ENERGY AND CO2 EMISSION EVALUATION OF CONCRETE WASTE POORIA RASHVAND This project report is submitted as a partial fulfillment Of the requirement for the award of the degree of Master of Science (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia NOVEMBER 2009 iii ACKNOWLEDGEMENT I would like to express my deep gratitude for the constant guidance and support from my supervisor, Dr Khairulzan Yahya, during the course of my graduate study. His insight, suggestions and criticism contributed in large measure to the success of this research. My thanks also goes to Mr Mukhtar Affandi abd ghani, project manager of one of construction sites under my investigation and also Faculty of Civil Engineering (FKA) for their support to conduct this work. Finally, my greatest thanks and appreciation go to my family. A thousand thanks to my parents. I thank my father for his unfailing wisdom and guidance, my mother for her caring and strength, my brother, Payam for his friendship. iv ABSTRACT A significant amount of solid wastes produced every year from construction and demolition activities, and had caused significant pollution to the environment and risen public concern. Therefore, the minimization of construction wastes has become a critical issue in construction industry Concrete is the most commonly used construction material in the world, and after water is the second most consumed product on the planet. The huge popularity of concrete also carries environmental costs, the most harmful of which is the high energy consumption and CO2 release during the production. This paper investigates the amount of energy used and CO2 emission generated during the production of concrete. Furthermore to estimate the total impact of both indicators based on concrete wasted generated on site. Data were obtained through questionnaire survey and interview within the building construction projects in U.T.M. These impact assessment were followed the life cycle assessment (LCA) methodology. The results show that the production of the raw material and the transports of the concrete are the main contributor to the total environmental load . The highest impact value was generated during the production of cement at upstream level .the amount of energy used and CO2 emission by cement production was about 70 percent of the total embodied energy and 95% of the carbon dioxide emissions of concrete production and Within the transportation operations, the transportation of concrete is the largest contributor equal to 25% to 28% the production of concrete and on the other hand 12% to 14% for CO2 emission. v ABSTRAK Jumlah sisa pepejal daripada kerja pembinaan bangunan menyebabkan pencemaran alam sekitar dan meningkatkan keprihatinan masyarakat awam akan perkara ini. Oleh yang demikian, pengurangan akan sisa tersebut menjadi isu yang kritikal dalam industri pembinaan. Konkrit merupakan bahan yang digunakan dalam kerja pembinaan. Penggunaannya yang berlebihan menyebabkan kesan kepada persekitaran iaitu pembebasan gas CO2 semasa proses penghasilannya. Kajian ini menyiasat tenaga yang digunakan dan pembebasan gas CO2 semasa menghasilkan konkrit. Kajian ini juga menganggar kesan bagi kedua-dua perkara tersebut. Data diperolehi dengan dapatan soal selidik dan temu bual yang dilakukan di sekitar projek pembinaan di UTM. Seterusnya penilaian kitar tenaga (LCA), di jalankan dan keputusan mendapati penghasilan bahan mentah dan pengangkutan konkrit merupakan penyumbang utama kepada beban persekitaran. Kesan tertinggi diperolehi semasa penghasilan simen pada peringkat akhir. Jumlah tenaga yang digunakan dan pembebasan gas CO2 oleh penghasilan simen ialah 70 peratus daripada jumlah sebenar tenaga yang digunakan dan 95 % pembebasan gas karbon dioksida. Dalam tempoh operasi penghantaran, iannya merupakan penyumbang terbesar iaitu 25% ke 28 % bagi penghasilan konkrit dan 12 % ke 14 % bagi pembebasan gas CO2. vi TABLE OF CONTENTS CHAPTER 1. 2. TITLE PAGE TITLE i DECLARATION ii ACKNOWLEDGMENT iii ABSTRACT iv ABSTRAK v TABLE OF CONTENTS vi LIST OF TABLES ix LIST OF FIGURES xii DIFINITIONS xiii INTRODUCTION 1.1 Introduction 1 1.2 Back ground of the study 2 1.3 3 Problem statement 1.4 Aim and Objectives of the study 4 1.5 Scope of the study 5 LITERATURE REVIEW 2.1 Construction and Demolition Waste 6 2.2 Environmental impact of concrete elements 8 2.2.1 Cement 12 2.2.1.1 Energy use in cement production 12 2.2.1.2 Air Emission from Cement production 13 vii 2.2.2 Aggregate 14 2.3 Concrete production 16 2.4 Environmental Impact of Transport Distance 17 2.5 Calculating the Concrete Waste 19 2.6 Recycling and land filling 19 2.7 Current Situation of Construction and Demolition Waste in Asia 2.8 Practice on C & D waste management in Malaysia 3. 26 2.8.1 Construction sector’s waste profile 26 2.8.2 Policies and laws 27 2.8.3 Practices 28 2.8.4 Waste Management Stakeholders 28 2.8.5 Waste Management Technologies 29 METHODOLOGY 3.1 Introduction 30 3.2 Inventory result 31 3.3 System boundary 33 3.4 Data Collection 34 3.4.1 4. 22 Questionnaire survey 34 3.4.1.1 Questionnaire structure 34 3.5 Data analysis 35 3.6 Stages of the study 35 ANALYSIS AND DISCUSSION 4.1 Concrete waste 4.1.1 Concrete Slabs, Walls, Beams, and Columns 39 40 4.2 Assumptions 43 4.3 Concrete production 43 4.4 Cement Energy Demand 44 4.5 Aggregate Energy Demand 45 4.6 Energy for Wasted Cement and Aggregate 46 4.7 CO2 Emission 47 4.8 Admixture 49 viii 5. 4.9 Transportation 51 4.10 Transportation concrete to the site from concrete plant 52 4.11 Disposal Options 62 4.11.1 Recycling 63 4.11.2 Land filling 78 CONCLUSION 5.1 Introduction 79 5.2 Conclusion 79 5.3 Recommendation for future research 80 5.3.1 Concrete reabsorbs CO2 80 REFRENCES 82 APPENDICES A-B 88 ix LIST OF TABLES TABLE NO. TITLE PAGE 2.1 Typical Constitutes of Concrete 9 2.2 Main ingredients for the production of 1 kg cement 11 2.3 Energy demand in production of 1 Kg cement 13 2.4 Emissions to air by cement production 14 2.5 Energy demand and emissions generated in the production 15 of 1 kg gravel 2.6 Energy demand and emissions to air for the production 17 of 1 m3 of concrete 2.7 Process energy emissions calculations for recycled aggregate 2.8 Transportation energy emissions calculations 21 for recycled aggregate 22 2.9 Aggregate Recycling Emission Factor (MTCE/TON) 22 2.10 Amount of reused and recycled construction waste materials on site 29 x 3.1 Vehicle Option 32 4.1 Cumulative quantity of ordering in construction no 1 (m3) 41 4.2 Different construction mixing design 44 4.3 Embodied Energy & CO2 Emission for One Cubic Meter of 56 Concrete Production(project 1) 4.4 Embodied Energy & CO2 Emission for Total Cubic Meter of 57 Concrete Production(project 1) 4.5 Embodied Energy & CO2 Emission for One Cubic Meter of 57 Concrete Production(project 2) 4.6 Embodied Energy & CO2 Emission for Total Cubic Meter of 58 Concrete Production (project 2) 4.7 Embodied Energy & CO2 Emission for One Cubic Meter of 58 Concrete Production (project 3) 4.8 Embodied Energy & CO2 Emission for Total Cubic Meter of 59 Concrete Production (project 3) 4.9 Embodied Energy & CO2 Emission for Total Cubic Meter of 61 Waste Concrete Production (project 1) 4.10 Embodied Energy & CO2 Emission for Total Cubic Meter of 61 Waste Concrete Production (project 2) 4.11 Embodied Energy & CO2 Emission for Total Cubic Meter of 62 Waste Concrete Production (project 3) xi 4.12 Process Energy Data for the Production of One Ton of Virgin Aggregate 4.13 Transportation Energy Consumption, million Btu/ton- 4.14 Process energy emission calculation for 64 mile Virgin aggregate (EIA, 2001) 4.15 4.17 67 Transportation Energy Emission Calculation for Virgin Aggregate 4.16 65 68 Process Energy Emissions Calculations for Recycled Aggregate (EIA2001) 71 Transportation Energy Emissions Calculations for Recycled 72 Aggregate (EIA2001) 4.18 Comparing recycling and virgin aggregate (84m3) 74 4.19 Comparing recycling and virgin aggregate (20m3) 75 4.20 Comparing recycling and virgin aggregate (20m3) 76 xii LIST OF FIGURES FIGURE NO. TITLE 2.1 Cement life cycle 2.2 Difference in environmental impact from cement PAGE 10 production between year 1995and 2005 12 2.3 Different distance in EP impact 18 2.4 C&D Waste Generation in Million Tons 23 2.5 Trend of National Account of Construction in Asia 24 2.6 Composition of total waste generation 27 3.1 General Flowchart for the concrete life cycle 33 4.1 Energy comparison between Virgin and Recycled Aggregate 77 4.2 CO2 emission between Virgin and Recycled aggregate 77 xiii DEFINITIONS Embodied energy: The sum of the energy used to manufacture a product from cradle up to the product is ready to be delivered from the producer and of its feedstock. Emission: Release or discharge of any substances, effluents or pollutants into the environment. Environmental impact: A change to the environment, whether adverse or beneficial, and the associated consequences for both humans and other ecosystem components caused directly by the activities of product or service development and production, wholly or partially resulting from an organization’s activities, products, or services, or from human activities in general Recycling: Recycling is used as a generic term for different forms of recycling. The here included forms are; reuse, material recycling and combustion with heat recovery. Reuse: The material is used for about the same purpose as initially. Reuse might imply upgrading or some renovation. Recycling Potential: The environmental impact from production of that material the recycled material will be a substitute for less the environmental impact from the recycling processes and connected transport. In this thesis the environmental impact is limited to embodied energy and use of resources. The recycling potential can therefore shortly be described as a way to express so much of the embodied energy and natural resources which, through recycling could be conserved. CHAPTER I INTRODUCTION 1.1 Introductions The construction industry plays a vital role in meeting the needs of its society and enhancing its quality of life. The industry remains as a major economic sector, thus the pollution generated from construction activities continuously presents a major challenge to implement environmental management in practice. The investigations demonstrated that construction business is a large contributor to waste generation. Environmental and human health impacts of materials are a hidden cost of our built environment. Impacts during manufacture, transport, installation, use, and disposal of construction materials can be significant, yet often invisible. A broad and complex web of environmental and human health impacts occurs for each of the materials and products used in any built landscape, a web that extends far beyond any project site. Construction materials and products can be manufactured hundreds, even thousands, of miles from a project site, affecting ecosystems at the extraction and manufacturing 2 locations, but unseen from the project location. Likewise, extraction of raw materials for these products can occur far from the point of manufacture, affecting that local environment. Transportation throughout all phases consumes fuel and contributes pollutants to the atmosphere. Disposal of manufacturing waste and used construction materials will affect still another environment. These impacts are “invisible” because they are likely remote from the site under construction and the designer’s locale. Parallel to rapid economic growth and urbanization in Asia, environmental impacts from construction and demolition (C&D) waste are increasingly becoming a major issue in urban waste management. C&D waste management in developing countries in the Asian region is relatively undeveloped and emerging. Environmental issues such as increase in volume and type of waste, resource depletion, shortage of landfill and illegal dumping, among others are evident in the region. Furthermore, the Asian countries have limited or no available data on C&D waste and the management aspects, particularly with regards to their C&D waste generation and composition; practices and policy, key actors and stakeholders’ participation. (Asian Institute of Technology,2008) 1.2 Background of the study Concrete is the most commonly used construction material in the world, and after water is the second most consumed product on the planet. Each year worldwide the concrete industry uses 1.6 billion tons of cement, 10 billion tons of rock and sand, and 1 billion tons of water. Every ton of cement produced requires 1.5 tons of limestone and fossil fuel energy inputs (Mehta 2002). The huge popularity of concrete also carries environmental costs, the most harmful of which is the high energy consumption and ` 3 CO2 release during the production of Portland cement. While the resources for aggregate and cement are considered abundant, they are limited in some areas, and more importantly, mining and extraction of the raw materials results in habitat destruction, and air and water pollution. (Mehta 1998). Several measures can be taken to minimize the environmental and human health impacts of concrete and some can result in improved performance and durability of the concrete as well. Perhaps the most important strategy is to minimize the use of Portland cement by substituting industrial by-products (e.g., fly ash, ground granulated blast furnace slag, or silica fume) or other cementitious materials for a portion of the mix. Recycled materials substituted for both coarse and fine natural aggregates will minimize use of nonrenewable materials and the environmental impacts of their excavation. (Mehta 2002) 1.3 Problem statement In Malaysia, the construction industry generates a lot of construction waste which cause significant impacts on the environment and increasing public concern(Begum et al., 2005). Thus, the minimization of construction waste has become a pressing issue. The source of construction waste at the project site includes materials such as soil and sand, brick and blocks, concrete and aggregate, wood, metal products, roofing materials, plastic materials and packaging of products. Concrete and aggregate is the largest component with 65.8% of total waste generation (Begum et al., 2005). CO2 production has been directly linked to climate change and global warming and governments have set specific targets to reduce national emissions. Production and demolition of concrete in sites are of direct importance both in terms of the contribution ` 4 to CO2 and energy. Environmental and human health impacts of materials are a hidden cost of our built environment. Impacts during manufacture, transport, installation, use, and disposal of construction materials can be significant, yet often invisible 1.4 Aim and Objectives The aim of this research is estimate the impact of concrete waste in construction sites in term of energy consumption and CO2 emission: i. To estimate the amount of energy used and CO2 emission for production of concrete in addition with transportation to the site. ii. To determine the amount of concrete waste in construction sites. iii. To estimate the total energy and CO2 emission based on the different weight of concrete waste on site. iv. ` To evaluate the disposal option of concrete waste. 5 1.5 Scope of the Study The scope of this study is as the following: i. Areas of study were within the building construction in U.T.M ii. The impact indicator used in the study were limited to the energy usage and CO2 emission only. The evaluation of total impact will be based on the percentage of concrete wastage on sites. ` 6 CHAPTER II LITERATURE REVIEW 2.1 Construction and Demolition Waste Environmental life-cycle assessment is a “cradle-to-grave,” systems approach for measuring environmental performance. The approach is based on the belief that all stages in the life of a product generate environmental impacts and must therefore be analyzed, including raw materials acquisition, product manufacture, transportation, installation, operation and maintenance, and ultimately recycling and waste management. (Mehta 2002). Graham2003 described that construction activity is one of the major contributors of CO2 emissions and other greenhouse gases to the atmosphere. Steel manufacture, for example, is estimated to cause emission of approximately two tons of CO2 for every one ton of steel produced, while cement manufacture causes approximately one ton of CO2 per ton of cement. Furthermore, four categories of environmental impact associated with ` 7 construction activities include resource depletion; physical disruption; pollution; and social and cultural effects (Graham, 2003). The construction industry is seen as one industry which has direct relation with development and where environmentally sound results should be achieved. It involves preventing waste and stimulating the reclamation of construction and demolition waste, which entail a reduction in the volume of waste produced during building activities, the separation of waste materials and reducing pollutive emission into the environment during production of building materials and the construction production process.( Franklin Associates 1998).According to him, C&D waste is waste material produced in the process of construction, renovation, or demolition of structures. These structures include buildings of all types in residential and nonresidential as well as roads and bridges. Components of C&D waste are typically concrete, asphalt, wood, metals, gypsum wallboard, and roofing. In addition, construction industry is one of the major contributors to the environmental impacts, which are typically classified as air pollution, waste pollution, noise pollution and water pollution. Open burning of C&D waste at construction sites is practiced in many rural areas as well as in many urban areas. The same issue can be observed perhaps in most countries in Asia where the practice of open burning is very evident. Moreover, aside from open burning, the most common management practice for C&D waste is land filling, where the waste is dumped in municipal solid waste (MSW) landfills, and on illegal dumping sites. Moavenzadeh as cited in Ofori (2000), noted that many government and organization has been accepted to consider environmental issues in the context of sustainable development. National and local governments and authorities in urban areas have attempted to meet the demand for housing and services through increased construction. However, lack of awareness of resource-efficient construction practices has resulted in excessive use of natural resources and generation of large amounts of construction waste that is rarely recycled. ` 8 C&D is an important resource which has the capability for recycling and reusing, so paying attention to this fact can be useful in order to reduce the waste which sent to landfill.landfilling is not the reasonable disposal option based on environmental issue such as increase in volume and type of waste, resource depletion, shortage of landfill and illegal dumping, among others are evident in countries. Environmental issues In Hong Kong SAR, Poon et al. (2004) reported that the waste generated by the building and demolition of construction projects assumes a large proportion of environmental waste. While in Malaysia, the construction industry generates a lot of construction waste which cause significant impacts on the environment and increasing public concern in the urban areas (Begum et al., 2006). Moreover, data is not readily available on the current structure of construction waste flows by the source of generation, type of waste, intermediate and final disposal and the amount of waste reduced at source, reused or recycled on-site or off-site. Moreover, potentially hazardous materials may be found in C&D waste, these include asbestos-based materials (e.g. asbestos-cement flat sheet, asbestos-cement corrugated sheets), lead-based materials (e.g. lead-based paint), materials used for construction such as damp-proofing chemicals, adhesives; mercurycontaining electrical equipments, toxic materials among others. 2.2 Environmental Impact of Concrete Elements Approximately 3.7 million tons of concrete were used in Sweden in buildings, roads and other constructions in 2004.1 This makes concrete one of the most common building materials on the market. The main ingredients in concrete are aggregate (7080 %), cement (10-20 %) and water (7-9 %), and to enhance specific characteristics, chemical admixtures (less than 1 %) are added. ` 9 Table2.1: Typical Constitutes of Concrete(Source: US.PCA,2006) Constituent Average Percentage Portland Cement 9.3 Fly ash 1.7 Coarse aggregate 41 Fine aggregate 26 Water 16 Air 6 2.2.1 Cement Cement is a hydraulic binder, which hardens when it is mixed with water. the main constituents of cement are limestone and clay. As shown in Fig 2.1 to produce cement, the limestone and clay are ground together. This raw material, called raw meal, is fed into a rotating kiln either wet or dry. Dry material is more often used since this is more energy efficient, as a wet kiln uses twice as much energy. The temperature in the kiln is approximately 1450 °C. (Burström, 2001) The calcinations process begins when the material passes from the kiln to the calcinatory. In this heating process CO2 is released from the limestone to produce cement clinker. The clinker consists of a mineral residue containing calcium oxide (CaO), alone or together with iron (Fe), aluminium (Al) or silicon (Si). The chemical process is: CaCO3 + heat > CaO + CO2. Most of the energy used in cement production is used in the calcinations process. The last step in cement production is the grinding together of the cement clinker and gypsum. Gypsum is added to prolong the binding of cement. Other material may be ` 10 added the cement, for example, bauxite or sand, to establish the required quality of the final product. After finishing and packaging, the cement is transported to cement depots. (Johansson, 1994) Mining Limestone Clay Grinding Depot Clinker Kiln & Calcinatory Transport Gypsum Grinding Cement Other Figure 2.1: Cement life cycle(U.S. Geological Survey 2007). Portland cement is the key ingredient in concrete, binding the aggregates together in a hard mass. However, it is also the ingredient in concrete that produces the greatest environmental burden. In 2006, more than 2 billion tons of Portland cement were consumed worldwide, with 131 million metric tons (MMT) consumed in the United States. This is a 16% increase over 2002. Ninety-nine MMT of cement were produced in the United States and 32 MMT were imported, primarily from Canada, Thailand, China, and Venezuela (U.S. Geological Survey 2007). Major raw materials for cement include limestone, cement rock/marl, shale, and clay. These materials contain calcium oxide, silicon dioxide, aluminum oxide, and iron oxide in varying contents. Because these contents vary, the mixture of raw materials differs among cement plants and locations. Typical proportions of raw materials for 1 kg of Portland cement are shown in the table 2.2 in the following page (Lippiatt 2000). ` 11 Table 2.2 Main ingredients for the production of 1 kg cement(lippiatt,2000) Ingredient Amount (kg) Limestone 1.4 Sand 70 Gypsum 30 Jeannette Sjunnesson in 2005, has studied about the cement production and he tried to compare cement production in 1995 by his finding in 2005,so that his finding is as following: The comparison clearly shows that the environmental load from cement production has decreased during the last ten years (Figure 2.2). The Global Warming Potential (GWP) has changed least, with a reduction of approximately 6 % and the POCP (Photochemical Oxidant Creation Potential is related to the potential for VOCs and oxides of nitrogen to generate photochemical or summer smog. It is usually expressed relative to the POCP classification factor for ethylene) has the highest reduction, approximately 80 %. The reduction in GWP is mainly because of the replacement of a part of the fossil fuels to alternative fuels. Much waste is used as fuels in cement production. The reason for the large reduction in (POCP) is probably that the incineration of fuel and the cleaning of emissions have improved over the ten-year period. Emissions of HC are 1 % of the emissions in 1995. The reason for the decrease in Acidification Potential (AP is a consequence of acids (and other compounds which can be transformed into acids) being emitted to the atmosphere and subsequently deposited in surface soils and water. Acidification Potential (AP) is based on the contributions of SO2, NOx, HCl, NH3 and HF to the potential acid deposition in the form of H+ (protons)). is a more effective sulphur removal in the production). There was five times as much Sulfur Oxides (SOx) emission from cement production in 1995 as in 2005. The reduction in Eutrophication Potential (EP is defined as the potential of ` 12 nutrients to cause over-fertilisation of water and soil which in turn can result in increased growth of biomass) is due to lower emissions of Nitrogen Oxides (NOx), of which today’s emission is only 1/3 of that in 1995. The comparison can be done since the system boundaries of the both studies are approximately similar. (Jeannette Sjunnesson LUNDS TEKNISKA HÖGSKOLA,2005) 120% 100% 80% 60% 1995 2005 40% 20% 0% EP Figure 2.2: AP POCP Difference in environmental impact from cement production between year 1995and 2005 (Vold & Rønning, 1995, Jeannette Sjunnesson,2005) 2.2.1.1 Energy Use in Cement Production Cement production is an energy-intensive process using primarily fossil fuel sources. Cement composes about 10% of a typical concrete mix but accounts for 92% of its energy demand. Cement production requires the preprocessing of large quantities of raw materials in large kilns at high and sustained temperatures to produce clinker. An average of almost 5 million Btus is used per ton of clinker. In 2004, the cement sector consumed 422 trillion Btus of energy, almost 2% of total energy consumption by U.S. manufacturing (US,PCA 2003). ` 13 Table below illustrates the average breakdown of fuel sources from four cement manufacturing processes. It also provides a weighted average with total energy of 4,798 kJ to produce one kilogram of cement (Medgar, Nisbet, and Van Geem 2007). Table 2.3: Energy demand in production of 1 Kg cement (Stripple, 2001,LCI Data). Energy Amount Coal 1.9 MJ Coke 0.51 MJ Diesel 0.03 MJ Car tires 0.42 MJ Bone meal 0.01 MJ Electricity 0.48 MJ TOTAL 3.35 MJ 2.2.1.2 Air Emissions from Cement Production Portland cement manufacturing include different emission such as carbon dioxide (CO2), particulate matter, carbon monoxide (CO), sulfur oxides (SOx), nitrogen oxides (NOx), total hydrocarbons, and hydrogen chloride (HCl). Emissions is different from type of cement, compressive strength, and blended constituents. CO2 emissions. Worldwide, the cement sector is responsible for about 5% of all man-made emissions of CO2, the primary greenhouse gas that drives global climate change (Humphreys and Mahasenan 2002). ` 14 Table 2.4: Emissions to air by cement production (Stripple, 2001,LCI Data). Emissions to air Amount CO2 0.71 kg CO 2.7 mg NOx 0.7g SOx 0.09g CH4 2.6g HC 1.3mg 2.2.2 Aggregate Aggregate is the highest ingredient in concrete by 60% and 75% of the volume. Aggregates can be mined or manufactured. Some are by-products of industrial processes or post-consumer waste products. Natural fine aggregates are usually quarried natural sand and coarse aggregates are either quarried or manufactured from crushed stone. Sand and gravel are typically dug or dredged from a pit, river, or lake bottom. They usually require minimal processing. Crushed rock, a manufactured aggregate, is produced by crushing and screening quarry rock or larger-size gravel (Lippiatt 2000). ` 15 Table 2.5: LCI Data for Energy demand and emissions generated in the production of 1 kg gravel (Stripple, 2001). Energy Amount Coal 9.6E-05 MJ Oil 1.0E-03 MJ Peat 1.1E-05 MJ Natural gas 2.2E-05 MJ Biomass fuel 1.1E-04 MJ Electricity 2.4E-03 MJ Emissions to air Amount Co2 0.07 g Co 0.07 mg Nox 0.6 mg Sox 0.05 mg Ch4 0.38 mg The impact of aggregate production in both terms of manufacturing and CO2 emission are not significant. The considerable impact by the aggregate production refers to dust in operations of mining and blasting, quarry roads, loading and unloading, crushing, screening, and storage piles. Primary impacts of crushed rock, aside from mining impacts, stem from fugitive dust released during crushing and screening operations. Processing of aggregates, particularly the commonly used silica sand, releases particulates into the air that can cause eye and respiratory tract irritations in humans. The operation of mining equipment consumes energy and releases emissions from internal combustion engines. Impacts from mining and quarrying aggregates are discussed in greater detail in the stone and aggregates chapter. Energy to produce coarse and fine aggregates from crushed rock is estimated by the PCA’s Life Cycle Inventory to be 35,440 kJ/metric ton. The energy to produce coarse and fine aggregate from uncrushed aggregate is 23,190 kJ/metric ton (Medgar, Nisbet, and Van Geem 2006). Energy sources are split evenly between diesel oil and electricity. Fuel consumption and ` 16 environmental impacts of fuel combustion for transportation of aggregates can be significant, as they are heavy and bulky materials. Using local or on-site materials for aggregate can minimize fuel use, resource consumption, and emissions. 2.3 Concrete Production Energy use and emissions of ready mix concrete vary widely by cement type and use of pozzolanic constituents such as fly ash, silica fume or slag. Mixes with lower cement content and higher percentages of other pozzolanic constituents have lower embodied energy and lower emissions. A Life-cycle Inventory by the Portland Cement Association of three different ready mixes supports this idea. One mix studied was a standard 28-day compressive strength, 3,000 psi ready mix with 100% Portland cement. The second mix replaced 25% of the cement with fly ash, and the third replaced 50% of the Portland cement with slag cement. Key findings are (Medgar et al. 2007) i. Embodied energy for the standard PCC mix is highest at 1.13 GJ/m3 of concrete and is lowest for the 50% slag cement mix at 0.73 GJ/m3. ii. CO2 emissions are highest for mix 1 at 211 kg/m3 and lowest for mix 3 at 112 kg/m3. CO2 reductions are even more substantial for mixes 2 and 3 because of the additional savings of CO2 release from calcination of limestone, which accounts for an average of 60% of CO2 emissions from the production of cement. iii. Particulate emissions from cement production account for 70% of the total and aggregate production for 30% of total particulate emissions for concrete. The use of fly ash and slag lowers total particulate emissions. ` 17 Table 2.6: Energy demand and emissions to air for the production of 1m3 of typical concrete (Rydh et al., 2002) 2.4 Energy Amount Oil 15 MJ Electricity 33 MJ Emissions to air Amount CO2 1.5 kg CO 0.86 g NOx 2.3 g SOx 3.3 g CH4 1.7 g HC 0.32 g Environmental Impact of Transport Distances Based on the investigation by Jeannette Sjunnesson,2005,he found that transport distances is one of the main contributors to the total environmental impact from concrete and in order to avoid this ,tried to show this important factor by evaluation the outcome changes when the transport distances vary. As shown in Figure 2.3 the transport operations stand for twice as much environmental impact as the raw material production. If the transport distances are reduced by 40 % the environmental impact between raw material production and transports becomes almost equal, only 10 % difference,. (Jeannette Sjunnesson LUNDS TEKNISKA HÖGSKOLA,2005) ` 18 EP (normal house building concrete 100% transport) 40 35 30 25 20 gPO4eqFU 15 10 5 0 Raw material Concrete Demolition Transports EP (normal house building concrete 60% transport) 40 35 30 25 20 15 gPO4eqFU 10 5 0 Raw material Concrete Demolition Transports Figures2.3 : Different distance in EP impact (Jeannette Sjunnesson, LUNDS TEKNISKA HÖGSKOLA,2005) ` 19 2.5 Calculating The Concrete Waste The amount of concrete waste, can be estimated if the material wastage level of concrete is known. Recent research indicated that the average wastage level is about 4%, which is considered the norm for the concreting trade. However, it could be reduced to 3% if careful material ordering and handling is applied. The amount of waste can be estimated according to: (Cheung, 1993) Concrete Waste = Quantity of Concrete Ordered - Quantity of Concrete Used 2.6 Recycling and land filling The impact of the construction and demolition works to the environment waste management for construction activities has been promoted (Shen et al., 2002). The construction industry plays a vital role in meeting the needs of society and enhancing the quality of life (Tse, 2001; Shen and Tam, 2002). However, the responsibility for ensuring the construction activities and products in consistent with environmental policies and needs to be defined and good environmental practices through reduction of wastes need to be improved (EPD, 2002). Normally, the best way to deal with material wastes is not to create it in the first place (Gavilan and Bernold, 1994). The environmental situation resulted from construction has become a pressing issue. According to the Environment Protection Department (EPD) (Chung, 2000), the construction industry generated about 32,710 tones of construction wastes per year in 1998, nearly 15% above the figure in 1997. To manage such a huge quantity of ` 20 construction wastes, must adopts a policy of disposing the waste to either land reclamation or landfills. For decades, landfill has provided a convenient and costeffective solution to the wasteful practices of the industry (Mills et al., 1999). According to Rogoff and Williams (1994), 29% of the solid-wastes in the USA are construction wastes. Wong and Tanner (1997) pointed out that the landfills, originally expected to last 40 to 50 years, would be filled up by 2010, even if there are adequate outlets for construction materials. All these investigations demonstrate that construction business is a large contributor to waste generation and that there is significant potential for protecting the environment through managing construction wastes properly. When structures are demolished, the waste concrete can be crushed and reused in place of virgin aggregate. Doing so reduces the GHG emissions associated with producing concrete using virgin aggregate material. Virgin aggregates, which include crushed stone, gravel, and sand, are used in a wide variety of construction applications, such as road base, fill, and as an ingredient in concrete and asphalt pavement. Over 2 billion tons of aggregates are consumed each year in the US, with an estimated 5 percent coming from recycled sources such as asphalt pavement and concrete. Unlike many of the other materials for which EPA has developed GHG emission factors (e.g., aluminum cans, glass bottles), concrete is assumed to be recycled in an “open loop” – i.e., concrete is recycled into a product other than itself, namely aggregate. Therefore, the GHG benefit of concrete recycling results from the avoided emissions associated with mining and processing aggregate that concrete is replacing. The GHG benefits of recycling are calculated by comparing the difference in emissions associated with producing and transporting a ton of virgin aggregate versus producing and transporting a comparable amount of recycled inputs (i.e., crushed ` 21 concrete). The GHG emissions associated with these steps result from the consumption of fossil fuels used in the production and transport of aggregate (combustion energy), as well as the upstream energy (pre-combustion energy) required to obtain these fuels. The calculation of avoided GHG emissions for concrete aggregate was broken up into two components: process energy and transportation energy emissions. Tables present these results, as well as the net GHG emission factor for recycling. The last part of this research conducted in the same way. Table 2.7: Process energy emissions calculations for recycled aggregate (U.S.EIA,2001) (a) Fuel Type Percent of Total Btu Diesel Fuel Total ` (b) Million Btu used for Aggregate Production (=0.0935 x a) (c) Fuelspecific Carbon Coefficient (MTCE/ Million Btu) (e) Process Energy CO2 Emissions (MTCE/Ton) (=b x c) (g) Total Transport Process Energy Emissions (MTCE/To n) 100% 0.0935 0.0199 0.0003 0.0019 100% 0.0935 n/a 0.0006 0.0019 22 Table 2.8: Transportation energy emissions calculations for recycled aggregate (a) Fuel Type Percent of Total a Btu (b) Million Btu used for Aggregate transport (=0.0352 x a) (c) Fuelspecific Carbon Coefficient (MTCE/ Million Btu) (e) Transport Energy CO2 Emissions (MTCE/Ton) (=b x c) (g) Total Transport Energy Emissions (MTCE/To n) Diesel Fuel 50% 0.0176 0.0199 0.0003 0.0004 National Average 50% 0.0176 0.0158 0.0003 0.0003 100% 0.0352 0.0357 0.0006 0.0007 Fuel Mix for Electricity Total Table2.9: Aggregate recycling emission factor (Wilburn and Goonan, 1998) (a) (b) (c) Process Transportation Total Energy Emission Energy Emission (a + b) Recycle Manufacture 0.0006 0.0019 0.0025 Virgin Manufacture 0.0009 0.0037 0.0047 Total(Recycled- virgin) -0.0003 -0.0019 -0.0021 2.7 Current Situation of Construction and Demolition Waste in Asia This section highlights the overview of current situation of construction and demolition waste in some selected Asian countries. As it shows by the following figures, figure 2.4 illustrates C&D waste generation in million metric tons in Asian countries. China has the highest waste generation in Asia, followed by Japan and South Korea. ` 23 Vietnam estimated C&D waste generation includes part of sewage waste which is quite minimal part of the total municipal solid waste. Currently, no data on C&D waste generation at national level for Thailand, but in Bangkok Metropolitan Area (BMA) tremendous amount of C&D waste is observed. Actual statistics of C&D waste generation is illustrated in countries like Hong Kong SAR, India, Japan, South Korea, Singapore, BMA Thailand, Taiwan and Vietnam. Most of the countries in Asia do not have data and information on C&D waste generation. The C&D waste is included in the Municipal waste. Countries with huge waste arising correlate with development particularly the construction activities. (Asian Institute of Technology,2008) Singapore(2003) 0.423 PRChina(2005) 200 Thailand(2005) 0.5 Taiwan(2004) 16,32 Malaysia(1994) 1.55 South Korea(2000) 28.75 Japan(2000) 85 India(2001) Hong 14.7 Kong(2004) Vietnam(2004) 20.5 1.35 Fig. 2.4: C&D Waste Generation in Million Tons. (Asian Institute of Technology,2008) According to Central Pollution Control Board India, the total generation of waste from construction industry is estimated to be 14.7 million tons per year (Pappu, 2006). As illustrated in Figure 2.4, the amount of construction waste generated in India is less compared with other countries, knowing that India has large geographical area which might somehow correlate with the size of the country, the reason because the generated ` 24 waste do not account the quantum amount renovation and demolition waste. In addition, the reason also is that because most of the C&D waste is dumped anywhere e.g. in Pune, India, C&D waste is dumped along the riverside haphazardly (Express India news, 2008). As cited by Li et. al. (2004) generally urban development directly leads to the increase of construction and demolition waste. Figure 2.5 depicts the construction activity in Asia in terms of GDP from 2000 to 2006. Data source in the figure is extracted from Key Indicators 2007 published by ADB. The trend in GDP from respective Asian country contributed by the construction sector indicates construction activities. Fig. 2.5: Trend of National Account of Construction Sector in Asia (% GDP) Source: Extracted from ADB Key Indicators 2007, Vol. 38 As illustrated in Fig 2.5, data results from literature review, interview and survey sources indicated that construction regulation in most of the Asian countries is practiced formally. Some countries consider only large size construction projects and middle end ` 25 size projects with construction regulations. While regulation to demolished buildings is still not yet recognize in most of the countries. Some of them like countries from Indonesia, India, Malaysia and Thailand practiced demolition permit in an informal way, meaning some cities and/or states (e.g. India) of these countries practiced it and some does not. It depends also of the size of the construction project that require demolition permit. No regulations are present on demolition activities at the moment in some countries in Asia. Countries such as Nepal and Sri Lanka does not recognize demolition permit. The unknown status indicates no data and information is available of this type of permit regulations. (Asian Institute of Technology,2008) Urban environmental management in the construction industry has been growing rapidly in some countries in Asia. Attaining towards sustainable development, some countries take efforts towards practicing environmental management system (EMS). Research in Singapore and Hong Kong SAR highlighted that C&D waste imposes an environmental burden. Construction industry has one of the highest resource uses and responsible for waste pollution. Some international and local construction industries in Singapore have already adopted the structured approach for improvement of the environmental performance of construction by ISO 14000 EMS (Ofori, 2000). Another case in Hong Kong where the local industry has been promoting measures such as establishing waste management plans, reduction and recycling of C&D wastes, providing in-house training on environmental management, and legal measures on environmental protection. ` 26 2.8. Practices on C&D Waste Management in Malaysia National/Local Government lead in the promotion of exercising reduce, reuse and recycle practices on C&D waste management in Malaysia. National and local government units for formulation, development and enforcement are National Environment Agency, Ministry of Environment, Ministry of Construction, Building and Construction Authority, Environmental Protection Department and other local authorities e.g. Construction Department. These national/local authorities have waste management plan, either individually or as part of a regional plan, that addresses C&D waste issues. 2.8.1 Construction Sector’s Waste Profile In Malaysia, the construction industry generates a lot of construction waste which cause significant impacts on the environment and increasing public concern. Thus, the minimization of construction waste has become a pressing issue. The source of construction waste at the project site includes materials such as soil and sand, brick and blocks, concrete and aggregate, wood, metal products, roofing materials, plastic materials and packaging of products. The composition of total waste generation is shown in Figure 2.6, which is percentage by weight. Concrete and aggregate is the largest component with 65.8% followed by soil and sand (27%), 5% from wood based materials such as timber, lumber, etc., 1.6% from brick and block, 1% from metal products, 0.2% from roofing materials and 0.05% from plastic and packaging products such as papers, cardboards, etc (Begum et al., 2006). ` 27 1.16% 1% 0.20% 5% 0.05% concreteand aggregate soilandsoil 27% woodmaterial 65.80% brickandblocks metalproduct Figure 2.6: Composition of total waste generation (Begum et al., 2005). 2.8.2 Policies and laws In the case of Malaysia, few regulating bodies’ in some municipalities or cities which deal with construction waste management, namely Local Authorities Ordinance (LAO), Local Authorities Cleanliness by law (LAC), Natural Resources and Environment Ordinance (NREO). Existing regulations are concerned with waste flow generation, transportation and disposal. Different Municipalities in Malaysia has a numbers of provisions that are available to regulate the management of construction waste (Tang & Larsen 2004, Chong, Tang & Larsen 2001 cited in Lau & Whyte, 2007). Existing provisions are currently not put in place due to the fact that the C&D waste management is yet informal. Furthermore in 2007, Department of National Solid Waste Management under Ministry of Housing and Local Government is in the process of formulating policies in addressing to C&D waste. The department is still new. C&D waste is categorized as another unit of waste, and not included in the municipal waste category (source: interview with officer at Ministry of Housing and Local Government, Malaysia,2008). ` 28 2.8.3 Practices Sustainable Building in South East Asia (SBSEA), a sub-regional forum for discussion among stakeholders and relevant institutions - to overcome the challenges and obstacles in implementing Sustainable Building Construction (SBC). SBSEA is designed to support local, national and regional initiatives of sustainable building and construction (SBC). It brings together different stakeholders. The forum is a dialogue for contribution to sustainable development in the region and options for supporting and promoting SBC (http://www.cibklutm.com). Partners and collaborators for this event are the International Council for Research & Innovation in Building and Construction International Initiative, for Sustainable Built Environment United Nations, Environmental Programme United Nations, the host country Institution and Sustainable Building & Construction Initiative World Green Building Council. 2.8.4 Waste Management Stakeholders Malaysian Stakeholders Participation on C&D waste management includes developers, contractors, construction industry, research institutes, local authority and government and NGOs. Large contractors give some awards for 3R to the Project managers, site supervisors and also workers. Construction waste disposal charge in Bangi, Selangor Area (local) in average RM 50 or US$ 15 per ton. ` 29 2.8.5 Waste Management Technologies In 2007, Malaysia has sanitary landfill for C&D wastes; however, the status of the facility is still weak as it needs participation from construction practitioner. Reuse and recycle of concrete and aggregate and construction wood waste A study done by Begum et al. (2006) of the project sites in Malaysia, construction waste materials contain a large percentage of reusable and recyclables. Estimated 73% of the waste materials in the project site are reused and recycled. Table 2.9 shows the amount of reused and recycled waste materials on the site. The highest amount of reused and recycled materials is concrete and aggregate, comprising 67.64% of the total reused and recycled material. It is followed by soil and sand, wood, brick and block, metal products and roofing materials. The practice reuse and recycling of construction waste materials is common on the site of one of the project sites. (Begum, 2006). Table 2.10: Amount of reused and recycled construction waste materials on site (Begum et al., 2006) Amount of reused and recycled ` Construction Waste Material Tonnage Percentage Soil and Sand 5400 27.33 Brick and block 126 0.64 Concrete and aggregate 13365 67.64 Wood 810 4.00 Metal products 54 0.27 Roofing material 5.4 0.03 Total 19760.4 100 30 CHAPTER III RESEARCH METHODOLOGY 3.1 Introduction This research methodology will explain how the objective of this study can be achieved. This chapter describes the method used in carrying out this study. This study was carried out first through the literature search and will follow by questionnaire survey. Subsequently, data being analyzed and their results and inference will be presented. This environmental assessment follows the standard protocol of life cycle assessments, LCA, (ISO 14040-14043). LCA was used as a method to evaluate the environmental impact from the entire life cycle of a product, from “the cradle to the grave”. Here life cycle inventory (LCI) data were collected from existing LCA reports, environmental reports. The results are presented both per kg material for each raw material and per functional unit (FU) (see APPENDIX B – Inventory tables) which is equivalent to 1 m3 of concrete. The data reported included, energy, and CO2 emissions to air for each stage in the manufacturing. All fuels, energy and emissions associated with transportation were reported separately. The ready mixed concrete for super ` 31 structure building represents in this study with the strength levels 20 MPa (3,000 psi).There would be some assumption that describe in Analyzing and Discussion part. Finally this paper shows the comparison of different way of disposal by land filling or recycling and data sources used to develop greenhouse gas (GHG) emission factors for recycled concrete, and land filling presented are the latest in a series of emission factors developed by the U.S. Environmental Protection Agency (EPA). 3.2 Inventory result The goal of the inventory phase is to determine quantities of all materials, energy, and CO2 pollutants that contribute to the product or system being investigated. These data must be assembled for all life cycle stages. For example, since concrete consists of cement, water, aggregate, and chemical admixtures, a concrete wall has these life cycle stages. The data for production of cement and other ingredient of concrete collected from the last research by (Jeannette Sjunnesson,2005) which collected from various ingredients utilized in cement production in Cementa AB’s report. Data for aggregate production is taken from an existing LCA report.(Stripple, 2001) .Data for admixture were taken from an EPD by the European Federation of Concrete Admixture Associations (EFCA). Data on transportation modes ,Transportation of cement, aggregates, and other constituent materials to ready-mix plant and distances for raw materials are primarily from NTM (Natverket for Transporter och Miljon, 2005).The transports for the raw materials and concrete produced are by trucks; either heavy trucks or medium heavy trucks except for the transport of cement to depot which is not consider in this research,. Cement and admixtures are both transported by heavy trucks. ` 32 Aggregate by a medium heavy truck. Ready- mixed concrete is transported in a liquidconcrete carrier, which is assumed to have the same characteristics as a medium heavy truck. Data for vehicle transportation in APPENDIX A – LCI data. All transport distances are as following table : Table 3.1: Vehicle Option (Jeannette Sjunnesson,2005) Transported goods Vehicle Distance(KM) Cement (to concrete plant from depot) Heavy truck 50 aggregate (to concrete plant) Medium heavy 20 Super plasticizer (to concrete plant) Heavy truck 50 Concrete (from concrete plant) Medium heavy 100 Comparison of disposal options i.e. land filling and recycling was also conducted by using data sources of emission factors developed by the U.S. Environmental Protection Agency (EPA) such as greenhouse gas (GHG) emission factors for recycled concrete, and land filling. To calculate the benefit of recycling concrete to displace virgin aggregate the following steps were done: Step 1: Calculate the emissions for virgin production of aggregate, Step 2: Calculate the emissions associated with processing and delivering a comparable amount of recycled concrete to be used in place of virgin aggregate, Step 3: Calculate the difference in emissions between recycled and virgin scenarios.For the calculation of this emission factor, in this thesis assumed that virgin aggregates must be transported 30 miles to the end user. For the calculation of this emission factor, assumed that recycled aggregate (waste concrete) must be transported 15 miles to the end user. ` 33 3.3 System boundaries The phases of the life cycle of concrete included in this study are shown in Figure 3.1. The use of water as a raw material is excluded since water is not regarded as a limited resource. To get a fair picture of the environmental impact of concrete, the time-frame must be sufficiently long. However, the carbonization of concrete will not be taken into consideration since the duration of this process is too long for this study. T T R R A A N N Cement Aggregate S Water Admixture Concrete S P P O O R R T T On site Disposal of concrete waste Figure 3.1: General Flowchart for the concrete life cycle Jeannette Sjunnesson (Jeannette Sjunnesson,2005) ` 34 3.4 Data Collection Data was collected from various sources including literatures and actual site investigation. A set of questionnaire was distributed to the selected construction sites. Interview sessions were also conducted from selected respondents to obtain their professional views. 3.4.1 Questionnaire Survey The questionnaire survey was carried out to gather information from the three construction sites in U.T.M. these questionnaires were distributed by manual and followed by interviews session. 3.4.1.1 Questionnaire structure The questionnaire was structured into three sections: Section A: To obtain information about the respondent’s background Section B: To survey the level of wastage in construction sites Section C: To survey the different mixing design Section D: To survey the disposal option The sample of questionnaire used for the survey in this project is shown in Appendix A. ` 35 3.5 Data analysis Upon the collection of questionnaire, every type of the data received under different question will be separated to answer different study objectives. The data will be analyzed manually by using the LCI and EPA data and which mentioned in this chapter. for calculation the wastage of concrete level, there is formula(Cheung, 1993) Concrete Waste = Quantity of Concrete Ordered - Quantity of Concrete Used Analysis was also conducted in term of the environmental impact based on two impact indicators i.e. energy and CO2 due to the quantity of the concrete waste generated. The analysis on the disposal option of the concrete waste was also discussed. 3.6 Stages of the study Three stages of the action were formulated for the approach of the study. Stage 1 comprises of a search on literatures on and surrounds of the subjects. Stage 2 comprise of the interviewing involving the key stakeholders seeking on the data and information of the particular of the study. Stage 3 comprises of analysis the finding, making conclusion and recommendations based on the founded information from the stages 1 and 2.In stage 1, in depth literature reviews were conducted related to the interest of the study. This stage involve of a search on the ‘review of the current concrete wastage issues in construction industry sites. Stage 2 comprises of interview and questionnaire survey involving the key personnel of stakeholders. The target respondents were identified by their qualification. In the questionnaire there are three sections which start by finding the amount of concrete wasted in construction site in U.T.M by asking for ` 36 quantity of ordering and cumulative of work done for the concrete for super structures. The second part consists of amount of ingredient for making of concrete in 1 m3 from aggregate, water, cement and admixtures. The third part would ask about the disposal of concrete in different situation such as Recycling or Land filling and Incineration. The questionnaire could be found in Appendix “B” which consists of 3 sections. This list is provided for completeness of the project report. The use of this list for any other purposes is strictly prohibited. At stage 3 the analysis of data and information’s gathered from the survey were done. ` 37 Literature review ¾ Literature search using books and journals ¾ Study and explore the concrete wastage level in construction sites ¾ Study and explore the causation of concrete waste ¾ Questionnaire survey distributed to 3 construction sites in U.T.M ¾ The objectives were to: ƒ Questionnaire survey ƒ ƒ ƒ To estimate the amount of energy used and CO2 emission for production of concrete To estimate the total energy and CO2 emission based on the different weight of concrete waste on sites. To evaluate the disposal option of concrete waste. To determine the amount of concrete waste in construction sites. Data Analysis and discussion ¾ The data will be analyzed manually by using the table which mentioned in this chapter. Conclusion and Recommendation ¾ Conclude the finding ¾ Recommendation for improvement and suggestion for further research. ` 38 CHAPTER IV ANALYSIS AND DISCUSSION This chapter discusses the presentation of data from a record of data collected, the analysis, interpretation and discussion of the results obtained through the survey research implemented. The purpose of data preparation is to present the data, to have a feel of the data, and to get the data correct and ready for analysis. The process of analysis began by summarizing and rearranging the raw data into appropriate format which ease for further analysis. The interpretation of data must clear and appropriate involved explaining the meaning of data collected and making inference. To ease the process of analysis, the following terminology has been adopted throughout the analysis: ` 39 There are three sections in the questionnaire which start by calculating the amount of concrete wasted in construction site in U.T.M by asking for quantity of ordering and cumulative of work done for the concrete for super structures. The second part consists of amount of ingredient for making of concrete in 1 m3 from aggregate, water, cement and admixtures. The third part would ask about the disposal of concrete in different situation such as Recycling or Land filling and Incineration. The questionnaire could be found in Appendix “B” which consists of 3 sections. This list is provided for completeness of the project report. The use of this list for any other purposes is strictly prohibited. 4.1 Concrete Waste The first analysis was to find out the amount of concrete wasted in construction sites. The amount of concrete waste can be estimated if the material wastage level of concrete is known. Recent research indicated that the average wastage level is about 4%, which is considered the norm for the concreting trade in this guideline. However, it could be reduced to 3% if careful material ordering and handling is applied. ` 40 4.1.1 Concrete Slabs, Walls, Beams, and Columns Portland cement concrete, typically referred to as “concrete,” is a mixture of Portland cement (a fine powder), water, fine aggregate such as sand or finely crushed rock, and coarse aggregate such as gravel or crushed rock. Ground granulated blast furnace slag (slag cement), fly ash, silica fume, or limestone may be substituted for a portion of the Portland cement in the concrete mix. Concrete with 21 MPa strength is used in applications such as residential slabs and basement walls, while strengths of 28 MPa and 34 MPa are used in structural applications such as beams and columns. Portland cement concrete products like beams and columns are modeled based on volume of concrete (e.g., a functional unit of 1 ft3), while basement walls and slabs are modeled on an area basis (e.g., a functional unit of 1 ft2). The amount of concrete required depends on the dimensions of the product (e.g., thickness of slab or wall and surface area). Above-grade walls are typically 15 cm (6 in) thick. Basement walls are 20 cm (8 in) thick, slabs 10 cm (4 in) thick, and a typical column size is 51 cm by 51 cm (20 in by 20 in). Manufacturing data for concrete products are taken from the Portland Cement Association’s LCA database. Based on the information obtained from different construction sites, the table 4.1 received for Construction No 1. ` 41 TABLE4.1: Cumulative quantity of ordering (m3) in Construction No 1 ` TARIKH G25 14/01/09 18 28/02/09 25 07/03/09 22 14/03/09 65 21/03/09 161 31/03/09 133 07/04/09 24 14/04/09 14 21/04/09 99 28/04/09 181 30/04/09 56 07/05/09 11 14/05/09 60 31/05/09 97 07/06/09 50 14/06/09 108 21/06/09 94 30/06/09 98 07/07/09 37.5 14/07/09 111 21/07/09 8 31/07/09 185.5 TOTAL 1728 M3 42 In this construction site no 1 the amount of concrete poured base on the plan dimensions is 1644.845 M3 So the amount of wastage for construction no 1 is: (1) Cumulative quantity of ordering (m3)=1728 M3 (2) cumulative work done (m3) =1644 M3 (3) wastage (m3) =84 (4) actual wastage percentage : 5 % The amount of concrete waste indicated that the average wastage level is about 5%, which is considered 1% more than the norm for the concreting trade. The amount of wastage for construction no 2 is: (1)Cumulative quantity of ordering (m3) =370 M3 (2) Cumulative work done (m3) =350 M3 (3) Wastage (m3) =20 M3 (4) Actual wastage percentage: 5.5 % The amount of concrete waste indicated that the average wastage level is about 5.5%, which is considered 1.5% more than the norm for the concreting trade. The amount of wastage for construction no 3 is: (1)Cumulative quantity of ordering (m3) =500 M3 (2) Cumulative work done (m3) =480 M3 (3) Wastage (m3) =20 M3 (4) Actual wastage percentage: 4 % ` 43 The amount of concrete waste indicated that the average wastage level is about 4%, which is considered equal the norm for the concreting trade. 4.2 Assumptions Several assumptions were made to calculate the LCI of concrete. i. The functional unit for concrete is one cubic yard ii. Distances to the concrete plant are 100 km (60 miles) for Portland. iii. Road transportation is assumed in all cases, which is conservative from an energy consumption and emissions standpoint (i.e. higher energy and emissions than rail or barge transportation). 4.3 Concrete production Mixing the aggregate and admixtures together with concrete paste makes concrete. The admixture can be added differently, for example, before transport or before casting or already during cement production, depending on what kind of effect is to be achieved. The concrete paste is cement mixed with water and it is the binder in the concrete. Its characteristics are controlled by the ratio of water to cement, the w/c ratio. ` 44 If the concrete is mixed and worked up appropriately the strength of the concrete is determined by the w/c ratio. Based on the information obtain from this research, the mixing design of the concrete are as following: Table 4.2: Different construction mixing design Concrete mix Ready Mixed Concrete description Construction No 1 Construction No 2 Construction No 3 28 day comp. strength 3,000 psi 3,000 psi 3,000 psi Portland cement(Kg) 361 300 320 Slag cement 0 0 0 Fly ash 0 0 0 Silica fume 0 0 0 Water 180 180 180 Coarse aggregate 990 1000 830 Fine aggregate 777 827 970 Total 2308 2307 2300 4.4 Cement Energy Demand Based on the information obtained from construction site the amount of cement which used in this construction sites is 1728 M3 * 361 Kg/M3= 623808 Kg cement and based on the table 2.3 in order to produce 1 Kg cement 3.35 MJ energy needed so that for the amount of total ordering concrete is equal to 3.35 MJ/Kg * 623808 Kg = 2089756 MJ = 2089.7 GJ (construction no 1) ` 45 3.35 MJ/Kg * 111000 Kg = 371800 MJ = 371.85 GJ (construction no 2) 3.35 MJ/Kg * 160000 Kg = 536000 MJ = 536 GJ (construction no 3) 4.5 Aggregates Energy Demand In aggregate production diesel is used in internal transports. All of the crushing machines are driven by electricity. In the extraction of gravel a wheel loader is used to excavate the gravel, while the internal transports use lorry loaders. Inventory results for macadam and gravel production based on the table 2.5 is 0.067 MJ/Kg. So for project 1, for 1767 Kg/m3 aggregate the energy required is: 0.067 MJ/Kg * 1767 Kg/m3 = 118.4 MJ/m3= 0.118 GJ/m3 1728 m3 (concrete ordering) * 1767 Kg/m3 (aggregate) = 3053376 Kg (total aggregate) Total Energy demand = 0.118 GJ/m3 * 1728 m3 = 204 GJ Total Energy demand = 3053376 Kg * 0.067 MJ/Kg = 204 GJ So for project 2, for 1827 kg/m3 aggregate the energy required is 0.067 MJ/kg * 1827 Kg/m3 = 122.4MJ/m3 = 0.122 GJ/m3 370 m3 (concrete ordering) * 1827 m3 = 675990 kg (total aggregate) Total energy demand = 0.122 GJ/m3 * 370 m3 ~45 GJ So for project 3, for 1800 Kg/m3 aggregate the energy required is 0.067 MJ/Kg * 1800 Kg/m3 = 120.6 MJ/m3= 0.12 GJ/m3 500 m3 (concrete ordering) * 1800 Kg/m3 (aggregate) = 900000 Kg (total aggregate) Total Energy demand = 0.12 GJ/m3 * 500 m3 = 60 GJ Total Energy demand = 900000 Kg * 0.067 MJ/Kg ~ 60 GJ ` 46 4.6 Energy for Wasted Cement and Aggregate Based on the amount of cement which wasted, the energy demand is: Project 1 Wasted cement for 84 M3 = 30324Kg Energy demand for production of this amount = 3.35 MJ/Kg * 30324 Kg = 101585.4 MJ = 101.6 GJ Energy for wasted cement/energy for total cement =101.6 / 2089.7 = 0.04 = 4% Based on the result, 4 % extra energy wasted for production of wasted cement And also for production of wasted aggregate also: Wasted aggregate = 84 m3 * 1767 kg/m3 = 148428 kg Energy demand = 148428 Kg * 0.067 MJ/Kg = 99451 MJ= 10 GJ Energy for wasted aggregate/energy for total aggregate = 0.04 = 4% Based on the result, 4 % extra energy wasted for production of wasted aggregate Project 2 Wasted cement for 20 M3 = 6000Kg Energy demand for production of this amount = 3.35 MJ/Kg * 6000 Kg = 20100 MJ ~ 20 GJ Energy for wasted cement/energy for total cement =20 / 371.85 = 0.055 = 5.5% Based on the result, 5.5 % extra energy wasted for production of wasted cement. And also for production of wasted aggregate also: Wasted aggregate = 20 m3 * 1827 kg/m3 = 36540 kg Energy demand = 36540 Kg * 0.067 MJ/Kg = 2448 MJ= 2.44 GJ Energy for wasted aggregate/energy for total aggregate = 0.055 = 5.5% Based on the result, 4 % extra energy wasted for production of wasted aggregate ` 47 Project 3 Wasted cement for 20 M3 = 6400Kg Energy demand for production of this amount = 3.35 MJ/Kg * 6400 Kg = 21440 MJ ~ 21.5 GJ Energy for wasted cement/energy for total cement =21.5 / 536= 0.04 = 4% Based on the result, 4 % extra energy wasted for production of wasted cement. And also for production of wasted aggregate also: Wasted aggregate = 20 m3 * 1800 kg/m3 = 36000 kg Energy demand = 36000 Kg * 0.067 MJ/Kg = 2412 MJ ~ 2.4 GJ Energy for wasted aggregate/energy for total aggregate = 0.04 = 4% Based on the result, 4 % extra energy wasted for production of wasted aggregate 4.7 CO2 Emission CO2 is the chemical formula for carbon dioxide, a gas which exists in relatively small amounts (380 parts per million or ppm) in our atmosphere. Based on the table above total Co2 emission for production of cement is: 623808 Kg * 0.71 Kg = 442903 Kg (project 1) 111000 Kg * 0.71 Kg = 78810 Kg (project 2) 160000 Kg * 0.71 Kg = 113600 Kg (project 3) And also CO2 Emission for wasted cement production is Project 1 30324 Kg * 0.71Kg = 21530 Kg Which means 21530/442903 = 0.04 = 4 %( extra CO2 emission) ` 48 Project 2 6000 Kg * 0.71 Kg = 4260 Kg Which means 4260/78810 = 0.055 = 5.5 % (extra CO2 emission) Project 3 6400 Kg * 0.71 Kg = 4544 Kg For aggregate CO2 Emission: Based on the table by LCI data, the amount of CO2 Emission for 1 Kg aggregate is 0.9 g So based on this information, CO2 emission for production of total aggregate is: 3053376 Kg * 0.9 g = 2748038 g ~2748 Kg (project 1) 675990 Kg * 0.9 g = 608391 g ~ 608 Kg (project 2) 900000 Kg * 0.9 g = 810000 g = 810 Kg (project 3) And on the other hand CO2 emission for wasted aggregate is: Project 1 148428Kg * 0.9 g ~ 133 Kg So that the extra CO2 Emission is 133 Kg/ 2748 Kg = 0.04 = 4 % Project 2 36540Kg * 0.9 g ~ 33 Kg So that the extra CO2 Emission is 33 Kg/ 608 Kg = 0.055 = 5.5 % Project 3 36000Kg * 0.9 g ~ 33 Kg So that the extra CO2 Emission is ` 49 33 Kg/ 810 Kg = 0.04 = 4 % 4.8 Admixture Daratard admixture is a ready-to-use aqueous solution of modified salts of hydroxylated carboxylic acids. Ingredients are factory pre-mixed in exact proportions to minimize handling, eliminate mistakes and guesswork. One Liter weighs approximately 1.17 kg (9.8 lb/gal). In all construction sites in U.T.M, the only admixture which in used was Daratard. Based on the information by EFC (Environmental Declaration Super plasticizing Admixtures, 2002), for 1 kg Daratard 16 MJ energy consumed for production and also 0.69 kg CO2 emission for 1 kg Daratad. And based on the information given by site project 1, for 400ml Daratard for 100 kg cement used. So that for 1 m3 concreting Project 1 361 kg (cement) = 1444ml Daratard = 1.44 L 1 liter Daratard = 1.17 kg 1.44 liter Daratard = 1.7 kg 1kg Daratard = 16 MJ/kg >>>>>1.7 kg Daratad = 27 MJ = 0.027 GJ So based on this information for total concreting (1728 m3) 0.027 GJ * 1728 m3 = 47 GJ Wasted = 0.027 * 84 m3 = 2.268 Project 2, 410 ml for 100 kg cement ` 50 300 kg (cement) = 1.23 L = 1.44 kg Energy: 1.44 kg * 16 MJ/kg = 23 MJ = 0.023 GJ Total concreting = 370m3 * 0.023 GJ =8.5 GJ Wasted = 0.023 GJ * 20m3 = 0.46 GJ Project 3, 400 ml for 100 kg cement 320 kg (cement) = 1.28 L ~ 1.5 kg Energy: 1.5 kg * 16 MJ/kg = 24 MJ = 0.024 GJ Total concreting = 500 m3 * 0.024 GJ =12 GJ Wasted = 20 m3 * 0.024 GJ = 0.48 GJ Emission by admixture Based on the information by EFC data, for 1 kg admixture, 0.69 kg CO2 emission produced. So that For 1 m3 concreting = 1.7 kg Daratard * 0.69kg = 1.173 kg For total concreting = 1728 m3 * 1.173 kg = 2027 kg (project 1) For 1 m3 concreting = 1.44 kg Daratard * 0.69kg = 1 kg For total concreting = 370m3 * 1kg = 370 kg (project 2) For 1 m3 concreting = 1.5 kg Daratard * 0.69kg ~1 kg For total concreting = 500 m3 * 1kg = 500 kg (project 3) For wasted concreting = 84 m3 * 1.173 kg = 98.5 kg (project 1) For wasted concreting = 20 m3 * 1.173 kg = 23.5 kg (project 2) For wasted concreting = 20 m3 * 1.173 kg = 23.5 kg (project 3) ` 51 4.9 Transportation Project 1 1m3 cement= 361 kg/m3 0.361 ton/m3 *50 KM * 0.6 MJ/tkm = 10.83 ~ 0.01GJ(1m3 of Cement production) 1m3 aggregate = 1767 Kg/m3 1.767 ton/m3 * 20 KM * 1.9 MJ/tkm = 67 MJ ~0.067 GJ(1m3 of Aggregate production) 1m3 admixture = 1.7 kg 0.0017 ton/m3 * 50 KM * 0.6 MJ/tkm = 0.051 GJ(1m3 of Admixture production) So for 1 m3 of concrete production, the transportation will have 0.128 GJ energy consumption and for total production 221.2GJ Also for CO2 emission: 0.361 ton/m3 *50 KM * 0.048 kg/tkm = 0.86kg(1m3 of Cement production) 1.767 ton/m3 * 20 KM * 0.14 kg/tkm = 5 kg(1m3 of Aggregate production) 0.0017 ton/m3 * 50 KM * 0.048 MJ/tkm = 0.004 GJ(1m3 of Admixture production) So for 1 m3 of concrete production, the transportation will have 5.86Kg CO2 emission and for total production 10133Kg Project 2 1m3 cement= 300 kg/m3 0.3 ton/m3 *50 KM * 0.6 MJ/tkm = 9 = 0.009GJ(1m3 of Cement production) 1m3 aggregate = 1827 Kg/m3 1.827 ton/m3 * 20 KM * 1.9 MJ/tkm = 69.4 MJ ~0.0694 GJ 1m3 admixture = 1.44 kg 0.00144 ton/m3 * 50 KM * 0.6 MJ/tkm = 0.0432 GJ So for 1 m3 of concrete production, the transportation will have 0.1216 GJ energy consumption and for total production 45GJ Also for CO2 emission: 0.3 ton/m3 *50 KM * 0.048 kg/tkm = 0.72kg(1m3 of Cement production) ` 52 1.827 ton/m3 * 20 KM * 0.14 kg/tkm = 5.1 kg(1m3 of Aggregate production) 0.00144 ton/m3 * 50 KM * 0.048 kg/tkm = 0.0034 kg(1m3 of Admixture production) So for 1 m3 of concrete production, the transportation will have 5.82Kg CO2 emission and for total production 2154.6Kg Project 3 1m3 cement= 320 kg/m3 0.320 ton/m3 *50 KM * 0.6 MJ/tkm = 9.6 ~ 0.0096GJ(1m3 of Cement production) 1m3 aggregate = 1800 Kg/m3 1.8 ton/m3 * 20 KM * 1.9 MJ/tkm = 68.4 MJ ~0.0684 GJ 1m3 admixture = 1.5 kg 0.0015 ton/m3 * 50 KM * 0.6 MJ/tkm = 0.045 GJ So for 1 m3 of concrete production, the transportation will have 0.123 GJ energy consumption and for total production 61.5GJ Also for CO2 emission: 0.32 ton/m3 *50 KM * 0.048 kg/tkm = 0.768kg(1m3 of Cement production) 1.8 ton/m3 * 20 KM * 0.14 kg/tkm = 5 kg(1m3 of Aggregate production) 0.0015 ton/m3 * 50 KM * 0.048 kg/tkm = 0.0036 kg(1m3 of Admixture production) So for 1 m3 of concrete production, the transportation will have 5.76Kg CO2 emission and for total production 2882Kg 4.10 Transportation concrete to the site from concrete plant Project 1 2308kg/m3 ~2.3 ton ` 53 2.3ton * 100 Km * 1.9 MJ/tkm = 437 MJ = 0.437 GJ So the energy required for 1728 m3 total concreting: 1728m3 * 0.437GJ = 755 GJ Based on the finding, the wastage amount is 84 m3 Therefore 84 m3 * 0.437 GJ ~ 36.7 That 36.7/755 = 4.8% Project 2 2307 kg/m3 ~ 2.3 ton Energy required for 370 m3 total concreting: 370 * 0.437 = 161 GJ Therefore 20 m3 * 0.437 GJ = 8.74 That 8.74/161 = 0.055 = 5.4% Project 3 2300 kg/m3 = 2.3 ton Energy required for 500 m3 total concreting: 500 * 0.437 = 218.5 GJ Therefore 20 m3 * 0.437 GJ = 8.74 That 8.74/218.5 = 0.04 = 4% CO2 Emission to air by transportation Project 1 Based on LCI data, the amount of CO2 emission for 1tkm is equal 0.14kg 2.3ton * 100 Km * 0.14 Kg/tkm = 32.2 kg (for 1 m3 of concrete) Total concreting: 1728 m3 * 32.2 kg/m3 = 55641.6 kg Based on the amount of wastage, we have: ` 54 84 m3 * 32.2 kg/m3 = 2704.8 kg Percentage of wastage = 2704.8 / 55641.6 = 4.8 %( extra CO2 emission) Project 2 Total concreting: 370m3 * 32.2kg/m3 = 11914 kg Based on the amount of wastage, we have: 20 m3 * 32.2 kg/m3 = 644 kg Percentage of wastage = 644 / 11914 = 5.5 %( extra CO2 emission) Project 3 Total concreting: 500m3 * 32.2kg/m3 = 16100 kg Based on the amount of wastage, we have: 20 m3 * 32.2 kg/m3 = 644 kg Percentage of wastage = 644 / 16100 = 4 %( extra CO2 emission) Based on the different quantity of ordering concrete on site, three construction sites have different total embodied energy and CO2 emission. Based on the table 4.2 for 1 m3of concrete mixing design, although all the construction sites have the same strength quality (3,000 psi for 28 days), it is acceptable to see the differences in percentage of mixing design for concrete with the same characteristic. So that it is the reason in tables 4.3,4.5,4.7 by having 1 m3 concreting, there is different embodied energy and CO2 emission. For example for Construction No 1,based on the amount in table 4.2,the amount of cement for 1m3 concreting is 361kg/m3 which provide 1.2 GJ/m3 embodied energy and 256 kg/m3 CO2 emission, on the other hand construction no 2 has 300 kg/m3 cement for 1m3 of concreting so that the embodied energy based on the table 4.5 is 1 GJ/m3 and ` 55 213kg/m3 CO2 emission. For construction no 3,320 kg/m3 cement is equal to 1.07GJ/m3 embodied energy and 227kg/m3 CO2 emission. Base on the tables 4.2 and comparison with the tables 4.3,4.5,4.7 it can be understandable that even with this different mixing design, it’s the cement production that make this different bigger in terms of embodied energy and CO2 emission. Aggregate production, transportation material to the plant, concrete plant operation and admixture production are mostly the same for 1 m3 concreting. In order to get the fair picture of impact of concrete to the environment in terms of embodied energy and CO2 emission tables 4.4,4.6,4.8 shows the total concreting in 3 different construction site. In construction no 1,1728 m3 is the cumulative quantity of ordering of concrete in which 2988.7 GJ energy consumed to produce this amount and 457811 kg CO2 emission produced. In this construction, Portland cement manufacturing with 2089.7 GJ energy consumption and 442903 kg CO2 emission is the highest amount which is equivalent to 70% of total energy consumption and 95 % of total CO2 emission. More ever, there is another considerable amount by transportation of concrete to the site ,which is about 755 GJ that is more than the other mixing production and concrete plant operation value. The transportation of concrete to the site is 25% of total energy consumption and 10% of total CO2 emission of total concrete production. So based on the distance which assumed 100 km for the transportation of concrete to the site, it can be significant if this distance reduced. There is the same scenario for the rest two construction sites. In construction no 2, the cumulative quantity of ordering is 370m3 that cement manufacturing by 371.85 GJ embodied energy and 78810 kg CO2 emission is the highest between the other manufacturing process. In construction no 3, 500 m3 is the total quantity of ordering in which cement by 536 GJ and 113600 kg CO2 emission is in top between the other manufacturing process. As it appears, by increasing the amount of concreting, it’s the cement manufacturing which make this gap bigger and bigger. ` 56 As can be seen ,although the cement composes about 10 % of the total concrete mix design but account for 70 % of the total embodied energy. The highest energy demand in production of 1 kg cement is coal in which consumed 1.9 MJ energy. Besides that, cement also is the highest in terms of CO2 emission between the other composers. Based on the calculation above, it is about 95 % of the carbon dioxide emission in concrete production were produced by cement manufacturing. Table 4.3: Embodied Energy & CO2 Emission for One Cubic Meter of Concrete Production Concrete mix description ` Ready mix concrete project 1 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 1.2 256 Aggregate production 0.118 1.57 Transporting materials to Plant 0.128 5.86 Concrete plant operations 0.247 N/A Admixture production 0.027 1.173 Total 1.72(GJ/m³) 264.6(kg/m3) 57 Table 4.4: Embodied Energy & CO2 Emission for Total Cubic Meter of Concrete Production Concrete mix description Ready mix concrete project 1 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 2089.7 442903 Aggregate production 204 2748 Transporting materials to Plant 221.2 10133 Concrete plant operations 426.8 N/A Admixture production 47 2027 Total 2988.7(GJ/m³) 457811(kg/m3) Table 4.5: Embodied Energy & CO2 Emission for One Cubic Meter of Concrete Production Concrete mix description ` Ready mix concrete project 2 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 1 213 Aggregate production 0.122 1.65 Transporting materials to Plant 0.1216 5.82 Concrete plant operations 0.247 N/A Admixture production 0.023 1 Total 1.51(GJ/m³) 221.47(kg/m3) 58 Table 4.6: Embodied Energy & CO2 Emission for Total Cubic Meter of Concrete Production Concrete mix description Ready mix concrete project 2 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 371.85 78810 Aggregate production 45 608 Transporting materials to Plant 45 2154 Concrete plant operations 91.4 N/A Admixture production 8.5 370 Total 561.75(GJ/m³) 81942(kg/m3) Table 4.7: Embodied Energy & CO2 Emission for One Cubic Meter of Concrete Production Concrete mix description ` Ready mix concrete project 3 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 1.07 227 Aggregate production 0.12 1.62 Transporting materials to Plant 0.123 5.76 Concrete plant operations 0.247 N/A Admixture production 0.024 1 Total 1.58 (GJ/m³) 235.38(kg/m3) 59 Table 4.8: Embodied Energy & CO2 Emission for Total Cubic Meter of Concrete Production Concrete mix description Ready mix concrete project 3 Energy(GJ/m³) CO2 Emission(kg/m3) Portland cement Manufacturing 536 113600 Aggregate production 60 810 Transporting materials to Plant 61.5 2880 Concrete plant operations 123.5 N/A Admixture production 12 500 Total 793(GJ/m³) 117790(kg/m3) In order for better understanding of the importance impact of concrete waste in terms of embodied energy and CO2 emission for concrete production, the tables below show this waste amount from production until the transportation of concrete to the site. As it shows the construction no 1, 84 m3 of concrete wasted that based on the table 4.9,144.71GJ embodied energy consumed and 22253.7 kg CO2 emission produced by this amount of waste that compare to the total concreting for 84m3, 3743.7GJ energy and 513452.6 kg CO2 are the impacts of concreting in which these numbers include the wasted amount. So this amount of waste is about 4% of total embodied energy and CO2 emission. In table 4.9 Portland cement manufacturing by 101 GJ embodied energy is the considerable amount between the others. Based on the table 4.6 the total embodied energy for Portland cement manufacturing was 2089.7 GJ that 101 GJ wasted energy is included in that amount. So minus these amount will give us the ideal amount which must be consumed to produce the cement( 2089.7 GJ – 101 GJ = 1988.7 GJ).so 101 GJ is about 4.8 % extra energy consumed to produce the cement. It’s the transportation operation to the plant as can ` 60 be seen in tables 4.9,4.10,4.11 that have the second important amount compared to the other manufacturing. Based on the table 4.9 transportation of concrete to the plant has 36.7 GJ energy consumption and 2704.8 kg CO2 emission which compare to the to the total concreting is about 5% extra energy and CO2 emission. For construction no 2,wasted concrete is 20 m3 which 20 GJ extra energy used to produced the Portland cement which compare to the total energy for cement manufacturing in this construction site is (371.85GJ – 20GJ = 351.85).so about 5% extra energy consumed for cement manufacturing. For construction no 3 also 4% extra energy consumed for cement production. Also the same calculation can be done to see the differences in CO2 emission, in construction no 1, 21530 kg CO2 emission produced which compare to the total CO2 emission, its 4.8 % extra CO2 produced. Which for the rest construction sites are as following, construction no 2 is 5 % and construction no 3 is 4% extra CO2 emission produced. Transportation of concrete to the site also is considerable in which for construction no 1, 755 GJ energy compared to 36.7 GJ for wasted which is about 4.5 % extra energy consumption and for CO2 emission is 4.8% extra CO2 emission. ` 61 Table 4.9: Embodied Energy & CO2 Emission for Total Cubic Meter of Waste Concrete Production Concrete mix description Ready mix concrete project 1 Waste Energy(GJ/m³) Portland cement CO2 Emission(kg/m3) 101 21530 10 133 10.75 492.2 Concrete plant operations 20.7 N/A Admixture production 2.26 98.5 Transportation of concrete to the site 36.7 2704.8 Manufacturing Aggregate production Transporting materials to Plant Total 144.71(GJ/m³) 22253.7(kg/m3) Table 4.10: Embodied Energy & CO2 Emission for Total Cubic Meter of Waste Concrete Production Concrete mix description Ready mix concrete project 2 Waste Energy(GJ/m³) Portland cement manufacturing CO2 Emission(kg/m3) 20 4260 Aggregate production 2.44 33 Transporting materials to 2.43 116.4 Concrete plant operations 4.94 N/A Admixture production 0.46 23.5 Transportation of concrete to the site 8.74 644 Plant Total ` 30.26(GJ/m³) 4433(kg/m3) 62 Table 4.11: Embodied Energy & CO2 Emission for Total Cubic Meter of Waste Concrete Production Concrete mix description Ready mix concrete project 3 Waste Energy(GJ/m³) Portland cement CO2 Emission(kg/m3) 23.5 4544 Aggregate production 2.4 33 Transporting materials to Plant 2.46 115.2 Concrete plant operations 4.94 N/A Admixture production 0.48 23.5 Transportation of concrete to the site 8.74 644 Manufacturing Total 4.11 3178(GJ/m³) 4715.7(kg/m3) Disposal Option Concrete waste from construction and demolition is an environmental concern, but great strides have been made in the last decade to lessen the waste burden through reuse of concrete debris. Concrete is estimated to account for 67% by weight of construction and demolition waste—the largest single component (U.S. EPA 1998). ` 63 4.11.1 Recycling When structures are demolished, the waste concrete can be crushed and reused in place of virgin aggregate. Doing so reduces the GHG emissions associated with producing concrete using virgin aggregate material. Virgin aggregates, which include crushed stone, gravel, and sand, are used in a wide variety of construction applications, such as road base, fill, and as an ingredient in concrete and asphalt pavement (USGS 2000). The GHG benefits of recycling are calculated by comparing the difference in emissions associated with producing and transporting a ton of virgin aggregate versus producing and transporting a comparable amount of recycled inputs (i.e., crushed concrete). To calculate the benefit of recycling concrete to displace virgin aggregate, the following steps were necessary: Step 1: Calculate the emissions for virgin production of aggregate. Step 2: Calculate the emissions associated with processing and delivering a comparable amount of recycled concrete to be used in place of virgin aggregate. Step 3: Calculate the difference in emissions between recycled and virgin scenarios. Step 1. Calculate the emissions for virgin production of aggregate. For project 1 Based on the table 4.12 and the amount of concrete waste, the calculation as following: ` 64 Table 4.12: Process Energy Data for the Production of One Ton of Virgin Aggregate (EPA 1998) Fuel (a) (b) (c) Combustion energy Million Btu/ton Precombustion energy Million Btu/ton Total energy Million Btu/ton Process energy Coal 0.0007 0.00000 0.0007 Distillate fuel oil 0.0248 0.0046 0.0293 Residual fuel oil 0.0024 0.0004 0.0028 Gas 0.0029 0.0004 0.0033 Gasoline 0.0003 0.0015 Electricity 0.0013 0.0110 0.0000 0.0110 Total 0.0429 0.0056 0.0486 84 m3 = concrete waste 1767 kg/m3 * 84 m3 = 148428 kg (total aggregate waste) 148.428 ton * 0.0486 million btu/ton =7.2 million Btu 7.2 million btu / 0.0009478 million btu = 7596.5 MJ ~ 7.6 GJ Project 2 20 m3 = concrete waste 1827 kg/m3 * 20 m3 = 36540 kg (total aggregate waste) 36.54 ton * 0.0486 million btu/ton =1.77 million Btu 1.77 million btu / 0.0009478 million btu = 1867.5 MJ ~ 1.86 GJ ` 65 Project 3 20 m3 = concrete waste 1800 kg/m3 * 20 m3 = 36540 kg (total aggregate waste) 36 ton * 0.0486 million btu/ton =1.75 million Btu 1.75 million btu / 0.0009478 million btu = 1846 MJ ~ 1.84 GJ Transportation: For the calculation of this emission factor, we assumed that virgin aggregates must be transported 30 miles to the end user. Table 4.13 : Transportation Energy Consumption, million Btu/ton-mile(US,EIA,2001) Transportation energy Transportation energy Transportatio n Transportation energy Diesel fuel (Million btu/tonmile) Distance (million btu/ton) 30 0.0610 15 0.0305 (Joule/kg-km) Virgin aggregate 3800 0.0020 Recycle aggregate 3800 Project 1 148.428ton aggregate * 0.0610 million btu/ton = 9 million btu 9 million btu / 0.0009478 million btu = 9552.7 MJ ~ 9.5 GJ So that the energy required producing the virgin aggregate is: ` 66 7.6 GJ + 9.5 GJ = 17.1 GJ Project 2 36.5 ton aggregate * 0.0610 million btu/ton = 2.23 million btu 2.23 million btu/0.0009478 milion btu = 2351 MJ ~ 2.3 GJ So that the energy required producing the virgin aggregate is: 1.86 GJ + 2.3 GJ = 4.16 GJ Project 3 36 ton aggregate * 0.0610 million btu/ton = 2.2 million btu 2.2 million btu/0.0009478 milion btu = 2321 MJ ~ 2.32 GJ So that the energy required producing the virgin aggregate is: 1.84 GJ + 2.32 GJ = 4.16 GJ CO2 emission by production of virgin aggregate Based on the information by EIA 2001, the amount of production rate for virgin aggregate is 0.9 g for 1 Kg aggregate. ` 67 Table 4.14: Process energy emission calculation for Virgin aggregate(U.S.EIA,2001) Million Btu used for aggregate production Process Energy CO2 emission (MTCE/TON) Process energy CH4 emission (MTCE/TON) 3.16 0.0015 <0.0001 <0.0001 <0.0001 Distillate Fuel 60.42 0.0293 0.0006 <0.0001 0.0006 Residual Fuel National Average 5.68 0.0028 0.0001 <0.0001 0.0001 Fuel Mix for Electricity 22.61 0.0110 0.0002 <0.0001 0.0002 Coal Used by Industry (NonCoking Coal 1.40 0.0007 <0.0001 <0.0001 <0.0001 Natural Gas 6.74 0.0033 <0.0001 <0.0001 <0.0001 100 0.0486 0.0009 <0.0001 0.0009 Gasoline Total Project 1 So we have 84 m 3 wastage, and 84m3 * 1767 kg = 148428 kg aggregate 148.428 ton * 0.0009MTCE/ton = 0.133 MTCE ~ 132.5 kg Project 2 20 m3 * 1827 Kg = 36540 kg 36.540 ton * 0.0009 MTCE = 0.03 MTCE ~ 32.6 kg ` Total process Percentage of total BTu Fuel type energy emission (MTCE/TON) 68 Project 3 20 m3 * 1800 Kg = 36000 kg 36 ton * 0.0009 MTCE = 0.032 MTCE ~ 32 kg CO2 emission by transportation of virgin aggregate: Based on the information by the table below, the transportation of virgin aggregate will: Table 4.15: Transportation Energy Emission Calculation for Virgin aggregate(US.EIA,2001) Fuel type Percentage of Total Btu Million Btu used for aggregate transport Transportation Energy CO2 emission (MTCE/TON) Transport energy CH4 emission (MTCE/TON) Total transport energy emission (MTCE/TON) Diesel Fuel 100 0.1869 0.0037 <0.0001 0.0037 Total 100 0.1869 0.0037 <0.0001 0.0037 Project 1 148.428 ton * 0.0037MTCE/ton = 0.55MTCE ~ 545.5 kg So that the total emission by CO2 for producing and transporting of virgin aggregate is: 545.5 kg + 132.5 kg = 678 kg Project 2 36.540 ton * 0.0037MTCE/ton = 0.134 g ~ 134 kg 134kg + 32.6 kg= 166.6kg ` 69 Project 3 36 ton * 0.0037MTCE/ton = 0.133 MTCE ~ 132 kg So 132kg + 32 kg = 164 kg Step 2: Calculate the emissions associated with processing and delivering a comparable amount of recycled concrete to be used in place of virgin aggregate. Recycle: Project 1 Based on the table 4.16 148428 kg = 148.428 ton 148.428 ton * 0.0352 million btu/ton= 5.22 million btu 1 mega joule = 0.0009478 million btu 5.22 million btu/ 0.0009478 = 5507 MJ ~ 5.5 GJ Project 2 36.540 ton * 0.0352 million btu/ton= 1.28 million btu 1.28 million btu/ 0.0009478 = 1350 MJ ~ 1.35 GJ Project 3 36 ton * 0.0352 million btu/ton= 1.26 million btu 1.26 million btu/ 0.0009478 = 1329.5 MJ ~ 1.33 GJ ` 70 Transport: Project 1 Based on the table 4.16 148.428ton aggregate * 0.0305 million btu/ton = 4.5 million btu 4.5 million btu / 0.0009478 million btu = 4776.3 MJ ~ 4.77 GJ So that the energy required recycling the waste aggregate is: 4.77 GJ + 5.5 GJ = 10.27 GJ Project 2 36.540 ton aggregate * 0.0305 million btu/ton = 1.11 million btu 1.11 million btu / 0.0009478 million btu = 1171 MJ ~ 1.17 GJ 1.17 GJ + 1.35 GJ = 2.52 GJ Project 3 36 ton aggregate * 0.0305 million btu/ton = 1.1 million btu 1.1 million btu / 0.0009478 million btu = 1158.5 MJ ~ 1.16 GJ 1.16 GJ + 1.33 GJ = 2.49 GJ As we can see, by recycling of wasted concrete can be useful by almost 2 times more saving energy than producing virgin aggregate. ` 71 Table 4.16: Process Energy Emissions Calculations for Recycled Aggregate(US.EIA2001) (a) Fuel Type Diesel Fuel Total Percent of Total Btu (b) Million Btu used for Aggregate transport (=0.0352 x a) (c) Fuel-specific Carbon Coefficient (MTCE/ Million Btu) (e) Transport Energy CO2 Emissions (MTCE/Ton) (=b x c) (g) Total Transport Energy Emissions (MTCE/Ton) (=e + f) 50% 0.0176 0.0199 0.0003 0.0004 50% 0.0176 0.0158 0.0003 0.0003 100% 0.0352 0.0357 0.0006 0.0007 CO2 emission by Recycling aggregate Based on the table 4.16, CO2 emission by recycling the wasted aggregate is about 0.6 g for 1 kg aggregate. So that the amount is as following: 148.428 ton * 0.0006 MTCE/ton = 0.089 MTCE~ 89 kg (project 1) 36.540 ton * 0.0006 MTCE/ton = 0.021 MTCE ~ 21 kg (project 2) 36 ton * 0.0006 MTCE/ton = 0.0216 MTCE = 21.6 kg (project 3) CO2 emissions by transportation of recycle aggregate: Based on the table 4.17, CO2 emission by transporting recycling the wasted aggregate is about 1.9 g for 1 kg aggregate. So that the amount is as following: ` 72 Table 4.17: Transportation Energy Emissions Calculations for Recycled Aggregate(EIA2001) (a) Fuel Type Percent of Total Btu (b) Million Btu used for Aggregate Production (=0.0935 x a) (c) Fuel-specific Carbon Coefficient (MTCE/ Million Btu) (e) Transport Energy CO2 Emissions (MTCE/Ton) (=b x c) (g) Total Transport Process Energy Emissions (MTCE/Ton) (=e + f) Diesel Fuel 100% 0.0935 0.0199 0.0019 0.0019 Total 100% 0.0935 n/a 0.0019 0.0019 Project 1 148.428 ton * 0.0019 MTCE/ton = 0.282 MTCE ~ 282 kg So the total amount of CO2 emission by transportation and recycling aggregate is as following: 282 kg + 89 kg = 371 kg Project 2 36.540 ton * 0.0019 MTCE/ton = 0.069 MTCE ~ 70 kg Total amount of CO2 emission by transportation and recycling aggregate: 70 kg + 21 kg = 91 kg Project 3 36 ton * 0.0019 MTCE/ton = 0.068400 g ~ 68.4 kg Total amount of CO2 emission by transportation and recycling aggregate: 68.4 kg + 21.6 kg = 90 kg ` 73 The above calculations show the benefit of recycling of concrete waste to displace virgin aggregate by comparing the emission of both virgin aggregate production and recycling aggregate. In these comparison transportation also included which assumed 30 miles for virgin aggregate and 15 miles for recycled aggregate. There are 3 tables for 3 different construction sites. Based on the table 4.18, construction no 1 by 84m3 concrete waste need 7.6GJ embodied energy to produce this amount of aggregate as a virgin aggregate but if this amount of aggregate after the waste tried to be recycle, it seems by 5.5 GJ embodied energy has reasonable amount compared to produce it from virgin. Table 4.19 and table 4.20 show that Construction No 2 and No 3 which are almost the same by 1.86GJ embodied energy for production of virgin aggregate and 1.35 GJ for recycling process, because they have the same wastage (level of 20m3).For the energy consumed by transportation factor, as shown in table 4.18 the recycling has more benefits with two times more saving than producing. Tables 4.19 and table 4.20 also show the same finding in which 2.3 GJ energy consumed for transportation of aggregate to the place while another 1.17GJ was for recycling. It also the same for the CO2 emission by transportation where it produced approximately 1.5 to 2 time more saving in CO2 emission. ` 74 Table4.18: Comparing recycling and virgin aggregate (84m3) Wastage for project 1 Energy emission by Virgin aggregate Recycle aggregate 7.6 GJ 5.5 GJ 9.5 GJ 4.77 GJ 132.5 kg 89 kg 545.5 kg 282 kg Production Energy emission by Transportation CO2 emission by production CO2 emission by Transportation ` 75 Table4.19: Comparing recycling and virgin aggregate (20m3) Wastage for project 2 Energy emission by Virgin aggregate Recycle aggregate 1.86 GJ 1.35 GJ 2.3 GJ 1.17 GJ 32.6 kg 21 kg 134 kg 70 kg Production Energy emission by Transportation CO2 emission by production CO2 emission by Transportation ` 76 Table 4.20: Comparing recycling and virgin aggregate (20m3) Wastage for project 3 Virgin aggregate Recycle aggregate Energy emission by 1.84 GJ 1.33 GJ 2.32 GJ 1.16 GJ 32 kg 21.16 kg 132 kg 68.4 kg Production Energy emission by Transportation CO2 emission by production CO2 emission by Transportation ` 77 18 16 14 12 10 8 6 4 2 0 Energyemissionby Production Energyemissionby Transportation Total(GJ/M3) Figure 4.1: Energy comparisons between Virgin and Recycled Aggregate 1600 1400 1200 1000 800 Total(kg/M3) 600 400 200 0 CO2emissionby Transportation CO2emissionby production Figure 4.2: CO2 emissions between Virgin and Recycled aggregate ` 78 4.11.2 Land filling Typically, the emission factor for land filling is comprised of four parts: landfill CH4, CO2 emissions from transportation and landfill equipment operation, landfill carbon storage, and avoided utility emissions. However, as with other inorganic materials for which EPA has developed emission factors, there are no CH4 emissions, or avoided utility emissions associated with land filling concrete. Studies have indicated that over time, the cement portion of concrete is capable of absorbing CO2. (Gadja, John 2001) .based on the CO2 emission which occur by the time elapsing after concrete land filling, it could be difficult to obtain the data for this impaction so that, these emissions were estimated at 0.01 MTCE per ton of concrete land filled( Landfill data obtained from FAL 1994). based on the same underlying data that was used for other materials in the EPA 2002 report. Project 1 84 m3 (total waste concrete) = 2.3 ton 2.3 ton * 0.01 MTCE = 0.023 MTCE 0.023 MTCE * 84 m3 = 1932 kg The total emission is 1932 kg Project 2 20 m3 (total waste concrete) = 2.3 ton 0.023 MTCE * 20 m3 = 460 kg Project 3 20 m3 (total waste concrete) = 2.3 ton 0.023 MTCE * 20 m3 = 460 kg ` 79 CHAPTER V CONCLUSION 5.1 Introduction This chapter is intended to give an overall conclusion of this study. The aim and objectives of this study which established earlier would be confirmed in this chapter by reviewing the information gathered through the literature review and questionnaire survey. None the less, there are some recommendation are given to readers for further research and reading. 5.2 Conclusion This study shows that it is the raw material production (concerning GWP) together with the transportation operations and concrete plant operations that are the ` 80 main contributors to the environmental impact of concrete .In concrete; cement is the most energy intensive of all the materials used. Even though it only makes up about 10 to 20 percent of an entire concrete mixture, it is responsible for up to 70 percent of the total embodied energy and 95% of the carbon dioxide emissions of concrete. Cement is the most energy intensive, and therefore has the greatest environmental impact, of the constituent materials of concrete. However, cement only represents 10% to 15% of the total mass of concrete. Based on the finding in recycling and producing virgin aggregate, it shows that Recycling of wasted concrete can be useful by 1.5 to 2 times more saving energy and CO2 emission than producing virgin aggregate 5.3 Recommendation for future research Although land filling is the easiest and safe way to release the wasted concrete, it has considerable disadvantage which appear long years after land filling. Based on the limited time for doing this research, the finding due to land filling is not sufficient based on the following reason: 5.3.1 Concrete Reabsorbs CO2 During the life of a concrete structure, the concrete carbonates and absorbs the CO2 released by calcinations during the cement manufacturing process. Once concrete ` 81 has returned to fine particles, full carbonation occurs, and all the CO2 released by calcinations is reabsorbed. A recent study indicates that in countries with the most favorable recycling practices, it is realistic to assume that approximately 86% of the concrete is carbonated after 100 years. During this time, the concrete will absorb approximately 57% of the CO2 emitted during the original calcinations. About 50% of the CO2 is absorbed within a short time after concrete is crushed during recycling operations. ` 82 References Asian Development Bank, Institute for Global Environmental Strategies and United Nations Environment Programme. (2006). Synthesis Report of 3R South Asia Expert Workshop Katmandu, Nepal. Asian Development Bank and the Clean Air Initiative for Asian Cities (CAI-Asia) Center. (2006).Country Synthesis Report on Urban Air Quality Management: Vietnam. ADB: Philippines. Burström P. G., 2001, Byggnadsmaterial Uppbyggnad, tillverkning och egenskaper, Chapter 12, Studentlitteratur, Lund Begum, R., Siwar C., Pereira J., and Jaafar A. H. (2006). A benefit–cost analysis on the economic feasibility of construction waste minimisation: The case of Malaysia. Resources, Conservation and Recycling, Elsevier Science Ltd. Volume 48, Issue 1, pp. 86-98. Björklund T. & Tillman A-M., 1997, LCA of Building Frame Structures Environmental Impact over the Life Cycle of Wooden and Concrete Frames, Technical Environmental Planning Report 1997:2 Chalmers University of Technology, Uppsala Chung, J.K.O. (2000), Monitoring of solid waste in Hong Kong 1998, Environment Protection Department, Hong Kong Government. EFCA, Environmental Declaration Superplasticizing Admixtures, 2002, European Federation of Concrete Admixture Associations, URL: http://www.admixtures.org.uk/downloads/xIS%Environmental%Declaration%20Supe plasticizer. ` 83 EIA 2001. Annual Energy Review: 2000, U. S. Department of Energy, EIA. August 2001. EPA 1998. Greenhouse Gas Emissions from Management of Selected Materials in Municipal Solid Waste, U.S. Environmental Protection Agency, Office of Solid Waste. Franklin Associates. US EPA (1998). Characterization of Building-related Construction and Demolition debris in the United States. Retrieved date: March 13, 2007. Website: http://www.epa.gov/epaoswer/hazwaste/sqg/c&d-rpt.pdf. Franklin Associates. US EPA (1998). Characterization of Building-related Construction and Demolition debris in the United States. Retrieved date: March 13, 2007. Website: http://www.epa.gov/epaoswer/hazwaste/sqg/c&d-rpt.pdf. Gadja, John 2001. “Absorption of Atmospheric Carbon Dioxide by Portland Cement Concrete,” Portland Cement Association, Skokie, Illinois, PCA R & D Serial No. 2255a Gavilan, R.M. and Bernold, L.E. (1994), Source Evaluation of Solid Waste in Building Construction, Journal of Construction Engineering and Management 120, 536-552. Graham, P. (2003). Building Ecology: First Principles for a Sustainable built Environment. UK:Blackwell Science Ltd. Guthrie, P., Woolveridge, A.C. and Patel, V.S. (1999), Waste minimization in construction: site guide, London: Construction Industry Research and Information Association. Humphreys, K., and M. Mahasenan. 2002, March. Substudy 8:Climate Change—oward a Sustainable Cement Industry. An Independent Study Commissioned by the World Business Council for Sustainable Development (WBCSD) ` 84 Jeannette Sjunnesson,2005 Life Cycle Assessment of Concrete, Master thesis Johansson S-E., 1994, Cement in Betonghandbok Material, Ed ited by Ljungkrantz, Möller & Petersons, AB Svensk byggtjänst, Solna Kulatanga, U., Amaratunga, D., Haigh, R. and Rameezden, R. (2006). Attitudes and perceptions of construction workforce on construction waste in Sri Lanka. Management of Environmental Quality: An International Journal. Emerald Group Publishing Ltd., United Kingdom. Vol. 17, No. 1, pp. 57-72. Lau,H.H. et al.(2008). Composition and Characteristics of Construction Waste Generated by Residential Housing Project,Internayional journal of environmental research. Li et. al (2004). Recycling concrete—an overview of development and challenges. DEMEX Consulting Engineers A/S, Denmark. Fourth International RILEM Conference on the Use of recycled Materials in Buildings and Structures, Barcelona, Spain Lippiat, B. (2000). BEES 1.0. Building for Environmental and Economic Sustainability. NISTIR 6144. U.S. Department of Commerce. Medgar, L. M., M. A. Nisbet, and M. G. Van Geem. 2006. “Life Cycle Inventory of Portland Cement Manufacture.” PCA R&D Serial No. 2095b, prepared for the Portland Cement Association (PCA), Skokie, Illinois Medgar, L. M., M. A. Nisbet, and M. G. Van Geem. 2007. “Life Cycle Inventory of Portland Cement Concrete.” PCA R&D Serial No. 3011, prepared for the Portland Cement Association (PCA), Skokie, Illinois. Mehta, P. K. 1998. The role of fly ash in sustainable development. Concrete, Fly Ash and the Environment Proceedings, December 8, 1998. pp. 13–25. ` 85 Mehta, P. K. 2002. “Greening of the Concrete Industry for Sustainable Development,” Concrete International, Vol. 24, No. 7, July 2002, pp. 23–28. Mills, T.M., Showalter, E. and Jarman, D. (1999), A cost-effective waste management plan, Cost Engineering, 35-43 NTM – Nätverket för Transporter och Miljön, [2005-05-13] www.ntm.a.se Ofori, G., Briffett, C., Gang, G. and Ranasinghe, M. (2000). Impact of ISO 14000 on construction enterprises in Singapore. Construction Management and Economics. 18, pp. 935–947 Pappu, A., Saxena, M. and Asolekar, S. (2006). Solid wastes generation in India and their recycling potential in building materials. Building and Environment, Volume 42, Issue 6, pp. 2311-2320. PCA, U.S. and Canadian Labor-Energy Input Survey 2003, Portland cement association, Skokie, Illinois, USA, 2005, 46 pages. Poon, C.S., Yu, T.W. and Ng, L.H. (2001a), A Guide for Managing and Minimizing Building and Demolition Waste, The Hong Kong Polytechnic University. Poon, C.S., Yu, A; Wong, S. and Cheung, E. (2004). Management of construction waste in public housing projects in Hong Kong. Construction Management and Economics. UK: Taylor and Francis Ltd. 22:7, pp. 675 – 689. Portland Cement Association (PCA). “Concrete Thinking for a Sustainable World.” Skokie, IL: Portland Cement Association. http://www.cement.org/concretethinking/ (accessed April 14, 2006). ` 86 Rogoff, M. J. and Williams, J. F. (1994), Approaches to implementing solid waste recycling facilities, Noyes, Park Ridge, NJ. Rydh C. J., Lindahl M. & Tingström J., 2002, Livscykelanalys –en metod för miljöbedömning av produkter och tjänster, Studentlitteratur, Lund Stripple H., 2001, Life Cycle Assessment of Road –A Pilot Study for Inventory Analysis, p.48, 2nd revised Edition, IVL-report B1210E, March URL: 2001, Gothenburg, Sweden http://www.ivl.se/rapporter/pdf/B1210E.pdf Skoyles, E.R. and Skoyles, J.R. (1987), Waste prevention on site, London: Mitchell. Shen, L. Y., Tam, W. Y. Vivian, Chan, C. W. Steven and Kong, S. Y. Joseph (2002), “An examination on the waste Management practice in the local construction site”, Hong Kong Surveyor 13(1), 39-48. Snook, K., Turner, A. and Ridout, R. (1995), Recycling waste from the construction site, England: Chartered Institute of Building. Tam, V. and Tam, C. (2005). A review on the viable technology for construction waste recycling. Resources, Conservation and Recycling. Elsevier Science Ltd. UK. U.S. Geological Survey (USGS). 2007. “Cement.” In 2005 Minerals Yearbook. Washington, DC: USGS. USGS 2000. “Recycled Aggregates—Profitable Resource Conservation.” USGS Fact Sheet FS–181–99 Vold M. & Rønning A., 1995, LCA of Cement and Concrete –Main report OR 32.95 Stiftelsen Østfoldforskning, Fredriksstad, Norway ` 87 U.S. EPA 2002a. Solid Waste Management and Greenhouse Gases: A Life-Cycle Assessment of Emissions and Sinks, U.S. Environmental Protection Agency, June 2002. EPA530-R-02-006. Wilburn and Goonan 1998, “Aggregates from natural and recycled “U.S. Geological Survey ` 88 APPENDIX A Calculations and LCI data for cement production The amounts of the various ingredients utilized in cement production have been collected from Cement AB’s report. The three main ingredients are limestone, sand and gypsum. Information used in calculations for LCI data for cement production is presented below. Table A.1 Main ingredients for the production of 1 Kg Cement Lime stone 1.4 Kg Sand 70 g Gypsum 30 g The impact of sand production is the same as that of gravel production (Table A.4). Fuels used in the production of cement are coal and coke. The emissions from the use of these fuels are presented as a total sum in the production of the cement (Table A.2) at the factory. Emissions from the production and distribution of these fuels are calculated separately and both coal and coke are regarded as coal (Table A.2). Transports of the raw material to the location of cement production are not taken into consideration since most of the raw materials are usually situated in the vicinity of the cement production facility. LCI data for cement production is presented in Table A.2 ` 89 Table A.2 LCI data for the production of 1 kg cement Limestone Sand Gypsum Production of cement Total Energy Coal 2.89E-06 Oil 3.14E-05 1.88 3.14E-05 Coke 0.50 Natural gas 6.73E-07 Peat Diesel Biofuel 0.506 6.73E-07 3.26E-07 0.0249 1.88 3.26E-07 5.01E-04 0.0254 3.26E-06 3.26E-06 Car tyres 0.416 0.416 Bone meal 0.0109 0.0109 0.432 0.478 704 714 Electricity 0.0458 7.23E-05 2.26 0.00220 4.80E-04 Emissions to air (g) CO2 ` 0.0394 90 Table A.3 LCI data for the production of 1 kg gypsum Unit Material use Explosives g 0.2 Gypsum kg 1 Energy use Electricity MJ 1.59E-02 Diesel MJ 1.66E-02 CO g 4.98E-03 CO2 g 1.31E+00 HC g 3.45E-03 NOx g 2.26E-02 Particles g 1.67E-03 g 2.56E-03 Emissions to air SO2 ` 91 Table A.4 LCI data for the production of 1 kg gravel (sand)(StrippleStripple, 2001) UNIT Energy Biomass fuel MJ 1.08E-04 Oil MJ 0.00104 Peat MJ Coal MJ 9.59E-05 Natural gas MJ 2.23E-05 Uranium MJ 0.00348 Hydropower MJ 0.00113 Electricity MJ 0.0024 CO2 g 0.0728 SO2 mg 0.0467 NOx mg 0.597 Dust mg 0.0231 CO mg 0.0736 HC mg 0.044 CH4 mg 0.376 1.08E-05 Emissions to air ` 92 Table A.5 LCI data for the production of 1 kg chemical admixture Unit load Raw Material crude oil (feedstock) kg 0.091 natural gas (feedstock) kg 1E-04 water kg 7.4 Energy Coal MJ 1.7 Crude oil MJ 3.2 Natural gas MJ 8.2 Electricity MJ 2.9 CO2 kg 0.69 CO g 2.1 HC g 2.2 CH4 g 1.2 Methanol g 1.1 NOx g 3.5 SOx g 6.6 Emissions to air Calculations and LCI data for concrete mixing In the fabrication of concrete only electricity is used, 32.7 MJ/m3, while oil is used for heating the plant, 1.5E-05 MJ/m3 concrete.83 Information used in calculations for LCI data for concrete mixing is presented below. Oil Energy content of oil: 39 GJ/m3 (average) ` 93 Emissions for oil production, distribution and usage are taken from Table B.1. Electricity, Swedish average Emissions for electricity production are taken from Table B.1. Table B.1 LCI data for the mixing of 1 m3 of concrete Unit Energy Oil MJ 1.51E-05 Electricity MJ 32.7 Emissions to air ` NOx g 0.491 SOx g 0.426 CO g 0.589 HC g 0.0949 CO2 kg 0.256 CH4 g 1.6 NH3 g 0.0072 94 LCI data for Transports B.3 the transportation vehicles used in the study is heavy trailers Heavy trailer Unit total weight ton 60 total load ton 40 Diesel Mk1 l/10km 4.9 MJ/tkm 0.6 % 70 Energy demand (fossil) Load capacity Emissions to air per tkm CO2 g 48 CO g 0.045 B.4 the transportation vehicles used in the study is medium heavy trailers Medium Heavy Trailer Unit total weight ton 24 total load ton 14 Diesel Mk1 l/10km 3.5 MJ/tkm 1.9 % 70 CO2 g 0.14 CO g 0.13 Energy demand (fossil) Load capacity Emissions to air per tkm ` 95 B.5 Process Energy Emissions Calculations for Virgin Aggregate (U.S.EIA,2001) (a) Fuel Type Percent of Total a Btu (c) Fuel-specific Carbon Coefficient (MTCE/ b (e) Process Energy CO2 Emissions (MTCE/Ton) (=b x c) Million Btu) (g) Total Process Energy Emissions (MTCE/Ton) (=e + f) Gasoline 3.16 0.0015 0.0192 <0.0001 <0.0001 Distillate Fuel 60.42 0.0293 0.0214 0.0006 0.0006 Residual Fuel 5.68 0.0028 0.0214 0.0001 0.0001 0.0110 0.0158 0.0002 0.0002 0.0007 0.0251 <0.0001 6.74 0.0033 0.0138 <0.0001 <0.0001 100 0.0486 n/a 0.0009 0.0009 National Avera Fuel Mix for 22.61 Electricity Coal Used by 1.40 Industry (NonCoking Coal) Natural Gas Total ` (b) Million Btu used for Aggregate Production (=0.0352 x a) 96 A Appendix B Faculty F of civil c engineeering University U T Technology of Malaysiaa Skud dai,Johor PRIV VATE AND COFIDEN NTIAL SUR RVEY QUE ESTIONNA AIRE R RESEARCH H TITLE: Energ gy and CO22 Emission Evaluation E of Concretee Waste OBJECTIV VE: i. To determine d the amount off concrete waaste in construction sites ii. To estimate e the amount of energy useed and CO2 emission for f productioon of concrete P PROFILE OF O STUDENT: N Name: Pooriia Rashvandd C Course: Masster in Consttruction Mannagement S Supervisor: Dr D Khairulzaan E Email: poory ya_rashvandd@yahoo.com m H H/phone: 0177804523 ` ` 97 All data compiled are solely for academic purposes would really appreciate if you could complete the questionnaire within 5 days. I shall collect back the questionnaire once completed. Thank you for your cooperation and interest in making this research success. Section A This section aims to obtain information on the background of the respondent. Profile of respondent: Name of company Company stamp Designation Type of construction: Concrete frame design Steel frame design ` 98 Section B The question will refer to amount of concrete which ordered. Different order for concrete: Beams: Density (kg/m3) Grade: Cumulative quantity of ordering (m3) Cumulative work done (m3) Columns: Density: Grade: Cumulative quantity of ordering (m3) Cumulative work done (m3) Slab: Density: Grade: Cumulative quantity of ordering (m3) ` Cumulative work done (m3) 99 Section C Design mix Density: Ingredients in terms of percentage or Kg for 1m3 Percentage % Ingredients Aggregate Fine aggregate Sand Rock Coarse aggregate Gravel Cement Aggregate Water Admixtures Mineral admixtures Slag Fly ash Silica fume Chemical admixtures Super plasticizer ` Weight(kg)