaysia v Thelma Fernandez [1967] 1 MLJ 194. Reference may be also be made to the Indian Supreme Court decision of Fateh Chand v Balkrishan Dass AIR 1963 supreme court 1405. 21 Vohrah, B. and Wu, Min Aun. (2003). The Commercial Law of Malaysia. Malaysia: Pearson Malaysia Sdn. Bhd., pp.179 22 Ibid. 23 [1969] 2 MLJ 6 24 [2003] 5 MLJ 116 25 Allen, P.E.(Jan, 1995). The Estimation of Construction Contract Liquidated Damages. URL:http://www.library.findlaw.com.civil.remedies/damages/liquidated.damages./html 26 Ibid. 27 Supra. 6 As a result, the court is now applying the principle of mitigation in awarding LAD and the employer should be prudent while imposing LAD, whereby they will have to make sure that they fulfil the requirements of mitigation by taking reasonable steps to mitigate his losses and damages upon the breach of contract by the contractor. 1.2 Problem Statement Each of the standard form of contract provides for payment of an agreed sum by the contractor when completion of work is not within the stipulated time. The payment is known as liquidated and ascertained damages. The amount is usually recorded in the appendix to the form of a contract. 28 Liquidated damages are a sum, which represents a genuine pre-estimate of the loss caused by the breach, that is, of what is needed to put the plaintiff into as good a position as if the contract had been performed. 29 The liquidated damages provisions in the usual standard forms of contract for construction work is to stipulate a rate for each day of delay in completing the works, clearly links the severity of delay to the quantum of damages payable. 30 Most standard forms of construction contract are drafted to permit the parties to fix the damages payable for late completion in advance. When these damages are a genuine preestimate of the loss likely to be suffered or a lesser sum, they can rightly be termed as liquidated damages. 31 28 Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th ed. England: Pearson Education Limited., pp.32 29 Burrows, A. S. (1987). Remedies for Torts and Breach of Contract. London: Butterworth & Co. (Publishers) Ltd., pp.283 30 Chow, Kok Fong. (1988). An Outline of the Law and Practice of Construction Contract Claims. Singapore: Longman Singapore Publishers Pte. Ltd., pp.159 31 Eggleston, B. (1997). Liquidated Damages and Extension of Time in Construction Contracts. 2nd ed. London: Blackwell Science Ltd., pp.4 7 Most construction contracts provide a contractual mechanism, which allows the employer to deduct liquidated damages from amounts due to the contractor. 32 For examples, in PAM 98 33 (clause 22), PWD 203A 34 (Clause 40), and CIDB 35 (Clause 26) provide a provision of Damages and Non-completion to enable the employer to recover their damages in the event of late completion by contractor. However, contractors often seek to challenge the enforceability of Liquidated Damages clause 36 , which they consider that it has been wrongly deducted and alleged that employer actually suffered no loss in the event of delay and fails to mitigate his losses in the event of breach. 37 Such challenges may cause an uncertainty to the employer, as it is not expressed in the provisions. Further, the employers may not be aware that they are obligated to take mitigation in enforcing LAD. Thus, this matter may give raise to some queries, such as, whether the employer is bound to mitigate his loss in the event of enforcing the LAD. Since all standard forms of contract are silent about the duty to mitigate loss, then what are the rules that may override the provisions of LAD in the contract? In addition, if the employer is really bound to comply with the mitigation rules, then what are the circumstances does the employer could take mitigation and to what extent they should act to mitigate his losses? Regarding the quantum of damages, whether the employer is entitled only for the loss that he managed to mitigate, or he is totally not entitled to recover his loss if he failed in taking the duty of mitigation. Furthermore, it may be doubted that what are the circumstances that the employer is considered has conducted the said duty and how does the tribunal make the decision on this matter. 32 Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-with Particular reference to PWD/JKR standard Forms of Contract. 27 July, 2004. Kuala Lumpur: James R Knowles (M) Snd. Bhd., pp.17 33 Agreement and Conditions of Building Contract 34 Standard Form of Contract to be used where Bills of Quantities Form Part of The Contract 35 Standard Form of Contract for Building works (2000 Edition) 36 Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-with Particular reference to PWD/JKR standard Forms of Contract. 27 July, 2004. Kuala Lumpur: James R Knowles (M) Snd. Bhd., pp.18 37 Ibid. 8 In short, whether the duty to mitigate should have a controlling influence on the conduct of the innocent / injured party, or whether it is merely a method of assessing the recoverable loss and how does the mitigation may effect the enforcement of LAD by the employer? As a result, it is important to investigate the actual position of employer in enforcing the LAD. 1.3 Objectives of the Study The objectives of the study are: 1. To determine the requirements of mitigation in enforcing the LAD provisions in Construction Contracts. 2. To determine the extent that employer has to mitigate his losses in enforcing LAD provisions. 1.4 Scope and Limitations of the Study This research will be focused on following matter:- 1. The provision of Liquidated and Ascertained Damages in the standard forms of contract used in Malaysia, namely, JKR 203A, PAM98, and CIDB 2000. 2. Court cases related to the issue particularly Malaysian cases. Reference is also made to cases in other countries such as United Kingdom, Brunei, Singapore, Australia, and Hong Kong. 9 1.5 Significance of the Study The provision of LAD is provided in most standard form of building contracts in favour of the employer to recover their damages or losses due to delay in completion. However, the contractor often seek to challenge the enforcement of LAD is challenged by the contractor on certain grounds as before discussed. Such challenge put the employer in an uncertain position while enforcing LAD although the compensation for non-completion has pre-agreed by the contracting parties and stipulated in the contract. Therefore, this study is expected to unfold the queries that arise in the event of enforcing LAD in relation to mitigation. Thus, an employer will be aware of their obligations, rights, and duties in the event of recovering his damages or losses. In short, the finding of the study could be used as guidance to the employer and putting them in a better position in enforcing LAD. Finally, it is believed that the result will also be capable to resolve disputes in relation to LAD in the construction industry. 1.6 Research Methodology Briefly, the research process will be divided into five (5) stages: a. Identifying the research issue, b. Literature review, c. Data and information collection, d. Research analysis, e. Conclusion and recommendations 10 1.6.1 Stage 1: Identifying Research Issue Identifying the research issue is the initial stage of the whole research. To identify the issue, firstly, it involves reading on variety sources of published materials, such as journals, articles, seminar papers, previous research papers or other related research papers, newspapers, magazines, and electronic resources as well through the World Wide Web and online e-databases from University of Technology Malaysia, UTM library’s website. 38 1.6.2 Stage 2: Literature Review Literature review is the second stage of the research. Literature review will be involved the collection of documents which from secondary data for the research, such as books, journals, newspapers. 39 Indeed, published resources like books, journals, varies standard form of contract, and related statutory are the most helpful in this literature review stage. Besides this, reported court cases from different sources like Malayan Law Journal, Australia Law Report, and Building Law Reports will be referred. 1.6.3 Stage 3: Data and Information Collection Third stage of this research is data and information collection stage. This is an important stage towards achieving the objectives. This stage will be begun just 38 39 http://www.psz.utm.my Blaxter, L., et al. (1996). How to research. Buckingham; Open University Press., pp.109 11 after the previous two stages are completed. The further action is to collect the relevant information based on the secondary data from the published resources and carry out case studies. Lexis-Nexis database is the main source in getting the related cases. The system provides cases based on different sources of law reports available, such as Appeal Cases Report, All England Report, Building Law Report, King’s Bench Report, Singapore Law Report and other common jurisdictions. 1.6.4 Stage 4: Research Analysis In this stage, it is able to determine whether the stated objectives has been achieved or vice versa. Different types of analysis will be carried out according to the requirements of the objectives. It is important in conducting case study in the way to identify the trends and developments in the issue that is to be studied. 1.6.5 Stage 5: Conclusion and Recommendations Conclusion and recommendations is the final stage of the research. In this stage, the findings would able to show the result of the research. A conclusion need to be drawn in-line with the objectives of the research. At the same time, some appropriate recommendations related to the problems may be made for a better solution in relation to the said problem, or for further research purposes. 12 13 1.8 Conclusion Briefly, this research is related to the issues on principles of mitigation, and Liquidated and Ascertained Damages (LAD) in building contracts. The report will be divided into five (5) chapters. 1.8.1 Chapter 1: Introduction The first chapter is an introduction to the whole research and consisting of a few sub topics. The first sub topic is background of the study; followed by problem statement, that influence such research to be carried out. Subsequence is the objectives of the research that stated the aims of the study; the significance of the research as to overcome certain problems in the industry; scope and limitations to the research and finally is the research methodology that to be used during the process of research. 1.8.2 Chapter 2: Liquidated and Ascertained Damages (LAD) Briefly, this chapter will be covered by a few important subtopics, such as introduction, definition of the term, LAD and LD, principle of LAD, LAD in the Malaysian position and finally the issues or cases in relation to the enforceability of LAD in the event of breach of contract. 14 1.8.3 Chapter 3: Mitigation This chapter will discuss the definition, theories, rules, and principles of mitigation. Besides that, the function of the principle applied in damages as remedy in the event of breach of contract will also be discussed. Related cases will be incorporated in the explanation for getting a better understanding of the terms and its application. 1.8.4 Chapter 4: Requirements of Mitigation and The Extent of Mitigation in Enforcing LAD Provisions This chapter is the essential part of the whole report. The significant task is to obtain the research’s findings, namely the requirements of mitigation, and to what extent the employer has to mitigate his losses in enforcing LAD provisions. 1.8.5 Chapter 5: Conclusion and Recommendations This chapter is the final part of the whole report and is considered the conclusion chapter. Briefly, this chapter includes the summary on the research findings, conclusion and recommendations and suggestions for further research. CHAPTER 2 LIQUIDATED AND ASCERTAINED DAMAGES (LAD) CHAPTER 2 LIQUIDATED AND ASCERTAINED DAMAGES (LAD) 2.1 Introduction The parties to a contract may themselves specify in that contract an amount which is payable to the plaintiff in the event of breach, such clauses are known as liquidated or agreed damages clauses 1 Liquidated damages, synonymous with the term Liquidated and Ascertained Damages and the abbreviation ‘LAD’ remain a remedy most commonly encountered consequence of non-completion. 2 When the contractor is unable to complete the works by the original date for completion set in the contract or by any new date fixed by the contract administrator and the cause or causes of delay does not entitle the contractor to any valid extension of time under the contract, he is guilty of breaching the contract. 3 A liquidated damages clause ‘makes for greater certainty by allowing the parties to determine more precisely their rights and liabilities consequent upon breach or termination’. 4 1 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.450 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. . Selangor: Malayan Law Journal Sdn. Bhd., pp.501 3 Ibid. 4 AMEV-UDC Finance Ltd. v Austin [1986] 162 CLR 170, 193 2 16 In many projects, where time is the essence of construction, the owner and the contractor agree under the contract that if the contractor fails to complete the project by the stipulated date, it is finally liable to the owner for a pre-agreed sum for each day beyond the specified completion date that it takes the contractor to finish the work. 5 When liquidated damages are agreed in this way, the employer’s only remedy for late completion is a sum not exceeding the specified liquidated damages amount and the employer does not have the option to claim unliquidated damages. 6 In English Law, the courts will have to decide if they are liquidated damages or a form of penalty. 7 The rules against penalties renders void a clause which requires payment of a sum which is extravagant or unconscionable having regard to the greatest loss which could be suffered by the plaintiff following the breach of contract to which the sum relates. 8 If the amount is found to be a penalty then the employer can only recover damages to the extent that they are proved. In addition, the burden of proving that a stipulated sum is a penalty and not liquidated damages in such situations rests with the contractor. 9 Whether a stipulated sum is liquidated damages or a penalty depends upon the intention of the parties, but the Court have laid down certain guiding rules. 10 However, the distinction between damages and a penalty does not apply in Malaysia by virtue of Section 75 of the Contracts Act, 1950 as both are dealt in the same manner. 11 5 Section 75 of the Contracts Act provides an instance in which Fisk, E.R. (2004). Construction Project Administration. 7th Ed. New Jersey; Prentice Hall., pp.580 Martin, R. In What Circumstances Does An Employer Have The Right To Levy Liquidated Damages? James R Knowles (M) Sdn. Bhd. URL: www.jrk.com.sg/ARTICLES/employerliqdamages.htm 7 Vohrah, B. and Wu, Min Aun. (2003). The Commercial Law of Malaysia. Malaysia: Pearson Malaysia Sdn. Bhd., pp.178 8 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.450 9 Martin, R. In What Circumstances Does An Employer Have The Right To Levy Liquidated Damages? James R Knowles (M) Sdn. Bhd. URL: www.jrk.com.sg/ARTICLES/employerliqdamages.htm 10 see Lord Dunedin in Dunlop Tyre Co. Ltd. v New Garage & Motor Co. Ltd. [1915] AC 78 11 Martin, R. In What Circumstances Does An Employer Have The Right To Levy Liquidated Damages? James R Knowles (M) Sdn. Bhd. URL: www.jrk.com.sg/ARTICLES/employerliqdamages.htm 6 17 Malaysia law departs significantly from the line of English common law. 12 Compensation is apparently recoverable up to the limit of the stipulated figure if that was a genuine pre-estimate and is considered by the court to be reasonable. 13 There is no support for the view that a plaintiff may recover a genuine pre-estimate without proof of any actual loss. 14 Thus, it is important for the employer to ensure that the amount stipulated as liquidated damages is a reasonable calculation of the likely loss to the employer and not an exaggerated sum since the purpose is only to provide the employer with reasonable compensation. 15 In short, this chapter addresses the consequences of non-completion focussing on the issue of ‘LAD’, as a remedy to be compensated by the nonbreaching party flow from a breach of contract. 2.2 Breach of Contract A breach of contract occurs where a party does not perform her or his obligations in accordance with the terms of the contract. 16 Eggleston, B. (1997) in his book Liquidated Damages and Extensions of Time in Construction Contract 17 mentioned that every breach of contract carries with the potential for dispute and breach of contract in the construction industry are common either by the employer or 12 Robinson, N. M., et al. (1996). Construction Law in Singapore and Malaysia. 2nd ed. Singapore: The Butterworth Group of Companies., pp.244. See also in Linggi Plantations Ltd v Jagatheesan [1972] 1 MLJ 89. 13 see Larut Matang Supermarket Sdn. Bhd. v Liew Fook Yung [1995] 1 MLJ 379, Song Toh Chu v Chan Kiat Neo [1973] 2 MLJ 206, Woon Hoe Kan & Sons Sdn. Bhd. v Bandar Raya Development Bhd. [1972] 1 MLJ 75. 14 Dato’ Visu sinnadurai. (1987). The Law of Contract in Malaysia and Singapore: Cases and Commentary. 2nd ed. Singapore: Butterworth & Co. (Asia) Pte Ltd., pp. 704. 15 Martin, R. In What Circumstances Does An Employer Have The Right To Levy Liquidated Damages? James R Knowles (M) Sdn. Bhd. URL: www.jrk.com.sg/ARTICLES/employerliqdamages.htm 16 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.333 17 Eggleston, B. (1997). Liquidated Damages and Extensions of Time in Construction Contract. 2nd ed. London: Blackwell Science Ltd. 18 by the contractor because of lack or neglect in the performance of his obligations under the contract. 18 When the employer is in breach by way of interference or prevention arising from late supply of information, failure to give full possession of the site and the like, the result for the contractor is delay, disruption, and involvement in loss and expense or extra cost. 19 On the other hand, the contractor’s breaches of contract are most commonly due to failure to proceed with due diligence, failure to meet specified standard and failure to complete the project on time. 20 The employer’s position is significantly different from the contractor’s. Whereas the contractor has a financial remedy for numerous and various breaches, the employer has his for only one breach of common occurrence – failure by the contractor to complete on time. 21 The financial effects of the employer’s breach on the contractor can rarely by estimated in advance because of the involvement of subcontractors, but the financial effects of the contractor’s late completion can usually be estimated with some certainty. 22 Consequently, in order to resolve these disputes, most standard forms of construction contract are drafted to permit the parties to fix the damages payable for late completion in advance and containing clauses that detailing with the procedures to be applied in the event of breach. 23 18 Eggleston, B. (1997). Liquidated Damages and Extensions of Time in Construction Contract. 2nd ed. London: Blackwell Science Ltd., pp.3 19 Ibid. 20 Ibid. 21 Ibid, pp.4 22 Ibid. 23 Ibid. 19 2.2.1 Remedies for Breach of Contract A breach of contract occurs when one party fails to perform an obligation under the terms of the contract. 24 An award of damages is the primary remedy for any breach of contract. 25 Contract law uses various remedies to repair the damage caused by a breach of contract. 26 The purpose of contract damages is to compensate the plaintiff for loss caused by a breach of contract. 27 An award of damages is to place the victim of the breach, so far as an award of damages can, in the position he would have been in if the contract had been performed. 28 When there is a breach of contract, the party who is not in default may claim one or more of the remedies, namely rescission of contract, damages, specific performance, and injunction. 29 Rescission is a form of relief which, in appropriate circumstances, is available to victims of the following vitiating factors: mistake, misrepresentation, duress, undue influence, unconscionable dealing, breach of fiduciary duty, and under the rule in Yerkey v Jones [1940] 63 CLR 649. 30 The purpose and effect f rescission, as traditionally understood, is to set aside the contract and restore the parties to their original pre-contractual positions. 31 Section 40 of the Contracts Act stated that when a party to a contract has refused to perform / disable himself from performing his promise, then the promise may put on end. 32 24 Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th ed. England: Pearson Education Limited., pp.31 25 Ibid 26 Damages and otherRemedies for Breach of Contract. URL:http://www.law.washington.edu/courses/ramasastry/A50k/handouts/remedies.html 27 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.234 28 Robinson v Harman [1848] 1 Exch 850. See to similar effect Viscount Haldane LC in British Westinghouse Electric and Manufacturing Co Ltd v underground Electric Railways Co of London Ltd [1912] AC 673 at 689: ‘The first is that, as far as possible, he who has proved a breach of a bargain to supply what he had contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed. The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach.’ 29 Vohrah, B. and Wu, Min Aun. (2003). The Commercial Law of Malaysia. 2nd ed. Selangor: Pearson Malaysia Sdn. Bhd., pp.176 30 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.605 31 Ibid. 32 In Choo Yin Loo v Visuvalingam Pillay [1930] 7 FMSLR 135, the court affirmed the view that section 40 enacted English law on the subject. See also in Ban Hong Joo Mine Ltd. v Chen & Yap Ltd [1969] 2 MLJ 83, Tan Hock Chan v Kho Teck Seng [1980] 1 MLJ 308, and Smith Construction Co. Ltd. v Phit Kirivata [1955] MLJ 8 20 Specific performance is an order of the court compelling the defendant to perform his or her part of the contract.33 The courts will enforce a party to do what it has contracted to do, in preference to awarding damages to the aggrieved party. 34 Specific performance will only be granted where damages are an inadequate remedy. 35 However, specific performance will not be granted where the contracts requiring constant supervision, or the contracts involves personal services or lack of mutuality at the time of the judgment. 36 Oxford dictionary of law stated that injunction is a remedy in the form of a court order addressed to a particular person that either prohibits him from doing or continuing to do a certain act or orders him to carry out a certain act. In other words, an injunction may be granted to restrain a breach of negative stipulation (a promise not to do something) in the contract. 37 In addition, the Specific Relief Act, defines injunction as a remedy is classed in the Part III as ‘Preventive Relief’ and there are various types of injunction, namely, Prohibitory Injunction, Interlocutory Injunction, Quia Timet Injunction, Mareva Injunction, Anton Piller order and Erinford Injunction. 38 2.3 Damages Whenever a party (the defendant) breaches a contract, the other party (the plaintiff) will be entitled to an award of damages as monetary compensation for the breach. 39 Damages are normally awarded based on a basis of placing the innocent 33 Duxbury, R. (1991). Contract in A Nutshell. London: Sweet & Maxwell., pp.101 Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th ed. England: Pearson Education Limited., pp.33 35 Duxbury, R. (1991). Contract in A Nutshell. London: Sweet & Maxwell., pp.101 36 Ibid. 37 Ibid, pp.102 38 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.217-222 39 Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.411 34 21 party in the same financial position as if the contract had been properly performed. 40 In addition, whether rightly or wrongly, under the English law, damages for breach of contract are designed to compensate the innocent party for the breach, to make good the actual loss, within certain parameters rather than to punish the guilty party. 2.3.1 General Principles of Damages Damages are granted to the innocent party for the damage, loss or injury he has suffered for a breach of contract. 41 In addition, there are two further points need to be considered in relation to the general approach to damages. These are: a. If the parties have expressly agreed and stipulated in their contract or agreement a particular remedy for the breach complained or, due effect will be given to this means of redress provided, it is not repugnant to the law; and b. Once the innocent party has selected a particular remedy to pursue and has manifested his choice to the defaulting party; who in reliance upon the manifestation has taken any action, the choice is binding and will bar recourse to any other alternative. Syed Ahmad Alsagoff (2003) states that the law grants the damages to a party as monetary compensation for the damage, loss or injury suffered through a breach of contract. He added that, the court will not award compensation to the plaintiff for all the losses suffered because of breach, provided he has fulfil certain qualifications required. The requirements are related to remoteness of damages and the plaintiff 40 Duxbury, R. (1991). Contract in A Nutshell. London: Sweet & Maxwell., pp.102 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.200 41 22 must shows that it was the defendant’s breach that caused him to suffer the said loss. The both requirements will be discussed in further detail in subtopic 2.3.4. 2.3.2 Types of Damages Damages can be classified into a few types 42 as following: a) General Damages These are damages, which the law presumes to have resulted from the act of the defaulting party (defendant) and which need not be specially pleaded. They are recoverable as compensation for such loss as the parties may reasonably foresee as a natural consequence of the breach or act complained of. Examples include damages for pain, inconvenience, disappointment, etc: Frank & Collingwood Ltd v. Gates. 43 b) Special Damages Special damages are damages of a kind which the law will not presume in the innocent party’s (plaintiff’s) favour, but which must be specially pleaded and proved at the trial or arbitration hearing, e.g. loss of profit, interest on money, etc. 42 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.209 43 [1983] 1 Con LR 21 23 c) Nominal Damages Nominal damages are damages awarded where, although there is a technical breach resulting in the contravention of a right but it results in no real loss to the innocent party. Examples include trespass 44 , failure of claimant to mitigate loss 45 , or where the plaintiff is better off as a result of the breach. d) Substantial Damages Substantial damages represent compensation that is given for loss actually sustained by the aggrieved party. These are in essence, pecuniary compensation intended to put the aggrieved party (plaintiff) in the position he would have enjoyed had the contract been performed. These represent the classic example of damages based on the ‘compensatory’ principle. e) Exemplary Damages Exemplary damages are vindictive or punitive and are awarded so as to punish a defaulting party (defendant). Exemplary damages consist of a sum awarded which is far greater than the pecuniary loss suffered by the innocent party. These damages are awarded only in exceptional circumstances, eg. defamation, breach of promise to marry etc: Dennis v Sennyah. 46 f) Unliquidated Damages Unliquidated damages are unascertained damages that need to be proved. These damages are dependent on the circumstances of the case. 44 Kilbourne v Tan Tiang Guee [1972] 2 MLJ 94 Hong Leong Co. Ltd. v Pearlson Enterprises Ltd (No.2) [1968] 1 MLJ 262 46 [1963] MLJ 95 45 24 g) Liquidated Damages These are damages agreed between the parties at the time of contracting and stated in the contract as the damages payable in the event of a specified breach, usually that is of late completion. The sum must be a genuine preestimate of loss likely to be caused by the breach or lesser sum. Liquidated damages cannot be recovered simpliciter: Wearne Brothers (M) Ltd. v Jackson. 47 These damages are covered comprehensively by the provisions of section 75 of the Contracts Act 1950. 2.3.3 Statutory Provisions In Malaysia, the consequences of breach of contract are amply covered under Part VII of the Contracts Act 1950 principally in the following sections. 48 a) Section 74 – Compensation For Loss Or Damage Caused By Breach Of Contract. (1) When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damages caused to him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. 49 47 [1966] 2 MLJ 155. See also Selva Kumar a/l Murugiah v Thiaragajah a/l Retnasamy [1955] 1 MLJ 817. 48 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.202 49 see Hadley v Baxendale [1854] 9 Ex 341 25 (2) Such compensation is not to be given for any remote and indirect loss or damages sustained by reason of the breach. 50 (3) When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default as if the person had contracted to discharge it and had broken his contract. Explanation – In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account. b) Section 75 – Compensation For Breach Of Contract Where Penalty Is Stipulated For. When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual loss is proved to have been caused thereby, to receive from the party who has broken the contract, reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for. 51 Explanation – A stipulation for increased interest from the date of default may be a stipulation by way of penalty…. 50 51 see Tham Cheow Toh v Associated Metal Smelters Ltd [1972] 1 MLJ 171 see Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 26 c) Section 76 – Party Rightfully Rescinding Contract Entitled To Compensation. A person who rightfully rescinds a contract is entitled to compensation for any damages which he has sustained through the non-fulfilment of the contract. 2.3.4 Recovery of Damages The limits to a plaintiff’s claim for damages under the English law are governed by the rules relating to the remoteness of damage in contracts. 52 The classic statement on this aspect of the law can be found in the judgement of Alderson B in Hadley v Baxendale. 53 The rule enunciated by Alderson B was subsequently explained in Victoria (Laundry Windsor) Ltd v Newman Industries Ltd. 54 In Malaysia, section 74 of the Contracts Act sets out the consequences of a breach of contract and the rule embodied in section 74 has its origin in the rule as expounded in Hadley v Baxendale. 55 Section 74 of the Contracts Act limits a plaintiff’s claim for damages caused by a breach of contract. There are two limbs under section 74 (1) under which compensation become to the injured party. 56 52 Dato’ Visu sinnadurai (1987). The Law of contract in Malaysia and Singapore: Cases and Commentary. 2nd ed., pp.669 53 [1854] 9 Ex 341; 156 ER 145 54 [1949] 2 KB 528 55 Dato’ Visu sinnadurai (1987). The Law of contract in Malaysia and Singapore: Cases and Commentary. 2nd ed., pp.670 56 Syed Ahmad Alsagoff. (2003). The Principles of the Law of Contract in Malaysia. 2nd ed., pp.370 27 1. When the damage or loss caused to the injured party arose naturally in the usual course of things fro the breach. 2. When the parties to the contract were fully aware at the time when they made the contract that damage or loss or likely to result from the breach. In either situation, the compensation claimable must not be too remote or indirect. 57 2.3.4.1 Remoteness of Damage A party culpable of breaching a contract is not generally liable for all damages, which ensues from his breach of contract. 58 Some damage is said to be too remote and therefore irrecoverable. In contract, the general rule governing the remoteness of damage was laid down in the case of Hadley v Baxendale 59 in the following words: When two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e according to the usual course of thing from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it. 57 Ibid, pp.370 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.204 59 1854] 9 Ex 341; 156 ER 145 58 28 In summary, the rule in Hadley v Baxendale comprises of two limbs, i.e: in the first limb, damages arising naturally or directly; in the second limb, damages as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it. The Contracts Act 1950 had codified the common law rule in Hadley v Baxendale in the form of section 74(1). This fact has been expressly acknowledged by local courts in a string of cases, notable of; Tham Cheow Toh v Associated Metal Smelters Ltd 60 , and Toeh Kee Keong v Tambun mining Co. Ltd. 61 In Tham Cheow Toh v Associated Metal Smelters Ltd, the appellant had agreed to sell a metal furnace to the respondent and giving a responsibility that the melting furnace would have a temperature of not lower than 2,600 degree F. This specification was not fulfilled and consequently, the respondent brought an action alleging breach of condition and claimed damages, including loss of profits. The Federal Court pointed out that the appellant would not liable for the payment of damages for loss of profits unless there was evidence showing that the special object of the furnace had been drawn to their attention and they are contracted on the basis liable to the payment of loss of profits. On the facts, the appellant was knew about the requirement of producing the specified temperature and the urgency of delivery. Therefore, they were liable to pay for the certain loss of profits suffered by the respondent. Again, the rules were applied in a prominent Scottish’s case, Balfour Beatty Construction (Scotland) Ltd v Scottish Power plc. 62 . In this case, the plaintiffs were constructing a concrete aqueduct over a main road, installed a concrete batching plant and arranged for electricity to be supplied by the defendants. The plaintiffs needed to pour all the concrete in a single continuous operation and so, when the 60 [1972] 1 MLJ 171 [1968] 1 MLJ 39 62 [1994] 71 BLR 20 61 29 electricity supply failed during the pour, the plaintiffs had to demolish all the works, which had been done. The case was held that although the defendant were clearly in breach of contract, they were not liable for these consequences, since they had not been told that a continuous pour was essential. In short, the loss recoverable is subjected to the provision that such compensation is not to be given for any remote and indirect loss or damage sustained as a result from the breach. 2.3.4.2 Measure of Damage The measure of damages in contract is the principle involved in the assessment of the actual monetary compensation that needs to be paid to the innocent party for the damage sustained as a result of the breach of contract.63 Under the common law, damages may be claimed under two established principles, namely: 1. Principle in Robinson v Harman 64 The quantum of damage is assessed in the dictum that provided the damages suffered is not too remote, the innocent party is entitled to be placed, so far as money can do it, to the position he would have been, had the contract been performed (or that the particular damage had not occurred), ie there must be restitution in integrum. 65 63 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.206 64 [1848] 1 Ex 850 65 Harbans Singh. (2004). Engineering and Construction Contracts Management: Law and Principles. Selangor: Malayan Law Journal Sdn. Bhd., pp.206 30 2. Principle under the Rule in Hadley v Baxendale 66 The quantum of damage is assessed on the premise that provided the damage suffered is not too remote, the innocent party is entitled to receive damages which are fairly and reasonable considered to be either arising naturally, i.e according to the usual course of things from such breach of contract itself or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it. From the two principles adverted earlier, the second principle as codified in section 74 of the Contracts Act 1950 is commonly employed locally. 2.3.5 Proof of Damages A plaintiff claiming damages for breach of contract must produce evidence in court of the loss that he has suffered because of the breach. 67 In the absence of documentary evidence, the court can make a reasonable evaluation of the loss incurred. However, the plaintiff must lead at least sufficient or satisfactory evidence to enable the court to make a fair and reasonable assumption of loss. 68 A local case in relation to construction contracts, SEA Housing Corporation Sdn. Bhd. v Lee Poh Choo 69 , the developer delayed in completing the house and the owner claimed for her loss of use and enjoyment of the house at a monthly rate at RM 2,500. Her evidence was that she called the developer’s office and was informed that the rental would be at that monthly rate, without witness or document 66 [1854] 9 Ex 341 Syed Ahmad Alsagoff. (2003). The Principles of the Law of Contract in Malaysia. 2nd ed., pp.387 68 Ibid 69 [1982] 1 MLJ 324 67 31 to sustain her claim. The Judge, Mohamed Dzaiddin held that the house owner could not recover his loss as she failed to prove her loss of her house and occupation of the said building by was of rental. Therefore, party who claim for damages they will have the duty to prove their damages. In recovery of special damages, plaintiff must have to plead and prove to his claim. In another local case, Syed Jaafar bin Syed Ibrahim v Maju Mehar Singh Travel & Tours Sdn. Bhd. 70 , whereby a performance of Haj by 151 persons was cancelled due to the defendant not obtain the visas and the plaintiff claimed for his expenses to putting the passenger for certain duration in Kuala Lumpur. The plaintiff had spent for RM 27,810 for the cost of bringing the passengers from Kota Bahru to Kuala Lumpur and expenses for putting the passengers in Kuala Lumpur from 11 May 1992 to 5 June 1992. The defendant denied the plaintiff’s claim. The court refused the plaintiffs claim for RM 27,810 because there was no evidence produced by plaintiff to sustain his claim. According to the Judge, the plaintiff should produced either the receipts from hotels and restaurants or by at least called the hotel and restaurant proprietors to show the nexus of his loss that he had collected the sum from the 151 passengers. As a result, this case held that the plaintiff must both specifically plead and prove his damages. In short, it can be concluded that the innocent party who claiming for damages should bear in mind that he/ she has the burden of proof for their actual damages/ losses by showing the evidence of suffering and must be pleaded. 70 [1999] 4 MLJ 413 32 2.4 Liquidated and Ascertained Damages (LAD) Delay can cause incalculable damages to an owner. On a construction project and such damages, however, may be very difficult to quantify with reasonable accuracy. Thus in order to help avoid the uncertainty and expense of long evidentiary battles to establish (or refuse) the owner’s actual damages, parties to a construction contract may agree in advance to liquidate those damages. 71 Liquidated and ascertained damages are a common way of dealing with the consequences of delay in construction and engineering projects. 72 LAD is stated in the contract at a rate per day. If the contractor fails to complete the works before the date for completion, then the amount of liquidated damages can be readily ascertained by multiplying the number of days delayed by the daily rate of liquidated damages. 73 2.4.1 Express Contractual Provisions Most standard form of construction contracts provide for the insertion of liquidated damages clause. 74 LAD clause can be found in several standard forms of contract in local construction industry; namely Clause 40 75 of JKR Forms 203 and 203A (Rev 10/83), Clause 22 76 of PAM 1998 Forms (With and Without Quantities) 71 Stockenberg, R.A. Building Design & Construction: Liquidated Damages – A two-edged sword. May, 2002; 43, 5; ABI/INFORM Global. pp29. URL: http://www.bdemag.com 72 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL: http://www.prettys.co.uk/business_law/construction/lads.shtml. 73 Lynch, B.G., (June, 2003). Building Journal Hong Kong China: Focus on legal: The Employer’s Risk? URL: http://www.building.com.hk/forum/09_03employer.pdf 74 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL: http://www.prettys.co.uk/business_law/construction/lads.shtml. 75 Entitled ‘Damages for Non-completion’. JKR Standard Form of Contract 76 PAM Agreement and Conditions of Building Contract., pp.17 33 Editions, Clause 26 77 of the CIDB Form (2000 Edition), Clause 31.4 78 IEM.ME 1/94 Form, Clause 42 79 of the PWD Form DB/T- (2000 Edition), Clause 27 80 of JKR 203N Form (Rev 10/83), Clause 7.0 81 of PAM 1998 Sub-Contract Form, Clause 50 82 and Clause 25 83 of the Putrajaya Conditions of Contract for Main Contract and Nominated Sub-Contract respectively. Generally, these clauses are drafted to provide a mechanism, whereby the parties can agree in advance the damages payable by the contractor and recoverable by the employer if he fails to complete the works by the date for completion stated in the appendix / within any extended period certified by the Architect or Superintending Officer under the extension of time clauses. Although differing widely in wording and scope, these express provisions essentially stipulated the common matters for non-completion, whereas the employer’s right to deduct the said damages, the situation under which such right can be exercised contractually, the procedures involved and the conditions precedent, and other administrative matters. For example, clause 22.1 of PAM 98 and clause 40 of JKR 203A include provisions for the Architect / S.O. issuing a certificate when the contractor fails to complete on time. In terms of scope, the most concise are the provisions in the JKR 203 and 203A Forms, whilst the CIDB Form is the most detailed and elaborate. The rest of the forms, e.g. Putrajaya and PAM 1998 fall somewhat in between. 84 77 Entitled ‘Non-Completion and Damages For Delay in Completion’. CIDB Standard Form of Contract For Building Works. 78 Entitled ‘Delay in Completion’. IEM Standard Form of Contract. 79 Entitled ‘Damages for Non-Completion’. PWD Form DB/T 80 Entitled ‘Damages for Non-Completion’. JKR 203N Form 81 Entitled ‘Damages for Non-Completion’. Sub-Contract Form 82 Entitled ‘Damages for Non-Completion’ Putrajaya Conditions of Contract (Main Contract) 83 Entitled ‘Damages for Non-Completion’ Putrajaya Conditions of Contract (Nominated SubContract) 84 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. . Selangor: Malayan Law Journal Sdn. Bhd., pp.507 34 2.4.2 Definition of LAD Liquidated and Ascertained Damages (LAD) is defined in various ways. First and foremost, Professor Vincent Powell-smith defines the term LAD as a sum of money stated in a contract as the damages payable in the event of a specific breach, usually that of late completion. The sum must be a genuine pre-estimate of the loss of the likely to be caused by the breach or a lesser sum. There is no need to prove actual damage after the event and it does not matter that the actual loss or greater or less than the stated sum or even if in the event there is no loss…. 85 Eggleston in ‘Liquidated Damages and Extension of Time in Construction contracts’ 86 states: … most standard forms of construction contract are drafted to permit the parties to fix in advance the damages payable for late completion. When these damages are a genuine pre-estimate of the loss likely to be suffered or a lesser sum, they can be termed liquidated damages. However, Robinson and Lavers 87 on the other hand, explains the term in this manner:, …the term “liquidated’ means only that the sum is agreed to in advance of the event by the two parties, as opposed to ‘unliquidated’ meaning damages left to be assessed after the event… . Furthermore, LAD is the ascertained amount, expresses in Ringgit and Sens, which an injured party has sustained, or is taken to have sustained. 88 It is an ascertained or calculated monetary loss claimed in an action and also a sum provided by a contract (with agreement) as payable in the event of breach. Where contracting 85 Powell-Smith, V. et.al. An Engineering Contract Dictionary. Legal Studies and Services Ltd., pp.336 86 Eggleston, B. (1997). Liquidated Damages and Extensions of Time in Construction contract. 2nd ed. London: Blackwell Science Ltd., pp.4 87 Robinson, et.al. Construction Law in Singapore and Malaysia. 2nd Ed. Butterworths Asia., pp.242 88 Abdul Aziz Hussin Amn. Liquidated Ascertained Damages (LAD). URL: http://www.hbp.usm.my/aziz/LIQUIDATED%20ASCERTAINED%20DAMAGES.htm 35 parties make a genuine pre-assessment of the loss that would flow from any particular breach, and stipulate accordingly in their contract that this sum shall be payable in the event of a breach.89 In short, LAD is a pre-determined amount of money that the parties to a contract agree will be awarded to one or both parties if there is a breach of contract. 90 2.4.3 Merit of the LAD Provision Construction contracts often contain a liquidated damage provision that provides for payment a stipulated amount in the event that work is not completed within a specified period. 91 The general theme of such a provision is that if the contractor does not complete construction within a certain number of days after construction begins, the contractor will be liable to the owner for a certain amount of money for each day beyond the contractual completion date. 92 The amount to be paid generally represents the employer’s estimated loss in the event completion is delayed. 93 Most commonly within the construction industry, liquidated damages are levied where a contractor fails to meet the contractual completion date without a 89 Abdul Aziz Hussin Amn. Liquidated Ascertained Damages (LAD). URL: http://www.hbp.usm.my/aziz/LIQUIDATED%20ASCERTAINED%20DAMAGES.htm 90 Johnson, M.J. and Boates, C.T. Business Credit; Legal Jargon: Liquidated Damages. Business Credit; Mar 2002; 104,3; ABI/INFORM Global., pp.68 91 Costs, W. (2005). Liquidated Damages Provisions: Are they Always Enforceable? Texas Construction. Baton Rouge: Mar 2005. vol.13, Iss. 3; pp43. URL: http://proquest.umi.com/pqdwed?did=807437291&sid=6&Fmt=3&clientld=21690&RQT=309&VNa me=PQD. 92 Karas, Hal and Brower, D. (June2, 2003). The Daily Reporter: Liquidated Damages: Clause must be reasonable. The Daily Reporter, Issued Monday, June 2, 2003.URL: http://bmf-law.com 93 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL: http://www.prettys.co.uk/business_law/construction/lads.html 36 valid reason to claim a sufficient extension of time. 94 It is not uncommon for parties to agree to a liquidated damages clause in a construction contract. 95 Briefly, the nature and intention of liquidated damages clauses are: 96 1. To fix an amount agreed between the parties to be paid in the event of non-performance of a contractual obligation. 2. To provide certainty to the employer as to the amount, which he will be entitled to recover in the event of non-performance without having the difficulty of proving loss. 3. During tender stage, it also provides contractors with certainty as to the extent of the risk they are taking and allows them to estimate and price the risk within their tender. It is apparent that, the typical liquidated damages clause provides that if the contractor fails to complete the work by the agreed completion date, he will be required to pay the owner a stipulated amount for each day thereafter until completion. 97 Furthermore, the employer will be entitled to recover his damages without proving his loss as both the employer and contractor have agreed on the amount stated in the contract. 94 Zakir Mulla. (25 February 2005). Liquidated damages: North Sea Ventilation Ltd v Consafe Engineering. URL: htp://www.rics.org 95 Karas, Hal and Brower, D. (June2, 2003). The Daily Reporter: Liquidated Damages: Clause must be reasonable. The Daily Reporter, Issued Monday, June 2, 2003.URL: http://bmf-law.com 96 Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-With particular reference to PWD/JKR Standard Forms of Contract. 27 July, 2004. Grand Plaza Parkroyal Kuala Lumpur. James R Knowles (M) Sdn. Bhd., pp.17 97 Kerry, P. (2001). Liquidated damages: how much of a threat can they be?. Heavy Construction News. Toronto: Mar 2001. Vol.45 Iss.6; pp32. URL: http://proquest.umi.com/pqdweb?did=374776101&sid=8&Fmt=3&clientd=21690%RQT=309&VNa me=PQD. 37 2.4.4 Advantages of LAD Provision It is a common assumption that construction contracts frequently contain a “liquidated damages” clause is in favour of the owner. 98 However, liquidated damages clauses in contracts provide benefits for both the Employer and Contractor. For the contractor, he is aware of his maximum risk and can include for this in his tender. For the Employer, the right to liquidated damages means that he has no need to provide evidence demonstrating that the Contractor’s delay caused loss, or to prove the amount of that loss. 99 It is often beneficial to have a contract provision which allows the owner to assess liquidated damages in the event of a delay in construction beyond the date for substantial completion specified in the contract100 . Yet, with a liquidated damages clause in the contract, the Employer can determine the total amount of liquidated damages pursuant to the contract and deduct this amount from payment due to the contractor. 101 Liquidated damages are extremely useful, because they provide a financial incentive for the contractor to adhere to the programme and provide the Employer with an automatic remedy without the difficulty of proving actual loss and this may result in a considerable saving of costs since it is quite often proving that the loss is complex and difficult. 102 In addition, a liquidated damages provision can be a useful 98 Kerry, P. (2001). Liquidated damages: how much of a threat can they be?. Heavy Construction News. Toronto: Mar 2001. Vol.45 Iss.6; pp32. URL: http://proquest.umi.com/pqdweb?did=374776101&sid=8&Fmt=3&clientd=21690%RQT=309&VNa me=PQD. 99 Lynch, B.G., (June, 2003). Building Journal Hong Kong China: Focus on legal: The Employer’s Risk? URL: http://www.building.com.hk/forum/09_03employer.pdf 100 Cheney, D. (Oct 15, 2005). Putting The Owner in The Best Position For a Successful Construction Contract. URL: http://www.brickerstaff.com/articles/cheney2001.htm 101 Lynch, B.G., (June, 2003). Building Journal Hong Kong China: Focus on legal: The Employer’s Risk? URL: http://www.building.com.hk/forum/09_03employer.pdf 102 Zakir Mulla. (25 February 2005). Liquidated damages: North Sea Ventilation Ltd v Consafe Engineering. URL: htp:://www.rics.org 38 tool, as it saves a great of time and money by eliminating the need to prove the actual amount of loss if a dispute or lawsuit arises. 103 2.5 Component Costs of LAD Parties include the LAD clause in construction contracts as means of “fixing” the amount of compensatory damages that would be awarded in the event of a breach by either party to the contract. 104 Reasonable compensation for actual damages is the legitimate objective of such provisions. In addition, the size of a project and the types of losses anticipated help to determine the amount of the liquidated damages to be included in a contract. 105 The amount of LAD is determined by projects’ basis. The party will examine the scope of each individual contract, determines where that contract fits in the procurement and scheduling of the entire project and estimates specifically how much support services such as resident engineers, office engineers, field inspectors, and secretaries would be needed if the project were to go beyond its contract completion dates. 106 Besides that, the cost will be considered are associated with permits, fees, licenses, and most importantly evaluates the impact completion milestone or final project completion dates. 107 In fact, there are different approaches used by the professional consultants in calculating the amount of LAD. This is because they are considering different component costs incorporated for LAD. 108 103 Johnson, M.J. and Boates, C.T. Business Credit; Legal Jargon: Liquidated Damages. Business Credit; Mar 2002; 104,3; ABI/INFORM Global., pp.68 104 Partks, G.T. (March, 2002). A Primer on Construction Damages: A Damage Is a Damage? Not Really!. URL: http://www.bricker.com/legalservices/industry/construction/heavyhighway/article3.asp 105 Ibid. 106 Allen, P.E. (Jan, 1995). The Estimation of Construction Contract Liquidated Damages. URL: library.findlaw.com/1995/Jan/1/129415.html. 107 Ibid. 108 See, Seow Lee. (1995/96). Prinsip Pemakaian Dantirugi Tertentu dan Ditetapkan dari Perspectif Perundangan. Universiti Teknologi Malaysia : Degree Thesis., pp.55 39 However, a research found that typical costs that an owner may seek include rental costs, use and value loss, financing costs, overhead costs, supervisory costs, and business profit loss. 109 This finding is quite similar to a local research in relation to the component costs incorporate in determine the amount of LAD. The component costs consist of loss of income, financing loss, business disruption loss, management costs, and professional fees. The details of costs associated in each type of the said costs are summarised as the following. 2.5.1 Loss of Income Generally, the owner will claim for his losses in relation to loss in rental, delayed on sales, rent of alternative premises, loss of trading profit and financial liability to purchasers. The owner will incur losses in term of rental for the premises in commercial projects; late in getting profit from the sales of premises for housing projects or late in selling the shop lots for commercial projects, such as shopping mall. In addition, owner might suffer extra cost for rental in order to get an alternative premise for their business operation or accommodation temporarily during the delayed duration. For factory projects, late completion probably will cause an owner fail to deliver his products on time and breach of the contract. This is because he could not start the production while pending the completion of the factory. 109 Irvin, E.R. (1987). Construction Claims and the Problems of Cost Management. Cost Engineering, Morgantown: Aug 1987. Vol.29, Iss.8; pg.20. URL: http://proquest.umi.com/pqdweb?did=924865&sid=2&Fmt=2&client=21690&PQT=309&VName=P QD 40 2.5.2 Financing Loss Developer, employer, or the project owner will incur additional costs or losses such as interest on loan and additional capital to carry on a project in the event of late completion. a. Interest on Loan It is common that a banker will charge interest on the employers’ bridging loan. The owner has to bear more interest charged on the balance of loan if the project is in late completion. By right, the project will be completed within the planned duration and no more interest will be charged for delayed duration. b. Additional Capital The owner could make a decision, either to apply for loan from any financial institution or using his own money to bear with extra costs involved. If he decides to use his own money, then he might not afford to invest in other businesses for profit making purpose. Therefore, this is considered a loss for the owner that may incur in the event of late completion. 2.5.3 Business Disruption Loss When businesses could not be implemented on time due to late completion and causing an obvious loss to the owner, then such cost will be considered as a business disruption loss. Usually, business disruption loss arises in renovation or extension projects, recreation projects which provides the facilities of sport, and equipment, and hotel projects. 41 2.5.4 Management Costs Developer or the owner of the project may suffer the cost for management. The component costs incorporated to management costs are wages to project managers, consultants, clerk of works, and other workers engaged in handling management works. In addition, the owner has to pay allowances for travelling and accommodation if the project is far away from the headquarters. 2.5.5 Professional Fees Professional consultants are employed to supervise or manage a project. Once a project is in late completion, the employer has to pay more for the services provided by the professional consultants. As a result, this may cause the employer to incur extra expenses. 2.6 LAD and Penalties As mentioned earlier, briefly, LAD is a payment of agreed damages by the contractor when completion of works is not within the stipulated time and their amount should be recorded in the Appendix to the form of contract. The characteristic of liquidated damages is that loss need not to be proved. 110 The sum stated should be a genuine estimate of the damage that the building owner may 110 Eggleston, B. (1997). Liquidated Damages and Extensions of Time in Construction contract. 2nd ed. London: Blackwell Science Ltd., pp.53 42 suffer. If the sum stated is excessive and bears no relation to the actual damages, then it may be regarded as a penalty. 111 However, a penalty is “a sum which a party similarly agrees to pay or forfeit in the event of breach, but which is fixed not as a pre-estimate of the probable actual damages but as punishment, the threat of which is designed to prevent the breach”.112 In other words, if the stipulated amount is too high, the clause will be declared invalid as a “penalty”. 113 In addition, a liquidated damages clause could not be enforceable when it constitutes a “penalty”. 114 In such circumstances, the employer is left to claim unliquidated damages in respect of whatever loss or damage that can be proved. 115 2.6.1 Distinction between LAD and Penalties One of the arguments, which are sometimes used as defences to a liquidated damages clause is penalty and it is sometimes difficult to ascertain whether the damages are penalties or liquidated damages. However, the case of Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd 116 established that the stated damages must be a genuine pre-estimate of the anticipated loss if the clause is not to be struck down as a penalty.117 In this case, Dunlop contracted to sell tyres and other accessories to New Garage on terms designed to ensure that the tyres, etc. were not 111 Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th ed. England: Pearson Education Limited., pp.33 112 Liquidated Damages for construction Delays: Definitions and Legal interpretation in Connection with delays. URL: http://www.CTS2000.bizland.com/liquidated.htm 113 Wallenfang, R.L. (2001). Coordinator – Construction Law Group – Liquidated Damages for Delay in Construction Contracts. URL: http://www.concretemasonry.org/design/Liquidated_damages.htm 114 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL: http://www.prettys.co.uk/business_law/construction/lads.shtml. 115 Murdoch, J. and Hughes, W. (1996). Construction Contracts: Law and Management. 2nd Ed. UK; E & FN Spon., pp.327 116 [1915] AC 79 117 Zakir Mulla. (25 February 2005). Liquidated damages: North Sea Ventilation Ltd v Consafe Engineering. URL: htp:://www.rics.org 43 sold below the manufacturer’s list price. New Garage agreed to pay Dunlop ‘the sum of £5 for each and every tyre…sold or offered in breach of this agreement, as and by way of liquidated damages and not as a penalty’. New Garage sold tyres in breach of the agreement. The court held that, in the circumstances of the case, the sum of £5 was liquidated damages and not penalty. As a result, Lord Dunedin had noted guidelines, which have been long accepted as the best available to deal with this issue: 118 1. The terms used in the contract are not conclusive, though they may be persuasive, 2. Unlike a penalty, liquidated damages represent a genuine attempt at a pre-estimate of likely damage. 3. In deciding into which category a particular contract term falls, account must be taken of circumstances at the time of making the contract, not at the time of breach. 4. The following ‘tests’ may be helpful, or even conclusive: (a) If the sum stipulated is ‘extravagant and unconscionable’ compared with the greatest amount of loss which could be caused, it is a penalty. (b) If the breach consists simply of non-payment of money, and the sum stipulated is a greater sum, it is penalty. (c) If a single sum is payable for a range of breaches of varying severity, there is a presumption (but no more) that it is a penalty. (d) The fact that an accurate pre-estimation of the likely damage is almost impossible to achieve does not prevent a stipulation from being classed as liquidated damages. In fact, it is in precisely these cases – public buildings, housing association projects and other non-profit – making ventures – when a liquidated damages clause is most useful. Mr Justice Lopes in Law v Redditch Local Board 119 explained the distinction in this way: 120 118 Murdoch, J. and Hughes, W. (1996). Construction Contracts: Law and Management. 2nd Ed. UK; E & FN Spon., pp.328 119 [1892] 1 QB 127 44 ‘The distinction between penalties and liquidated damages depends on the intention of the parties to be gathered from the whole of the contract. If the intention is to secure performance of the contract by the imposition of a fine or penalty, then the sum specified is a penalty; but if, on the other hand, the intention is to assess the damages for breach of the contract, it is liquidated damages.’ 2.6.2 Pleading Cases in Distinguishing LAD and Penalties In order to give a clearer view in relation to distinguish between damages and penalties, the following cases are highlighted. First and foremost is Kemble v Farren. 121 A contract for the defendant to appear as principal comedian at Covent Garden Theatre at the rate of £3.6s.8d per night for four seasons, contained a provision that if either party failed to fulfil the contract or any part thereof, such party should pay the other party by way of liquidated damages the sum of £1000. The defendant refused to act during the second season and was sued. It was held that, the sum of £1000 was a penalty because, had the plaintiff failed to make a single payment of £3.6s.8d, he would have been liable to pay £1000 and had the defendant contravened any regulations of the theatre, however minute, he would have been similarly liable. In addition, in Stanor Electric Ltd v R Mansell Ltd 122 , the main contractor, Mansell, sought to deduct liquidated damages for late completion by their electrical sub-contractor, Stanor, of work on two houses where liquidated damages were stages at £5000 per week. Judge Fox-Andrews held that as a matter of construction of the 120 Eggleston, B. (1997). Liquidated Damages and Extensions of Time in Construction contract. 2nd ed. London: Blackwell Science Ltd., pp.57 121 [1829] 6 Bing 141 122 [1988] CILL 399 45 particular clause in the contract where work was to be done on two houses, therefore the clause in the evidently a penalty. Furthermore, in of Public Works Commissioner v Hills 123 , a contractor for construction of a railway provided that the contractor should forfeit the retention moneys under the contract ‘as and for liquidated damages’ for late completion. It was held that, since the amount of retention money would depend upon the progress of works, it was an indefinite sum and could not be a genuine pre-estimate of loss, therefore, to be considered as a penalty. Briefly, a ‘liquidated damages clause’ is likely to be unenforceable as a penalty if: 124 a) The pre-estimate sum is considered to be an unreasonable estimate of the probable loss; or b) It has been used by one party to impose pressure or oppression on the other (which could be said to be another way of expressing the unreasonable nature of the predetermined sum). However, in Malaysia, the position on the deduction of liquidated damages is somewhat different from other common law jurisdictions. 125 In Malaysia, ‘there is no difference between penalty and liquidated damages’. 126 The further explanation in relation to this issue will be discussed in subchapter 2.7 as following. 123 [1906] AC 368 Freeman, K. (May, 2005). UK contract Articles in Association with Kendall Freeman: Upholding liquidated damages and avoiding penalties. URL: http://www.legal500.com/devs/uk/co/ukco_022.html 125 Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-with Particular reference to PWD/JKR standard Forms of Contract. 27 July, 2004. Kuala Lumpur: James R Knowles (M) Snd. Bhd., pp.18 126 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd., pp.193 124 46 2.7 Liquidated and Ascertained Damages: The Malaysian Position The following discussion will revolved around the common law position in relation to the recovery of liquidated damages by the employer consequent upon the contractor's non-completion by a defined or stipulated date. The Malaysian courts have considered various facets of the subject of liquidated damages and have made relevant pronouncements; which process has built up a body of judicial precedents which must be followed in the local context. 127 Therefore, local practitioners must therefore be conversant not only with the common law principles but also the position taken by the Malaysian courts; hence the relevance of this discussion. 128 2.7.1 Applicable Statutory Provision In Malaysia, the relevant statutory provision that deals directly with the issue of liquidated damages and penalties is Section 75 of the Contracts Act 1950 (Rev 1974) entitled ‘Compensation for breach of contract where penalty stipulated for’. 129 Section 75 reads: When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damages or loss is proved to have been caused thereby, to receive from the party who has broke the contract reasonable compensation 127 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. Selangor: Malayan Law Journal Sdn. Bhd., pp.572 128 Ibid, pp.572 129 Ibid, pp.572 47 not exceeding the amount so named or, as the case may be, the penalty stipulated for. Section 75 is in pari material with Section 74 of the of the Indian Contracts Act 1872 where it was first enacted and then followed in the local application. 130 Mr. Sundra Rajoo in his book on ‘The Malaysia Standard Form of Building Contract (The Pam 1998 Form)’ stated that; Section 75 of the Contracts Act 1950 deals with the effect of a sum named in a contract which is payable in cases of breach of contract. Further, in Malaysia ‘there is no difference between penalty and liquidated damages’; see SS Maniam v The State of Perak 131 and Linggi Plantation Ltd v Jagatheesan. 132 2.7.2 Interpretation of Section 75 of Contracts Act 1950 Section 75 apparently permits the recovery of liquidated damages ‘whether or not damage or loss is proved have been caused by the breach of late completion. 133 However, Professor Dato’ Sinnadurai in his book on Law of Contract in Malaysia and Singapore: Cases and Commentary (2nd ed, 1987) says: The case seems to suggest that the plaintiff cannot recover simpliciter the sum fixed in the contract, whether as a penalty or liquidated damages. The plaintiff is required to prove the actual damages he has suffered, see Bhai 130 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. Selangor: Malayan Law Journal Sdn. Bhd., pp.572 131 [1975] MLJ 75 132 [1972] 1 MLJ 89 133 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd., pp.194 48 Panna Singh v Bhai Arjun Singh 134 ; Lord Hailsham in Linggi Plantations Ltd v Jagatheesan 135 and Wearne Brothers v Jackson 136 . He added that in every case, The court has to be satisfied that every sum of money payable by way of liquidated damages is reasonable… Upon the court being satisfied that the said sum is a genuine pre-estimate and it represents a reasonable sum for the loss suffered, it may order the said sum to be paid as damages. In practice terms, therefore, an architect must take an actual calculation of the likely loss to the employer and any temptation to increase the figure should be avoided as otherwise it may well be found not to be a ‘reasonable compensation’. 137 In an Indian Case of Bhai Panna Singh v Bhai Arjun Singh 138 the Privy Council, in interpreting Section 74 of the Indian Contracts Act 1872 held that, the effect of s74 of the Contracts Act 1872 is to disentitle the plaintiffs to recover simpliciter the sum of Rs10,000, whether as penalty or liquidated damages. The plaintiffs must prove the damages that they have suffered. In S.S. Maniam v The State of Perak 139 , Thomson confirmed: In the first place, in this country there is no difference between penalty and liquidated damages ... . As said by Pollock and Mulla on the Indian Contracts Act (7th Edition), 'This section 64 boldly cuts the most troublesome knot in the common law doctrine of damages. In brief, in our law in every case, if a sum is named in a 134 [AIR 1929 PC 179] [1972] 1 MLJ 89 136 [1966] 2 MLJ 155 137 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd., pp.194 138 AIR 1929 PC 179 139 [1975] MLJ 75 135 49 contract as the amount to be paid in case of breach it is to be treated as a penalty, see Bhai Panna Singh v Bhai Arjun Singh AIR 1929 PC 179. In Wearne Brothers (M) Ltd v Jackson 140 , the Malaysian High Court held that whether the clause in the agreement was a penalty clause or not was irrelevant in view of Section 75 of the Contracts (Malay States) Ordinance 1950, which provides that in every case the court must determine what is the reasonable compensation. The effect of the section is that the plaintiff is disentitled from recovering simpliciter the sum fixed in the contract whether as penalty or liquidated damages and must prove the damage suffered by him unless the sum named is a genuine pre-estimate. Lord Hailsham put a seal of approval on the said interpretation in the case of Linggi Plantations Ltd v Jagatheesan 141 where he held that Section 75 of the Contracts Act 'was intended to cut through the rather technical rules of English law relating to liquidated damages and penalties'. In Brunei, the Court put a further gloss on the interpretation afforded thus far by holding in Chung Syn Kheng Electrical Co Bhd. v Regional Construction Sdn Bhd 142 that: ... the amount provided for liquidated damages will only be enforced in favour of the plaintiff if it can be shown that the amount was a genuine pre-estimate of the damages likely to flow from the specified breach. The amount of loss or damage which has actually occurred must be a major factor in deciding whether the amount provided for was an honest preestimate of the likely loss or damage. If the actual loss or damage suffered is very much less than the sum agreed, the court will refuse to 140 [1966] 2 MLJ 155 [1972] 1 MLJ 89 142 [1987] 2 MLJ 763 141 50 enforce the agreement to pay a specified sum by way of liquidated damages. The Federal Court having meticulously reviewed all the previous case law and authorities on this issue in the case of Selvakumar a/1 Murugiah v Thiagarajah a/1 Retnasamy 143 held, that: 1 In Malaysia, there is no distinction between liquidated damages and penalties as understood under English law in view of s75 of the Contracts Act 1950 which provides that in every case the court must determine what is reasonable compensation, 'whether or not actual damage or loss is proved to have been caused thereby' ('the words in question'); 2 The words in question must be given a restricted construction. Hence, despite the words in question, a plaintiff who is claiming for actual damages in an action for breach of contract must still prove the actual damages or reasonable compensation in accordance with the settled principles in Hadley v Baxendale 144 . Any failure to prove such damages will result in the refusal of the court to award such damages; 3 For cases where the court finds it difficult to assess damages for the actual damage as there is no known measure of damages employable, and yet the evidence clearly shows some real loss inherently which is not too remote, the words in question will apply. The court ought to award substantial damages as opposed to nominal damages which are reasonable and fair according to the court's good sense and fair play. In any event, the damages awarded must not exceed the sum so named in the contractual provision. 143 144 [1995] 1 MLJ 817 [1854] 9 Ex 341 51 In light of the above-mentioned judicial pronouncements, the local position on liquidated damages can be summarized as the following: By virtue of Section 75 of the Contracts Act 1950 (Rev 1974), in Malaysia there is no difference between penalty and liquidated damages; Therefore, all liquidated damages clauses are to be treated as if they had been penalties under English Law; The employer cannot recover simpliciter the sum fixed in the contract whether as a penalty or liquidated damages. He must prove the actual damages or the reasonable compensation in accordance with the settled principles of Hadley v Baxendale 145 or Section 74 of the Contracts Act 1950 (Rev 1974); The measure of damages stated in the contract will be enforced provided that it is proved by the employer that he had suffered loss or damage limited to the extent of the quantum of the 'agreed compensation', ie the liquidated damages sum; and The amount of damages ordered by the court in these circumstances cannot exceed the specified amount. Therefore, the figure inserted in the contract is a limitation on the amount for which the contractor is liable. 2.7.3 Recovery of LAD When the LAD is agreed, the employer’s only remedy for late completion by the contractor is a sum not exceeding the specified amount and he does not have an option of claiming unliquidated damages. 146 However, in the PAM 1998 Form, if the date for completion is not inserted in the Appendix, then no liquidated damages to be recoverable, but in such case, the employer 145 [1854] 9 Ex 341 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd., pp.191 146 52 would be able to recover general damages by legal action on the basis of his actual proven loss. 147 In light of the ruling in Selvakumar a/1 Murugiah v Thiagarajah a/1 Retnasamy 148 , the recovery of liquidated damages generally follows a process as highlighted in Appendix A. The said process entails principally the following steps. 149 1. Should the contractor be liable to pay liquidated damages following noncompletion, provided the conditions precedent have been fulfilled, eg the Certificate of Non-Completion (CNC) is issued, etc, the employer may proceed to deduct the liquidated damages simpliciter; 2. The contractor has an option of challenging such deduction by the employer. Should the contractor fail to defend or acquiesce to the deduction, this may ultimately compromise his later challenge to the deduction; 3. In the event the contractor proceeds with his challenge, this matter needs to be arbitrated or litigated; 4. The employer must then prove on a balance of probabilities the actual damages suffered or reasonable compensation as per the settled principles of Hadley v Baxendale 150 or Section 74 of the Contracts Act 1950 (Rev 1974); and 5. Should the employer prove his loss or damage to be less than the amount stipulated in the contract, he can recover only the lesser amount. However, should this turn out to be more than the stipulated amount, he is entitled only to the stipulated amount which effectively acts as the ceiling amount to recovery. 147 Ibid, pp.192 [1995] 1 MLJ 817 149 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. Selangor: Malayan Law Journal Sdn. Bhd., pp.576 150 [1854] 9 Ex 341 148 53 2.8 Conclusion As mentioned earlier, most building contracts provide an express provision for Liquidated as Ascertained Damages (LAD) to enable an employer to claim his damages measured by the amount of loss for every day or week of delay by the contractor under the contract. Indeed, the nature and purpose of such clause is to save time and money on arbitration or litigation to resolve on disputes arising from in this matter. The typical component costs to LAD are loss of income, financing loss, management costs, business disruption loss and professional fees. In Malaysia, there is no difference between LAD and penalties as understood under English Law. Furthermore, the recovery of LAD in the local context is governed by the section 75 of Contract Act 1950. Whereby, the court will consider whether damages claimed is reasonable compensation instead of amount LAD stipulated in a contract. In addition, the employer is required to prove the actual loss that he had suffered as the principle set down in Bhai Panna Singh v Bhai Arjun Singh 151 ; Linggi Plantations Ltd v Jagatheesan 152 , Wearne Brothers v Jackson 153 and Selvakumar a/1 Murugiah v Thiagarajah a/1 Retnasamy 154 . It has been argued that such an approach has put the liquidated damages recovery mechanism on a similar footing to the recovery of unliquidated (general) damages at common law. 155 Furthermore, it could not deny that such decision may cause certain criticism, whereby such defence seems to defeat the ordinary purpose of having such clause in a contract. Therefore, the requirements of mitigation in relation to recover LAD will be discussed in the following chapter in order to resolve on this problem. 151 [AIR 1929 PC 179] [1972] 1 MLJ 89 153 [1966] 2 MLJ 155 154 [1995] 1 MLJ 817 155 Harbans Singh. (2004). Engineering and Construction Contracts Management: Commencement and Administration. Selangor: Malayan Law Journal Sdn. Bhd., pp.576 152 CHAPTER 3 MITIGATION CHAPTER 3 MITIGATION 3.1 Introduction The basic concept of damages in contract is to place the plaintiff in the same position he would have been in had the contract been carried out, is subject to the test of remoteness. 1 However, the basic concept is limited by the notion of mitigation of loss. 2 This chapter discusses the rules of mitigation and the related matters. Generally, it covers the precise rules and principles of mitigation, when may the duty to mitigate exist; in what circumstances the duty apply, to what extent the mitigation should be carried and etc., as guidance to innocent parties to recover their damages and losses. 1 2 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp352 Ibid, pp352 55 3.2 Definition of Mitigation Oxford Dictionary of Law 3 defines mitigation as the reduction in the loss or injury resulting from a tort or breach of contract and the injured party is under a duty to take all reasonable steps to mitigate his loss when claiming damages. Mitigation (also known as the doctrine of “avoidable consequences”) holds that an injured party cannot ignore an opportunity act as to reduce the continuing increase in damages from that injury, and recover the same from defendant. 4 In short, mitigation essentially means that a plaintiff will not be able to claim for losses, which he could have avoided by taking of reasonable steps to reduce those losses once he has elected to treat the contract at an end. 5 3.3 General Rules and Principles of Mitigation Mitigation of damages is a common law defences, often known as the law of avoidable consequences. 6 The recovery of damages is subjected to this limitation, namely mitigation; the law does not allow a plaintiff to recover damages to compensate him for loss which would not have been suffered if he had taken reasonable steps to mitigate his losses. 7 3 Oxford Dictionary of Law (2003). Oxford University Press: Market House Books Ltd. pp318 TCPALaw.com, Headnote Issues Research. (August 2, 2003). Mitigation of Damages. URL: http://.www.tcplaw.com/free/head2.pdf 5 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp352 5 Ibid, pp352 6 TCPALaw.com, Headnote Issues Research. (August 2, 2003). Mitigation of Damages. URL: http://.www.tcplaw.com/free/head2.pdf 7 Andrew Phang, Boon Leong. (1998). Cheshire, Flfoot and Furmston’s, Law of Contract in Singapore and Malaysia. 2nd Ed. Singapore: The Butterworth Group of Companies. pp1022 4 56 The classic judicial formulation of this is Viscount Haldane LG’s in British Westinghouse Electric Co. v Underground Electric Railway Co. of London 8 (a contract case). The Judge said that the principle ‘…impose on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent in the breach and debars him from claiming any part of the damage which is due to his neglect to take such steps.’ 9 The facts of the case 10 were that the appellants, Westinghouse had contracted to supply turbines to the respondents. The respondent laid down that the turbines had to meet certain specifications. While the appellants built and delivered the turbines they never met the specifications required by the contract. Eventually, the respondent had to replace the turbines with those produced by a different manufacturers. The new turbines were highly efficient, so much so that they quickly paid for themselves. Nevertheless, the respondents sued for the cost of purchasing and installing the new turbines. It was held that they could not do so. The respondents were required to mitigate their losses and they had done so, but so efficiently as to eliminate the costs of replacing the original turbines, and therefore nothing could be recovered as regards these losses. They were entitled, however, to compensation for the losses sustained while the inefficient turbines were being used. However, whether the plaintiff has failed to take a reasonable opportunity of mitigation is a question of fact and the question revolving around is whether the plaintiff had done everything as reasonable man might be expected to do in the ordinary course of business. 11 8 [1912] AC 673 Burrows, A.S. (1987). Remedies for Torts and Breach of Contract. UK: Butterworth & Co. Ltd. pp64 10 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp352 11 Ibid, pp353 9 57 3.4 Mitigation in Malaysian Position In Malaysia, Singapore and Brunei, the explanation of Section 74 of Contract Act 1950 appears to statutorily embody the principle of mitigation.12 The Section 74 reads as follows: 74 (1) When the contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. 74 (2) Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach. 74 (3) When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default as if the person had contracted to discharge it and had broken his contract. In estimating the loss or damage arising from a breach of contract, the means which existed of remedying the inconvenience caused by the non-performance of the contract must be taken into account. The plaintiff seeking for general damages should always be able to show that he mitigated the losses he suffered from the defendant’s breach.13 This principle was illustrated in local cases; for instance, Hong Leong Co Ltd v Pearlson Enterprise Ltd 12 Andrew Phang, Boon Leong. (1998). Cheshire, Fifoot and Furmston’s, Law of Contract in Singapore and Malaysia. 2nd Ed. Singapore: The Butterworth Group of Companies. pp1028 13 Robinson, N.M. et. al. (1996). Construction Law n Singapore and Malaysia. 2nd Ed. Singapore; The Butterworth Group of Companies. pp241 58 (No 2) 14 , and Tansa Enterprise Sdn Bhd v Temenang Engineering Sdn Bhd. 15 In the case of Hong Leong v Pearlson Enterprise, it was only concerned with the counterclaim, which was ordered to be retried by the Federal Court on August 7, 1967. On the retrial, the court merely had to decide on the quantum of damages under the first two items of the counterclaim. The case held that, as to the first item of the counterclaim (namely the difference between the contract price and the lowest possible market price for 281,004 bricks of No. 3 commercial quality) the defendants were not entitled to any damages. This is because the offer made by the plaintiffs was reasonable and the defendants should have mitigated their loss by accepting the plaintiffs’ offer and no loss would have been suffered by the defendants if they had accepted it. The defendant were not entitled to any damages in respect of second item of the counterclaim for $ 11,868 (being wages paid to 18 workers for 69 days at $ 172 per day). This is because the loss could have been avoided as it was the practice in the building trade for bricklayers and carriers to be sent away without pay if there was no work for them to do due to lack of bricks. However, the defendant is entitled only to recover nominal damages for breach of contract. The sum of $ 10 was awarded as nominal damages. In further, as the plaintiffs by their breach of contract caused the defendants considerable inconvenience and unreasonably delayed the construction the flats, they should pay the defendants the costs of the retrial and the original trial of the counterclaim to be taxed on the lower scale. In Tansa Enterprise v Temenang Engineering, the main issue in this case is the defendant appealed against the order for summary judgement and applied to set aside the injunction on a few grounds. The defendant also applied for stay of execution of judgement pending the outcome of its counterclaim against the plaintiff. One of the counterclaims was transportation costs of RM 400 incurred by having to buy replacement bricks. The court dismissed the appeal on the basis that the counterclaim for cost of transportation for the replacement bricks was not reasonable. By assuming that the plaintiff was in breach of contract, the defendant had not mitigated its damages because the supply of the bricks as per the contract are common bricks and there was no shortage of bricks in the market at the material 14 15 [1968] 1 MLJ 262 [1994] 2 MLJ 353 59 time. However, in fact the defendant was already buying bricks from other suppliers (Messrs Lin Hoo Brothers) at cheaper prices. Therefore, if the defendant had mitigated its losses by buying bricks from other sources, the defendant suffered no loss. In this case, the defendant did not suffer any loss due to the lower prices paid for the bricks. The gain made by the lower prices had offset the added cost of transportation. The Judge added that the defendant may, at best, claim for loss suffered as a result of having to pay cash for the bricks from other sources and such loss, but it may be quite minimal. 3.5 The Duty to Mitigate The “duty to mitigate loss” is a rule of contract law and this rule arises in the event of breach. 16 It is the duty of every plaintiff to make a reasonable effort to prevent the amount of loss or harm from increasing. 17 For example 18 , if constant rain is raising the level of lake next to your home, you have the responsibility to take steps to prevent damage from flood which is about to occur. Therefore, you may move your property to higher ground or putting out sand bags to prevent water from entering your home. 19 The party seeking damage is under a duty to mitigate the loss – Explanation to section 74 of Contract Act 1950. 20 In Kabatasan timber Extraction Co. v Chong Fah Shing 21 , the Federal Court recognised this general duty and held that the plaintiff’s claim should be reduced accordingly. In this case, the appellants had 16 3.11 The Duty to Mitigate Loss (Keeping Costs to a Minimum). (January, 2004). URL: http://www/taswa.org/tm/chapter3/3_11.htm 17 What is the ‘duty to mitigated damages?’ URL: http://injurylaw.freeadvice.com/property_damage/mitigate_duty.htm 18 Ibid 19 Ibid 20 Lee, Mei Pheng. (2005). General Principles of Malaysian Law. 5th Ed. Selangor; Penerbit Fajar Bakti Sdn. Bhd. pp166 21 [1969] 2 MLJ 6 60 contracted to supply timber to the respondent to be delivered at the site of the sawmill to be erected by the respondent. The timber was delivered in three lots. The second lot of 198 logs and 4 of the 22 logs in the third lot were not delivered to the sawmill but were dumped at a distance of more than 500 feet from the sawmill. The learned trial judge gave judgement for the appellant for RM 9,892.41 being the balance due under the contract and awarded damages to the respondent on his counter-claim for breach of contract for the sum of RM 13, 192.40. In the instance case, the judge had dismissed the appeal in respect of the claim and allowed the appeal in respect of counter-claim by reducing the amount. It was the duty of the respondent in this case to take reasonable steps to mitigate the damage. There was no need for the respondent to have gone to the expense of buying logs from elsewhere when the logs were lying a few hundred feet away from the sawmill and all that was required was the additional expenses for hauling them up to the sawmill. The appropriate damages to be awarded to the counter-claim was an approximate cost of hauling the logs to the sawmill, which amounted to RM 1,000. The decision of the case follows the rule that damages are compensatory only in that one who has suffered loss from a breach of contract must take any reasonable steps that are available to him to mitigate the extent of the damage caused by the breach. 22 Although the measure of damages for breach of contract to deliver goods is ordinarily the difference between the contract price of the goods and the market price at the time when delivery should have been given. Yet, if the plaintiff might have mitigated his loss, for example, by any immediate purchase at a low price of goods to replace those not delivered, or by accepting a reasonable offer from the defendant to make good part of the loss, this is to be taken into account in assessing his damages. 23 22 23 Guest, A.G. (1975). Anson’s Law of Contract. 24th Ed. London; Oxford University Press. pp549 see Brace v Clader [1895] 2 Q.B. 253, and Payzu Ltd. v Saunders [1919] 2 K.B. 581. 61 Mr. Burrows, A.S. 24 in his book ‘Remedies for Torts and Breach of Contract’ stated that the duty to mitigate is sometimes used as a positive reason for awarding damages. He added; on one hand, a plaintiff should not sit back and do nothing to minimise loss flowing from a breach but should use his resources to do what is reasonable to put himself into a position as good as if the contract had been performed. On the other hand, he should not unreasonably incur expense subsequent to the wrong. In Payzu Ltd v Saunders 25 , the plaintiff agreed to buy certain goods from the defendant over a period of nine months with payment within one month of delivery, and deliveries monthly. The plaintiff failed to make prompt payment for the first instalment, and the defendant, in breach of contract, refused to deliver any more under the contract, but offered to deliver the goods at the contract price if the plaintiff paid cash on delivery of the order. The plaintiff refused this and claimed damages, these being the difference between the contract price and the market price. It was held that the plaintiff had permitted himself to sustain a large measure of the loss, which as prudent and reasonable people, they ought to have avoided. He had the cash available to meet the defendant's demands and could have mitigated by purchasing off the defendant at the contract price as the defendant offered, instead of going into the market to purchase at a higher price. Although the defendant was liable to pay damages, these should be limited to the value of the month’s credit, as the claimant was under a duty to mitigate his loss and accept the defendant’s offer. As a result, he was therefore, not entitled to damages. However, the Court of Appeal emphasised that the claimant must only take such steps as are reasonable to mitigate his loss; he is not bound to accept every offer made by his contractual partner. 24 Burrows, A.S. (1987). Remedies for Torts and Breach of Contract. UK: Butterworth & Co. Ltd. pp64 25 [1919] 2 KB 581 62 In short, the plaintiff must minimise the loss resulting from the breach by taking all reasonable steps available to him. If he fails to do so, then he cannot recover anything in respect of the extra loss. There are three rules that lay under the duty to mitigate, whereby: 26 1. The plaintiff cannot recover for loss which the plaintiff could have avoided by taking reasonable steps. 2. The plaintiff cannot recover for any loss he has actually avoided, even though he took more steps than were necessary in compliance with the above rule. 3. The plaintiff may recover loss incurred in taking reasonable steps to mitigate his loss, even though he did not succeed. However, the particular acts required in mitigating the damages are determined on a case-to-case basis, whereby it is set as what is ‘reasonable’ under the particular circumstances. 27 Whether the plaintiff has failed to take a reasonable opportunity of mitigation is a question of fact dependent upon the particular circumstances of each case and the burden of proving such failure rests upon the defendant as in Payzu Ltd v Saunders 28 In this context, it should be noted that provided the plaintiff’s attempt to mitigate are reasonable at the time, it is irrelevant if they are subsequently found to be inefficient, as stated in Gebruder Metel Mann GmbH & Co. KG v NBR (London) Ltd. 29 26 Remedies For Breach 1 – Damages. URL: http://www.lawteacher.net/Contract/Discharge%20and%20Remedies/Remedies%20Lecture%20.htm 27 What is the ‘duty to mitigated damages?’ URL: http://injurylaw.freeadvice.com/property_damage/mitigate_duty.htm 28 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp353 29 [1984] 1 Lloyd’s Rep 614 63 3.6 Limitation of Mitigation upon Recovery of Damages The doctrine of mitigation of loss means that a plaintiff cannot recover damages for any part of loss which could have been avoided by taking reasonable steps. 30 Mr. Emanuel, S. 31 stated that, “Duty to mitigate” is only in the sense that if plaintiff fails to do it, he will lose the right to collect damages, not in the sense that he has breached some obligation. In other words, the “duty to mitigate” only requires the plaintiff to make reasonable efforts to mitigate damages. He added that, plaintiff does not have to embark on a hazardous or uncertain course of action that causing him incur substantial expense or inconvenience, damage his reputation, or break any contracts, in order to mitigate. Thus, it was held in Pilkington v Wood 32 that the plaintiff was not obliged to embark upon a difficult and complicated litigation. In this case, a solicitor, in breach of contract, obtained for the plaintiff a house which had a defective title. The plaintiff tried to sue the solicitor, who argued that the plaintiff should have mitigated by suing the vendor under the covenants for title under s76 LPA 1925. The court remarked: "The so-called duty to mitigate does not go so far as to oblige the injured party, even under an indemnity, to embark on a complicated and difficult piece of litigation against a third party. It is no part of the plaintiff's duty to embark on the proposed litigation in order to protect his solicitor from the consequences of his own carelessness' (per Harman J)." 33 30 Murdoch, J. and Hughes, W. (1997). Construction Contracts: Law and Management. 2nd Ed. UK; E & FN Spon. pp324 31 Emanuel, S. Emanuel Law Outlines: Contracts: Chapter 10: Remedies. URL://http:www.stcl/students/sba/EmanuelContractsOutline.doc 32 [1953] 2 Ch 770; [1953] 3 WLR 522 33 Cases on Damages. ULT: http://www.lawteacher.net/Contract/Discharge%20and %20Remedies/Remedies%20Lecture%20htm 64 Similarly, in Selvanayagam v University of the West Indies 34 , it was held that the plaintiff was not required to undergo an operation which carried a risk of postoperative complications in order to mitigate the loss. 35 3.7 Mitigation in Building Contracts By referring to Construction Contracts; Law and Management, written by Murdoch, J. and Hughes, W., mitigation is one of the important qualifications for a party to compensate for all general damages or losses which flow from a breach of contract. The principle of mitigation was applied in some construction cases which can be seen as follows. Firstly, in William Tompkinson & Sons Ltd. v Parochial Church Council of St. Michael 36 , the employer who unreasonably refuses to let the original contractor return to the site during a Defects Liability Period in order to carry out remedial work will not be able to recover the extra cost incurred by having the work carried out by another contractor. In this case, an employer refused to allow the original contractor access to the site to remedy defects but, instead, sued the contractor for the cost of having these rectified by another contractor. It was held that the employer’s decision amounted to an unreasonable failure to mitigate the loss suffered. The damages were reduced by the amount by which the employer’s costs exceeded what it would have cost the original contractor to carry out the work. 34 [1983] 1 WLR 585 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp353 36 [1990] 6 Const. LJ 319 35 65 Similarly, in Hutchinson v Harris 37 , an employer cannot hold an architect liable for rental income lost due to neglect supervision of a conversion project, where the evidence shows that the employer could easily have done what was required to render the premise lettable. In Rockingham Country v Luten Bridge Co. 38 , it was a contract to build a bridge. The country decides not to build the bridge because there is no road to it. Due to this problem, the Government gave notice not to continue building bridge. However, the contractor continued to build it by ignoring the notice. The Court said that, there was a duty to mitigate rests on the contractor, therefore they have to stop work and should not have continued. 3.8 Significance Aspects in Relation to Mitigation Andrew Phang, Boon Leong in his book Cheshire, Fifoot and Furmston’s, Law of Contract in Singapore and Malaysia states briefly a few salient points in relation to the doctrine of mitigation in local context. It can be summarised as following: a) Reasonable Duty to Mitigate Loss A person who suffers from a breach of contract is bound to do all that a reasonable and prudent man would do in the circumstances to mitigate his loss. This principle was applied in Pasuma Pharmacal Corp v McAlister & Co Ltd. 39 This 37 [1978] 10 BLR 19 [1929] US Ct of App. 39 [1965] 1 MLJ 221 38 66 decision also cited and applied in the leading English precedent of Payzu Ltd Saunders 40 , which has been discussed in previous subtopic. b) No advance action of mitigation Further, principles of mitigation cannot apply ‘in advance’. On this basis, an application for an interlocutory injunction to mitigate loss was rejected in Government of Pakistan v Seng Peng Sawmills Sdn Bhd. 41 As observed by the Judge, Abdul Razak in this case: I have not been indicated on what authority injunction, and a mandatory one at that can be made to mitigate one’s loss where the question whether there had been loss all and by whom had yet to be decided. In saying that the application was to mitigate his loss the applicant had arrogated to itself the right to say that the … respondent was at fault and therefore it must now only be the court’s duty to mitigate his loss. c) Insufficient of Evidence In the event when the issue of mitigation is raised too late, whereby in a stage the proceedings with the result that insufficient evidence is available to the court, it would appear that a re-trial on the issue of damages can be ordered. This rules was applied in a case decided by the Brunei court of Appeal in Pacific Electrical Co Ltd v Seng Hup Electrical Co (S) Pte Ltd. 42 40 [1919] 2 KB 581 [1979] 1 MLJ 219 42 [1978] 1 MLJ 162 41 67 d) No Duty to Mitigate Furthermore, it would appear that express statutory provision to the contrary can result in the exclusion of the principle of mitigation. This point can be seen in the Sarawak decision of Kueh Sing Khay v Lim Boon Chuan. 43 It has also been held in Morello Sdn Bhd v Jaques (International) Sdn Bhd 44 , that ‘the right to recover an unpaid deposit or to forfeit a deposit which has been paid, puts the vendor in the position of being able to obtain compensation without having to prove his damage and so there is no duty on his part to mitigate’ 3.9 Conclusion Duty to mitigate is an important limitation on the award of general damages. The non-breaching party is obligated to mitigate, or minimize, the amount of damages to the extent reasonable. For example, when there is a roof leak, the owner should move, remove, or cover valuables that might get wet and place protective plastic sheeting or vessels where needed. This is in satisfaction of the implied contractual duty to mitigate damages. In addition, damages cannot be recovered for losses that could have been reasonably avoided or substantially restore d after the breach occurred. The nonbreaching party’s failure to use reasonable diligence in mitigation the damages means that any award of damages will be reduced by the amount that could have been reasonably avoided. 43 44 [1950] SCR 23 [1995] 1 MLJ 577 (also reported at [1995] 2 CLJ 23, [1995] 1 AR 873 and [1995] 1 MAC 153) 68 However, the doctrine of mitigation in minimising the damages or losses is applied on a case-to-case basis. The non-breaching party does not have to embark on a hazardous or uncertain course of action that causing him incur substantial expenses or inconveniences, damage his reputation, or breach any contracts, in order to mitigate as decided in Pilkington v Wood. In the circumstances of the example given, if the owner fails to minimize damages when possible, it would be difficult to hold the contractor responsible for consequential damages. All of the owner’s extra costs for necessary mitigation efforts should be charged to the contractor. Thus, in short, when one party has breach the contract, the other party must take all reasonable steps to mitigate the losses consequent on the breach, and if he fails to do so, he is disqualified from recovering in respect of any part of the damages, which is due to his negligence to take such steps. CHAPTER 4 REQUIREMENTS OF MITIGATION AND THE EXTENT OF MITIGATION IN ENFORCING LAD PROVISIONS CHAPTER 4 REQUIREMENTS OF MITIGATION AND THE EXTENT OF MITIGATION IN ENFORCING LAD PROVISIONS 4.1 Introduction The principles and rules of Liquidated and Ascertained damages (LAD) and mitigation had been explained in the previous chapter. Consequently, this chapter focus on the achievement of each objective that had set up. In other words, this chapter is the most important part for the whole research, whereby it will determine whether the objectives that had set in the earlier stage of the research could be achieved. Briefly, this chapter will be divided into two (2) parts as following: 1: Requirements of Mitigation in Enforcing LAD provisions 2: The extent that employer has to mitigate his losses in enforcing LAD provisions 70 4.2 Requirements of Mitigation in Enforcing LAD Provisions It was a query that whether the employer is bound to mitigate his losses in enforcing LAD in the event of contractor’s late completion as such requirement is not stipulated in the LAD provisions. Due to this issue, the requirements of mitigation in the event of breach, and what are the rules that may override the provisions should be identified. As explained in chapter 3, mitigation of damages is a common law defence, and is often known as the law of avoidable consequences. 1 Thus, it is necessary to look at the Malaysian legal system and the sources of Malaysian Law in order to find out what are the rules that may override the building contracts. 4.2.1 Malaysian Law Malaysian law can be classified into written, unwritten law and Muslim law. 2 Written law is the most important source of law and it refers to that portion of Malaysian law which includes the Federal and State Constitutions. The Federal Constitution is the supreme law of land. There are also Constitutions of the thirteen States comprising the Federation, which from part of written law in Malaysia. Legislation enacted by Parliament and the State Assemblies, (e.g. Acts of Parliament, Ordinances, Enactments, etc.). Subsidiary legislation made by persons or bodies under powers conferred on them by Acts of Parliament or State Assemblies (e.g. Rules and Regulations, By-laws, guidelines, etc.). 3 1 TCPALaw.com, Headnote Issues Research. (August 2, 2003). Mitigation of Damages. URL: http://.www.tcplaw.com/free/head2.pdf 2 Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp17 3 Ibid 71 Unwritten law is simply that portion of Malaysian law which is not written, i.e. law which is not being enacted by Parliament or the State Assemblies and which is not found in the written Federal and State Constitutions. Unwritten law is found in cases decided by the courts, local customs, etc. The unwritten law comprises the principles of English law applicable to local circumstances, judicial decisions of the superior courts, i.e. the High Courts, Court of Appeal and the Federal Court and customs of the local inhabitants which have been accepted as law by the courts. Muslim law is also an important source of Malaysian law but it is applicable to Muslims only and is administered by a separate system of courts. 4 In Malaysia, Muslim or Islamic law is increasingly being applied in our local laws. 5 For instance, currently there is a move to incorporate some Islamic principles into land laws ad banking laws. In further, it is applies to all person who are Muslims and of particular are the laws relating to family matters and estate matters relating to the division of property and assets when a person dies. 6 4.2.2 English Law English common law and the rules of equity form part of the laws of Malaysia. 7 English law can be found in the English common law and rules of equity. However, not all of England’s common law and rules of equity form part of Malaysian law. 4 Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp23 5 Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp18 6 Ibid. 7 Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp24 72 Section 3(1) of the Civil Law Act 1956 (Revised 1972) provides that: a. in West Malaysia or any part of thereof, apply the common law of England and the rules of equity as administered in England on the 7th April, 1956; b. in Sabah, apply the common law of England and the rules of equity, together with statutes of general application, as administered or in force in England on the 1st day of December, 1951; c. in Sarawak, apply the common law of England and the rules of equity, together with statutes of general application, as administered or in force in England on the 12th day of December, 1949… It is to be noted that, Section 3(1) (a) applicable to West Malaysia mentions the application of “the common law of England and the rules of equity” whereas Section 3(1) (b) and (c) applicable to Sabah and Sarawak allows the application of “the common law of England and the rules of equity, together with statutes of general application”. 8 However, the application of the law of England throughout Malaysia is subjected to two limitations: 9 a. Firstly, it is applied only in the absence of local statutes on the particular subjects. Local law takes place precedence over the England law as the latter is meant only to fill in gaps in the local system. 8 Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp24-25 9 Ibid, pp26 73 b. Secondly, only that part of the England law that is suited to local circumstances will be applied. The provision to Section 3 (1) of the Civil Law Act is the authority for this. The provision stated that ‘the said common law, rules of equity and statutes of general application shall be applied so far only as the circumstances of the States of Malaysia and their respective in habitants permit and subject to such qualifications as local circumstances render necessary’. This provision is necessary as the population in Malaysia comprise of diverse races practicing a variety of customs and religions, most of which are totally different from those of the English. 10 The cases which recognized this fact include Chulas v Kolson 11 , Khoo Tiang Bee v Tan Beng Guat 12 , Khoo Hooi Leong v Khoo Chong Yeok 13 , and Chou Choon Neoh v Spottiswoode 14 . 15 In Chou Choon Neoh v Spottiswoode, Maxwell C.J. held that the English Superstitious Uses Act, 1947 and the Mortmain Acts of 1531 and 1735 were not applicable in the Straits Settlements. The extent of the application of common law of England in Malaysia was also decided in Syarikat Batu Sinar Sdn. Bhd. & Ors v UMBC Finance Bhd. & Ors. 16 . This case concerned ownership claim over a second-hand tractor. The problem of double financing arose because the first purchaser’s (UMBC Finance’s) ownership was not indorsed on the registration card o vehicle. UMBC Finance Bhd. wanted to repossess the tractor. The plaintiffs sued them, seeking a declaration that the defendants were not entitled to the tractor. The High Court allowed the plaintiffs’ application. 10 Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp25 11 [1867] Leic.462 12 [1877] 1 Ky. 423 13 [1930] A. C. 346 14 [1869] 1 Ky. 216 15 Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp25 16 [1990] 3 MLJ 468 74 The case was held that, all buyers of second-hand cars in Peninsular Malaysia have always depended on the absence of any registered endorsement of claim to ownership in the registration card as a ‘green light’ to deal with sellers whose names are registered as owners on the registration cards or their mercantile agents. The practice in Peninsular Malaysia combined with local statutory provisions in regard to the registration of ownership claims would constitute such a distinctive local circumstance of the inhabitants of Peninsular Malaysia that the decisions in English cases on the point of failure to have an ownership claim registered should not be followed. 4.2.3 English Commercial Law Section 5(1) introduces into the former Malay States principles of English Commercial Law as it stood on 7th April, 1956 in the absence of local legislation. This section states that: In all questions or issues which arise or which have to be decided in the states of West Malaysia other than Malacca and Penang with respect to the law of partnerships, corporations, banks and banking, principals and agents, carriers by air, land and sea, marine insurance, average, life and fire insurance, and with respect to mercantile law generally, the law to be administered shall be the same as would be administered in England in the like case at the date of the coming into force of this Act, if such question or issue had arisen or had to be decided in England, unless in any case other provision is or shall be made by any written law. On the other hand, section 5(2) of Civil Law Act, which applies to the States of Penang, Malacca, Sabah and Sarawak provides that English Commercial Law 75 shall apply to the matter which has to be decided in the named States as it would in England. The said subsection provides that: “…the law to be administered shall be the same as would be administered in England in the like case at the corresponding period, if such question or issue had arisen or had to be decided in England”. Thus, in the four States mentioned above, there is still a continuing reception of English commercial Law in the absence of local legislation. 17 However, since there are so many local statutes already passed which deal with commercial subjects, there is no total reliance on English commercial Law. 18 Such local statues include the Companies Act 1956 (Revised 1973), Partnership Act 1961 (Revised 1974), Banking and Financial Institutions Act 1989 Contracts Act 1950 (Revised 1974), Insurance Act 1963 (Revised 1972), and Bills of Exchange Act 1949 (Revised 1978). In Kon Thean Soong v Tan Eng Nam 19 , it was held that English Law of partnership was not applicable in Malaysia since there is a local statute applicable, that is, the Contract (Malay States) Ordinance. 4.2.4 Requirements of Mitigation in Enforcing LAD Provisions In order to determine whether the employer is bound to take mitigation in enforcing LAD, the sources of Malaysian law was investigated. As before mentioned, English common law and the rules of equity form part of the laws of Malaysia. Its application is subjected to two limitations as it is applied only in the absence of local statutes on the particular subjects and only for the parts is suited to local circumstances. Since principle of mitigation is silent in Malaysian law, then it will be referred to English Law. 17 Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp27-28 18 Ibid 19 [1982] 1 MLJ 323 76 In a recent High Court’s case, namely Joo Leong Timber Merchant v Dr Jaswant Singh a/l Jagat Singh 20 , damages were assessed on the basis that an innocent party had a duty to mitigate his damages. It was held that, a victim of a breach of contract could not cut short his duty to mitigate his loss by the mere commencement of an action for damages (see Techno Land Improvements Ltd v British Leyland (UK) Ltd [1979] EGD 519). This was an appeal by the appellant against the decision of the sessions court (the trial court). The session court had dismissed the appellant’s claim for RM 31, 700 the balance sum due and payable by the respondent to appellant in respect of building works executed and materials supplied by the appellant towards the erection of a single storey bungalow for the respondent. On the other hand, the sessions court allowed the respondent’s counterclaims for RM 63,000 for the cost of remedial works and RM 300 per month from 15 August 1985 to 22 October 1998 for the loss of rental income from 15 August 1985 to 22 October 1998. High court allowed the appeal due to some errors done by the trial court, whereby not refusing the compensation as claimed. By right, the respondent must prove the alleged damages suffered by adopting the principles of s 75 of the Contracts Act 1950 ('the Act'). The failure to prove damage should have resulted in the refusal of the trial court to award compensation in the sum of RM300 per month for the period of 15 August 1985 to 22 October 1998. The principle in Penang Port Commission v Kanawagi s/o Seperumaniam 21 followed. In addition, the respondent had not shown that he had taken any steps to mitigate his damage. The respondent not ending the alleged loss of rental income, in relation to his duty to mitigate was not reasonable. An innocent party can recover no greater damages for breach of contract that the loss he would have sustained had he acted reasonably to avoid or reduce losses. 20 21 [2003] 5 MLJ 116 [1996] 3 MLJ 427 77 In this case, the damages are assessed on the basis that an aggrieved party has a duty to mitigate his damages (West v Versil Ltd & Ors Court of Appeal (Civil Division), The Times, 31 August 1996; Kleinwort Benson Ltd v Birmingham City Council [1996] 4 All ER 733). Since the employer failed to show that he had taken steps to mitigate his loss by resuming the works, he could not recover liquidated and ascertained damages for a period of time, which would have been avoided had he taken such steps. The settled principle is ‘innocent party can recover no greater damages for breach of contract than the loss would have sustained had he acted reasonable to avoid or reduce loss’ as per Goulding J. in Techno Land improvement Ltd v British Leyland (UK) Ltd. 22 Mitigation of damages is a common law defence. A claim for damages is subjected to a duty to mitigate the loss (Westwood v Secretary of State for Employment [1985] AC 20; Maredelanto Compania Naviera SA v Bergbau-Handel GmbH; 'The Mihalis Angelos' [1970] 3 WLR 601; Boyo v Lambeth London Borough Council [1994] ICR 727; Hopkins v Norcross plc [1993] 1 All ER 565). In addition, the right to damages is qualified by a duty to mitigate (T & S Contractors Ltd v Architectural Design Associated QBD (Official Referee's Business) 16 October 1992). In short, a party claiming damages for breach of contract is under the duty to mitigate the losses he has suffered as imposed generally by the common law. From the case analysis, the case of Joo Leong Timber Merchant v Dr Jaswant Singh a/l Jagat Singh 23 is the first case which due with the requirements of mitigation in enforcing LAD provision in Malaysian context. This case had drawn a clear line that employer as the innocent party in the event of late completion is bound to take mitigation in order to reduce his losses from such breach in building contracts. As a result, employers should be aware and more cautious of this requirement while enforcing the LAD provisions. Further, the requirement of mitigation under common law is applicable while enforcing the LAD provision in the event of late completion. 22 23 [1979] EGD 519 [2003] 5 MLJ 116 78 4.3 The Extent That Employer Has to Mitigate His Losses in Enforcing LAD Provisions There is a general principle that where a breach has occurred, the injured party who accepts the breach as discharging the contract, must take all reasonable steps to mitigate the loss occasioned by the breach. 24 However, to what extent does the employer has to mitigate his losses in the event of late completion while enforcing LAD is the main issue. Hence, analysis against the principles and rules of mitigation should be taken. 4.3.1 The Extent in Loss Mitigation Briefly, mitigation is reduction in the loss resulting from a breach of contract and the innocent party is under a duty to take all reasonable steps to mitigate his loss when claiming damages. Failure or negligence to take such steps will debar the innocent party from claiming any part of the damages as held in British Westinghouse Electric Co. v Underground Electric Co. of London. 25 As discussed in chapter 3, the “duty to mitigate” only requires the plaintiff to make reasonable efforts to mitigate damages. The most significant aspect in relation to the doctrine of mitigation is reasonableness in taking mitigation. The innocent party is bound to take a reasonable duty to mitigate loss, but the innocent party is not liable to take mitigation in the event of interlocutory of breach. On the other hand, the plaintiff does not have to embark on a hazardous or uncertain course of action that causing him incur substantial expense or inconvenience, damage his reputation, or breah any contracts, in order to mitigate. 24 25 Upex, R. (1991). Davies on Contract. 6th ed. London: Sweet & Maxwell Limited. pp261 [1912] AC 673 79 4.3.2 Reasonableness in Taking the Duty to Mitigate The principle of reasonable duty in taking mitigation is governed by the doctrine of mitigation. A person who suffers from a breach of contract is bound to do all that a reasonable and prudent man would do in the circumstances to mitigate his loss, see Pasuma Pharmacal Corp v McAlister & Co Ltd. 26 and Payzu Ltd Saunders. 27 In addition, a reasonable duty of mitigation is a sensible, rational, logical or a realistic action that will be taken by a prudent man in reducing his losses. Based on a previous research’s finding as mentioned in chapter 2, the typical component costs incorporated to LAD are loss of income, financing loss, business disruption loss, management cost, and professional cost. Indirectly, the employer will suffer these losses in the event of late completion. For example, construction work for a double storey bungalow was in late completion due to contractor’s fault and this affected the owner could not move in his house on time. In order to resolve his accommodation problem, the owner might have to rent a temporary house or hotel for certain duration while waiting for the new bungalow to be completed. Consequently, the owner can recover his losses by enforcing the LAD provision for the cost of rental for the duration that the project has delayed. For instant, assuming that the bungalow worth around five hundred thousand and located in a small town area and the owner has two choices, either to rent a three stars hotel cost RM 300 a day or rent a five stars hotel cost RM 600 a day. In order to compliance with the requirements of mitigation, the owner is bound to take a duty 26 27 [1965] 1 MLJ 221 [1919] 2 KB 581 80 of mitigation to reduce his losses, whereby, he could not allow the losses increase without taking any reasonable steps. In fact, the owner has to rent a place with an equal or likely amount to the pre-estimate sum as losses that he would suffered. As a result, the owner should rent a three stars hotel instead of a five stars hotel. This decision was made by considering the value of the bungalow and the rental is reasonable. However, if the owner was going to claim RM 600 a day, it will be an unreasonable amount of losses that he might be entitled. This is because the amount is too high and unreasonable if compared to the value of the bungalow and the location as well, unless the bungalow is worth much more expensive. In further, the owner is not taking all reasonable steps to mitigate his losses and the court will refuse to award the damages. 4.3.3 Bottom Line of Mitigation It should be bear in mind that the “duty to mitigate” only requires the plaintiff to make reasonable efforts to mitigate damages. There is a bottom line in taking mitigation. Duty to mitigate is not an action that will embark the plaintiff into dangerous, risky, unsafe, incur substantial expense or inconvenience, damage his reputation, or breah any contracts, in order to mitigate. This principles was applied in Pilkington v Wood 28 . The court remarked: "The so-called duty to mitigate does not go so far as to oblige the injured party, even 28 [1953] 2 Ch 770; [1953] 3 WLR 522 81 under an indemnity, to embark on a complicated and difficult piece of litigation against a third party. It is no part of the plaintiff's duty to embark on the proposed litigation in order to protect his solicitor from the consequences of his own carelessness' (per Harman J)." 29 Similarly, in Selvanayagam v University of the West Indies 30 , the plaintiff was not required to undergo an operation which carried a risk of post-operative complications in order to mitigate the loss. 31 In a same example as discussed in subtopic 4.3.2 in reasonableness in taking mitigation, the owner of the bungalow is not liable to embark himself into trouble. For example, he is not necessary to rent hotel which far away from his working place that will cause him inconvenience in daily travel, or rent a house that located in a squatters area that the owner will be exposed to the risk of losses, injuries or troublesome, in order to comply with the duty to mitigate his losses. This is because none of these are considered a reasonable or sensible steps that a prudent man would do in the circumstances to mitigate his loss. 32 4.4 Conclusion It is common that employer will try to recover his damages or losses that he had suffered in the event of late completion by deducting such amount from any money due or become to the contractor. The analysis found that the principle of mitigation is silent in Malaysian law, and it will therefore be referred to English Common Law. This is because of English common law form part of the Malaysian law and will applied when a particular subject is absence in local statutes. 29 Cases on Damages. ULT: http://www.lawteacher.net/Contract/Discharge%20and %20Remedies/Remedies%20Lecture%20htm 30 [1983] 1 WLR 585 31 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp353 32 see Pasuma Pharmacal Corp v McAlister & Co Ltd. [1965] 1 MLJ 221 and Payzu Ltd Saunders. [1919] 2 KB 581 82 The requirement of mitigation is applied in the event of enforcing LAD although such requirement is not stipulated in the contract. Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh 33 is the first case which deals with the requirements of mitigation in enforcing LAD. Whereby, an employer is bound to make reasonable efforts to mitigate damages, not to take an action that will embark him on a hazardous or causing him incur substantial expense or inconvenience, damage his reputation, or breach any contracts as applied in Pilkington v Wood. Employers are advised to make sure that he had taken all the reasonable steps in order to mitigate his losses in the event of late completion, so that they may be able to recover their losses suffered during the delayed duration. 33 [2003] 5 MLJ 116 CHAPTER 5 CONCLUSION AND RECOMMENDATIONS CHAPTER 5 CONCLUSION AND RECCOMMENDATIONS 5.1 Introduction This chapter attempts to conclude the research’s findings based on the literature review, case studies, and analysis. In brief, it consist of the research’s findings, research’s constraints, some suggestions for future studies and conclusion to the whole study. 5.2 Research’s Findings The objectives of this study is to determine the requirements of mitigation and the extent that employer has to mitigate his losses in enforcing LAD provisions. The findings are summarised in following subtopics. 84 5.2.1 Objective 1: To Determine the Requirements of Mitigation in Enforcing the LAD Provisions in Construction Contracts Mitigation of damages is a common law defences, often known as the law of avoidable consequences. 1 English common law and the rules of equity form part of the laws of Malaysia. 2 English law can be found in the English common law and rules of equity. However, not all of England’s common law and rules of equity form part of Malaysian law. A limits of the application of the England law throughout Malaysia is only in the absence of local statutes on the particular subjects. In other words, English Law is meant to fill in gaps in the local system. 3 Therefore, whatever silent in Malaysian law will be referred to English law. From the analysis, the requirement of mitigation is applied in Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh 4 . If the plaintiff fails to take all reasonable steps to mitigate the loss consequent to the breach, he will be debarred from recovering in respect of any part of the damage which is due to his neglect to take such steps.5 In addition, the burden of proving such failure rests upon the defendant; see Payzu Ltd v Saunders. 6 It was found that, Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh is the first case that deals with the requirements of mitigation in enforcing LAD as normally it applied in claiming general damages. The principle applied is a victim of a breach of contract could not cut short his duty to mitigate his loss by the mere commencement of an action for damages (see Techno Land Improvements Ltd v British Leyland (UK) Ltd [1979] EGD 519). Thus, employer 1 TCPALaw.com, Headnote Issues Research. (August 2, 2003). Mitigation of Damages. URL: http://.www.tcplaw.com/free/head2.pdf 2 Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp24 3 Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp24-25 4 [2003] 5 MLJ 116 5 see Payzu v Saunders [1919] 2 KB 581 6 Richards, P. (2004). Law of Contract. 6th Ed. England; Pearson Education Limited. pp353 85 who claims for LAD is now bound to comply with the duty of mitigation in order to success in claiming his losses resulted consequent from the contractor’s breach of contract although such requirement not expressly stipulated in the form of contract. Failure in compliance with such requirements will cause the employer failing in recovery of his losses by enforcing LAD provision. 5.2.2 Objective 2: To Determine the Extent that Employer Has to Mitigate his Losses in Enforcing LAD Provisions A party claiming damages for breach of contract is under the duty to mitigate the loss he has suffered as imposed generally by the common law. The doctrine of mitigation of loss means that a plaintiff cannot recover damages for any part of loss which could have been avoided by taking reasonable steps. 7 However, the doctrine of mitigation in minimising the damages or losses is determined on a case-to-case basis. In addition, the “Duty to mitigate” is only in the sense that if plaintiff fails to do it, he will lose the right to collect damages, not in the sense that he has breached some obligation 8 The research found that the duty to mitigate is subject to certain limitations, namely reasonableness and the bottom line of mitigation. In other words, the “duty to mitigate” only requires the plaintiff to make reasonable efforts to mitigate damages. On the other hand, the bottom line of mitigation is that the plaintiff does not have to embark on a hazardous or uncertain course of action that will cause him incur substantial expense or inconvenience, damage his reputation, or breach any contracts, in order to mitigate, see Pilkington v Wood 9 . 7 Murdoch, J. and Hughes, W. (1997). Construction Contracts: Law and Management. 2nd Ed. UK; E & FN Spon. pp324 8 Emanuel, S. Emanuel Law Outlines: Contracts: Chapter 10: Remedies. URL://http:www.stcl/students/sba/EmanuelContractsOutline.doc 9 [1953] 2 Ch 770; [1953] 3 WLR 522 86 5.3 Research’s Constraints The main constraint of this study is insufficient of time. Due to the fixed time frame, the extent and scope of this research has been narrowed down and limited to certain objectives. Besides that, limitation of decided court cases in relation to the duty to mitigate losses in enforcing LAD also caused the difficulty in getting a comprehensive finding. This is because the requirements of mitigation commonly applied in claiming general damages but unlikely in enforcing LAD in building contracts. 5.4 Suggestions For Further Research In order to achieve the objective of the study within the time frame, the research only managed to answer the questions regarding the requirements of mitigation and the extent that employer has to mitigate his losses in enforcing the LAD provisions. There are a few aspects not covered in this research due to the constraints mentioned above. Therefore, in order to encourage further exploration and investigation on the issues deal with LAD, a few suggestions for further research emerged: 1. Study on the causes of delay that will give rise to LAD enforcement. 2. Study on the approaches that can be used by employer in taking the duty to mitigate his losses in enforcing LAD provisions. Perhaps further research may give a more comprehensive guidance and to safeguard the employers from the challenges while claiming their losses in the event of late completion. 87 5.5 Conclusion Most standard construction contracts provide the insertion of liquidated damages clause. 10 The intention of having LAD provisions in building contracts is to avoid uncertainties and expenses of long evidentiary battles to establish (or refuse) the owner’s actual damages, parties to a construction contract may agree in advance to liquidate those damages. 11 The LAD amount is agreed between the parties to be paid and provides a certainty to employer to the amount that he will be entitled to recover without having the difficulty of proving loss in the event of non-performance of a contractual obligation. Besides that, it also provide the contractor a certainty to the extent of risk they are taking in tender stage and allow them to estimate and price the risk within their tender. In Malaysia, the position on the deduction of LAD is somewhat different from other common law jurisdictions. 12 Whereby, in Malaysia ‘there is no difference between penalty and liquidated damages’ 13 , in view of s75 of the Contracts Act 1950, the court must determine what is reasonable compensation. Therefore, employer who claims for LAD is required to prove his losses. 14 In addition, from the analysis, it is found that employer who claims for LAD is required to mitigate his losses 15 although such requirements are not expressly stipulated in the form of contract. Failure or negligence of plaintiff in taking all reasonable steps to mitigate the loss consequent to the breach will debar him from recovering any part of the damages and the burden of proving such failure rests upon the defendant. 16 10 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL: http://www.prettys.co.uk/business_law/construction/lads.shtml. 11 Stockenberg, R.A. Building Design & Construction: Liquidated Damages – A two-edged sword. May, 2002; 43, 5; ABI/INFORM Global. pp29. URL: http://www.bdemag.com 12 Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-with Particular reference to PWD/JKR standard Forms of Contract. 27 July, 2004. Kuala Lumpur: James R Knowles (M) Snd. Bhd. pp18 13 Sundra Rajoo. (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 FORM). 2nd ed. Kuala Lumpur; Malayan Law Journal Sdn. Bhd. pp193 14 see Selvakumara/l Murugaih v Thiaragajah a/l Retnasamy [1995] 1 MLJ 817 15 see Joo Leong Timber Merchant v Dr. Jaswant Singh A/L Jagat Singh. [2003] 5 MLJ 116 16 Payzu v Saunders [1919] 2 KB 581 88 However, the “duty to mitigate” only requires the plaintiff to make reasonable efforts to mitigate damages. The plaintiff does not have to embark on a hazardous or uncertain course of action that will cause him incurs substantial expense or inconvenience, in order to mitigate loss. 17 Nevertheless, the Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh is the first case that deals with the issue of requirements and application of mitigation while enforcing LAD in building contracts. Therefore, employers are advised to be more prudent and cautious, so that they could claim their losses successfully. Thus, it can be used as guidance to employer as a significant reference in enforcing LAD. Finally, it would be a perfect solution against such challenges in enforcing LAD, or may beneficial to employer and reducing the dispute in relation to such matter in construction industry, if the proposed further studies can be carried out consequently. This is because the judgment did not suggesting any alternative action that can be used by the employer in order to comply with the requirements of loss mitigation. 17 Pilkington v Wood [1953] 2 Ch 770; [1953] 3 WLR 522 REFERENCES REFERENCES Abdul Aziz Hussin Amn. Liquidated Ascertained Damages (LAD). URL:http://www.hbp.usm.my/aziz/LIQUIDATED%20ASCERTAINED%20 DAMAGES.htm Allen, P.E. (Jan, 1995). The Estimation of Construction Contract Liquidated Damages. URL: library.findlaw.com/1995/Jan/1/129415.html. Allen, P.E. (Jan, 1995). The Estimation of Construction Contract Liquidated Damages.URL:http://www.library.findlaw.com.civil.remedies/damages/liqui dated.damages./html Alsagoff, Syed Ahamad. (2003). Principles of the Law of Contract in Malaysia. Malyaisa: Malaysia Law Journal Sdn. Bhd. pp.1 Andrew, Phang Boon Leong. (1998). Law of Contract. 2nd ed. Singapore: the Butterworth Group of Companies. pp1022, 1028 Ashworth, A. (2001). Contractual Procedures in the Construction Industry. 4th ed. England: Pearson Education Limited. pp16, 31, 33 Blake, P. Liquidated Damages – Case Law Review / Sectional Completion. URL:http://www.prettys.co.uk/business_law/construction/lads.shtml. Blaxter, L., et al. (1996). How to research. Buckingham; Open University Press. pp109-121 90 Burrows, A. S. (1987). Remedies for Torts and Breach of contract. UK: Butterworth & Co. (Publishers) Ltd. pp64, 283 Cases on Damages. ULT: http://www.lawteacher.net/Contract/Discharge%20and%20Remedies/Remedi es%20Lecture%20htm Chappell, D. (2003). Understanding. JCT Standard Building Contracts. 7th ed. London: Spon Press Cheney, D. (Oct 15, 2005). Putting The Owner in The Best Position For a Successful Construction Contract. URL: http://www.brickerstaff.com/articles/cheney2001.htm Chow, Kok Fong. (1988). Law and Practice of Construction Contract Claims. Singapore: Longman Singapore Publishers Pte Ltd. pp4, 27-29, 159 Chow, Kok Fong. (1993). Law and Practice of Construction Contract Claims. 2nd ed. Singapore: Longman Singapore Publishers Pte Ltd. Costs, W. (2005). Liquidated Damages Provisions: Are they Always Enforceable?Texas Construction. Baton Rouge: Mar 2005. vol.13, Iss. 3; pp43. URL:http://proquest.umi.com/pqdwed?did=807437291&sid=6&Fmt=3&clie ntld=21690&RQT=309&VName=PQD. Damages and otherRemedies for Breach of Contract. URL:http://www.law.washington.edu/courses/ramasastry/A50k/handouts/rem edies.html Dato’ Visu sinnadurai. (1987). The Law of Contract in Malaysia and Singapore: Cases and Commentary. 2nd ed. Singapore: Butterworth & Co. (Asia) Pte Ltd. pp669-762. 91 Duxbury, R. (1991). Contracts in a Nutshells. London: Sweet & Maxwell. pp1, 101, 102 Eggleston, B. (1997). Liquidated Damages and Extension of Time in Construction Contracts. 2nd ed. London:Blackwell Science Ltd. pp3-4, 53, 57 Emanuel, S. Emanuel Law Outlines: Contracts: Chapter 10: Remedies. URL://http:www.stcl/students/sba/EmanuelContractsOutline.doc Fisk, E. R. (2003). Constuction Project Administration. 7th ed. Pearson Education Limited. pp580-581 Freeman, K. (May, 2005). UK contract Articles in Association with Kendall Freeman: Upholding liquidated damages and avoiding penalties. URL: http://www.legal500.com/devs/uk/co/ukco_022.html Guest, A.G. (1975). Anson’s Law of Contract. 24th ed. London: Oxford University Press. pp549 Harbans Singh KS (2004). Engineering and Construction Contract Management: Commencement and Administration. Malaysia: Lexis Nexis Business Solutions. pp501, 507, 536-538, 572, 576 Harbans Singh KS (2004). Engineering and Construction Contract Management: Law and Principles. Malaysia: Lexis Nexis Business Solutions. pp200, 202, 204, 209, 217-222 Irvin, E.R. (1987). Construction Claims and the Problems of Cost Management. Cost Engineering, Morgantown: Aug 1987. Vol.29, Iss.8; pg.20. URL: http://proquest.umi.com/pqdweb?did=924865&sid=2&Fmt=2&client=21690 &PQT=309&VName=PQD Johnson, M.J. and Boates, C.T. Business Credit; Legal Jargon: Liquidated Damages. Business Credit; Mar 2002; 104,3; ABI/INFORM Global. pp68 92 Karas, Hal and Brower, D. (June2, 2003). The Daily Reporter: Liquidated Damages: Clause must be reasonable. The Daily Reporter, Issued Monday, June 2, 2003.URL: http://bmf-law.com Kenny, P. (2001, March). Liquidated Damages: how much of a threat can they be? Heavy construction News. Toronto: Mar 2001 vol.45. Iss.3. Pg.32. URL:http://proquest.umi.com/pqdweb?did-37477610&sid8&Fmt3&clientld.21690&RQT-309&VName-PQD Kerry, P. (2001). Liquidated damages: how much of a threat can they be? Heavy Construction News. Toronto: Mar 2001. Vol.45 Iss.6; pp32. URL: http://proquest.umi.com/pqdweb?did=374776101&sid=8&Fmt=3&clientd=2 1690%RQT=309&VName=PQD. Lee, Mei Peng. (2005). General Principles of Malaysian Law. 5th ed. Selangor: Penerbit Fajar Bakti Sdn. Bhd. pp17-18, 27-28, 166 Lim, Chong Fong. (2004). The Malaysian PWD Form of Construction Contract. Malaysia: Sweet & Maxwell Asia. Liquidated Damages for construction Delays: Definitions and Legal interpretation in Connection with delays. URL:http://www.CTS2000.bizland.com/liquidated.htm Lynch, B.G., (June, 2003). Building Journal Hong Kong China: Focus on legal: The Employer’s Risk? Martin, E. A. (2003). A Dictionary of Law. 5th ed. London: Oxford University Press. Martin, R. In What Circumstances Does An Employer Have The Right To Levy Liquidated Damages? James R Knowles (M) Sdn. Bhd. URL: www.jrk.com.sg/ARTICLES/employerliqdamages.htm 93 Murdoch, J. and Hughes, W. (1996). Construction Contracts, Law and Management. 2nd ed. London: E&FN Spon. pp324, 327-328 Oxford Dictionary of Law (2003). Oxford University Press: Market House Books Ltd. pp318 Partks, G.T. (March, 2002). A Primer on Construction Damages: A Damage Is a Damage? Not Really! URL: http://www.bricker.com/legalservices/industry/construction/heavyhighway/ar ticle3.asp Paterson, J. et.al. (2005). Principles of Contract Law, 2nd ed. Sydney: Lawbook Co., pp.234, 333, 411, 450, 605 Powell-Smith, V. and Furmston, M. (1987). A building Contract Casebook. London: BSP Professional Books. pp336 Remedies For Breach 1 – Damages. URL: http://www.lawteacher.net/Contract/Discharge%20and%20Remedies/Remedi es%20Lecture%20.htm Richards, P. (2004). Law of Contract. 6th ed. England: Pearson Education Limited. pp352, 353 Robb, G.G.G. and Brookes, J.P. (1970). An Outline of the Law of contract and Tort. 4th ed. London: The Estates Gazette Limited., pp.99 Robinson, N. M., et al. (1996). Construction Law in Singapore and Malaysia. 2nd ed. Singapore: The Butterworth Group of Companies. pp241-242, 244 See, Seow Lee. (1995/96). Prinsip Pemakaian Dantirugi Tertentu dan Ditetapkan dari Perspectif Perundangan. Universiti Teknologi Malaysia : Degree Thesis. pp55-64 94 Simon, M. S. (1979). Construction Contracts and Claims. United States: McGraw Hill, Inc. Steve, Chan. (2004). Lecture 4: Duty to Mitigate, Constructive Acceleration, Challenges to Liquidated Damages. Bullet-Proof EOTs-With particular reference to PWD/JKR Standard Forms of Contract. 27 July, 2004. Grand Plaza Parkroyal Kuala Lumpur. James R Knowles (M) Sdn. Bhd. pp17, 18 Stockenberg, R.A. Building Design & Construction: Liquidated Damages – A two edged sword. May, 2002; 43, 5; ABI/INFORM Global. pp29. URL: http://www.bdemag.com Stokes, M. and Finuf, J. L. (1986). Construction Law for Owners and Builders. United States: McGraw-Hill Book Company. Sundra Rajoo (1999). The Malaysian Standard Form of Building Contract (The PAM 1998 Form). 2nd ed. Malaysia: The Butterworth Group of Companies. pp191195 Syed Ahmand Alsagoof (2003). Principles of the Law of Contract in Malaysia. 2nd ed. Malaysia: Lexis Nexis Business Solutions. pp370, 387 Turner, D. F. (1971). Building Contracts: A Practical Guide. London: George Godwin Ltd. pp9, 17 Upex, R. (1991). Davies on Contract. 6th ed. London: Sweet & Maxwell Limited. pp261 Vohrah, B. and Wu, Min Aun. (2003). The Commercial Law of Malaysia. Malaysia: Pearson Malaysia Sdn. Bhd. pp176-179 Wallenfang, R.L. (2001). Coordinator – Construction Law Group – Liquidated Damages for Delay in Construction Contracts. URL: http://www.concretemasonry.org/design/Liquidated_damages.htm 95 What is the ‘duty to mitigated damages?’ URL: http://injurylaw.freeadvice.com/property_damage/mitigate_duty.htm Wu, Min Aun. (1982). An Introduction To The Malaysian Legal System. Revised 3rd ed. Malaysia: Heinemann (Malaysia) Sdn. Bhd. pp23-25 Zakir Mulla. (25 February 2005). Liquidated damages: North Sea Ventilation Ltd v Consafe Engineering. URL: htp://www.rics.org 3.11 The Duty to Mitigate Loss (Keeping Costs to a Minimum). (January, 2004). URL: http://www/taswa.org/tm/chapter3/3_11.htm APPENDICES A General Procedure In Recovery Of Liquidated Damages B Clause 40 Of The JKR Forms 203a (Rev 10/83) C Clause 22.0 Of The PAM 1998 Forms D Clause 26 Of The CIDB Form (2000 Edition) E Section 74-76 Of Contracts Act 1950 F Section 3, 5 Of Civil Law Act 1956 G Case 1: Joo Leong Timber Merchant v Dr Jasawant Singh a/l Jagat Singh [2003] 5 MLJ 116 H Case 2: Payzu Ltd. V Saunders [1919] 2 K.B. 581 I Case 3: Selva Kumar a/l Murugiah V Thiaragajah a/l Retnasamy [1955] 1 MlJ 817 APPENDIX A GENERAL PROCEDURE IN RECOVERY OF LIQUIDATED DAMAGES 96 APPENDIX A General Procedure In Recovery Of Liquidated Damages (Part I) 97 APPENDIX A General Procedure In Recovery Of Liquidated Damages (Part 1I) 98 APPENDIX A General Procedure In Recovery Of Liquidated Damages (Part III) APPENDIX B CLAUSE 40 OF THE JKR FORMS 203A (REV 10/83) 99 APPENDIX B Clause 40 of the JKR Forms 203A (Rev 10/83) APPENDIX C CLAUSE 22.0 OF THE PAM 1998 FORMS 100 APPENDIX C Clause 22.0 of the PAM 1998 Forms 101 APPENDIX C Clause 22.0 of the PAM 1998 Forms APPENDIX D CLAUSE 26 OF THE CIDB FORM (2000 EDITION) 102 APPENDIX D Clause 26 of the CIDB Form (2000 Edition) 103 APPENDIX D Clause 26 of the CIDB Form (2000 Edition) APPENDIX E SECTION 74-76 OF CONTRACTS ACT 1950 104 APPENDIX E Section 74-76 of Contracts Act 1950 105 APPENDIX E Section 74-76 of Contracts Act 1950 106 APPENDIX E Section 74-76 of Contracts Act 1950 107 APPENDIX E Section 74-76 of Contracts Act 1950 108 APPENDIX E Section 74-76 of Contracts Act 1950 109 APPENDIX E Section 74-76 of Contracts Act 1950 APPENDIX F SECTION 3, 5 OF CIVIL LAW ACT 1956 110 APPENDIX F Section 3, 5 of Civil Law Act 1956 111 APPENDIX F Section 3, 5 of Civil Law Act 1956 112 APPENDIX F Section 3, 5 of Civil Law Act 1956 113 APPENDIX F Section 3, 5 of Civil Law Act 1956 APPENDIX G CASE 1: JOO LEONG TIMBER MERCHANT V DR JASAWANT SINGH A/L JAGAT SINGH [2003] 5 MLJ 116 114 APPENDIX G Case 1: JOO LEONG TIMBER MERCHANT V DR JASWANT SINGH A/L JAGAT SINGH [2003] 5 MLJ 116 CIVIL APPEAL NO 12-14 OF 1998 HIGH COURT (MUAR) DECIDED-DATE-1: 30 NOVEMBER 2002 JEFFREY TAN J CATCHWORDS: Contract - Building Contract - Agreement to construct a house - Delay in completion Claim for loss of rental - Whether trial court should have considered s 75 of the Contracts Act 1950 - Whether claim should have been made for liquidated and ascertained damages - Whether claim for loss of rental has been proved Contract - Building Contract - Damages - Damages to be awarded - Duty to mitigate Whether failure to mitigate damages must be pleaded HEADNOTES: This was an appeal by the appellant against the decision of the sessions court ('the trial court'), dismissing the appellant's claim for RM31,700, it being allegedly the balance sum due and payable by the respondent to the appellant in respect of building works executed and materials supplied by the appellant towards the erection of a single storey bungalow for the respondent, and allowing the respondent's counterclaim for RM63,000, it being allegedly the respondent's costs of remedial works, and the respondent's counterclaim for RM300 per month from 15 August 1985 to 22 October 1998, it being allegedly the respondent's loss of rental income for the period 15 August 1985 to 22 October 1998 allegedly occasioned by the appellant's failure to complete the said single storey bungalow within the contractual period. With regard to the appeal on the claim, it was agreed that the outcome would be determined by a single finding, based on the appeal record, as to whether, one KC Ooi was or was not the architect for the proposed bungalow. Held, allowing the appeal: (1) The trial court had not considered s 75 of the Contracts Act 1950 ('the Act'). On the facts of the case, cl 22 of the building agreement providing that the sum of RM25 for each day's delay payable by the appellant as 'liquidated and ascertained damages', was unquestionably a clause falling within s 75 of the Act. The respondent must prove alleged damages suffered. The trial court did not appreciate that. The respondent had not proved the loss of rental for the period between 15 August 1985 to 22 October 1998. That failure to prove damage should have resulted in the refusal of the trial court to award compensation in the sum of RM300 per month for the period of 15 August 1985 to 22 October 1998. The trial court fell into error by not refusing the compensation as claimed (see pp 122G, 123G-124B); Penang Port Commission v Kanawagi s/o Seperumaniam [1996] 3 MLJ 427 followed. 115 (2) The respondent had not shown that he had taken any steps to mitigate his damage. The conduct of the respondent by not [*117] bringing the alleged loss of rental income to an end, in relation to his duty to mitigate was not reasonable. An innocent party can recover no greater damages for breach of contract that the loss he would have sustained had he acted reasonably to avoid or reduce loss. In Malaysia, there is no legal authority which states that the failure to mitigate damages must be pleaded (see p125BC, H); Techno Land Improvement Ltd v British Leyland (UK) Ltd[1979] EGD 519 followed. (3) It might be so that KC Ooi had not expressly stated that he was the architect. But KC Ooi had clearly conducted himself as the architect. The certificate of payment might have had been for a collateral purpose to obtain a bank loan. But it remains that only the architect could have issued the certificate of payment, and KC Ooi would not have issued the certificate if he had not accepted the appointment. And by issuing the certificate of payment, which was a deliberate act, KC Ooi had conducted himself as the architect, who was entitled to issue the certificate (see p 126G-I). Bahasa Malaysia summary Ini adalah rayuan perayu terhadap keputusan mahkamah sesyen ('mahkamah perbicaraan') yang menolak tuntutan perayu untuk jumlah RM31,700, yang dikatakan sebagai baki jumlah tertunggak dan perlu dibayar oleh responden kepada perayu bagi kerjakerja pembinaan yang telah dilakukan dan bahan-bahan binaan yang telah dibekalkan oleh perayu untuk tujuan pembinaan sebuah banglo satu tingkat responden, dan membenarkan tuntutan balas responden untuk jumlah RM63,000, yang dikatakan sebagai kos responden melakukan kerja-kerja pemulihan, dan tuntutan balas responden untuk RM300 sebulan dari 15 Ogos 1985 hingga 22 Oktober 1998, yang dikatakan sebagai kerugian pendapatan sewa bagi tempoh 15 Ogos 1985 hingga 22 Oktober 1998 yang disebabkan oleh kegagalan perayu untuk menyiapkan banglo setingkat tersebut mengikut tempoh yang dijanjikan. Untuk rayuan bagi tuntutan tersebut, adalah telah dipersetujui bahawa keputusan akan ditentukan dengan hanya satu penemuan yang berdasarkan kepada rekod rayuan, bahawa sama ada seorang KC Ooi adalah arkitek bagi pembinaan banglo tersebut. Diputuskan: (1) Mahkamah perbicaraan telah tidak menimbangkan s 75 Akta Kontrak 1950 (' Akta tersebut'). Dari fakta-fakta kes, kl 22 perjanjian pembinaan tersebut memperuntukkan bahawa perayu perlu membayar jumlah RM25 untuk setiap hari kelewatan sebagai 'liquidated and ascertained damages', yang mana tanpa ragu-ragu adalah satu klausa yang termasuk di dalam lingkungan s 75 Akta tersebut. Responden perlulah membuktikan kerugian [*118] yang dikatakannya. Mahkamah perbicaraan tidak mengambil kira perkara tersebut.Responden tidak membuktikan kerugian sewa bagi tempoh 15 Ogos 1985 hingga 22 Oktober 1998. Kegagalan untuk membuktikan kerugian tersebut sepatutnya akan menyebabkan mahkamah perbicaraan enggan untuk memberi award bagi pampasan berjumlah RM300 sebulan untuk tempoh 15 Ogos 1985 hingga 22 Oktober 1998. Mahkamah perbicaraan telah khilaf kerana tidak menolak pampasan seperti yang dituntut (lihat ms 122G, 123G-124B); Penang Port Commission v Kanawagi s/o Seperumaniam [1996] 3 MLJ 427 diikut. (2) Responden tidak menunjukkan bahawa beliau telah mengambil tindakan untuk mengurangkan kerugian yang di alaminya. Perbuatan responden yang tidak mengambil tindakan untuk menghentikan kerugian bagi pendapatan sewanya, berhubung dengan tanggungjawab beliau untuk mengurangkan kerugiannya, adalah tidak wajar. Pihak yang tidak bersalah boleh mendapat gantirugi yang tidak lebih daripada gantirugi bagi kemungkiran perjanjian yang akan ditanggungnya sekiranya beliau telah mengambil 116 tindakan yang sewajarnya bagi mengelak atau mengurangkan kerugian tersebut. Di Malaysia, tidak terdapat autoriti undang-undang yang mengatakan bahawa kegagalan untuk mengurangkan kerugian mesti diplidkan (lihat ms 125B-C, H); Techno Land Improvement Ltd v British Leyland (UK) Ltd[1979] EGD 519 diikut. (3) Memang berkemungkinan bahawa KC Ooi tidak mengatakan yang beliau adalah arkitek tersebut. Tetapi KC Ooi telah dengan jelas bertindak sebagai arkitek. Sijil pembayaran tersebut telah mungkin digunakan dengan tujuan mendapatkan pinjaman bank. Tetapi hanya arkitek sahaja yang boleh mengeluarkan sijil pembayaran tersebut dan KC Ooi tidak akan mengeluarkan sijil tersebut jika beliau tidak menerima perlantikan sebagai arkitek. Dan dengan mengeluarkan sijil pembayaran tersebut, yang mana adalah satu perbuatan yang sengaja, KC Ooi telah bertindak sebagai arkitek, yang mana beliau dibenarkan untuk mengeluarkan sijil tersebut (lihat ms 126G-I).] NOTES: Notes For cases on damages awarded in building contracts, see 3 Mallal's Digest (4th Ed, 2000 Reissue) paras 2141-2143. Cases referred to Aik Ming (M) Sdn Bhd & Ors v Chang Ching Chuen & Ors and another appeal [1995] 2 MLJ 770 Anderson v Benson Court of Appeal (Civil Division) 11 July 1991 Boyo v Lambeth London Borough Council [1994] ICR 727 [*119] British Westinghouse Electric and Manufacturing Company v Underground Electric Railways Company of London Ltd [1912] AC 673 Chik binti Abdullah v Itam binti Saad [1974] 1 MLJ 221 Goldburg v Shell Oil Co of Australia Ltd 95 ALR 711 Geest v Lansiquot [2002] 1 WLR 3111 Hadley v Baxendale (1854) 9 Exch 341 Hopkins v Norcross plc [1993] 1 All ER 565 Khushvinder Singh Chopra v Mookka Pillai Rajagopal & Ors [1999] 1 SLR 589 Kleinwort Benson Ltd v Birmingham City Council [1996] 4 All ER 733 Maredelanto Compania Naviera SA v Bergbau-Handel GmbH; 'The Mihalis Angelos' [1970] 3 WLR 601 Penang Port Commission v Kanawagi s/o Seperumaniam [1996] 3 MLJ 427 Reliance Shipping & Travel Agencies v Low Ban Siong [1996] 2 MLJ 543 Selva Kumar a/l Murugiah v Thiagarajah a/l Retnasamy [1995] 1 MLJ 817 T & S Contractors Ltd v Architectural Design Associated QBD (Official Referee's Business) 16 October 1992 Techno Land Improvement Ltd v British Leyland (UK) Ltd [1979] EGD 519 Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 West v Versil Ltd & Ors Court of Appeal (Civil Division), The Times, 31 August 1996 Westwood v Secretary of State for Employment [1985] AC 20 Yew Wan Leong v Lai Kok Chye [1990] 2 MLJ 152 Legislation referred to Contracts Act 1950 s 75 Supreme Court Rules [Eng] O 18 rr 12(1)(c), 13(4) Civil Suit No 52(62)-63 of 1998 (Sessions Court, Batu Pahat) KS Dass ( K Sila Dass & Partners) for the appellant. CC Aiyathurai ( CC Aiyathurai & Co) for the respondent. 117 APPFROM: Civil Suit No 52(62)-63 of 1998 (Sessions Court, Batu Pahat) LAWYERS: KS Dass ( K Sila Dass & Partners) for the appellant. CC Aiyathurai ( CC Aiyathurai & Co) for the respondent. JUDGMENTBY: JEFFREY TAN J : This is an appeal by the appellant/plaintiff against the decision of the Batu Pahat Sessions Court, dismissing with costs the appellant's claim for RM31,700, it being allegedly the balance sum due and payable by the respondent to the appellant in respect of building works executed and materials supplied by the appellant towards the erection of a single storey bungalow for the respondent, and allowing with costs the respondent's counterclaim for RM63,000, it being allegedly the respondent's costs of remedial works, and the respondent's counterclaim for RM300 per month from 15 August 1985 to 22 October 1998, it being [*120] allegedly the respondent's loss of rental income for the period 15 August 1985 to 22 October 1998 allegedly occasioned by the appellant's failure to complete the said single storey bungalow within the contractual period, together with interests at the rate of 8% per annum from 15 August 1985. According to Mr KS Das for the appellant, the trial court held that the appellant must prove that one KC Ooi was the architect of the proposed bungalow, and that the trial court was entirely wrong to have taken that issue to determine the claim, as whether KC Ooi was the architect was not a pleaded issue. Mr CC Aiyathurai for the respondent did not respond to that contention but suggested instead that the appeal on the claim be determined by a finding by this court, based on the appeal record, as to whether KC Ooi was the architect for the proposed bungalow. Mr Aiyathurai said, 'If the finding, based on the appeal record, is that KC Ooi was the architect and entitled to issue the certificate [of payment -- P8), then ... the claim should be allowed. On the other hand, if the finding is otherwise, the appeal on the claim should be dismissed'. And in a snap, that suggestion was accepted by Mr Das. Hence with regard to the appeal on the claim, it was agreed that the outcome would be determined by a single finding by this court, based on the appeal record, as to whether KC Ooi was or was not the architect for the proposed bungalow. But with regard to the appeal on the counterclaim, both learned counsel said that both parties would be free to advance all argument to attack or defend the trial court's judgment. Nonetheless, there was consensus in this court, that there were indeed works executed not according to approved plan (D4(A-D) and D5(A-D)). As a matter of fact, SP3, a consulting engineer, testified in the court below that he inspected the work and found that the level of the master bedroom was 30 inches lower than the level in the approved plan, that the levels of the ground beam and dining hall were lower than the levels in the approved plan, and that the level of the rooms was six inches off the level in the approved plan (see pp 52, 53 and 58 of the appeal record ('the AR')). Not surprising therefore, it was readily conceded by Mr Das that 'there were works executed not in accordance with the plans'. But Mr Das contended that the floor levels and size of the beams were varied at the specific request of the respondent. Indeed, it was the testimony of SP3 in the court below, that the respondent had confirmed to him that he (respondent) had authorized those variations to the approved plan (see pp 53 and 55 of the AR), and it was the testimony of the appellant in the court below that 'Dr Jaswant asked for a variation not in the RC plan' (see p 34 of the AR) and that the respondent agreed to the level of the master bedroom being 'two feet above normal' (see p 40 of the AR). Anyway, it could be said straightaway, that it was not pleaded by the appellant that such works executed not in accordance with the approved plan were so executed at the request of and/or approved by the respondent. It was specifically pleaded by the respondent (see para 5 of his defence and counterclaim) that the 118 ground beams of the master bedroom were constructed at the wrong levels, and [*121] that the construction of the bungalow was 'carried out ... in complete disregard and at variance to the architectural, structural and engineering drawings'. The alleged 'defective works' were particularized in para 5 of the defence and counterclaim. But all that was pleaded by the appellant, in his short reply to the defence and counterclaim, was that 'he delivered a house according to the architectural and engineering drawings and duly certified by the architect'. The appellant refuted the alleged defective works and required the respondent to strictly prove the alleged defective works. But it was not pleaded by the appellant that such works executed not in accordance with the approved plan were so executed at the request and/or with the approval of the respondent, an omission in the pleading that did not escape Mr Aiyathurai who submitted that it was not pleaded that the respondent had varied the approved plans and that all evidence adduced in connection with that non-pleaded issue should not have been admitted. It is settled law, that parties are bound by their pleadings (see Yew Wan Leong v Lai Kok Chye [1990] 2 MLJ 152), and that non-pleaded issues should not be heard (see Aik Ming (M) Sdn Bhd & Ors v Chang Ching Chuen & Ors and another appeal [1995] 2 MLJ 770 at p 794). There lies the importance of pleadings. A case in point is Chik binti Abdullah v Itam binti Saad [1974] 1 MLJ 221, where the Federal Court held that since it was not pleaded it was too late to raise the argument that the agreement had been entered into by the defendant in her personal capacity. There are countless other authorities on the function of pleadings, but an authoritative commentary of what is the law can be found in Halsbury's Laws of Malaysia Vol 1 para 10.3.129, which reads as follows: The function of pleadings is to give fair notice of the case which has to be met and to define the issues on which the court will have to adjudicate in order to determine the matters in dispute between the parties. Thus, a party is bound by his pleadings and his case is confined to the issues raised in the pleadings unless and until they are amended. A plaintiff who at the trial radically departs from his case as pleaded, however, is likely to fail. It follows that the pleadings enable the parties to decide in advance of the trial which evidence will be needed. From the pleadings, the appropriate method of trial can be determined. They also form a record which will be available if the issues are sought to be litigated again. The matters in issue are determined by the state of pleadings at their close. No issue was raised in the pleadings in the instant case that such works so executed not in accordance with the approved plan were so executed at the request and/or with the approval of the respondent. No notice was given in the pleadings, that the appellant would raise that issue. And since it was not pleaded, it could not be argued, be it here or below, that such works so executed not in accordance with the approved plan were so executed at the request and/or with the approval of the respondent ( Chik binti Abdullah v Itam binti Saad followed). The only pleaded issue that concerned the counterclaim, was whether the work executed was in accordance with approved plans. And that issue could only have been settled by the trial court in favor of the respondent, for both engineering report ('P16') [*122] produced by the appellant and testimony of SP3 who pertinently was a witness for the appellant, affirmed that the levels of the floors and ground beams were not in accordance with the levels in the approved plans. Here it was admitted by Mr Das, that 'there were works executed not in accordance with the plans'. Then the appellant could not have 'delivered a house according to the architectural and engineering drawings and duly certified by the architect'. Hence, the trial court's finding that the respondent had proved that work was executed not in accordance with approved plans, supported by the evidence from both sides, could not be disturbed. Indeed, it was the only proper finding that could have been reached. According to the testimony in the court below of DW3, the professional engineer who prepared the report (D24 -- see pp 221-238 of the AR) on 'the civil/structural shortcomings, mistakes, inadequacies, and/or non compliance with the relevant architectural and civil/structural drawings, remedial works would cost RM63,000 (see pp 87 and 227 of 119 the AR). And that testimony and report of DW3 on the costs of remedial works were not challenged by the appellant who had not adduced any opposing evidence on the costs of remedial works, a point also conceded by Mr Das. Hence, the trial court had only one set of evidence on the costs of remedial works to formulate its award. Then the trial court who had only one set of evidence to formulate its award, and unchallenged evidence at that, was only right to award RM63,000 towards remedial works, as the trial court without any opposing evidence had no evidential support to award anything less than RM63,000 towards remedial works, a fact that was appreciated by the trial court who decried that SP3's report had 'failed to quantify the remedial works or in any way to refute the observation in D24' (see p 162 of the AR). Hence, given the body of evidence, the award of RM63,000 towards remedial works was the only award that could have been made in the circumstances. But it is rather difficult to endorse the trial court's award of RM300 per month for the period 15 August 1985 (the due date of completion) to 22 October 1998. First, the trial court had not given a single reason to justify the compensation of RM300 per month and for that lengthy period. Secondly, the trial court had not considered s 75 of the Contracts Act 1950. When a contract has been broken, and if a sum is named in the contract as the amount to be paid in case of such breach, s 75 of the Contracts Act 1950 states: When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for. The effect of s 75 was clearly enunciated in Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 per Abdul Aziz J at p 155 of the holdings, as follows: [*123] whether the clause in the agreement was a penalty clause or not was irrelevant in view of s 75 of the Contracts (Malay States) Ordinance 1950 which provides that in every case the court must determine what is the reasonable compensation. The effect of the section is that the plaintiff is disentitled from recovering simpliciter the sum fixed in the contract whether as penalty or liquidated damages and must prove the damages suffered by him unless the sum named is a genuine pre-estimate. The effect of s 75 was further enunciated in Selva Kumar a/l Murugiah v Thiagarajah a/l Retnasamy [1995] 1 MLJ 817, where it was held by the then Federal Court per Peh Swee Chin FCJ that in every case the court must determine what is the reasonable compensation, that despite the words 'whether or not actual damage or loss is proved to have been caused thereby' a plaintiff who is claiming for actual damages in an action for breach of contract must still prove the actual damages or the reasonable compensation in accordance with the principle in Hadley v Baxendale (1854) 9 Exch 341 and that failure to prove such damages will result in the refusal of the court to award such damages, that the words 'whether or not actual damage or loss is proved to have been caused thereby' shall only apply where the court finds it difficult to assess damages for the actual damages, and that where the words 'whether or not actual damage or loss is proved to have been caused thereby' apply, the damages shall not in any event exceed the sum so named in the contractual provision, and also in Reliance Shipping & Travel Agencies v Low Ban Siong [1996] 2 MLJ 543, where it was held by the Court of Appeal that the words 'whether or not actual damage or loss is proved to have been caused thereby' are limited to those cases where the court would find it difficult to assess damages for the actual damages or loss, that a clause in an agreement falling within s 75 of the Contracts Act 1950 must be subject to the court's determination that such agreed damages is reasonable compensation for the injured party, that damages allegedly suffered must be proved, and that the measure of damages stated in an agreement is enforceable 120 provided that there is proof of the loss or damages limited to the extent of the quantum of the agreed compensation. The instant cl 22 of the agreement ('D18') providing that the sum of RM25 for each day's delay payable by the appellant as 'liquidated and ascertained damages' (see p 219 of the AR), was unquestionably a clause falling within s 75. But that was overlooked by the trial court. Alleged damages suffered must be proved by the respondent. That was not appreciated by the trial court, who adopted the quantum claimed, albeit with a deduction of RM60 per month that in the event was not explained by the trial court, as the true measure of damage without the respondent proving any loss. Yes, the respondent had not proved the loss of rental for the period between 15 August 1985 to 22 October 1998. The only 'evidence' on the loss of rental income was a solitary unavailing statement by the respondent that, 'I have counterclaimed RM360' (see p 100 of the AR), which was not any evidence tending towards any proof of any loss of rental income for the period 15 August 1985 to 22 October 1998. That failure to prove damage should have resulted in the refusal of the trial court [*124] to award compensation in the sum of RM300 per month for the period of 15 August 1985 to 22 October 1998. 'Damages are not awarded simply because the plaintiff has thrown them at the head of the court. The loss must be shown to have been actually occurred and also be recoverable in law before the award can be made' ( Penang Port Commission v Kanawagi s/o Seperumaniam [1996] 3 MLJ 427 at p 435 per Mahadev Shankar JCA). With respect, the trial court fell into error by not refusing the compensation as claimed. That is not however to say that the trial court should not award any compensation. There was undoubted delay and there should be compensation, even if nominal. The trial court should have determined the reasonable compensation. But what could have been the reasonable compensation in the instant case? There was evidential material for such an assessment before the trial court. To begin with, the contractual period for completion of all works was eight and a half months (see p 219 of the AR). If construction of the entire bungalow could be completed within eight and a half months, then remedial work or reconstruction should not reasonably take more than eight and a half months. The respondent would have to engage a new contractor who would have to mobilize workmen, equipment, and materials. There would be a passage of time before any actual remedial work could begin. A period of six months should be sufficient for the respondent to engage a new contractor and for the new contractor to mobilize workmen, equipment, and materials. The appellant discontinued all work in December 1985 (see p 241 of the AR) or in early 1986 (see p 245 of the AR). The respondent through another contractor could have resumed work in December 1985 or in early 1986. And if the respondent had resumed work in December 1985 or in early 1986, then the bungalow could have been completed within 14[half] months from December 1985 or early 1986, ie by April 1987, give or take a month or two. Given the evidential material before the trial court, the reasonable compensation could have been a sum approximating RM360 x 20 months (delay from 15 August 1985 to April 1987). But the alleged loss of rental income for the period from May 1987 to 22 October 1998 was not proved by the respondent, and it was not right to award any compensation for that period. It was also not right to award compensation for the period after May 1987 for a further reason. Damages are assessed on the basis that an aggrieved party has a duty to mitigate his damages ( West v Versil Ltd & Ors Court of Appeal (Civil Division), The Times, 31 August 1996; Kleinwort Benson Ltd v Birmingham City Council [1996] 4 All ER 733). A claim for damages is subject to a duty to mitigate the loss ( Westwood v Secretary of State for Employment [1985] AC 20; Maredelanto Compania Naviera SA v BergbauHandel GmbH; 'The Mihalis Angelos' [1970] 3 WLR 601; Boyo v Lambeth London Borough Council [1994] ICR 727; Hopkins v Norcross plc [1993] 1 All ER 565), and the right to damages is qualified by a duty to mitigate ( T & S Contractors Ltd v Architectural Design Associated QBD (Official Referee's Business) 16 October 1992). A victim of a breach of contract cannot cut short his duty to mitigate his loss by the mere [*125] commencement of an action for damages (see Techno Land Improvements Ltd v British Leyland (UK) Ltd [1979] EGD 519). Commercial good sense pointed not towards the 121 deferment of remedial or reconstruction works but to the resumption of work upon cessation of work by the appellant (see Khushvinder Singh Chopra v Mookka Pillai Rajagopal & Ors [1999] 1 SLR 589 at p 598). Early completion of remedial or reconstruction work would have brought the alleged loss of rental income to an end (see British Westinghouse Electric and Manufacturing Company v Underground Electric Railways Company of London Ltd [1912] AC 673). But the respondent had not shown that he had taken any steps to mitigate his damage. Suffice to say that the conduct of the respondent by not bringing the alleged loss of rental income to an end, in relation to his duty to mitigate was not reasonable. And 'it is well settled that innocent party can recover no greater damages for breach of contract than the loss he would have sustained had he acted reasonably to avoid or reduce loss' ( Techno Land Improvement Ltd v British Leyland (UK) Ltd [1979] EGD 519 per Goulding J). Mr Aiyathurai submitted that the issue of mitigation of damages 'should be pleaded' (counsel tendered the case of Goldburg v Shell Oil Co of Australia Ltd 95 ALR 711 as authority for his proposition) but was not pleaded by the appellant, and that the appellant had not adduced any evidence to show how damages could have been mitigated. With respect, Goldberg v Shell was just an action where mitigation of damages was pleaded but is not any authority that the issue of mitigation of damages should be pleaded by the appellant. Under O 18 r 12(1)(c) to be read together with r 13(4) of the former English Supreme Court Rules, it was 'incumbent upon the defendant, in order to be more informative about his defence to state the grounds on which he intends to contest the amount of damages by giving particulars of all the facts on which he relies to support any such ground as, for example, in mitigation of or otherwise in relation to, the amount of damages. The burden is cast upon the defendant to plead and prove the facts he relies on to support any positive case to contest the amount of damages claimed. In accordance with its policy of openness in pleading, the rule is expressed in general terms, so that the rule will apply to a plea in mitigation, not only in defamation actions but to all classes of actions, whether in contract or tort; and the rule will also apply to any ground on which it is open to the defendant to contest the amount of damages' (English Supreme Court Practice 1997 para 18/12/6). Perhaps it is a duty in England to plead the failure to mitigate damages (see Geest v Lansiquot [2002] 1 WLR 3111; Anderson v Benson Court of Appeal (Civil Division) 11 July 1991). But in Malaysia, there is no such O 18 r 12(1)(c) or corresponding rule in the Rules of the High Court 1980, and there is no legal authority which states that the failure to mitigate damages must be pleaded. As far as is known, there is no such rule that the failure to mitigate damages must be pleaded. As for the finding -- 'whether KC Ooi was the architect and entitled to issue the certificate of payment' -- specifically requested by both parties, the Appeal Record discloses the following: [*126] (1) The preamble to the agreement between the appellant and respondent stated that KC Ooi Associates was the architect (see p 200 of the AR) and clause 30 of the agreement provided that 'at the period of interim certificate ... the architect [meaning KC Ooi Associates] shall issue a certificate stating the amount due to the contractor from the employer' (see p 215 of the AR); (2) SP3 testified that KC Ooi 'came into the picture sometime in late Oct 1985. The original architect and engineer had been terminated' (see p 53 of the AR), that the respondent had asked him to get a new architect ... and he asked KC Ooi to assist' (see p 53 of the AR), that the appointment of KC Ooi was done verbally (see p 55 of the AR), that the respondent's letter dated 5 November 1985 was the letter appointing KC Ooi Associates (see p 60 of the AR) ; (3) KC Ooi testified that he was asked 'to come into the project to certify the construction value in order to secure the bank's release of payment' and that he entered the project in good faith (see p 43 of the AR), 122 that he had no appointment letter (see p 44 of the AR), that 'if I was retained I would have prepared the drawings for the remedial works' (see p 46 of the AR), and that he 'stepped in with the expectation of appointment' (see p 47 of the AR); (4) In his solicitors' letter dated 31 July 1986 to the Lembaga Arkitek Malaysia, KC Ooi stated that he had entered the project in utmost good faith and at the request of the respondent (see p 174 of the AR); (5) The respondent testified that he did not issue the letter appointing KC Ooi Associates 'as KC Ooi was already on record as the architect' (see p 100 of the AR), that he accepted KC Ooi as the architect (see p 94 of the AR); (6) In his letter dated 5 November 1985 to the Yang DiPertua Majlis Daerah Batu Pahat, the respondent informed the local authority that KC Ooi Associates was his architect (see p 171 of the AR); (7) In his letter dated 13 May 1986 to KC Ooi Associates, the respondent stated that KC Ooi was the architect and held himself as a client of KC Ooi Associates (see p 178 of the AR); Mr Aiyathurai conceded that the respondent had 'accepted Ooi as the architect', but contended that in actual fact there was no architect as 'KC Ooi did not say that he was the architect'. It might be so that KC Ooi had not expressly stated that he was the architect. But KC Ooi had clearly conducted himself as the architect. The certificate of payment might have had been for a collateral purpose to obtain a bank loan. But it remains that only the architect could have issued the certificate of payment, and KC Ooi would not have issued the certificate if he had not accepted the appointment. And by issuing the certificate of payment, which was a deliberate act, KC Ooi had conducted himself as the architect, who was entitled to issue the certificate. The issue could only be answered in favor of the appellant. [*127] For the reasons above, this appeal is allowed, but subject to the following orders; (i) the respondent is to pay to the appellant the sum of RM31,700 together with interest at the rate of 8% per annum from 1 November 1985 to date of satisfaction; (ii) the appellant is to pay to the respondent the sum of RM63,000 towards the costs of remedial works, and the sum of RM7,200 towards loss of rental income from 15 August 1985 to April 1987, both awards carrying interest at the rate of 8% per annum, the rate ordered by the trial court; (iii) costs below to be apportioned; (iv) all orders by the trial court, unless affirmed, are hereby set aside; and (v) no orders as to costs in this appeal. Appeal allowed. LOAD-DATE: September 22, 2003 APPENDIX H CASE 2: PAYZU LTD. V SAUNDERS [1919] 2 K.B. 581 123 APPENDIX H Case 2: Payzu, Ltd v Saunders COURT OF APPEAL [1918-1919] All ER Rep 219; [1918-19] All ER Rep 219 HEARING-DATES: 6, 7, 8 MAY 1919 27 JUNE 1919 CATCHWORDS: Damages - Mitigation - Duty to mitigate loss - What it is reasonable to do in mitigation a question of fact - No right to recover in respect of damage due to failure to mitigate. HEADNOTE: Where one party to a contract has broken the contract the other party must take all reasonable steps to mitigate the loss consequent on the breach, and, if he fails to do so, he is debarred from recovering in respect of any part of the damage which is due to his neglect to take such steps. What it is reasonable for a person to do in mitigation of his damage is a question of fact and not of law. Per SCRUTTON, LJ: In commercial contracts it is generally reasonable to accept an offer by the party in default. Appeal from an order of McCARDIE J. The following statement of facts is taken from His Lordship's judgment. The defendant was a dealer in silk, and on 9 November 1917, she agreed to sell to the plaintiffs a large quantity of silk - 200 pieces at the price of 4s 6d and 200 pieces at the price of 5s 11d, the total amount of the contract being about 3,500 pounds. Delivery was to be between January 1918, and September 1918; the payment was to be 2 1/2 per cent. discount one month. The meaning of those words in the trade is, that goods delivered up to the 20th of the month shall be paid for subject to the discount of this 2 1/2 per cent on or about the 20th of the next mouth. In the very first month of the contract, however, the defendant, at the express request of the plaintiffs, delivered certain goods prior to the date of the first contract obligation. Those goods amounted in value, less the 21 per cent discount, to 76 pounds 14s 2d. On 21 December 1917, the plaintiffs drew a cheque for that amount, noted the cheque on the counterfoil, and also noted it in the cash-book. At that time the plaintiffs' staff was greatly depleted by reason of the war; the managing director was seriously ill, and another director was also suffering from illness. The cheque so drawn was either not posted, or, if posted, failed to reach the defendant. The circumstances disclosed in the evidence are curious, but, after considering the facts, I am not satisfied that there was any dishonesty of conduct which could be charged against the plaintiffs. The cheque, if it had been received by the defendant and paid into the bank, would have at once been met by the plaintiffs' bankers in spite of the fact that a substantial overdraft already existed. At the beginning of January the defendant telephoned to the plaintiffs inquiring why the cheque had not been received. The plaintiffs answered that the cheque had in fact been sent on December 21, and the defendant then informed the plaintiffs that the cheque had not been received. Thereupon the plaintiffs stopped payment of the cheque of December 21 and they prepared another cheque of January 9. Owing to the difficulties of obtaining the signature of one of the directors, there was some little delay with regard to the matter; but on January 16 a second cheque for 76 pounds 14s 2d was sent to the defendant as for goods delivered in November less 2 1/2 per cent discount. The defendant did receive that cheque which the 124 plaintiffs had dispatched with a letter asking for further deliveries of goods. The defendant had formed a suspicious view with regard to this matter and hence she wrote the following letter: "Sir. - We are in receipt of your order by telephone; but before executing this order, we must insist on cash cover as we cannot do business on the terms you are taking. The account just paid was due net. You deduct 2 1/2 per cent which we will overlook this time. Then again the cheque was dated Jan 9." Further correspondence ensued between the parties, and on 4 February 1918, the plaintiffs, it is agreed, accepted the defendant's repudiation of the contract. At that time the market had risen further. The plaintiffs went to much trouble in trying to buy elsewhere, and undoubtedly incurred expense in doing so, but they were unable to purchase goods from any quarter. They claimed damages as from the middle of February 1918, and they based that claim upon the market price which prevailed at that date. McCARDIE, J, held that the delay in payment by the plaintiffs did not amount to a repudiation of the contract by them, and therefore, the defendant was liable in damages for breach of contract; that the plaintiffs, however, were under a duty to mitigate any loss they might suffer through the defendant's breach and should have accepted the defendant's offer to supply the goods for cash which offer was bona fide. By not accepting, the plaintiffs had sustained a greater loss than they might have, and therefore, the damages must be limited to the loss they would have suffered if they had accepted the defendant's offer. The plaintiffs appealed as regards the damages. NOTES: Notes Referred to: Banco de Portugal v Waterlow & Sons, Ltd (1931) 100 LJKB 465; on appeal, [1932] All ER Rep 181; Houndaditch Warehouse Co v Waltex, Ltd, [1944] 2 ER 518; Pilkington v Wood, [1953] 2 All ER 810. As to duty of plaintiff to mitigate damages, see 11 HALSBURY'S LAWS (3rd Edn) 289 et seq; and for cases see 17 DIGEST (Repl) 108-111. CASES-REF-TO: Cases referred to: (1) British Westinghouse Electric and Manufacturing Co, Ltd v Underground Electric Railways Co of London, Ltd, [1912] AC 673; 81 LJRB 1132; 107 LT 325; 56 Sol Jo 734, HL; 17 Digest (Repl) 108, 226. (2) Dunkirk Colliery Co v Lever (1878) 9 Ch D 20; 39 LT 239; 26 WR 841, CA; 17 Digest (Repl) 108, 225. COUNSEL: JB Matthews, KC, and HJ Turrell for the plaintiffs.; Compston, KC, and RJ Willis, for the defendant, were not called on to argue. Solicitors: WH Martin & Co; S Myers & Son. Reported by EDWARD JM CHAPLIN, ESQ, Barrister-at-Law. PANEL: BANKES AND SCRUTTON LJJ AND EVE J JUDGMENTBY-1: BANKES LJ: JUDGMENT-1: BANKES LJ: 125 At the trial of this action the defendant raised two points first, she contended that she had committed no breach of the contract of sale, and secondly that, assuming there was a breach, she had nevertheless offered and was always ready and willing to supply the pieces of silk, the subject of the contract, at the contract price for cash; that it was not reasonable on the part of the plaintiffs to refuse to accept that offer, and that therefore they cannot claim damages beyond what they would have lost by paying cash with each order instead of having a month's credit and a discount of 2 1/2 per cent. We must take it that this was the offer made by the defendant. The case was fought and McCARDIE, J, has given judgment upon that footing. It is true that the correspondence suggests that the defendant was at one time claiming an increased price. But in this court we must take it that the offer was to supply the goods at the contract price, with this difference only, that payment was to be made by cash instead of being on credit. In these circumstances the only question which arises is whether the plaintiffs can establish that as matter of law they were not bound to consider any offer made by the defendant because of the attitude she had taken up. Upon this point McCARDIE, J, referred to British Westinghouse Electric and Manufacturing Co v Underground Electric Railways Co of London, Ltd (1) ([1912] AC at p 689) where LORD HALDANE, LC, said: "The fundamental basis is thus compensation for pecuniary lose naturally flowing from the breach; but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps. In the words of JAMES, LJ, in Dunkirk Colliery Co v Lever (2) (9 Ch D at p 25): 'The person who has broken the contract is not to be exposed to additional cost by reason of the plaintiff's not doing what they ought to have done as reasonable men, and the plaintiffs not being under any obligation to do anything otherwise than in the ordinary course of business.'" It is plain that the question what is reasonable for a person to do in mitigation of his damages cannot be a question of law, but must be one of fact in the circumstances of each particular case. There may be cases where as matter of fact it would be unreasonable to expect a plaintiff in view of the treatment he has received from the defendant to consider an offer made. If he had been rendering personal services and had been dismissed after being accused in presence of others of being a thief, and if after that his employer had offered to take him back into his service, most persons would think he would be justified in refusing the offer, and that it would be unreasonable to ask him in this way to mitigate the damages in an action of wrongful dismissal. But that is not to state a principle of law, but a conclusion of fact to be arrived at on a consideration of all the circumstances of the case. Counsel for the plaintifs complained that the defendant had treated his clients so badly that it would be unreasonable to expect them to listen to any proposition that she might make. I do not agree. In my opinion each party to the contract was ready to accuse the other of conduct unworthy of a high commercial reputation, and there was nothing to justify the plaintiffs in refusing to consider the defendant's offer. I think the learned judge came to a right conclusion on the facts, and that the appeal must be dismissed. JUDGMENTBY-2: SCRUTTON LJ: JUDGMENT-2: SCRUTTON LJ: I am of the same opinion. Whether it be more correct to say that a plaintiff must minimise his damages, or to say that he can recover no more than he would have suffered if he had acted reasonably, because any further damages do not reasonably follow from the defendant's breach the result is the same. The plaintiff must take "all reasonable steps to mitigate the loss consequent on the breach" and this principle "debars him from claiming any part of the damage which is due to his neglect to take such steps": British 126 Westinghouse Electric and Manufacturing Co v Underground Electric Railways Co of London, Ltd (1) per LORD HALDANE, LC. Counsel for the plaintiffs has contended that in considering what steps should be taken to mitigate the damage all contractual relations with the party in default must be excluded. That is contrary to my experience. In certain cases of personal service it may be unreasonable to expect a plaintiff to consider an offer from the other party who has grossly injured him; but in commercial contracts it is generally reasonable to accept an offer from the party in default. However, it is always a question of fact. About the law there is no difficulty. JUDGMENTBY-3: EVE J: JUDGMENT-3: EVE J: I agree. But for the difficulty introduced by the defendant's demand for a higher price than that named in the contract, I think this is a plain case. That difficulty is more apparent than real. It was not raised is the court below, and there is not enough evidence to enable us to give effect to it, assuming it to be a matter of substance. DISPOSITION: Appeal dismissed. APPENDIX I CASE 3: SELVA KUMAR A/L MURUGIAH V THIARAGAJAH A/L RETNASAMY [1955] 1 MLJ 817 127 APPENDIX I Case 3: SELVA KUMAR A/L MURUGIAH V THIAGARAJAH A/L RETNASAMY [1995] 1 MLJ 817 APPEAL NO 02-289-93 FEDERAL COURT (KUALA LUMPUR) DECIDED-DATE-1: 7 APRIL 1995 MOHAMED AZMI, PEH SWEE CHIN AND WAN ADNAN FCJJ CATCHWORDS: Contract - Damages - Liquidated damages - Failure to pay instalments due after several payments made - Clause in contract provided that aggrieved party entitled to forfeit all money paid to date of breach - Sum paid included deposit paid upon signing of agreement - Whether aggrieved party could forfeit money - Whether penalty - Whether proof of actual damage required - Contracts Act 1950 s 75 Contract - Deposit - Forfeiture - Breach of contract - Whether deposit forfeitable per se Whether court must determine if amount is reasonable - Contract Act 1950 s 75 HEADNOTES: Both the appellant and respondent in this case are medical practitioners.The appellant entered into an agreement in writing ('the agreement') with the respondent whereby the respondent sold his clinic to the appellant for a total purchase price of RM120,000. Pursuant to the agreement, the appellant paid to the respondent RM12,000 on signing the agreement, and thereafter paid a further sum of RM48,000. The balance of RM60,000 was to be paid by 15 monthly instalments of RM4,000 each. However, at the stage when the appellant had paid up to a total sum of RM96,000 towards the total purchase price, he refused to go on paying the remaining six monthly instalments. The respondent sought to forfeit the RM96,000 by relying on a clause in the agreement which in effect, provided that if the appellant defaulted, all moneys paid to date of such breach would be forfeited absolutely to the respondent as agreed liquidated damages, and the agreement would be terminated. The respondent successfully obtained a declaration from the High Court that the clause was valid and enforceable. The appellant appealed. Held, allowing the appeal in part by ordering the respondent to refund the sum of RM84,000 to the appellant: (1) In Malaysia, there is no distinction between liquidated damages and penalties as understood under English law, in view of s 75 of the Contracts Act 1950 which provides that in every case the court must determine what is the reasonable compensation, 'whether or not actual damage or loss is proved to have been caused thereby' ('the words in question'). (2) However, the words in question must be given a restricted construction. Hence, despite the words in question, a plaintiff who is claiming for actual damages in an action for breach of contract must still prove the actual damages or the reasonable compensation in accordance with the settled principles in Hadley v Baxendale(1854) 9 Exch 341; [1843-60] All ER Rep 461. Any failure to prove such damages will result in the refusal of the court to award such damages. 128 [*818] (3) However, for cases where the court finds it difficult to assess damages for the actual damage as there is no known measure of damages employable, and yet the evidence clearly shows some real loss inherently which is not too remote, the words in question will apply. The court ought to award substantial damages as opposed to nominal damages which are reasonable and fair according to the court's good sense and fair play. In any event, the damages awarded must not exceed the sum so named in the contractual provision. (4) The instant case falls into the category of cases where damages could be proved by settled rules. The respondent could have proved the actual loss of, for example, use of the medical equipment in the clinic, but failed to do so. Therefore, the court could not quantify any award of damages to him. (5) In any event, apart from the real loss that had not been proved, the respondent was entitled to forfeit a reasonable amount of the deposit. The sum of RM12,000 was not too large to prevent it from being fully forfeitable. Accordingly, the respondent had to refund the sum of RM96,000 less the deposit to the appellant. Bahasa Malaysia summary Kedua-dua perayu dan responden dalam kes ini adalah pengamal perubatan. Perayu telah mengikat suatu perjanjian bertulis ('perjanjian tersebut') dengan responden di mana responden telah menjual kliniknya kepada perayu bagi jumlah harga belian sebanyak RM120,000. Mengikut perjanjian tersebut, perayu membayar kepada responden jumlah RM12,000 apabila menandatangani perjanjian tersebut, dan selepas itu membayar jumlah selanjutnya sebanyak RM48,000. Baki sejumlah RM60,000 perlu dibayar melalui 15 bayaran ansuran, setiapnya berjumlah RM4,000. Bagaimanapun, pada peringkat apabila perayu telah membayar RM96,000 terhadap jumlah harga belian, beliau enggan untuk meneruskan enam bayaran ansuran yang tertinggal. Responden cuba melucuthakkan RM96,000 tersebut berlandaskan suatu fasal di dalam perjanjian tersebut yang secara keseluruhannya, memperuntukkan bahawa jika perayu ingkar, kesemua wang yang telah dibayar sehingga tarikh kemungkiran perjanjian tersebut akan dilucuthakkan kepada penentang sebagai ganti rugi jumlah tertentu yang dipersetujui, dan perjanjian tersebut akan ditamatkan. Responden berjaya mendapatkan suatu deklarasi dari Mahkamah Tinggi bahawa fasal itu adalah sah dan boleh dikuatkuasakan. Perayu telah membuat rayuan. Diputuskan, membenarkan sebahagian rayuan tersebut dengan memerintahkan supaya responden mengembalikan wang berjumlah RM84,000 kepada perayu: (1) Di Malaysia, tidak terdapat perbezaan di antara ganti rugi jumlah tertentu dengan penalti, sepertimana yang terdapat di bawah undang-undang Inggeris, melihatkan s 75 Akta Kontrak 1950[*819] yang memperuntukkan bahawa dalam setiap kes, mahkamah mesti menentukan apa yang merupakan pampasan yang munasabah, 'sama ada kerosakan atau kerugian sebenar yang disebabkan olehnya telah dibuktikan atau tidak' ('perkataan yang berkenaan'). (2) Namun demikian, perkataan yang berkenaan mesti diberi pentafsiran yang terhad. Oleh itu, meskipun perkataan yang berkenaan, seorang plaintif yang menuntut ganti rugi sebenar di dalam suatu tindakan bagi kemungkiran kontrak masih perlu membuktikan kerosakan sebenar atau pampasan yang munasabah menurut rukun mantap di dalam Haxley v Baxendale(1854) 9 Exch 341; [1843-60] All ER Rep 461. Sebarang kegagalan untuk membuktikan kerosakan sedemikian akan mengakibatkan keengganan mahkamah untuk membuat award ganti rugi sedemikian. (3) Walau bagaimanapun, bagi kes di mana mahkamah mendapati susah untuk mentaksir ganti rugi untuk kerosakan sebenar oleh kerana tidak terdapat cara penyukatan 129 ganti rugi yang diketahui yang boleh digunakan, tetapi keterangan pula menunjukkan dengan jelasnya bahawa memang terdapat suatu kerugian sedia ada yang bukan di luar dugaan, perkataan yang berkenaan akan terpakai. Mahkamah patut mengawardkan ganti rugi yang substantial dan bukan nominal, yang munasabah dan adil mengikut akal budi mahkamah. (4) Kes ini jatuh ke dalam kategori kes di mana kerosakan boleh dibuktikan berdasarkan rukun-rukun yang mantap. Responden harus boleh membuktikan kerugian sebenar, misalnya, kegunaan alat-alat perubatan di dalam klinik, tetapi gagal berbuat demikian. Oleh itu, mahkamah tidak dapat menyatakan kuantiti untuk sebarang award ganti rugi kepadanya. (5) Walau bagaimanapun, selain daripada kerugian sebenar yang tidak dibuktikan, responden berhak untuk melucuthakkan sejumlah deposit yang munasabah. Deposit sebanyak RM12,000 itu tidak begitu besar jumlahnya untuk menghalangnya daripada dilucuthakkan dengan sepenuhnya. Dengan yang demikian, responden harus mengembalikan wang berjumlah RM96,000 tolak deposit tersebut kepada perayu.] NOTES: Notes For cases on liquidated damages, see 3 Mallal's Digest (4th Ed, 1994 Reissue) paras 1467-1472. For cases on forfeiture of deposit, see 3 Mallal's Digest (4th Ed, 1994 Reissue) paras 1497-1505. Bhai Panna Singh v Bhai Arjun Singh AIR [1929] PC 179 Chaplin v Hicks [1911] 2 KB 786, 1911-13 All ER Rep DEFAULT 224 (refd) [*820] Davies v Galmoye (1888) 39 Ch D 323 (refd) Fateh Chand v Balkishen Das [1964] 1 SCR 515, 1963 AIR SC 1405 (folld Hadley v Baxendale [1854] 9 Exch 341, [1843-60] All ER Rep 461 (refd) Linggi Plantations Ltd v Jagatheeson [1972] 1 MLJ 89 (folld) Maniam v The State of Perak [1957] MLJ 75 (folld) Maula Bux v Union of India [1970] 1 SCR 928 (folld) Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 (refd) Contracts Act 1950 s 75 Rules of the High Court 1980 O 28 Contract Act 1872 s 74 [Ind] Originating Summons No 34-340-91 (High Court, Shah Alam) RR Sethu (HS Dhillon with him) (HS Dhillon & Co) for the appellant. N Chandran (Sri Dev Nair with him) (Ram, Rais & Partners) for the respondent. JUDGMENTBY: PEH SWEE CHIN FCJ (DELIVERING THE JUDGMENT OF THE COURT) PEH SWEE CHIN FCJ (DELIVERING THE JUDGMENT OF THE COURT) This appeal raises a difficult but important question of interpretation of s 75 of the Contracts Act 1950, which is set out below for ease of reference (s 75 is hereafter 'the section in question'): When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for. 130 Both parties are medical practitioners. The respondent (hereafter 'the vendor'), sold his medical practice on certain terms and conditions under the name and style of 'Poliklinik dan Surgeri Thiager' to the appellant (hereafter 'the purchaser'), for a total price of RM120,000 and for this purpose they entered into an agreement in writing on 15 October 1988. The relevant parts of the agreement are set out below: The agreement made on this 15 October 1988 ... Whereas -Now this agreement witnesseth as follows: In consideration of the covenants, undertakings and payments set out hereinafter the parties mutually agree between themselves as follows: [*821] (1) (a) The vendor shall sell the said premises free of all encrumbrances to the purchaser for the total of RM120,000 the payment terms being as follows: (i) The purchaser shall pay to the vendor and hereby pays the vendor receipt of which the vendor hereby acknowledges by signing this agreement, the sum of RM12,000. (ii) The purchaser shall pay the vendor the sum of RM48,000 on or by 27 October 1988. (iii) The purchaser shall pay the vendor fifteen (15) equal monthly instalments of RM4,000 a month on or before the end of each month the first of which fifteen (15) payments is to commence on 30 November 1988. (2) (a) The vendor as tenant shall continue to hold the tenancy as trustee for and on behalf of the purchaser till the expiry date of 30 November 1989 and if requested by the purchaser shall in accordance with the tenancy agreement renew the said tenancy. On the expiry of the extended period if there shall not be any clause for further extension, the vendor's obligation in this clause shall cease and the purchaser will have full liberty to negotiate a new tenancy but so long as there shall be extensions to the current tenancy the vendor shall continue to hold the same for and to the benefit of the purchaser and to act on the purchaser's instructions. (b) Both parties represent to each other that they will not do anything to breach the terms of the tenancy and in the event of such breach occurring the party at fault shall and hereby ... fully indemnify the other party. ... (15)(a) In the event the vendor shall default in his obligations herein the purchaser shall be entitled to specific performance in which event all the costs incurred shall be to the vendor's account. (b) In the event the purchaser shall default in his obligations herein all moneys paid to date of such breach shall be forfeited absolutely to the vendor as agreed liquidated damages and thereupon this agreement shall be deemed null and void and the purchaser shall give up vacant possession of the said premises and shall give up the said practice to the vendor and shall have no further rights whatsoever. Signed by the abovenamed ) Dr Thiagarajah a/l Retnasamy ) --Sgd-the said vendor in the presence ) of: [*822] --Sgd-KB Thuraisingham 131 Advocate & Solicitor Kuala Lumpur Signed by the abovenamed ) Dr Selva Kumar a/l Murugiah ) --Sgd-the said purchaser in the presence ) of: --Sgd-KB Thuraisingham Advocate & Solicitor Kuala Lumpur The premises where the clinic is situated have, at all material times, belonged to a third party who had earlier granted a tenancy of the same to the vendor, who, after and under the agreement dated 15 October 1988, was 'to hold the tenancy as trustee for and on behalf of the purchaser ...', vide its cl 2 but the rent payable would be paid by the purchaser after the date of the said agreement to the vendor who would then in turn pay to the vendor's landlord. RM12,000 was paid on the signing of the agreement by the purchaser who was to pay a further sum thereafter in pursuance of the agreement leaving some balance to be paid by fifteen monthly instalments of RM4,000 each. Subsequently, to cut the story short, thus, sometime before 22 December 1989, the purchaser refused to go on paying the monthly instalments, leaving six instalments unpaid (RM24,000), and by then, a sum of RM96,000 had been paid by the purchaser to the vendor towards the aforesaid purchase price of the clinic. At that time, the purchaser had also failed to reimburse the vendor the rent payable to the extent of RM4,808. On 22 December 1989, the vendor wrote to the purchaser through his solicitors, terminating the said agreement, forfeiting the sum of RM96,000 and requiring the purchaser to hand over the medical equipment and vacant possession of the premises of the clinic. The originating summons herein was subsequently filed, claiming declarations that the said agreement was terminated, that the vendor was entitled to forfeit the sum of RM96,000, that in regard to the tenancy which the vendor held in trust for the purchaser, such trust be terminated and that the vendor be entitled to resume vacant possession of the clinic. Apart from the important interpretation of the section in question, there are several small points which may be very well briefly disposed of first. The first of such small points is to the effect that the purchaser was induced to enter into the said agreement by the misrepresentation from the vendor about the average monthly income of the clinic from the source of the 'contract patients' being at RM5,000, but the purchaser alleged that the actual income earned was half of that sum. This bare allegation was made by the purchaser apparently in order to explain the refusal or reluctance to go on paying the aforesaid monthly instalments. However, inter alia, no particulars at all were given in respect of such patients for the period from the date of the agreement in question. It was a mere allegation, equivocal, inconsistent, and insubstantial for reasons mentioned by the learned judge that compelled him to reject it. We are satisfied that the learned judge has not erred in doing so. We also reject such allegation. Yet another mundane point is to the effect that the learned judge has failed at the outset to make an order under O 28 of the Rules of the High [*823] Court 1980 to direct that the proceeding by the originating summons herein be continued as if it were begun by writ to determine the issue of misrepresentation. The purchaser at the hearing before the learned judge was represented by counsel. He never raised this procedural point at all. An appellant could be barred from raising an 132 objection to a point of procedure on appeal when such objection was not raised in the court below. Please see Davies v Galmoye (1888) 39 Ch D 323. By the same token, the purchaser as appellant, should be also barred from raising the procedural point in question, quite apart from the fact that this procedural point proved to be futile with hindsight. It is also desirable to mention two other matters, viz that the question of arrears of rent has not been submitted on by both parties before us, and the court is therefore prepared to treat this as being no longer an issue before us, and that it was common ground in the court below that the purchaser began to fail to pay those monthly instalments towards the purchase price as from July 1989. We now deal with the question of concern, ie the section in question; and the facts that call for its interpretation in this case are as follows. A total sum of RM96,000 was collected by the vendor from the purchaser to account of the total purchase price of the clinic, leaving a sum of RM24,000, the amount of six monthly instalments remaining unpaid. On 22 December 1989, the vendor wrote, inter alia, in effect, terminating the agreement, on the ground of failure to pay the balance of RM24,000, and stating that the said sum of RM96,000 had been forfeited absolutely as 'agreed damages'. This must have reference to cl 15 of the agreement as set out above. We have long known the object for which the section in question was enacted first in India and later here in our country. Thomson J (as he then was) in Maniam v The State of Perak [1957] MLJ 75 , commenting on arguments advanced before him as to whether a certain sum was to be regarded either as a penalty or as liquidated damages, said [at p 76]: In the first place, in this country there is no difference between penalty and liquidated damages. Section 75 of the Contract Ordinance which is the same as s 74 of the Indian Contract Act reads as follows: 'When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.' As is said in Pollock and Mulla on the Indian Contract Act(7th Ed) at p 410, 'This section boldly cuts the most troublesome knot in the common law doctrine of damages'. In brief, in our law in every case if a sum is named in a contract as the amount to be paid in case of breach it is to be treated as a penalty. See Bhai Panna Singh v Bhai Arjun Singh AIR 1929 PC 179. It is obvious that any submission as to whether a certain clause in a contract is a penalty or liquidated damages is an exercise in futility. [*824] Clause 15(b) of the agreement before us is therefore unenforceable and is to be regarded as a penalty, void in equity for being unconscionable. At common law, where there is no such section in question, the effect of a sum being found as a penalty, is therefore that the innocent party to a breach of contract is not left with no remedy, he can still recover damages or compensation which he has however to prove, and it is immaterial that such compensation if proved, exceeds or not, the stipulated penalty. However, the wording of the section in question seems to also differ from the common law on the aspect of proof of damages when a provision in a contract turns out to be a penalty. The relevant words in the section in question are: ... the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive 133 ... reasonable compensation not exceeding the amount so named or ... the penalty stipulated for. (The quoted words will be hereafter 'the expression in question'.) In particular, from the expression in question, the words, 'whether or not actual damage or loss is proved to have been caused thereby' (they are hereafter 'the words in question'), are unambiguous and plain, and by the primary rule of construction, ie literal construction of the same, they may seem to indicate clearly the dispensation of proof of actual damage or loss by an innocent party to a breach of contract, and this seems to be a departure from the common law brought deliberately about by the legislature. Let us examine the acceptability of this construction. It is useful to bear in mind that there is no such thing as a fixed hierarchy of application of rules of construction in which the primary rule of literal construction will be at the top of it. In the first place, such a literal construction would seem to be beyond the object of the section in question, viz the abolition of the distinction between a penalty and liquidated damages; secondly, it will produce a most unreasonable result in that it will change the existing law which is that if a plaintiff seeks to recover damages for the actual damage caused, he ought to prove them, unless he is content with the symbolic award, eg of nominal damages, for any infraction of his rights under a contract. This even seems to be a rule of some antiquity. We hold first, that the literal construction should not be strictly adhered to and the words in question should be given a restricted or limited construction though the language used in the words in question expresses really no circumscription of the area of operation. Having decided on a more limited construction of those words in question, we must now revert, at least briefly, to the more important and relevant cases in our own courts and the Privy Council, and the Indian Supreme Court to decide for ourselves how precisely the words in question should be construed. In Bhai Panna Singh v Bhai Arjun SinghAIR 1929 PC 179, an Indian appeal in the Privy Council in connection with a provision in a contract for [*825] the party in breach to pay Rs10,000, Lord Atkin said in connection with s 74 of the Indian Contract Act 1872 (corresponding to the section in question in our Act), held: The effect of s 74 of the Contract Act of 1872 is to disentitle the plaintiffs to recover simpliciter the sum of Rs10,000, whether the penalty or liquidated damages. The plaintiffs must prove the damages they have suffered. In that case, the plaintiffs managed to prove as their actual damage, the sum of Rs500 which they recovered. Lord Hailsham in Linggi Plantations Ltd v Jagatheeson [1972] 1 MLJ 89 observed at p 92 that the section 'was intended to cut through the rather technical rules of English law relating to liquidated damages and penalties ...'. In Maniam v State of Perak [1957] MLJ 75 , the object of the section in question suggested by Pollock and Mulla, the joint authors of the Indian Contract and Specific Relief Acts, was repeated by Thomson J (as he then was) with approval as set out above, but unfortunately the section in question was found by his Lordship to be irrelevant to the facts of that case, and consequently there was no expounding on the words in question. The view of Lord Atkin was adopted in our High Court case, viz Wearne Brothers (M) Ltd v Jackson [1966] 2 MLJ 155 , though the learned trial judge, while correctly holding that in a provision in a contract amenable to the section in question, the plaintiffs must prove damages they had suffered, erred in saying further [at p 156] that, 'unless the sum ... is a genuine pre-estimate'. It must be remembered that the expression 'liquidated damages' is the name for the contracting parties' supposedly genuine pre-estimate of 134 the loss to the innocent contracting party when the contract is broken by the other. Every such provision to which the section in question is applicable is to be regarded effectually as a penalty and is therefore void or unenforceable. The Indian Supreme Court in two leading cases adopted the view of Lord Atkin in Bhai Panna Singh v Bhai Arjun Singh that a plaintiff must prove the actual damage, ie he must prove the damages for the actual damage or loss, despite those words in question. The two Indian Supreme Court cases are cases in which the interpretation of this section in question was not a sideshow as in most of other cases mentioned, but was the main prominent issue discussed and dealt with. It will be necessary to set out the gist of them. The first of these two cases is Fateh Chand v Balkishen Das[1964] 1 SCR515; AIR 1963 SC 1405. This case concerns a sale of land for the price of Rs121,500. Rs1,000 was paid as earnest money. A part payment of Rs24,000 was further paid, whereupon the possession of the land was given by the vendor to the purchaser. The section in question was the issue before the court. The case was heard before a subordinate judge and on appeal against his decision to the High Court, the High Court allowed the appeal and held that the purchaser was in breach of contract for failing to pay the balance of the purchase price. There was a clause providing for forfeiture [*826] of all money paid for breach by the purchaser. The High Court however, ordered the purchaser to pay only a sum equivalent to 10% of the purchase price as reasonable compensation under the section in question in addition to and apart from the forfeiture of the sum of Rs1,000 being earnest money paid on signing the agreement. The High Court made also orders for payment of mesne profit for use of the land and for redelivery of premises of the land to the vendor. The Supreme Court of India held that reasonable compensation should be awarded 'to make good loss or damage which naturally arose in the usual course of things or which the parties knew when they made the contract, to be likely to result from the breach'. It cannot be lost on the mind of anybody that the Indian Supreme Court was reasserting the celebrated ratio in Hadley v Baxendale (1854) 9 Exch 341; [1843-60] All ER Rep 461. The Indian Supreme Court further found the award of the sum equivalent to 10% of the purchase price by the High Court as being an arbitrary assumption based on no principle they could find. The Supreme Court then went about their way to ascertain apparently, the reasonable compensation by looking at the evidence to find if there was any loss other than the loss suffered by being kept out of possession. The Supreme Court found no evidence of depreciation of the value of the land in question there. The Indian Supreme Court found that there was absence of proof of damage, but stated that the forfeiture of earnest money and the advantage of having the earlier use of Rs24,000 as being sufficient compensation. The Indian Supreme Court, therefore did not in effect and in reality award any distinctly and separately 'reasonable compensation' under the section in question, despite what might be regarded as a mere consolatory statement just mentioned, with the greatest respect. The ratio of the case seems to be that such 'reasonable compensation' must be proved according to the usual principles, and the court undertakes a consideration of the evidence adduced to see if there is any such proof or such evidence of such actual damage or loss. If there is no such evidence, there will be no award of such reasonable compensation. This ratio seems to be in accord with the view of Lord Atkin set out above. The second case is Maula Bux v Union of India [1970] 1 SCR 928. There, Bux agreed to supply certain foodstuffs to some military headquarters and deposited Rs18,500 with the Indian Government. The contract provided that for failure by Bux to perform it, the sum of Rs18,500 'would stand forfeited and be absolutely at the disposal of the Government without prejudice to any other remedy or action that the Government may have taken'. 135 Bux failed to perform the contract and the sum of Rs18,500 was forfeited. Bux sued for the return of the sum. The subordinate court ordered the return on the ground that the Government had not suffered any loss. The Government appealed to the High Court. The High Court allowed the appeal and allowed the Government to retain the sum on the ground that the sum might be regarded as earnest money. Bux appealed to the Supreme Court. The Supreme Court disagreed that the sum was earnest money and held to the effect that the sum was not a reasonable [*827] amount as earnest money, so that the sum would fall within the section in question. The Supreme Court ordered the refund to Bux of the sum with the interest at the rate of 3% from the date of action to the date of satisfaction. Fateh Chand v Balkishen Das[1964] 1 SCR 515; AIR 1963 SC 1405was clearly affirmed. With regard to the words in question, the Supreme Court held that the Government must prove the loss and thus could have produced but failed to produce evidence to prove the prices of the said foodstuffs in question when Bux failed to deliver them. But what is far more interesting in that case is that the Indian Supreme Court, when referring to the words in question, ie 'whether or not actual loss or damage was proved to have been caused thereby' stated that the words in question were intended to cover two kinds of contracts. In the first kind, the court would find it very difficult to assess such reasonable compensation. In the second kind, the court could assess such reasonable compensation with settled rules. Such dichotomy of contracts by the Indian Supreme Court represents, in our view, a logical basis for the words in question, words added by the legislature to the section in question without seemingly any thoughtfulness about the desirability of some appropriate limitations thereto. We agree with the Indian Supreme Court's dichotomy of such contracts. Secondly, we therefore further hold that the words in question, viz 'whether or not actual damage was proved to have been caused thereby', are limited or restricted to those cases where the court would find it difficult to assess damages for the actual damage or loss, as distinct from or opposed to all other cases, when a plaintiff in each of them will have to prove the damages or the reasonable compensation for the actual damage or loss in the usual ways. However, there remains to be done further work, for their Lordships in the Indian Supreme Court did not further identify or elaborate the contracts of the kind for the breach of which the court finds it difficult to assess damages or 'the reasonable compensation' for actual loss or damage. The search will have to continue for the precise attributes of this kind of contract. Conceivably, the archetype of cases of the kind just mentioned, in our view, is undoubtedly the well-known case of Chaplin v Hicks [1911] 2 KB 786 ; [1911-13] All ER Rep 224. In that case, Ms Chaplin, an actress agreed with Hicks, a theatrical manager, for Ms Chaplin to be at a meeting for him to interview her and also 49 other actresses where he would select 12 out of such 50 actresses for giving remunerative employment to. He was in breach of contract for not giving Ms Chaplin a reasonable opportunity to attend the interview. It was also argued for him in the Court of Appeal that only nominal damages were payable, and the award for substantial damages by the High Court was wrong. The submission of nominal damages was to the effect that she would have had only a chance of one in four of being successful. The argument for nominal damages was rejected by the Court of Appeal and the High Court's award was upheld. [*828] Very clearly, Ms Chaplin failed to prove the damages for the actual damage, ie the amount for such damage or loss, and one may query as to why she should be given substantial damages and not merely nominal damages, as would have been seemingly and normally the case. We feel we ought to explain even further below. 136 A few words may first be necessary to explain the nature of nominal damages, which are damages of, say RM10 (traditionally of about 40 shillings in England), which could be awarded in each and every breach of contract, in the absence of actual loss or damage, inherently in such a case, or alternatively in the absence or failure of proof of such actual loss or damage. To revert to the poser above about Ms Chaplin, basically, the evidence in Ms Chaplin's case indubitably suggested a real loss, a loss that was not too remote, going by the rules in Hadley v Baxendale(1854) 9 Exch 341;[1843-60] All ER Rep 461, but at the same time it was quite difficult to assess the damages or the amount of money that should be given to her for such loss of such opportunity to be selected. In a good number of cases, rules for quantifying amounts of money for damages have evolved in courts for some but not all types of cases, in other words, a measure of damages for some of these cases has been respectively established, eg the measure of damages in a sale of goods being the difference between market value and contract price, etc. However, a measure of damages, ie a settled rule for assessing damage, has not been developed for cases of the type of Ms Chaplin's, and such measure for her case has still not been established. It would still be left to the good sense and fair play of the court to fix a reasonable amount as compensation. Thus, it will mean that for lack of an established measure of damages in any particular case, that case will be one in which the court finds it difficult to ascertain the amount of actual loss or damage. The court will not shirk its duty, however, when such actual loss or damage is manifested from the evidence and it is not too remote, to find a reasonable sum for the plaintiff. It is significant to add that there are cases of contract in which the evidence therein shows there can be no real loss inherently, and in such event, nominal damages will be the only damages for a judgment obtained by a successful plaintiff either to use it 'as a peg to hang his costs on', or to establish a right or a declaration of right. It is not difficult to imagine such a case when the evidence shows clearly there can be no real loss. For an illustration of such a case clearly showing no real damage or loss where nominal damages would be the only remedy, let us say, eg that A, a doctor promises to examine the next day, B, a regular patient of his, who is very keen to have A examine him routinely on the following day, and A fails to do so the next day. Here A is in breach of contract; but the evidence here clearly shows no actual loss or damage. Whether in any particular case the evidence shows any real damage or not, appears to be largely a matter of common sense. Thirdly, therefore, we hold that the precise attributes of such contracts in which it is difficult for a court to assess damages for the actual damage or loss, are cases where there is no known measure of damages employable, [*829] and yet the evidence clearly shows some real loss inherently and such loss is not too remote; then the court ought to award, not nominal damages, but instead, substantial damages not exceeding the sum so named in the contractual provision, a sum which is reasonable and fair according to the court's good sense and fair play. Fourthly, we hold that in any case where there is inherently any actual loss or damage from the evidence or nature of the claim and damage for such actual loss is not too remote and could be assessed by settled rules, any failure to bring in further evidence or to prove damages for such actual loss or damage, will result in the refusal of the court to award such damages, despite the words in question. Having expressed our views above, we now deal with the facts in the instant case before us. The evidence shows clearly some actual loss, damages for which could be assessed by settled rules. The purchaser, eg was using the medical equipment. This is, therefore, a case where damages could be proved by settled rules. But the vendor has brought no evidence to prove damages for the actual loss as explained earlier, so that we could have awarded at least some damages as compensation for loss of use of the 137 medical equipment from some evidence of its rental value should it be rented out. Thus the real damage cannot be quantified. In other words, the damages have not been proved. The sum of RM96,000 paid towards the purchase price, less the sum comprised therein which was paid as earnest money, would have to be refunded to the purchaser by the vendor subject to what is to be further said below about the sum representing the earnest money or the deposit. Apart from the real loss (which has not been proved), the vendor ought to be entitled, in any event, to forfeit any reasonable amount of earnest money or deposit. We have in our case, the deposit or earnest money, ie the sum of RM12,000 which was paid on signing the agreement by the purchaser to the vendor, see cl 1(a)(i) of the agreement. The sum is equivalent to 10% of the purchase price and is part of the said sum of RM96,000 sought earlier to be forfeited by the vendor under cl 1(a)(i) of the agreement. The sum of RM12,000, in all the circumstances of this case, is not too large to prevent it from being fully forfeitable. We would not interfere with it, and would allow the vendor to forfeit it or keep it. We therefore allow the appeal in part by ordering the respondent to refund forthwith the sum of RM96,000 less the sum of RM12,000, ie to refund the sum of RM84,000 and to pay 8%pa as interest thereon from the date of judgment to the date of satisfaction. The order of the High Court below dated 8 November 1991 is to be varied accordingly, to take account of the said refund and interest thereon. The respondent is to pay the costs of appeal here but costs in the court below remain payable by the appellant. Order accordingly LOAD-DATE: March 14, 2005