DESIGN PHASE CONSTRUCTABILITY CONCEPTS IN HIGHWAY PROJECTS SITI HAFIZAN BINTI HASSAN A project report submitted in partial fulfilment of the requirements for the award of the degree of Master of Science (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia NOVEMBER 2005 ii ii iii To my beloved mother and father, my families, my lecturers, my friends and my special friend…..Thanks for the everlasting love and supports….. iv ACKNOWLEDGEMENTS First and foremost, grateful thanks to Allah S.W.T for guiding and helping me in this dissertation. Giving me chances in a way to complete it. I would like to extend my deepest appreciation and thanks to my supervisor, Ir. Dr. Rosli Mohamad Zin for his continuous guidance and encouragement in the effort to complete this thesis. I would also like to thank to all the engineers and architects who participated in the questionnaires survey and field interviews and also to those who were involved directly or indirectly in the completion of this project. Last but not least is my appreciation and gratitude to my mum, Puan Wan Fatimah, my dad, Encik Hassan, my brother, Encik Abdul Aziz, my families, my friends, Idris, Nik Zilazmi, Fareh, Roslina, Lenny, Aiza and Hasnizar for their understanding, support and encouragement. v ABSTRACT Nowadays, highway construction projects suffer from lack of constructability, which causes many problems; traffic, substantial number of changes, poor planning, disputes, cost overruns, poor safety practices and time delays. Some researchers have realized the seriousness of this shortfall and have suggested solutions to resolve it. Previous studies indicate that, overall constructability is not being implemented to its full potential in highway sector. So, this study tries to explore constructability implementation in the local construction industry particularly the highway sector. The aim of the study is to establish guideline that can be used by engineers in order to improve constructability of highway project design. The findings of the study shows there were eighteen design phase constructability concepts that are ‘very important’ and ‘important’ in highway sector. For the level of application, it was found that most of the concepts are in ‘medium application’. It can be concluded that the engineers have the constructability knowledge but lack of understanding of the concepts. Based on the survey exercise, a guideline has been developed consisting of two parts which are ‘very important’ and ‘important’. It is expected that by having this guideline, engineers will be able to apply this concepts effectively in highway project design in Malaysia. vi ABSTRAK Kesan daripada kurangnya aplikasi kebolehbinaan dalam pembinaan jalanraya pada masa kini telah menyebabkan berlakunya banyak masalah dalam pembinaan seperti lalulintas, perubahan rekabentuk, perancangan yang lemah, pertikaian, kos projek yang melebihi nilai projek sebenar, sistem keselamatan yang lemah, serta kelewatan masa penyiapan projek itu sendiri. Para penyelidik telah mengenalpasti betapa seriusnya masalah ini dan telah mencadangkan beberapa penyelesaian dalam menyelesaikannya. Kajian terdahulu menunjukkan bahawa keseluruhan kebolehbinaan ini tidak dilaksanakan secara sepenuhnya di dalam projek jalanraya. Maka, kajian ini cuba meninjau perlaksanaan kebolehbinaan ini di dalam projek pembinaan jalanraya setempat. Matlamat kajian ini adalah untuk menghasilkan satu garis panduan agar boleh digunakan oleh para jurutera dalam usaha untuk mempertingkatkan lagi penggunaan kebolehbinaan dalam fasa rekabentuk di dalam projek jalanraya. Hasil daripada kajian ini menunjukkan bahawa lapan belas konsep kebolehbinaan yang dikaji adalah ‘sangat penting’ dan ‘penting’ dalam projek jalanraya. Dari segi tahap penggunaan konsep ini pula, didapati bahawa semua lapan belas konsep yang dikaji di bawah kedudukan ‘penggunaan pertengahan’. Dapat disimpulkan bahawa jurutera di Malaysia mempunyai pengetahuan mengenai kebolehbinaan ini, tetapi kurangnya pemahaman dari segi konsep-konsepnya. Berdasarkan pemerhatian kajian yang dijalankan, garis panduan telah dibentuk di mana ia mengandungi dua bahagian iaitu ‘sangat penting’ dan ‘penting’. Adalah dijangkakan bahawa dengan adanya garis panduan ini, jurutera boleh mengaplikasikan konsep-konsep ini secara berkesan di dalam rekabentuk projek-projek jalanraya di Malaysia. vii TABLE OF CONTENT CHAPTER TITLE PAGE THESIS TITLE i DECLARATION SHEET ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLES xi LIST OF FIGURES xiv LIST OF APPENDIX xvi 1 INTRODUCTION 1 1.1 Introduction 1 1.2 Problem Statement 3 1.3 Aim and Objectives of the Study 4 1.4 Scope of Research 4 1.5 Research Methodology 4 viii 2 LITERATURE REVIEW 6 2.1 Constructability Definitions 6 2.2 General Overview Constructability in 7 Highway Project 2.3 2.2.1 Government Agency Observations 8 2.2.2 Design Firm Observations 11 2.2.3 Construction Firm Observations 14 Constructability in the Highway 14 Construction Project Process 2.3.1 Feasibility Design Stages 16 2.3.2 Design Stages 17 2.3.3 Construction 18 2.3.4 Operation 18 2.4 Maximum Benefit of Constructability 19 2.5 Constructability Concepts in Highway Projects 22 2.6 Design Phase Constructability Concepts 32 2.6.1 Carry Out Thorough Investigation of the Site 34 2.6.2 Design for Minimum Time Below Ground 36 2.6.3 Design for Simple Assembly 39 2.6.4 Encourage Standardisation/Repetition 40 2.6.5 Design for Preassembly or Modularisation 40 2.6.6 Analyse Accessibility of the Jobsite 41 2.6.7 Employ Any Visualisation Tools 42 to Avoid Physical Interference 2.6.8 Investigate Any Unsuspected Unrealistic 42 or Incompatible Tolerances 2.6.9 Investigate the Practical Sequence of 43 Construction 2.6.10 Plan to Avoid Damage to Work by Subsequent Operations 43 ix 2.6.11 Consider Storage Requirement at 43 the Jobsite 2.6.12 Investigate the Impacts of Design on 44 Safety during Construction 2.6.13 Design to Avoid Return Visit by Trade 45 2.6.14 Design for the Skills and Resources 45 Available 2.6.15 Consider Suitability of Designed Materials 46 2.6.16 Provide Detail and Clear Information 45 2.6.17 Design for Early Enclosure 46 2.6.18 Consider Weather Effect in Selecting Materials or Construction Methods 2.7 3 48 RESEARCH METHODOLOGY 3.1 Introduction 50 3.2 Research Process 50 3.3 Determining the Research Objectives 51 3.4 Steps in Methodology 52 3.4.1 Conceptualization 52 3.4.2 Literature Review 53 3.4.3 Questionnaire 53 3.4.4 Analysis 56 Development of Guidelines 57 3.5 4 Summary 47 DATA ANALYSIS AND DISCUSSION 4.1 Introduction 58 4.2 Respondent’s Background 59 4.2.1 Type of Organization 59 4.2.2 Level of Education 60 x 4.3 4.4 4.5 4.2.3 Field of Specialization 61 4.2.4 Position in Organization 62 4.2.5 Numbers of Years Practiced in Designing 63 4.2.6 Numbers of Years Practiced in Working 64 Level of Importance 66 4.3.1 Frequency Analysis 66 4.3.2 Average Index Analysis 77 Level of Application 81 4.3.3 Frequency Analysis 81 4.3.4 Average Index Analysis 91 The Development of Design Phase 95 Constructability Improvement Concepts 4.6 5 Discussion 99 CONCLUSION AND RECOMMENDATIONS 5.1 5.2 Conclusion 100 5.1.1 Objective 1 100 5.1.2 Objective 2 104 5.1.3 Objective 3 105 Recommendations 105 REFERENCES 107 APPENDIX 110 xi LIST OF TABLES TABLE NO. TITLE PAGE 4.1 Type of Organization 59 4.2 Level of Education 61 4.3 Field Of Specialization 62 4.4 Position in Organization 63 4.5 Number of Years Practiced in Designing in 64 Highway Projects 4.6 Number of Years Practiced in Working in 65 Highway Projects 4.7 Carry out Thorough Investigation of the Site 66 4.8 Provide Detail and Clear Design Information 67 4.9 Analyze Accessibility of the Jobsite 67 4.10 Investigate the Impacts of Design on Safety 68 during Construction 4.11 Consider Suitability of Designed Materials 69 4.12 Investigate the Practical Sequence of Construction 69 4.13 Consider Adverse Weather Effect in Selecting Materials 70 or Construction Methods 4.14 Plan to Avoid Damage to Work by Subsequent 71 Operations 4.15 Investigate Any Unsuspected Unrealistic or 71 xii Incompatible Tolerances 4.16 Designs for the Skills and Resources Available 72 4.17 Consider Storage Requirement at the Jobsite 72 4.18 Design for Minimum Time below Ground 73 4.19 Design for Early Enclosure 73 4.20 Encourage Standardization/Repetition 74 4.21 Employ Any Visualization Tools to Avoid 74 Physical Interference 4.22 Design for Simply Assembly 75 4.23 Design to Avoid Return Visit by Trade 76 4.24 Design for Preassembly and/or Modularization 76 4.25 Average Index Value for Degree of Importance of 79 Constructability Concepts during the Design Phase 4.26 Carry Out Thorough Investigation of the Site 81 4.27 Employ Any Visualization Tools to Avoid 82 Physical Interference 4.28 Encourage Standardization/Repetition 82 4.29 Consider Storage Requirement at the Jobsite 83 4.30 Design for Minimum Time below Ground 83 4.31 Investigate the Practical Sequence of Construction 84 4.32 Design for Simply Assembly 84 4.33 Design for the Skills and Resources Available 85 4.34 Investigate the Impacts of Design on Safety during 86 Construction 4.35 Analyze Accessibility of the Jobsite 86 4.36 Design For Preassembly and/or Modularization 87 4.37 Investigate Any Unsuspected Unrealistic or 87 Incompatible Tolerances 4.38 Design to Avoid Return Visit by Trade 88 4.39 Design for Early Enclosure 88 4.40 Provide Detail and Clear Design Information 89 xiii 4.41 Plan to Avoid Damage to Work by Subsequent 89 Operations 4.42 Consider Suitability of Designed Materials 90 4.43 Consider Adverse Weather Effect in Selecting Materials 90 or Construction Methods 4.44 Average Index Value for Degree of Application of Constructability Concepts during the Design Phase 93 xiv LIST OF FIGURES FIGURE NO. TITLE PAGE 1.1 Research Methodology Chart 5 2.1 The Highway Construction Project Process 16 2.2 Project Life Cycle and Designers Level of Influence 20 2.3 Ability to Influence Final Cost Over Project Life 21 2.4 Process of launching girder for elevated structure 35 2.5 Problems faced during launching of some girders 35 2.6 Details of elevated highway 37 2.7 Problem of compaction and result after 38 project start-up 3.1 Steps in Methodology 52 3.2 Questionnaire Flow Chart 55 4.1 Percentage of type of organization 60 4.2 Percentage of level of education 61 4.3 Percentage of field of specialization 62 4.4 Percentage of Position in Organization 63 4.5 Percentage of Number of Years Practiced in 64 Designing In Highway Projects 4.6 Number of Years Practiced in Working in 65 Highway Projects 4.7 Degree of Importance of Constructability Concepts 80 xv 4.8 Degree of Application of Constructability Concepts 94 4.9 Design Phase Constructability Improvement Concepts 96 For Malaysian Highway Projects xvi LIST OF APPENDIX APPENDIX A TITLE Questionnaire Form PAGE 110 CHAPTER 1 INTRODUCTION 1.1 Introduction Government and private agencies that carried out highway construction project are facing the reality that the public will no longer tolerate construction projects that are insensitive to road users and adjacent communities. According to Russell et al. (1993), highway construction projects are characterized by traffic problems, changes of design, poor planning, disputes, cost overruns, poor safety practices and time delays. Constructability is seen as one of the best solutions to these problems where it has demonstrated the potential to minimize the number and magnitude of changes, disputes, cost overruns, and delays during construction. Constructability has been defined in a number of ways. Constructability is described as the optimum use of construction knowledge and experience in planning, design, procurement, and field operations to achieve overall project objectives (Constructability, 1986). Constructability is also defined as a measure of the ease or expediency with which a facility can be constructed (Hugo et al., 1990). Lastly, constructability is often portrayed as integrating construction knowledge, resources, 2 technology and experience into the engineering and design of a project (Anderson et al., 1995). Highway project constructability can be particularly demanding for a range of reasons. For example, some of the highway construction technologies are varying hastily, and, as with most construction, the personnel is transient and site conditions can vary to the highest degree. Nearly all projects are subjected to severe public scrutiny involving open competitive bidding, thereby separating the planning and execution phases and largely precluding a fast-tracked approach to construction. Designs standards, authored by a multitude of organizations abound and often limit, if not discourage selective innovation. The prerequisite for nonproprietary specifications often leads to vagueness. In general, the perception is that project durations are longer than necessary and that construction costs can possibly be lowered. As a result, specifications supportive of constructability become an important element for improving project performance (Hugo et al., 1990). Beside the project performance, constructability also has been successfully used to reduce project durations. Eldin (1996) provides several examples of projects that have successfully used constructability to reduce project durations without increasing project cost. In a CII (1995) study five projects were analyzed, reporting 11 to 30% reductions in project duration directly attributed to constructability reviews (i.e., without cost increases). Although the majority of the projects were associated with industrial facilities, one of them was an interstate highway realignment that included the reconfiguration of eight bridges and the construction of two new bridges to facilitate the addition of a high occupancy vehicle lane in each direction (Eldin, 1996). Constructability review is the phase of construction project management where an independent and detailed analysis of all the contract drawings and construction documents is conducted before their release for construction. An effective constructability review process has the potential to incorporate into design 3 documents the best practices, guidelines, checklist, and lessons learned from previous projects, thereby improving the ease of construction and reducing life cycle costs. This critical process evaluates the “ability to construct” your construction project (Milstead, 1997). Constructability reviews of highway projects during design have the potential to minimize the number and magnitude of changes and delays during construction and thereby reduce durations (Anderson and Fisher 1997). A constructability analysis of six highway projects suggests that benefits may be as large as 25 times greater as costs (Anderson and Fisher 1997). Improved processes and management for effectively using constructability reviews to reduce total project durations can potentially improve construction project management. The way how to provide the best constructability review is by improving the understanding of application and importance of constructability concepts in highway projects. 1.2 Problem Statement Nowadays, highway construction suffers from lack of constructability, which causes traffic problems, changes of design, poor planning, disputes, cost overruns, poor safety practices and time delays. Researchers in developed countries have realized the seriousness of this shortfall and suggested solutions to resolve it. In Malaysia, research in constructability in highway projects has not been popular researched yet. One of the reasons is due to lack of understanding of constructability concepts among the engineers. Design Phase Constructability Improvement Concepts for Malaysian Highway Projects should be developed, that are aimed at encouraging the project team to apply them, where appropriate, to their projects. The basic message is that applying these constructability concepts will enhance project’s constructability, consequently optimizing the schedule, cost and quality of the project for the benefit of all parties involved. 4 1.3 Aim and Objectives of The Study The aim of this study is to establish Design Phase Constructability Guidelines For Highway Projects in Malaysian Construction Industry. In order to achieve it, the following objectives have been identified: a) To identify the constructability concepts in highway projects. b) To identify the level of importance and application of constructability concepts in highway projects. c) To establish Design Phase Constructability Improvement Guidelines for highway projects. 1.4 Scope of Research This research was carried out by questionnaires and interviews. The research focused on Malaysian Highway Projects with contract values of more than RM 5 million. The questionnaires were distributed to the senior construction management team like engineers, architect or project manager and etc, who involved in highway projects. 1.5 Research Methodology The methodology of research were help to realize the essential stages of methodology performed or steps of process carried in order to achieve the objectives 5 of this research. Figure 1.1 shows the research methodology chart that has been used in this research. CONCEPTUALIZATION • Phase 1 Design phase constructability concepts in highway projects LITERATURE REVIEW QUESTIONNAIRE SURVEYS • • DATA ANALYSIS Phase 2 Level of importance and application of constructability concepts Design Phase Constructability Improvement Guidelines for highway projects. CONCLUSION/ RECOMMENDATION Figure 1.1 Research Methodology Chart CHAPTER 2 LITERATURE REVIEW 2.1 Constructability Definitions The Construction Industry Institute “CII”, a national construction-research consortium, gives the following definition (“Constructability” 1986), quoted by the ASCE Committee on Construction and Management (1987), O’Connor et al. (1988) and O’Connor et al. (1993): “Constructability is the optimum use of construction knowledge and experience in the planning, engineering, procurement and field operations to achieve overall project objectives.” Eldin (1988) states that “Constructability is the integration of construction knowledge into all project phases as an effective means for reducing the project costs and the time required for its completion.” Further, constructability may be described as “the ability of project conditions to enable the optimal utilization of construction resources” (O’Connor et al., 1986). Constructability is the integration of construction expertise into the planning and design of a project so that the construction forces have the maximum opportunity to deliver the project in conformity with cost, quality, and schedule and safety objectives of the project’s stakeholders. Others posit that constructability is simply a matter of using features of 7 the site itself to make the work easier and faster (Kerridge, 1993). In the United Kingdom, the term buildability is defined as follows (“Buildability” 1983: “Buildability is the extent to which the design of the building facilitates ease of construction, subject to the overall requirements for the completed building.” Similarly, Ferguson (1989) defines buildability as “The ability to construct a building efficiently, economically and to agreed quality levels from its constituent materials, components and sub-assemblies.” These definitions stress the importance of overall project objectives, but the one that directly addresses the design-construction interface is more efficient in this study. So the definition from Fisher (1997) that “Constructability is the extent to which the design facilitates ease of construction, subjected to the requirements of construction methods” has been adopted in this study. 2.2 General Overview of Constructability in Highway Project Constructability in the highway industry has gained consideration attention over the past decades. Early research by O’Connor et al. (1991) identified that poor specifications can cause construction rework and delays. In fact, these authors state that 22% of all constructability problems are related to ineffective communication of engineering information, plans, and specifications, especially inadequacies in project specifications. This latter problem was confirmed in a national level study by Anderson et al. (1999). Based on a survey of government transportation agencies, Anderson and Fisher (1997) identified two of the three most critical issues related to implementing 8 constructability in transportation projects as the lack of response to designers and inadequate time to review. These issues are largely addressed by project managers through their decisions concerning the resources allocated to constructability reviews and the time spent on constructability reviews. The result of this work suggests that a lack understanding of the management of constructability reviews is an important barrier to reducing project durations. The current work tests the impacts of the two parameters identified by Anderson and Fisher (1997). Before the government transportation agencies management can address constructability implementation, critical issues affecting implementation must be understood. A survey by Stuart et al. (1999) was conducted to capture specific constructability issues from the perspective of agencies, design firms and construction contractors. The following were the result from the survey. 2.2.1 Government Agency Observations There were seven factors involved, which are Lack of Response to Designers, Enhancement of Plans and Specifications, Inadequate Time to Review, Lack of Practical Construction Experience by Design Personnel, Traffic Control, Cost and Manpower. 2.2.1.1 Lack of Response to Designers The contracting condition in which government agencies operate makes it a challenge for designers to obtain construction feedback for future project planning 9 and design. By the time that the contractor enters the project, the design is usually 100% complete. This clear separation between the design and construction phases makes it difficult to apply constructability. 2.2.1.2 Enhancement of Plans and Specifications Poor plans and specifications can cause major delays, claims and rework. Many agencies consider the need to improve plans and specifications a major issue in achieving a constructible project. The effective communication of engineering information is important in achieving efficient construction, resulting in time and cost savings. In the transportation industry, the effectiveness of the plans and specifications takes even greater importance because of the separation of the design and construction phases. Enhancement of plans and specifications remain the best approach to conveying the design intent to contractors. Constructability reviews would help communicate the design intent, thus enhancing a project’s constructability. 2.2.1.3 Inadequate Time to Review Their main concern seems to be the lack of time to apply a detailed analysis of designs from a construction perspective. Maintaining the status quo is considered the quickest way to meet the design schedule. Changing the process may be considered a potential source of delay in design operations. Increasing pressures to meet schedule have actually influenced their formalization of constructability reviews in an attempt to make them more efficient. 10 2.2.1.4 Lack of Practical Construction Experience by Design Personnel The separation of design and construction phases in the design-bid-build contracting environment makes it difficult for designers to expand construction experience. Once the design is complete, most designers leave the project. The lack of any formal requirement to maintain a lessons-learned database will hinder constructability even further. Experienced designers have few mechanisms for passing their knowledge to newly hired personnel. 2.2.1.5 Traffic Control The successful of a highway project often depends on an adequate level of traffic control planning. Poor traffic control management can effect in major delays, safety hazards and costs. Construction input can be valuable to the development of an effective traffic control plan. Lessons learned databases could also help in this area. Studies should be performed on site characteristics and traffic patterns that will result in maximum savings in time and overall cost of the project. This analysis should begin early during the planning phase and include construction input. 2.2.1.6 Cost The cost of implementing a formal constructability process is a concern for many agencies. The money up front has always been a deterrent to implementation of constructability in the construction industry (Constructability 1993). It is crucial that agencies understand that benefits returned will more than offset costs to 11 implement and apply a formal constructability program. Benefit/ cost data confirms this and reflects a $25 project cost savings for every dollar spent on constructability reviews (Anderson and Fisher, 1997). 2.2.1.7 Manpower Turning over personnel absolutely for the purpose of constructability could result in increased cost to the agency. This is a difficult issue, especially with many agencies downsizing their operations. Hence, the process has to be flexible enough so that implementation can fit into the actual structure of the agency without adding substantial new manpower requirements. 2.2.2 Design Firm Observations From the design firm observations, the issues are Inadequate Coordination of Designs, Plans and Specifications, Need of Experience and Knowledge, Poor Communication and Feedback, Inadequate Time and Funds for Constructability, Early Review of Designs, Uncoordinated Timing and Phasing, and Scheduling. 12 2.2.2.1 Inadequate Coordination of Designs, Plans, and Specifications This issue addresses the particular problem of a lack of coordination between designers and constructors, which results in poor coordination and interaction with construction. It has been described by respondents in terms of not enough design detail for construction, inefficient and inflexible designs, designs not coordinated with utilities within the scope of the project, and a lack of clarity in design criteria that must be met by the project. This issue becomes even more critical in its relation to other significant issues that impede constructability poor communication and feedback inadequate application of construction experience and lack of contractor input to the design process. 2.2.2.2 Need of Experience and Knowledge It was evident from responses within the design community that a major issue with respect to facilitating the constructability process is the need of construction experience and knowledge among designers. This issue is resolved within most firms by assigning design review responsibilities to senior design personnel. However, it is apparent that this effort does not effectively bridge the gap between designers and constructors so that efficient constructability analysis results. 2.2.2.3 Poor Communication and Feedback Unfortunately, this issue is one that is common to the inefficient internal operations of many organizations and is especially critical with respect to 13 constructability. Communications about project designs, plans, and specifications must be clearly understood by everyone involved in, as well as across the interfaces of, the planning- preparation-review processes. The contractor who is expected to apply designs must similarly understand communications. Feedback is essential to the ‘‘learning process’’ but, unless encouraged and acted upon, offers little to support the final outcome of a project. 2.2.2.4 Inadequate Time and Funds for Constructability This response is indicative of what seems to be the traditional method of performing work with regard to the planning-design-construction process. Constructability has not been embraced by many organizations to date, and time and funding simply have not been allocated for such an effort. As with programs such as value engineering, partnering, and total quality management, constructability must have the support of an organization’s leadership and management personnel so that time and funds may be allocated and benefits realized from these programs. 2.2.2.5 Early Review of Designs The early review of designs was deemed necessary as essential to the completion of correct and detailed designs as well as designs that would be effectively implemented by construction contractors. Because this issue has been raised, many design organizations must believe that early review is an area in which there is a shortfall of effort. There should be more emphasis on review of plans and designs early in the overall project process. This is consistent with the concept of constructability. 14 2.2.2.6 Uncoordinated Timing, Phasing, and Scheduling It is significant that this issue is critical to effective project management across the design/construction interface and is related to some of those issues indicated above, such as poor communication and feedback. It is fundamental that such issues be managed and overcome so that constructability can be realized throughout the overall project process. 2.2.3 Construction Firm Observations The five most critical construction firm issues are listed below. Each of these has already been discussed as a design firm issue. Their potential impact on constructability for construction firms is similar to that described for design firms: • Vague designs, plans, and specifications • Poor scheduling and phasing of construction • Need of communications and feedback • Need of experience and knowledge 2.3 Constructability in Highway Construction Project Process Construction of a project may be performed by several delivery methods. For the purpose of this research a traditional method was assumed because it is by far the most generic construction process Gould (1997) and it is this model that is usually applicable to infrastructure projects such as found in the great majority of road 15 construction projects. The diagram in Figure 2.1 is presented as the traditional construction process that consists of the feasibility or preliminary design, design, construction and operation phases. Although constructability is applied in all project phases this research project focuses on constructability in the design phase. In its possible terms of reference constructability remits aims to improve the integration within the total construction process of those parties that combine to procure, brief, design, construct, use and maintain a building or engineering product. Moreover, as a concept it seeks to interrelate the various separate phases of construction to produce a set of concepts that are implied and accepted and, inherently, apply constructability thinking to each stage for the benefit of the whole process. Essentially, constructability is usually seen as the contribution that design can make to assist construction work on site, but though this is vitally important, and a major part it is only one element in understanding the full concept (Griffith and Sidwell, 1988) To appreciate more fully the contribution that constructability can make, it is important to outline briefly what construction process seeks to achieve. Since the mid-nineteenth century, the design element of the construction process has increasingly diverged from the construction functions on site (Griffith and Sidwell, 1988). This situation produced a process in which the designer and contractor are both unsure as to the other’s role and function. This can only lead to designs that fail to bring out the best facets of design. The needs of clients, who want the best from their project, demand that constructability must be considered at each stage in the construction process. 16 Feasibility/ Preliminary Design Design Construction Operation Figure 2.1: The Highway Construction Project Process (Adapted from Garry D. Creedy, 2003) 2.3.1 Feasibility or Preliminary Design Stages Normally a project begins with a concept, where conceptual planning or a preliminary design will be performed and feasibility assessment will be made. During this feasibility phase conceptual drawings or a preliminary design is produced to help establish the feasibility of a project. The owner is also establishing requirements during this phase and therefore the concept’s scope may fluctuate. 17 Traditionally, constructability is not thought of at all at the feasibility phase, yet subsequently it will seen that modern construction demands that constructability be considered at this early stages. For example, within the client’s outline idea of need and requirement constructability can provide feedback from past projects to aid consideration of the current project. Constructability is also concerned with the basic method of procurement and employment of consultants. For example, consideration of constructability can involve evaluating the arrangement of the parties by suggesting the advantages and disadvantages of the traditional route as against design-build, management-based systems or design-and-manages approaches. Constructability can assess not only the technological aspects and potential methods of construction, but also the formal arrangement between the participants. 2.3.2 Design Stages If the project is feasible in terms of a sound business case, then a detailed design is performed. The design phase of a project will produce detailed drawings, specifications and quantity and cost schedules. During the design phase cost control is performed through scope control and value engineering. Value engineering is a team effort between designers, owners and builders to optimize the cost of a project. It is best applied in the design phase of a project and can result in savings of between 5-10% of construction costs. The consideration of constructability is basic to this phase, as it allows the detailed scrutiny of alternative design solutions and of the ergonomics of layout, both internally and externally, it also helps to determine how the design solution can directly increase ease of construction on site when the work is carried out. The broad design situation is critical to constructability for example, uncomplicated construction using repetitive elements may have a high constructability factor, whereas a bespoke construction project may be intrinsically costly and have a lower 18 factor of constructability because it incorporates innovative materials or requires specialized assembly. 2.3.3 Construction During the construction phase the actual physical building of the project is accomplished. This stage is comprised of two parts, planning and execution. During the planning phase a detailed time schedule is developed and in the execution phase the actual project gets built. Contractor is the person who responsible for the constructability during the construction phase. He must consider all aspect of constructability in undertaking all aspects of the site production process. This means that he also assumes that responsibility for ensuring that general concepts of constructability are also carried out by the subcontractors and other providers of specialist inputs to the process. Good relationship with the design team also important in order to provide feedback on the construction phase for future analysis and the betterment of knowledge. The key to effective and efficient constructability on site is good planning, adequate resources and continuous control, which add up to good general site practice. 2.3.4 Operation The operation of a new facility begins once the construction is completed. As soon as the contractor’s final payment and release of retention has been made, another and final phase of the project begins. At this point, assuming that all contractual obligations of both parties have been met, the project manager takes over all of the activities regarding the project, and the project operation activities start. 19 From the explanation above, it can be conclude that constructability is considered in every stage in project process. In achieving high application and maximum benefit of constructability, construction personnel play the important roles in using construction method and construction knowledge about constructability itself. 2.4 Maximum Benefit of Constructability in Highway Projects Constructability can be implemented throughout the entire project process i.e. from the preliminary stage to the operation stage. Since the development of a project evolves through different stages and involved many participants over its lifecycle thus the contributions of constructability improvements by each of the participants vary accordingly. Among many of participants involved in the project, the designers are expected to play the central role for constructability improvement (Hassan, 1997). Designers are seen to have significant roles as they are responsible for most technical problems which arise during project design, in the construction and commissioning of the project. Figure 2.2 illustrates the stages of project life cycle and the designer level of influence on the project cost over the project time. It can be seen that the level of influence of the designer is higher at the beginning of the project and decreasing towards the end of project. On the other hand the expenditure is increasing as the project progresses. The figure also illustrates that the best time to achieve good constructability of project design is at the earlier stages of project development. 20 CONCEPTUAL PLANNING DESIGN PROCUREMENT CONSTRUCTION COMMISSIONING MAINTENANCE START COMPLETE High Influence Low Low Expenditure Expenditure Low Expenditure Low Influence Results Results High Expenditure 100% Increasing Expenditure Cumulative Project Cost Level Of Influence Decreasing Influence 0% Project Time Figure 2.2: Project Life Cycle and Designers Level of Influence (Adapted from Hassan, 1997) There have been reports that indicate many problems that are encountered during construction can be traced back to the design process (Jergeas, 1989; Alshawi and Underwood, 1994; Madelsohn, 1997; Griffith and Sidwell, 1995). These problems can be as high as 75% of the total problems encountered during construction (Madelsohn, 1997). In view of the problem it is necessary that constructability of project designs be improved in order to minimise the design-related problems during construction. 21 The need is more critical especially in the context of the Malaysian construction industry where constructability has been neglected for quite sometimes. The constructability improvement will eventually improve the efficiency of the construction industry. This early constructability improvement is desired, as the benefits of constructability that can be gained is high and the ‘early cost influence’ can be taken advantage off. The ‘early cost influence’ is a concept where the ability to influence the project cost decreases with the project lifetime. Figure 2.3 depicted the cost influence of constructability implementation throughout the project lifecycle. Figure 2.3: Ability to Influence Final Cost Over Project Life (CII (1986) ‘Constructability – A Primer’ 22 2.5 Constructability Concepts in Highway Projects Concept is a significant, distinct and executable objective for enhancing constructability. Concepts are not specific or unique with respect to project type or organization. It presents a desperate need and requirement to improve the construction project constructability (O’Connor et al., 1987). Several basic researches on constructability have been developed over the last two decades. The Construction Industries Research and Information Association (CIRIA) initiated one of the early studies in the development of constructability concepts in the UK. CIRIA identified seven concepts of constructability concepts for implementation during design phase and called them “Buildability Concepts” (“Buildability: An Assessment” 1983). The study was quoted by Powell (1983) and these concepts are: 1. The thoroughness of design and investigation. 2. Planning for site production requirements. 3. Planning for practical sequence of operations and early enclosure. 4. Planning for simplicity of assembly and logical trade sequences. 5. Detailing for maximum repetition and standardization. 6. Detailing for achieving tolerances; and 7. Specify robust and suitable materials. Another basic study in this field is the study of O’Connor et al. (1987) published in June 1987 which presented seven concepts for improving constructability during the above two phases. These concepts have been adopted by CII in August 1987 and listed below: 23 1. Constructability is enhanced when design and procurement schedules are construction-driven. 2. Constructability is enhanced when designs are configured to enable efficient construction. 3. Constructability is enhanced when design elements are standardized and repetition is taken advantage of. 4. Constructability is enhanced when pre-assembly work scoped in advance and module pre-assembly designs are prepared to facilitate fabrication, transport, and installation. 5. Constructability is enhanced when designs promote accessibility of manpower, materials and equipment. 6. Constructability is enhanced when design facilitate construction under adverse weather conditions when they exist; and 7. Constructability is enhanced when owner, designer, and constructor personnel review specifications in detail. It also serves to simplify the field construction process. Other basic study are the two written by Boyce (1991) in which he offered ten concepts for improving constructability during the design phase only and he called them “The Ten Commandments of KISS Design”. These concepts are: 1. Keep it straight and simple; 2. Keep its specification simple; 3. Keep it shop standard; 4. Keep its standards simple; 5. Keep it standard size; 6. Keep it same size; 7. Keep it square and squatty; 8. Keep it support simple; 9. Keep it site suitable; and 10. Keep its schedule sacred. 24 From Nima (2001), there are twenty three concepts that are discussed in order to derive the constructability concepts that will be identified according to the construction project process. Project constructability enhancement during conceptual planning phase comprises concepts C1 to C7. 1. Concept C1: The project constructability program should be discussed and documented within the project execution plan, through the participation of all project team members. 2. Concept C2: A project team that includes representatives of the owner, engineer and contractor should be formulated and maintained to take the constructability issue into consideration from the outset of the project and through all its phases. 3. Concept C3: Individuals with current construction knowledge and experience should achieve the early project planning so that interface between design and construction can be avoided. 4. Concept C4: The construction methods should be taken into consideration when choosing the type and the number of contracts required for executing the project. 5. Concept C5: The master project schedule and the construction completion date should be construction-sensitive and should be assigned as early as possible. 6. Concept C6: In order to accomplish the field operations easily and efficiently, major construction methods should be discussed and analyzed indepth as early as possible to direct the design according to these methods. 25 7. Concept C7: Site layout should be studied carefully to perform the construction, operation and maintenance efficiently, and to avoid the interfaces between the operations performed during these phases. Project constructability enhancement during design and procurement phases comprises concepts C8 to C15. 1. Concept C8: Design and procurement schedule should be dictated by construction sequence. Thus, the construction schedule must be discussed and developed prior to the design development and procurement schedule. 2. Concept C9: Advanced information technologies are important to any field including the field of construction industry. Therefore, the usage of those technologies will overcome the problem of fragmentation into specialized roles in this field, hence enhancing constructability. 3. Concept C10: Designs, through design simplification by designers and design review by qualified construction personnel, must be configured to enable efficient construction. 4. Concept C11: Projects elements should be standardized to an extent that will never affect the project cost negatively. 5. Concept C12: The project technical specifications should simplify and configured to achieve efficient construction without sacrificing the level or the efficiency of the project performance. 6. Concept C13: The capability of modularization and preassemblies for project elements should be taken into consideration and studied carefully. Modularization and preassembly design should be prepared to facilitate fabrication, transportation and installation. 26 7. Concept C14: Project design should take into consideration the accessibility of construction personnel, materials and equipment to the required position inside the site. 8. Concept C15: Design should facilitate construction during adverse weather conditions. Good effort should be given to planning the construction of the project under suitable weather conditions. Otherwise, the designer must increase the project elements that could be pre-fabricated in workshops. Project constructability enhancement during field operations phase comprises concepts C16 to C23. 1. Concept C16: Field task sequencing should be configured in order to minimize damages or rework of some project elements, minimize scaffolding needs, formwork used, or congestion of construction personnel, material and equipment. 2. Concept C17: Innovation of a temporary construction materials/systems, or implementing innovative ways of using available temporary construction materials/systems, which have not been defined or limited by the design drawings and technical specifications. 3. Concept C18: Innovation of new methods in using off-the-shelf hand tools, or modification of the available tools, or origination of new hand tools that reduce labour-intensity, increase mobility, safety or accessibility. 4. Concept C19: Innovative uses of new methods in using the available equipment or modification of the available equipment to increase their productivity. 5. Concept C20: Encouragement of the usage of constructor-optional preassembly in order to increase the productivity, reduce the need for 27 scaffolding, or improve the project constructability under adverse weather conditions. 6. Concept C21: Encouragement of the innovation of temporary facilities. 7. Concept C22: Contracts should not be awarded based on low bids only, but by considering other project variables such as materials and time. Also, good contractors should be considered for future construction works. 8. Concept C23: Evaluation documentation and feedback of the issues of the constructability concepts used throughout the project. These twenty three constructability enhancement concepts usher the ways in which construction knowledge and experience may be used efficiently through the process of engineered construction. The implementation of these concepts in a project will greatly improve its constructability. From the study that has been done by Rosli Mohamad Zin (2004), there are eighteen concepts for the design phase which are: 1. Carry Out Thorough Investigation of the Site Constructability is improved when the information gathered from site investigation is thorough and complete. In this context CIRIA (“Buildability : An Assessment” 1983) recommended that thorough site surveys (including determination of ground conditions, underground hazards and other potential problems) are essential to avoid risk of delays and design changes during construction. 2. Design for Minimum Time Below Ground Constructability is improved when the design minimize work below ground. According to Adams (1989) the application of this concept is important especially when the ground is hazardous, poor or wet. In those conditions the 28 speed and flow of the project can be increased when less work are carried our below ground. 3. Design for Simply Assembly Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the building, particular element or group of elements. Adams (1989) mentioned that designers should endeavor to produce the simplest possible details with the overall requirements for the building, particular element, or group of elements. This open the way to efficient, defect-free work that will satisfactorily perform its end function. 4. Encourage Standardization/Repetition O’Connors et al. (1987), stated that the standardization of components is based on recognition that savings can be realized when the number of variations of components is kept minimum. Many construction project elements have potential for standardization. Building systems, material types, construction details, dimensions and elevations may be standardized for increased field efficiency. 5. Design for Preassembly and/or Modularization Tatum et al. (1985) gave the following definitions: Preassembly is a process by which various materials, prefabricated components and/or equipment are joined together at a remote location for subsequent installation as a unit. Preassembly often involves decoupling sequential activities into parallel activities; and A module is a product resulting from a series of remote assembly operations; it is usually the largest transportable unit or component of a facility. Modules may contain prefabricated components or preassemblies and are usually constructed away from the job site. 29 6. Analyze Accessibility of the Jobsite The effect of accessibility can sometimes be quite serious such as delay in progress, slowed productivity and increased damaged to completed work. 7. Employ Any Visualization Tools to Avoid Physical Interference Constructability is improved when visualization tools are employed to visualize any possibility of physical interference during construction. Ghanah et al. (2000) highlighted that computer visualization allows investigations to iron out difficulties that may occur before construction commences on site. 8. Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Particular attention should be given to the problems of fit which occur at the interfaces between different products, methods of construction, materials and method of manufacture, and suitable jointing methods should be adopted. 9. Investigate the Practical Sequence of Construction Constructability is improved when adequate consideration of practical sequence of construction is given. The method of construction of project should encourage the most effective sequence of building operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimized delay. 10. Plan to Avoid Damage to Work by Subsequent Operations Constructability is improved when the damage to work by subsequent operations is considered. The design should enable work to be carried out in a workmanlike manner without risk of damage to adjacent finished elements and with minimum requirement for special protection. 11. Consider Storage Requirement at the Jobsite Constructability is improved when storage requirement is adequately considered. Consideration should be given during the design stage to be location of material storage and unloading facilities. The space occupied by 30 shoring, scaffolding, formwork, plant, compounds and workshops for example can be considerable. Their efficient location and distribution is necessary for good constructability. Poor consideration of storage requirement may result in nearby streets to be closed, scaffolding and offices may straddle the pavements and it may not possible to locate the tower crane within the site. 12. Investigate the Impacts of Design on Safety During Construction Constructability is improved when the impact of design on safety during construction is adequately considered. The design produced by the designers should enable the contractor to carry out their works in a safe like manner. The design should be arranged so as to facilitate safe working in works such as foundation and earth works, when materials and components are being handled, and wherever traversing for access is necessary. 13. Design to Avoid Return Visit by Trade Constructability is improved when the design enable a trade or specialist to complete all its work at a work place with as few return visit as possible. 14. Design for the Skills and Resources Available Constructability is improved when the technology of the design solution matched with the skills and resources available. With regard to this constructability concept Adams (1989) highlighted that any design is only good as skills available to execute it, either off-site or on-site. Labour and skills requirements vary between one project to another, between one locality to another. Design must include a realistic assessment of the level of skill likely to be available from appropriately chosen contractors and specialists. 15. Consider suitability of Designed Materials Constructability is improved when suitable and robust materials are used. According to Adams (1989), products and materials should be selected with care, particularly, any which have not long been established and accepted within the industry. They should be proven to be suitable for the use for which they are selected. Products and materials should be selected which 31 utilize normal site assembly methods and sequences, with subsequent operation and wear and tear in mind. Care should be taken to ensure that manufacturer recommendations on handling, storage, application, assembly and protection are complied with. 16. Provide detail and clear Design Information Constructability is improved when thorough and clear presentation of design information before the start of construction. Sufficient time and resources must be allowed for this in design budget. Complete project information should be planned and coordinated to suit the construction process and to facilitate the best possible communication and understanding on site. According to Ghanah et al. (2000) communication between designers and other participants in construction project are normally performed using traditional methods i.e. paper based drawing, schedule, written statements etc. In order to improve constructability, priority must be given on the reliability of the information communicated through these methods. Therefore, the accuracy, understandability and clarity of information generated during the design process must be checked at all times. 17. Design for Early Enclosure Constructability is improved when the design enables early enclosure of the constructed building. CIRIA (“Buildability: An Assessment” 1983) suggests that the construction and detailing of a building shell, including the roof (whether framed or loading bearing construction), should facilitate the enclosure of the building at the earliest possible stage. Following operations can then commence early in the programmed, and they can be carried out without hindrance from weather. 18. Consider Adverse Weather Effect in Selecting Materials or Construction Methods Constructability is improved when the effect of adverse weather is considered. Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. 32 Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimized. 2.6 Design Phase Constructability Concepts for the Highway Projects Among many of participants involved in the project, the designers are expected to play the central role for constructability improvement (Hassan, 1997). Designers are seen to have significant roles as they are responsible for most technical problems which arise during project design, in the construction and commissioning of the project. Madelsohn (1997) seemed to agree with the view that designers do not give enough consideration to the problems that contractors had to face during construction. In an article “The Constructability Review Process: A Constructor’s Perspective”, Madelsohn (1997) highlighted that 75% problems in the field are generated in the design phase. Fisher and Rajan (1996) described the constructability of designs as the integration of construction knowledge, resources, technology, and experience into the engineering and design of a project. Discovering and addressing design errors and omission in a timely manner is critical for short project durations (Ford and Sterman 1998; Cooper 1993). Constructability problems are one type of these errors and omissions. Constructability problems that are not identified and addressed during design can have a negative impact on project schedule performance by slowing construction operations and generating unplanned delays. This impact was cited as an important issue for highway projects in a National Cooperative Highway Research Program project (Russel and Anderson, 2000). The same research identified “constructability” and “methods to minimize project duration” as two several critical issues necessary for improving construction 33 and the quality of highway projects. Therefore, reviewing designs and specifications to identify and address constructability issues is a primary means of reducing highway project durations. An example highlighted by Mendelsohn (1999) illustrates the potential impacts of addressing constructability problems during highway project design: A bridge was to be designed over four lanes of divided highway. The original design used large precast girders that spanned from abutment to abutment. Constructability review identified that, because of ground conditions and traffic, locating cranes of sufficient capacity on the median strip to place the girders called for in the design would be very difficult and time consuming. As an alternative, a pier was designed and built on the median at midspan, allowing the use of shorter, lighter, and shallower girders that could be handled by a smaller crane. Additionally, the reduced girder depth permitted a lower grade to the bridge deck, thereby reducing earth filling requirements at the approaches. The faster crane mobilization, handling of smaller girders, reduced interruptions to traffic, and less fill work shortened the project duration by three months. The cost savings paid for the additional mid-span pier. Many of the design decisions made early in the design process affect the construction of the project. Consequently, construction expertise is often incorporated in the design process to improve the constructability of the design. In 2.5, the constructability concepts that are applicable in all phases of construction project were described. It can be observed that during the design phase the concepts developed by Rosli Mohamad Zin (2004) are more thorough with respect to ease of construction. It was discovered from his study that 9.2% of respondent were involved in highway projects. The findings indicate that constructability concepts for buildings projects were almost similar to the highway projects. The following are detail description of the constructability concepts identified by Rosli Mohamad Zin (2004). 34 2.6.1 Carry Out Thorough Investigation of the Site Constructability is improved when the information gathered from site investigation is thorough and complete. In this context CIRIA (“Buildability : An Assessment” 1983) recommended that thorough site surveys (including determination of ground conditions, underground hazards and other potential problems) are essential to avoid risk of delays and design changes during construction. An example of application of this concept is in bridge construction as highlighted by Nima et.al (2002). In this project, the difficulties of launching the bridge girders was not properly dealt with during the early phases of the project, as the contractor faced big difficulties in launching numerous girders along the elevated structure. The elevated structure passed through the town, and the road reserve width inside the town was not similar to that outside the town due to land acquisition cost and some social reasons. Thus, the existing buildings inside the town hampered the lifting of the girders to their final position. Figure 2.4 illustrates the normal process of launching the girders. In contrast, Figure 2.5 shows the site at which the contractor faced the problem. Panel A in Figure 2.5 shows that the existing town market and its fence are very close to the elevated highway. Accordingly, there was not enough room for the cranes to launch the girders. In order to solve this problem, the contractor dismantled the fence, launched the girders, and rebuilt the fence. Panel B in Figure 2.5 shows a span in another location of the project, in which the launching was impeded by two buildings that could not be dismantled due to economic reasons and non agreement of their owners. This problem was dealt with only after reaching the critical step of launching the girders. It was solved by transporting the cranes to the adjacent constructed spans, and from this position the launching was done after causing work schedule delays. The reason for this problem was that there was no construction input to the major construction methods and the site layouts during the conceptual planning phase. 35 Figure 2.4: Process of launching girder for elevated structure (Adapted from Nima, 2002) Figure 2.5: Problems faced during launching of some girders (Adapted from Nima, 2002) 36 In other case as experienced by Nima (2004) in highway projects, especially in rural areas, the problem of site layouts is less severe than that of projects in metropolitan areas. In metropolitan area, an adequate space was necessary for casting, pre stressing, curing, and storing the girders (up to 35 m long) until the time of erection. This requirement was not thought of until after the construction was resumed. The contractor was fortunate to find a vacant lot of land that was available for rent, adjacent to the construction site, which then was used for pre casting and storing these members. Sometimes, the acquired land for the project site was greater than what the actual structures and the civil engineering works required. Therefore, this concept has to study thoroughly, during the design phase. 2.6.2 Design for Minimum Time Below Ground Constructability is improved when the design minimize work below ground. According to Adams (1989) the application of this concept is important especially when the ground is hazardous, poor or wet. In those conditions the speed and flow of the project can be increased when less work are carried out below ground. An example of problem related to this concepts as shown in Figure 2.6 and Figure 2.7. Figure 2.6 shows the plan and a cross section of a part of the elevated highway, and Figure 2.7 illustrates the problem and the consequences of the difficulty of compacting the soil and sub base between two pile caps after the start-up of the project. This was due to the lack of enough space for traditional compacting equipment to do the compaction properly. 37 Figure 2.6: Details of elevated highway (Adapted from Nima, 2002) 38 Figure 2.7: Problem of compaction and result after project start-up (Adapted from Nima, 2002) 39 2.6.3 Design for Simply Assembly Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the building, particular element or group of elements. Adams (1989) mentioned that designers should endeavor to produce the simplest possible details with the overall requirements for the building, particular element, or group of elements. This open the way to efficient, defect-free work that will satisfactorily perform its end function. The implementation of this concept in the highway project was accomplished by simplifying the design of the piers and decks. Some projects with the major structure consisted of repetitive detailing had a good potential for detailing simplification. As was discussed by Nima et al. (1999) aesthetics is one of the main project objectives, which frequently overrides the constructability requirements. For this reason, implementing this concept was preserved for the approaches only and constituted a high percentage of the total cost of the project. The following techniques and measures were applied: • Using the prefabricated post-tensioned I-Beams for the decks reduced the usage of scaffolding, • Decreasing the number of elements, and • Using the prefabricated girders to reduce construction task interdependencies. For example, work on the cast-in-elements could proceed while fabricating the girders off-site is in progress. From the above discussion it is clear that designs can be simplified and configured to enable efficient construction through different 40 means and methods. Also, one might properly suggest that it is wise to seek opinion from experienced construction personnel on a continuous basis to review the designs to ensure that this constructability principle is effectively implemented. 2.6.4 Encourage Standardization/Repetition O’Connors et al. (1987), stated that the standardization of components is based on recognition that savings can be realized when the number of variations of components is kept minimum. Many construction project elements have potential for standardization. Building systems, material types, construction details, dimensions and elevations may be standardized for increased field efficiency. This concept supports standardization of the project’s components. The consultant made good use of this concept by standardizing the majority of the project’s elements. Examples include the piers, crossbeams, and decks. The standardization of girders was used for the approach ramps. All elements including, pile types, pier columns, pier cross beams, girders, parapets, handrails, guardrails and drainage system can be standardized. 2.6.5 Design for Preassembly and/or Modularization Tatum et al., (1985) gave the following definitions: • Preassembly is a process by which various materials, prefabricated components and/or equipment are joined together at a remote location for subsequent 41 installation as a unit. Preassembly often involves decoupling sequential activities into parallel activities; and • A module is a product resulting from a series of remote assembly operations; it is usually the largest transportable unit or component of a facility. Modules may contain prefabricated components or preassemblies and are usually constructed away from the job site. This concept advocated using prefabrication, preassembly, and modularization. In order to apply this constructability concept, some of highway projects used of pre stressed M-beams and U-beams for the spans that made up the elevated highway and post tensioned I-beams for the intersections with the town roads and railway tracks. However, as O’Connor et al. (1987) warned, lifting limitations and delivery route restrictions should be studied when planning to implement this concept. From experience by Nima (2004) in his cable stayed project, this concept advocates using modules and preassemblies in design. The usage of the prefabricated post-tensioned I-beams was an application of this concept. Furthermore, the spun piles were used for the same portion, i.e., the approach ramps. Those two elements made up a high percentage of the total cost of the project. By using these two elements, many constructability concepts were applied. Consequently the quality, cost, and schedule were optimized. 2.6.6 Analyze Accessibility of the Jobsite The effect of accessibility can sometimes be quite serious such as delay in progress, slowed productivity and increased damaged to completed work. This concept highly promotes accessibility to enhance project constructability. The road 42 reserve width inside the town was narrower, which made the contractor face many accessibility problems that caused delays in progress and decreased productivity. 2.6.7 Employ Any Visualization Tools to Avoid Physical Interference Constructability is improved when visualization tools are employed to visualize any possibility of physical interference during construction. Ghanah et al., (2000) highlighted that computer visualization allows investigations to iron out difficulties that may occur before construction commences on site. This concept advocates the consultants to employ the capabilities of advanced information technology. This concept was well used during the design and preparation of the plans. Examples of application of this concept include using the internet and developing models (software) to test the structural behavior in the early stages of the conceptual design. 2.6.8 Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Particular attention should be given to the problems of fit which occur at the interfaces between different products, methods of construction, materials and method of manufacture, and suitable jointing methods should be adopted. 43 2.6.9 Investigate the Practical Sequence of Construction Constructability is improved when adequate consideration of practical sequence of construction is given. The method of construction of project should encourage the most effective sequence of building operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimized delay. According to this concept, construction sequence should generally dictate the procurement and engineering sequences. The schedules for design and procurement activities should be driven by the needs of the construction. Thus, a construction schedule must be developed before design and procurement schedules are initiated (CII 1987, 1993). 2.6.10 Plan to Avoid Damage to Work by Subsequent Operations Constructability is improved when the damage to work by subsequent operations is considered. The design should enable work to be carried out in a workmanlike manner without risk of damage to adjacent finished elements and with minimum requirement for special protection. 44 2.6.11 Consider Storage Requirement at the Jobsite Constructability is improved when storage requirement is adequately considered. Consideration should be given during the design stage to be location of material storage and unloading facilities. The space occupied by shoring, scaffolding, formwork, plant, compounds and workshops for example can be considerable. Their efficient location and distribution is necessary for good constructability. Poor consideration of storage requirement may result in nearby streets to be closed, scaffolding and offices may straddle the pavements and it may not possible to locate the tower crane within the site. 2.6.12 Investigate the Impacts of Design on Safety During Construction Constructability is improved when the impact of design on safety during construction is adequately considered. The design produced by the designers should enable the contractor to carry out their works in a safe like manner. The design should be arranged so as to facilitate safe working in works such as foundation and earth works, when materials and components are being handled, and wherever traversing for access is necessary. 2.6.13 Design to Avoid Return Visit by Trade Constructability is improved when the design enable a trade or specialist to complete all its work at a work place with as few return visit as possible. 45 As for this concept, Boyce (1991) proposed using the ‘‘performance type specification approach.’’ This can be achieved by selecting a vendor with a good reputation and experience in the required specialization who will supply the item with a guarantee. This approach was used for many items in the project rather than implementing ‘‘gold-plated’’ off-the-shelf specifications that O’Connor and Miller (1994) considered one of the barriers to constructability implementation. The best example is the elastomeric bearing pads for the viaduct and the approach ramps. 2.6.14 Design for the Skills and Resources Available Constructability is improved when the technology of the design solution matched with the skills and resources available. With regard to this constructability concept Adams (1989) highlighted that any design is only good as skills available to execute it, either off-site or on-site. Labour and skills requirements vary between one projects to another, between one locality to another. Design must include a realistic assessment of the level of skill likely to be available from appropriately chosen contractors and specialists. 2.6.15 Consider Suitability of Designed Materials Constructability is improved when suitable and robust materials are used. According to Adams (1989), products and materials should be selected with care, particularly, any which have not long been established and accepted within the industry. They should be proven to be suitable for the use for which they are selected. Products and materials should be selected which utilize normal site assembly methods and sequences, with subsequent operation and wear and tear in 46 mind. Care should be taken to ensure that manufacturer recommendations on handling, storage, application, assembly and protection are complied with. In one case study by Brasic (2004), the composite single steel box girder/concrete deck bridges are not commonly constructed in Canada. On this project, they were implemented for the single lane, high-speed ramps connecting the existing highway system with the approach roads to the New Terminal One building. The single steel box girder bridge type was adopted as the optimal solution compared to other structure types, for specific locations. The governing criteria for type selection were complex geometry and deck width, feasibility, the need to maintain traffic under the bridges throughout construction, and limited space under the bridges to provide false work supports. The number of spans varies between four and nine with the maximum spans up to 56 meters in length. Total length of bridges varies between 164 and 371 meters. Road geometry constraints resulted in minimum horizontal curve radius of 148.5 meters and maximum 6% grades. The unique details used in these bridges present an alternative, cost-effective approach in meeting each of the Client’s needs using innovative detailing and appropriate construction technology. The structures were tendered approximately 15% below the engineer’s estimates. 2.6.16 Provide Detail and Clear Design Information Constructability is improved when thorough and clear presentation of design information before the start of construction. Sufficient time and resources must be allowed for this in design budget. Complete project information should be planned and coordinated to suit the construction process and to facilitate the best possible communication and understanding on site. According to Ghanah et al., (2000) communication between designers and other participants in construction project are normally performed using traditional methods i.e. paper based drawing, schedule, 47 written statements etc. In order to improve constructability, priority must be given on the reliability of the information communicated through these methods. Therefore, the accuracy, understandability and clarity of information generated during the design process must be checked at all times. 2.6.17 Design for Early Enclosure Constructability is improved when the design enables early enclosure of the constructed building. CIRIA (“Buildability: An Assessment” 1983) suggests that the construction and detailing of a building shell, including the roof (whether framed or loading bearing construction), should facilitate the enclosure of the building at the earliest possible stage. Following operations can then commence early in the programmed, and they can be carried out without hindrance from weather. 2.6.18 Consider Adverse Weather Effect in Selecting Materials or Construction Methods Constructability is improved when the effect of adverse weather is considered. Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimized. This concept encourages facilitating construction under adverse weather conditions through design. This concept was practiced through using the pre cast 48 units for the girders and drainage systems for roadsides and manholes. The pre cast elements were not damaged by rain when compared with the cast-in situ type of construction. Moreover, using the precast drainage systems helped in discharging rainwater during rainy weather. While preparing his case study about Kuala Lumpur International Airport, Stevens (1997) discovered four major threats confronting the contractors and subcontractors who were participating in this giant project. One of those threats was the adverse weather condition. Once again, using prefabricated spun piles and girders met the requirements of this concept. 2.7 Summary Through the literature survey on constructability in construction projects, the following summaries are made: (i) The specific constructability issues from the perspective of agencies, design firms and construction contractors, are applicable to all types of construction but some additional aspect such as traffic controls have to be determined in highway projects. (ii) The applications of constructability concepts can be entirely applied in highway project process. But, maximum benefit of constructability can be achieved in the early phases of the project such as conceptual planning and design phases. 49 (iii) The constructability concepts proposed by the various researchers are applicable to highway construction projects. However, with respect to the design phase the constructability concepts identified by Rosli Mohamad Zin (2004) is found to be most thorough an appropriate. The concepts are: • Carry out thorough investigation of the site; • Design for minimum time below ground; • Design for simple assembly; • Encourage standardisation/repetition; • Design for pre-fabrication, pre-assembly or modularization; • Analyse accessibility of the jobsite; • Employ any visualisation tools such to avoid physical interference; • Investigate any unsuspected unrealistic or incompatible tolerances; • Investigate the practical sequence of construction; • Plan to avoid damage to work by subsequent operations; • Consider storage requirement at the jobsite; • Investigate the impacts of design on safety during construction; • Design to avoid return visit by trade; • Design for the skills available; • Consider suitability of designed materials; • Provide detail and clear design information; • Design for early enclosure; and • Consider adverse weather effect in selecting materials or construction methods CHAPTER 3 RESEARCH METHODOLOGY 3.1 Introduction Various steps can be adopted to fulfill the objectives of this study. The research methodology for this research includes discussion on method of data collection, the approach used, research consideration such as design of questionnaire and data analysis. 3.2 Research Process The research process involves literature review to gather information on the subject, development of questionnaire to establish the level of importance and application of constructability concepts from data analysis. 51 Data have been collected in Johor Bharu, Terengganu and Kelantan. Data collection is made through questionnaire to be filled and submit back to the researcher. After that data have been analyzed using Statistical Package for Science Social 11.0 (SPSS). 3.3 Determining the Research Objectives The main objective of this research is to identify the constructability concepts in construction. The other objectives are to identify the level of application and importance of constructability concepts in design phase for highway project in Malaysia. In determining the research objectives, a review process is undertaken to determine the suitable methodology in terms of its feasibility, achievability to achievable data collection, and its analysis. 52 3.4 Steps in Methodology CONCEPTUALIZATION LITERATURE REVIEW QUESTIONNAIRE DATA ANALYSIS CONCLUSION Figure 3.1: Steps in Methodology 3.4.1 Conceptualization Conceptualization is aimed at understanding the importance and basics of the work to be carried out. In this stage, the objectives of the project will be set and the problem will be stated. After that, literature review will be undertaken. 53 3.4.2 Literature Review The main aim in carrying out the literature review is to gather information on the topic. Former studies on the issues will be analyzed the scope of the topic. Relevant articles, journals, paperwork, thesis and books have been looking for. Few book and thesis are related to the topic, journal papers and proceeding also help to get more information. 3.4.3 Questionnaire A four and five scale Likert Type questionnaire has been used as research tools for collecting data concerning opinions and attitudes of experienced engineers in constructability. Likert Scale is a widely use instruments in measuring opinions, beliefs and attitudes (Devellis, 1991). The final form of the questionnaire consisted of four parts, as shown in Figure 3.2. The first part consists of the background of the respondent, such as his engineering field, years of experience, and etc. The second part consist of 18 Likerttype five scale questions, each presenting one constructability concept in design phase in highway project, and each requiring only one choice to be made out of five; Very Important, Important, Moderate, Little Important and Not Important. The third part was formulated to collect information regarding the rate of application of each constructability concept in design phase in highway project in Malaysia. The respondents were asked to evaluate the degree of application of design concept, by choosing one of the following 18 Likert type four scale questions 54 responses; High Application, Medium Application, Little Application and Not applied at all. The fourth part consists of one free question. The objective of the question is to have ideas of the problems faced by engineers and experienced highway construction personnel. Questionnaire has been done with the people who are expertise in highway projects. The researchers produce 70 questionnaires then distributed to the potential respondent in Kelantan, Terengganu and Johor (Johor Bharu). The questionnaires were distributed to professionals in fifty organizations registered with Institution of Engineers Malaysia (IEM) and were selected randomly that represent the clients, contractors and consultant. 55 Start Part One: Demographics 7 Questions Part Two: Degree of Importance 18 Questions Part Three: Degree of Application 18 Questions Part Four: Feedback 1 Question End Figure 3.2: Questionnaire Flow Chart 56 3.4.4 Analysis The collected data were analyzed by using the Statistical for Social Science (SPSS) program version 11.0. Frequency and average index method is adopted for analysis. The frequency and the percentage will be represented in the form of table and pie chart. 3.4.4.1 Average Index In part two and part three of the questionnaire, the respondents are asked to evaluate the level of importance and application of constructability concepts in design phase in highway projects in Malaysia. From the frequency analysis that have been done, the frequency value will be used in determining the average index value. Refer to Odeh and Batainneh, 2001, the average index value will be calculated using this formula: Average index = ∑ (aX), where X = n / N a = constant expressing the weight given N = total number of respondent n = variable expressing the frequency of respondent The classification of the rating scales proposed by Abd. Majid (1997) are as follows: 57 • “Very Satisfy” 1.00 < Average Index < 1.50 • “Satisfy” 1.50 ≤ Average Index < 2.50 • “Fair” 2.50 ≤ Average Index < 3.50 • “Less Satisfy” 3.50 ≤ Average Index < 4.50 • “Not Satisfy” 4.50 ≤ Average Index < 5.00 3.5 Development of Guidelines From the study and analysis, Design Phase Constructability Improvement Guidelines for Malaysian Highway Projects have been developed after an expert interview between two experience personnel from the highway projects for validation. CHAPTER 4 DATA ANALYSIS AND DISCUSSION 4.1 Introduction Data analysis was discussed for 35 questionnaires submitted. The questions asking included the three parts which are: i. Part One: Demographics Respondent’s background which included information about organization, education, field of specialization, position in the company, designing and working experience in highway projects. ii. Part Two: Opinions Respondent’s opinions about the degree of importance of the constructability concepts in the design phase in highway projects. 59 iii. Part Three: Opinions Respondent’s opinions about the degree of application of the constructability concepts in the design phase in highway projects. iv. 4.2 Part Four: Feedback Respondent’s Background Amongst the four parts included in the questionnaires, part one, which is demographic, is the only one referring to the respondent background. 4.2.1 Type of Organization Referring to Table 4.1 and Figure 4.1, 2.9% of the respondents (1 person) an owner, 48.6% (17 persons) works in consultant firms, 31.4% (11 persons) work with contractor and 17.1% (6 persons) in other type of organization like developer and etc. Table 4.1: Type of Organization Owner Consultant Contractor Others Total Frequency Percent 1 17 11 6 35 2.9 48.6 31.4 17.1 100.0 Valid Percent (%) 2.9 48.6 31.4 17.1 100.0 Cumulative Percent (%) 2.9 51.4 82.9 100.0 60 Others 17% Contractor 31% Owner 3% Consultant 49% Figure 4.1: Percentage of type of organization 4.2.2 Level of Education The level of education among the respondent in this study are from 60% (21 persons) have B.Sc, 17.1% (6 persons) are engineers or designers with M.Sc Qualification. The others qualifications are from PhD to Diploma in Civil Engineering request 22.9% (8 persons) which can refer to Table 4.2 and Figure 4.2 below. 61 Table 4.2: Level of Education B.Sc M.Sc Others Total Frequency Percent 21 6 8 35 60.0 17.1 22.9 100.0 Valid Percent (%) 60.0 17.1 22.9 100.0 Cumulative Percent (%) 60.0 77.1 100.0 Others 23% M.Sc 17% B.Sc 60% Figure 4.2: Percentage of level of education 4.2.3 Field Of Specialization Most of the respondent, 80% (28 persons) are civil engineers. Beside that, one respondent is Mechanical Engineer (2.9%). The others including Quantity Surveyor and Building personnel cover 17.1% or 6 persons. The proportioning is shown in the Table 4.3 and Figure 4.3. 62 Table 4.3: Field Of Specialization Civil Engineer Mechanical Eng Others Total Frequency Percent 28 1 6 35 80.0 2.9 17.1 100.0 Valid Percent (%) 80.0 2.9 17.1 100.0 Cumulative Percent (%) 80.0 82.9 100.0 Others 17% Mechanical Eng 3% Civil Engineer 80% Figure 4.3: Percentage of field of specialization 4.2.4 Position in Organization Table 4.4 and Figure 4.4 show the position holding by the respondent. 20% (7 persons) of the respondents are designers in their company or organization, 2.9% or 1 person is planner. Quantity surveyors are 14.3% or 5 persons of the respondents. The others site engineer, project manager, site supervisor, and etc are 62.9% or 22 persons. 63 Table 4.4: Position in Organization Designer Planner Quantity Surveyor Others Total Frequency Percent 7 1 5 22 35 20.0 2.9 14.3 62.9 100.0 Valid Percent (%) 20.0 2.9 14.3 62.9 100.0 Cumulative Percent (%) 20.0 22.9 37.1 100.0 Designer 20% Planner 3% Others 63% Quantity Surveyor 14% Figure 4.4: Percentage of Position in Organization 4.2.5 Number of Years Practiced in Designing in Highway Projects The highest percentages, 88.6% or 31 persons of the respondents have 0-5 years of experience. This is because most of the highway projects are under the supervision of civil engineers. Generally, in an organization the same persons are in charge of both buildings and highway projects. But 5.7% (2 persons) of respondents have 6-10 years of experiences in designing highway projects. The respondent with PhD qualification is 64 the only one who has more than 20 years of experience as shown in Table 4.5 and Figure 4.5. Table 4.5: Number of Years Practiced in Designing in Highway Projects 0-5 Years 6-10 Years 11-15 Years More than 20 Years Total Frequency Percent 31 2 1 1 35 88.6 5.7 2.9 2.9 100.0 6-10 Years 5.7% Valid Percent (%) 88.6 5.7 2.9 2.9 100.0 Cumulative Percent (%) 88.6 94.3 97.1 100.0 More than 20 Years 2.9% 11-15 Years 2.9% 0-5 Years 88.6% Figure 4.5: Percentage of Number of Years Practiced in Designing In Highway Projects 4.2.6 Number of Years Practiced in Working in Highway Projects The numbers of years practiced in working in highway projects as represented in Table 4.6 and Figure 4.6 shows that 91% (32 persons) the respondents have 0-5 years of 65 experience is 91.4% (32 persons), 2.9% (1 person) have 6-10 years, 2.9 %( 1 person) between 11-15 years and 2.9% (1 person) have more than 20 years. Table 4.6: Number of Years Practiced in Working in Highway Projects 0-5 Years 6-10 Years 11-15 Years More than 20 Years Total Frequency Percent 32 1 1 1 35 91.4 2.9 2.9 2.9 100.0 6-10 Years 3% Valid Percent (%) 91.4 2.9 2.9 2.9 100.0 Cumulative Percent (%) 91.4 94.3 97.1 100.0 More than 20 Years 3% 11-15 Years 3% 0-5 Years 91% Figure 4.6: Number of Years Practiced in Working in Highway Projects 66 4.3 Level Of Importance of Constructability Concepts The researcher will use two types of analysis; frequency analysis and average index. 4.3.1 Frequency Analysis Using the result of the data collected, the SPSS software is using to analyze the frequency analysis. 4.3.1.1 Carry out Thorough Investigation of the Site Referring to the Table 4.7 below, 77.1% of the respondent agreed that the first concept of constructability which is ‘Carry out Thorough Investigation of the Site’ is “very important” in the design phase in highway projects in Malaysia. For 20%, this concept is “important”, and only 1 person judges it “moderate”. Table 4.7: Carry out Thorough Investigation of the Site Moderate Important Very Important Total Frequency Percent 1 7 27 35 2.9 20.0 77.1 100.0 Valid Percent (%) 2.9 20.0 77.1 100.0 Cumulative Percent (%) 2.9 22.9 100.0 67 4.3.1.2 Provide Detail and Clear Design Information For the second concept, Table 4.8 shows that 57.1% of the respondents agreed that ‘Provide Detail and Clear Design Information’ is “very important” while 42.9% agreed that this concept is “important”. Table 4.8: Provide Detail and Clear Design Information Important Very Important Total Frequency Percent 15 20 35 42.9 57.1 100.0 Valid Percent (%) 42.9 57.1 100.0 Cumulative Percent (%) 42.9 100.0 4.3.1.3 Analyze Accessibility of the Jobsite ‘Analyze Accessibility of the Jobsite’ is also a key for constructability in design phase for highway projects. Table 4.9 shows that 54.3% of the respondent agreed that this concept is “very important”, 42.9% judged it “important” and 2.9% judged it “moderate”. Table 4.9: Analyze Accessibility of the Jobsite Moderate Important Very Important Total Frequency Percent 1 15 19 35 2.9 42.9 54.3 100.0 Valid Percent (%) 2.9 42.9 54.3 100.0 Cumulative Percent (%) 2.9 45.7 100.0 68 4.3.1.4 Investigate the Impacts of Design on Safety during Construction Table 4.10 shows that the constructability concept that is ‘Investigate the Impacts of Design on Safety during Construction’ is also important in design phase. 54.3% of the respondent found it “very important”, 28.6% as “important”, 14.3% “moderate” and 1% “little important”. Table 4.10: Investigate the Impacts of Design on Safety during Construction Little Important Moderate Important Very Important Total Frequency Percent 1 5 10 19 35 2.9 14.3 28.6 54.3 100.0 Valid Percent (%) 2.9 14.3 28.6 54.3 100.0 Cumulative Percent (%) 2.9 17.1 45.7 100.0 4.3.1.5 Consider Suitability of Designed Materials The other constructability concept that must be considered while designing is ‘Consider Suitability of Designed Materials’. Table 4.11 below shows that this concept is “very important” for 42.9%, “important” for 42.9% and the other 14.3% judged it “moderate”. 69 Table 4.11: Consider Suitability of Designed Materials Moderate Important Very Important Total Frequency Percent 5 15 15 35 14.3 42.9 42.9 100.0 Valid Percent (%) 14.3 42.9 42.9 100.0 Cumulative Percent (%) 14.3 57.1 100.0 4.3.1.6 Investigate the Practical Sequence of Construction ‘Investigate the Practical Sequence of Construction’ is one of the constructability concepts that need to be beware of by the designer in design process. 45.7% of the respondent judges it “very important”, 37.1% as “important”, 14.3% as “moderate” and the other 2.9% judged it of “little important”, as shown in Table 4.12 below. Table 4.12: Investigate the Practical Sequence of Construction Little Important Moderate Important Very Important Total Frequency Percent 1 5 13 16 35 2.9 14.3 37.1 45.7 100.0 Valid Percent (%) 2.9 14.3 37.1 45.7 100.0 Cumulative Percent (%) 2.9 17.1 54.3 100.0 70 4.3.1.7 Consider Adverse Weather Effect in Selecting Materials or Construction Methods Table 4.13 below shows that 17.1% of the respondents ‘Consider Adverse Weather Effect in Selecting Materials or Construction Methods’ is “very important”. It is “important” for 62.9%, 17.1% for “moderate” and 2.9% for “little important”. Table 4.13: Consider Adverse Weather Effect in Selecting Materials or Construction Methods Little Important Moderate Important Very Important Total Frequency Percent 1 6 22 6 35 2.9 17.1 62.9 17.1 100.0 Valid Percent (%) 2.9 17.1 62.9 17.1 100.0 Cumulative Percent (%) 2.9 20.0 82.9 100.0 4.3.1.8 Plan to Avoid Damage to Work by Subsequent Operations Table 4.14 shows that 28.6% of the respondents think that ‘Plan to Avoid Damage to Work by Subsequent Operations’ is “very important”, while 45.7% of them responded that it is “important”, and 25.7% judge it as “moderate”. 71 Table 4.14: Plan to Avoid Damage to Work by Subsequent Operations Moderate Important Very Important Total Frequency Percent 9 16 10 35 25.7 45.7 28.6 100.0 Valid Percent (%) 25.7 45.7 28.6 100.0 Cumulative Percent (%) 25.7 71.4 100.0 4.3.1.9 Investigate Any Unsuspected Unrealistic or Incompatible Tolerances ‘Investigate Any Unsuspected Unrealistic or Incompatible Tolerances’ is also one of the constructability concepts that have to be considered in design stages in highway projects in Malaysia and it supported by the respondent opinion in Table 4.15. 28.6% of the respondents respond it as “very important”, 45.7 as “important” and the other 25.7% respond it as “moderate”. Table 4.15: Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Moderate Important Very Important Total Frequency Percent 9 16 10 35 25.7 45.7 28.6 100.0 Valid Percent (%) 25.7 45.7 28.6 100.0 Cumulative Percent (%) 25.7 71.4 100.0 72 4.3.1.10 Design for the Skills and Resources Available The result in Table 4.16 shows that 34.3% of the respondent agree that the concept ‘Design for the Skills and Resources Available’ is “very important”, 34.3% judged it “important”, 25.7% as “moderate” and the other 2% as “little important”. Table 4.16: Design for the Skills and Resources Available Little Important Moderate Important Very Important Total Frequency Percent 2 9 12 12 35 5.7 25.7 34.3 34.3 100.0 Valid Percent (%) 5.7 25.7 34.3 34.3 100.0 Cumulative Percent (%) 5.7 31.4 65.7 100.0 4.3.1.11 Consider Storage Requirement at the Jobsite Table 4.17 below shows that 17.1% of the respondents agree that the constructability concept ‘Consider Storage Requirement at the Jobsite’ is “very important”, 60% as “important” and 22.9% as “moderate”. Table 4.17: Consider Storage Requirement at the Jobsite Moderate Important Very Important Total Frequency Percent 8 21 6 35 22.9 60.0 17.1 100.0 Valid Percent (%) 22.9 60.0 17.1 100.0 Cumulative Percent (%) 22.9 82.9 100.0 73 4.3.1.12 Design for Minimum Time Below Ground From the Table 4.18 below, it can be noticed that 22.9% of the respondent agreed that ‘Design for Minimum Time below Ground’ is “very important”, 37.1% think it is “important” and 40% “moderate”. Table 4.18: Design for Minimum Time below Ground Moderate Important Very Important Total Frequency Percent 14 13 8 35 40.0 37.1 22.9 100.0 Valid Percent (%) 40.0 37.1 22.9 100.0 Cumulative Percent (%) 40.0 77.1 100.0 4.3.1.13 Design for Early Enclosure From the Table 4.19 below, the constructability concept which is ‘Design for Early Enclosure’ is “very important” for 20% of the respondents, 48.6% for “important”, 20% for “moderate” and 11.4% for “little important”. Table 4.19: Design for Early Enclosure Little Important Moderate Important Very Important Total Frequency Percent 4 7 17 7 35 11.4 20.0 48.6 20.0 100.0 Valid Percent (%) 11.4 20.0 48.6 20.0 100.0 Cumulative Percent (%) 11.4 31.4 80.0 100.0 74 4.3.1.14 Encourage Standardization/Repetition The study shows that the respondent opinion is as follows; 11.4% of them respond that ‘Encourage Standardization/Repetition’ is “very important”, more than half of them 60% respond it is “important”, and 28.6% of them respond it is “moderate”. Table 4.20: Encourage Standardization/Repetition Frequency Percent Valid Percent (%) 10 21 4 35 28.6 60.0 11.4 100.0 28.6 60.0 11.4 100.0 Moderate Important Very Important Total Cumulative Percent (%) 28.6 88.6 100.0 4.3.1.15 Employ Any Visualization Tools to Avoid Physical Interference From the survey that have been done, it can be indicated that, 14.3% of the respondent agreed that ‘Employ Any Visualization Tools to Avoid Physical Interference’ is a “very important” constructability concept in design phase in highway projects. 51.4% agreed that it is “important”, 28.6% respond it as “moderate” and 5.7% respond it as “little important”. Table 4.21: Employ Any Visualization Tools to Avoid Physical Interference Little Important Moderate Important Very Important Total Frequency Percent 2 10 18 5 35 5.7 28.6 51.4 14.3 100.0 Valid Percent (%) 5.7 28.6 51.4 14.3 100.0 Cumulative Percent (%) 5.7 34.3 85.7 100.0 75 4.3.1.16 Design for Simply Assembly From Table 4.22 below, it indicates that 11.4% of the respondent respond that Design For Simply Assembly respond it as “very important”, 54.3% respond it as “important”, 25.7% respond it as “moderate”, 5.7% as “little important” and 2.9% respond it as “not important”. Table 4.22: Design for Simply Assembly Not Important Little Important Moderate Important Very Important Total Frequency Percent 1 2 9 19 4 35 2.9 5.7 25.7 54.3 11.4 100.0 Valid Percent (%) 2.9 5.7 25.7 54.3 11.4 100.0 Cumulative Percent (%) 2.9 8.6 34.3 88.6 100.0 4.3.1.17 Design to Avoid Return Visit by Trade ‘Design to Avoid Return Visit by Trade’ is also one of the concepts that should be considered by designer in constructability in highway projects. More than half of the respondent agreed that it is “important”, 8.6% respond it is “very important”, 31.4% it is “moderate”, and 8.6% it is “little important”. 76 Table 4.23: Design to Avoid Return Visit by Trade Little Important Moderate Important Very Important Total Frequency Percent 3 11 18 3 35 8.6 31.4 51.4 8.6 100.0 Valid Percent (%) 8.6 31.4 51.4 8.6 100.0 Cumulative Percent (%) 8.6 40.0 91.4 100.0 4.3.1.18 Design For Preassembly and/or Modularization Referring to Table 4.24 below, it is seen that 5.7% of the respondent ‘Design For Preassembly and/or Modularization’ is “very important”, 37.1% respond it is “important”, 48.6% it is “moderate”, 5.7% respond it is “little important” and 2.9% it is “not important”. Table 4.24: Design For Preassembly and/or Modularization Not Important Little Important Moderate Important Very Important Total Frequency Percent 1 2 17 13 2 35 2.9 5.7 48.6 37.1 5.7 100.0 Valid Percent (%) 2.9 5.7 48.6 37.1 5.7 100.0 Cumulative Percent (%) 2.9 8.6 57.1 94.3 100.0 77 4.3.2 Average Index Analysis for Degree of Importance of Constructability Concepts in the Design Phase in Highway Projects In analyzing the data using the average index, the following assumed values have been used for the degree of importance of Constructability Concepts during the Design Phase in Highway Projects; “Very Important”, “Important”, “Moderate”, “Little Importance”, and “Not Important” and were coded as 5, 4, 3, 2 and 1 respectively. Table 4.25 shows the overall results for the Average Index Value for Degree of Importance of Constructability Concepts during the Design Phase. It can be seen that, the highest average index which is “Very Important” is 4.74 and the lowest value is 3.37 which is “moderate”. The highest 4.74 belongs to ‘Carry out Thorough Investigation of The Site’ and the lowest is ‘Design For Preassembly and/or Modularization’ with the index value 3.37. The “Very Important” concept for the degree of importance of constructability concepts in design phase in highway project that are the highest value 4.74 belongs to ‘Carry out Thorough Investigation of The Site’. This is followed by ‘Provide Detail and Clear Design Information’ (4.57) and ‘Analyze Accessibility of the Jobsite’ (4.51). The “Important” concepts are ‘Investigate the Impacts of Design on Safety During Construction’ (4.34), ‘Consider Suitability of Designed Materials’ (4.29), ‘Investigate the Practical Sequence of Construction’ (4.26), ‘Consider Adverse Weather Effect in Selecting Materials or Construction Methods’ (4.23), ‘Plan to Avoid Damage to Work by Subsequent Operations’ (4.03), ‘Investigate Any Unsuspected Unrealistic or Incompatible Tolerances’ (4.03), ‘Design for the Skills and Resources Available’ (3.97), 78 ‘Consider Storage Requirement at the Jobsite’ (3.94), ‘Design for Minimum Time Below Ground’ (3.83), ‘Design for Early Enclosure’(3.83), ‘Encourage Standardization/ Repetition’ (3.77), ‘Employ Any Visualization Tools to Avoid Physical Interference’ (3.74), ‘Design for Simply Assembly’ (3.66) and ‘Design to Avoid Return Visit by Trade’ (3.60). The only one concept that is moderate is ‘Design for Preassembly and/or Modularization’ with the index value 3.37. From the results above, it can be conclude that all the 18 constructability concepts that are studying are important, with the overall average index which is 4.04. 79 Table 4.25: Average Index Value for Degree of Importance of Constructability Concepts during the Design Phase Respondent’s Frequency 1.Carry Out Thorough Investigation of The Site 2.Provide Detail and Clear Design Information 3.Analyze Accessibility of the Jobsite 4.Investigate the Impacts of Design on Safety During Construction 5.Consider Suitability of Designed Materials 6.Investigate the Practical Sequence of Construction 7.Consider Adverse Weather Effect in Selecting Materials or Construction Methods 8.Plan to Avoid Damage to Work by Subsequent Operations 9.Investigate Any Unsuspected Unrealistic or Incompatible Tolerances 10.Design for the Skills and Resources Available 11.Consider Storage Requirement at the Jobsite 12.Design for Minimum Time Below Ground 13.Design for Early Enclosure 14.Encourage Standardization/Repetition 15.Employ Any Visualization Tools to Avoid Physical Interference 16.Design for Simply Assembly 17.Design to Avoid Return Visit by Trade 18.Design For Preassembly and/or Modularization OVERALL AVERAGE INDEX F 0 0 0 0 0 0 1 % 0.0 0.0 0.0 0.0 0.0 0.0 f 0 0 0 1 0 1 2 % 0.0 0.0 0.0 2.9 0.0 2.9 f 1 0 1 5 5 5 3 % 2.9 0.0 2.9 14.3 14.3 14.3 f 7 15 15 10 15 13 4 % 20.0 42.9 42.9 28.6 42.9 37.1 f 27 20 19 19 15 16 5 % 77.1 57.1 54.3 54.3 42.9 45.7 Total f % 35 100.0 35 100.0 35 100.0 35 100.0 35 100.0 35 100.0 0 0.0 6 2.9 6 17.1 22 62.9 6 17.1 35 100.0 0 0 0 0 0 0 0 0 1 0 1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.9 0.0 2.9 0 0 2 0 0 0 4 2 2 3 2 0.0 0.0 5.7 0.0 0.0 0.0 11.4 5.7 5.7 8.6 5.7 9 9 9 8 14 10 7 10 9 11 17 25.7 25.7 25.7 22.9 40.0 28.6 20.0 28.6 25.7 31.4 48.6 16 16 12 21 13 21 17 18 19 18 13 45.7 10 28.6 35 100.0 45.7 10 28.6 35 100.0 34.3 12 34.3 35 100.0 60.0 6 17.1 35 100.0 37.1 8 22.9 35 100.0 60.0 4 11.4 35 100.0 48.6 7 20.0 35 100.0 51.4 5 14.3 35 100.0 54.3 4 11.4 35 100.0 51.4 3 8.6 35 100.0 37.1 2 5.7 35 100.0 *1=Not Important, 2=Little Important, 3= Moderate, 4=Important, 5=Very Important Average Position Index 4.74 1 4.57 2 4.51 3 4.34 4 4.29 5 4.26 6 4.23 7 4.03 4.03 3.97 3.94 3.83 3.83 3.77 3.74 3.66 3.60 3.37 4.04 8 9 10 11 12 13 14 15 16 17 18 80 5.00 4.74 4.57 4.51 4.34 4.29 4.26 4.23 4.50 Average Value 4.00 4.03 4.03 3.97 3.94 3.83 3.83 3.77 3.74 3.66 3.6 3.50 3.37 3.00 2.50 2.00 1.50 1.00 0.50 0.00 C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 Constructability Concepts Where C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 Carry Out Thorough Investigation of The Site Provide Detail and Clear Design Information Analyze Accessibility of the Jobsite Investigate the Impacts of Design on Safety During Construction Consider Suitability of Designed Materials Investigate the Practical Sequence of Construction Consider Adverse Weather Effect in Selecting Materials or Construction Methods Plan to Avoid Damage to Work by Subsequent Operations Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Design for the Skills and Resources Available Consider Storage Requirement at the Jobsite Design for Minimum Time Below Ground Design for Early Enclosure Encourage Standardization/Repetition Employ Any Visualization Tools to Avoid Physical Interference Design for Simply Assembly Design to Avoid Return Visit by Trade Design For Preassembly and/or Modularization Figure 4.7: Degree of Importance of Constructability Concepts during the Design Phase 81 4.4 Level Of Application of Constructability Concepts In this part, detail analysis using the SPSS program were use to clarify the objectives. The researcher will use two types of analysis which are frequency analysis and average index. 4.4.1 Frequency Analysis Using the result from the questionnaire, the SPSS software is used to do the frequency analysis of the level of application of constructability concepts in highway projects. 4.4.1.1 Carry out Thorough Investigation of the Site Referring to Table 4.26, it is seen that 65.7% of the respondents agreed that ‘Carry out Thorough Investigation of the Site’ is highly applied and the other 34.3% it is in “medium application". Table 4.26: Carry Out Thorough Investigation of the Site Medium Application High Application Total Frequency Percent 12 23 35 34.3 65.7 100.0 Valid Percent (%) 34.3 65.7 100.0 Cumulative Percent (%) 34.3 100.0 82 4.4.1.2 Employ Any Visualization Tools to Avoid Physical Interference Table 4.27 shows that 11.4% of the respondent agreed that this concept is highly applied, 60% judged it of “medium application”, and 28.6% of “little application”. Table 4.27: Employ Any Visualization Tools to Avoid Physical Interference Little Application Medium Application High Application Total Frequency Percent 10 21 4 35 28.6 60.0 11.4 100.0 Valid Percent (%) 28.6 60.0 11.4 100.0 Cumulative Percent (%) 28.6 88.6 100.0 4.4.1.3 Encourage Standardization/Repetition For 31.4% of the respondents ‘Encourage Standardization/Repetition’ is high applied, for 57.1% it is medium applied, 8.6% think is “little application” and the other 2.9% respond it “not applied at all”. Table 4.28 shows the percentage of this concept. Table 4.28: Encourage Standardization/Repetition Not Applied At All Little Application Medium Application High Application Total Frequency Percent 1 3 20 11 35 2.9 8.6 57.1 31.4 100.0 Valid Percent (%) 2.9 8.6 57.1 31.4 100.0 Cumulative Percent (%) 2.9 11.4 68.6 100.0 83 4.4.1.4 Consider Storage Requirement at the Jobsite ‘Consider Storage Requirement at the Jobsite’ is one of the constructability concepts that have been applying in design phase in highway projects in Malaysia. Table 4.29 shows that 34.3% of the respondent said that it is highly applied, 57.1% said it is “medium application” and 8.6% respond it as “little application”. Table 4.29: Consider Storage Requirement at the Jobsite Little Application Medium Application High Application Total Frequency Percent 3 20 12 35 8.6 57.1 34.3 100.0 Valid Percent (%) 8.6 57.1 34.3 100.0 Cumulative Percent (%) 8.6 65.7 100.0 4.4.1.5 Design for Minimum Time below Ground Refer to Table 4.30, it shows that 17.1% of the respondent replied that this concept is “high application” in design phase in the highway projects in Malaysia. 62.9% respond it is “medium application” and 20% of them respond it as “little application”. Table 4.30: Design for Minimum Time below Ground Little Application Medium Application High Application Total Frequency Percent 7 22 6 35 20.0 62.9 17.1 100.0 Valid Percent (%) 20.0 62.9 17.1 100.0 Cumulative Percent (%) 20.0 82.9 100.0 84 4.4.1.6 Investigate the Practical Sequence of Construction Refer to the Table 4.31, it shows that ‘Investigate the Practical Sequence of Construction’ have been applying in the highway projects with 40% of the respondent respond it as “high application”, 31.4% respond it as “medium application”, 25.7% respond it as “little application” and 2.9% respond it as “not applied at all”. Table 4.31: Investigate the Practical Sequence of Construction Frequency Percent 1 9 11 14 35 2.9 25.7 31.4 40.0 100.0 Not Applied At All Little Application Medium Application High Application Total Valid Percent (%) 2.9 25.7 31.4 40.0 100.0 Cumulative Percent (%) 2.9 28.6 60.0 100.0 4.4.1.7 Design for Simply Assembly For 37.1% of the respondent respond this concept is “highly applied”, 45.7% respond it is “medium application”, 14.3 respond it is “little application” and 2.9% respond it is “not applied at all”. Table 4.32: Design for Simply Assembly Not Applied At All Little Application Medium Application High Application Total Frequency Percent 1 5 16 13 35 2.9 14.3 45.7 37.1 100.0 Valid Percent (%) 2.9 14.3 45.7 37.1 100.0 Cumulative Percent (%) 2.9 17.1 62.9 100.0 85 4.4.1.8 Design for the Skills and Resources Available Referring to Table 4.33, 37.1% of the respondent said it is highly applied, 57.1% of the respondent found it as “medium application” and for 5.7% “little application”. Table 4.33: Design for the Skills and Resources Available Little Application Medium Application High Application Total Frequency Percent 2 20 13 35 5.7 57.1 37.1 100.0 Valid Percent (%) 5.7 57.1 37.1 100.0 Cumulative Percent (%) 5.7 62.9 100.0 4.4.1.9 Investigate the Impacts of Design on Safety during Construction ‘Investigate the Impacts of Design on Safety during Construction’ is one of the constructability concepts that have been applying in highway projects in Malaysia. 42.9% of the respondent agreed it is “high application”, 40% it is “medium application” and the other 17.1% it is “little application”. 86 Table 4.34: Investigate the Impacts of Design on Safety during Construction Little Application Medium Application High Application Total Frequency Percent 6 14 15 35 17.1 40.0 42.9 100.0 Valid Percent (%) 17.1 40.0 42.9 100.0 Cumulative Percent (%) 17.1 57.1 100.0 4.4.1.10 Analyze Accessibility of the Jobsite Referring to the Table 4.35, it can be seen that 42.9% of the respondent considered this concept as “high application”, 40% as “medium application” and 17.1% as “little application”. Table 4.35: Analyze Accessibility of the Jobsite Little Application Medium Application High Application Total Frequency Percent 6 14 15 35 17.1 40.0 42.9 100.0 Valid Percent (%) 17.1 40.0 42.9 100.0 Cumulative Percent (%) 17.1 57.1 100.0 4.4.1.11 Design For Preassembly and/or Modularization The level of application of ‘Design For Preassembly and/or Modularization’ concept, is high for 8.6% of the respondent, medium 68.6%, and little application for 22.9%. 87 Table 4.36: Design For Preassembly and/or Modularization Little Application Medium Application High Application Total Frequency Percent 8 24 3 35 22.9 68.6 8.6 100.0 Valid Percent (%) 22.9 68.6 8.6 100.0 Cumulative Percent (%) 22.9 91.4 100.0 4.4.1.12 Investigate Any Unsuspected Unrealistic or Incompatible Tolerances From Table 4.37 below, it can be seen that this concept’s level of application is high for 20% of the respondent, medium for more than half of the respondent (57.1%) and little for 22.9%. Table 4.37: Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Little Application Medium Application High Application Total Frequency Percent 8 20 7 35 22.9 57.1 20.0 100.0 Valid Percent (%) 22.9 57.1 20.0 100.0 Cumulative Percent (%) 22.9 80.0 100.0 88 4.4.1.13 Design to Avoid Return Visit by Trade Majority of the respondent (45.7%) classified ‘Design to Avoid Return Visit by Trade’ in medium level of application, whereas 28.6% clarified it as “high application”, 22.9% as “little application”. This concept is “not applied at all” for 2.9% of the respondent’s opinion. Table 4.38: Design to Avoid Return Visit by Trade Not Applied At All Little Application Medium Application High Application Total Frequency Percent 1 8 16 10 35 2.9 22.9 45.7 28.6 100.0 Valid Percent (%) 2.9 22.9 45.7 28.6 100.0 Cumulative Percent (%) 2.9 25.7 71.4 100.0 4.4.1.14 Design for Early Enclosure The result from Table 4.39 below show that majority of the respondent (74.3%) agreed that ‘Design for Early Enclosure’ is of medium level of application, 14.3% respond it as “high application”, 8.6% “little application”, and 2.9% respond as “not applied at all”. Table 4.39: Design for Early Enclosure Not Applied At All Little Application Medium Application High Application Total Frequency Percent 1 3 26 5 35 2.9 8.6 74.3 14.3 100.0 Valid Percent (%) 2.9 8.6 74.3 14.3 100.0 Cumulative Percent (%) 2.9 11.4 85.7 100.0 89 4.4.1.15 Provide Detail and Clear Design Information 57.9% of the respondents accepted that ‘Provide Detail and Clear Design Information’ have been “medium application” in design phase constructability concepts in highway projects in Malaysia. 37.1% respond it as high level of application, and 5.7% as little level of application. Table 4.40: Provide Detail and Clear Design Information Little Application Medium Application High Application Total Frequency Percent 2 20 13 35 5.7 57.1 37.1 100.0 Valid Percent (%) 5.7 57.1 37.1 100.0 Cumulative Percent (%) 5.7 62.9 100.0 4.4.1.16 Plan to Avoid Damage to Work by Subsequent Operations From Table 4.41, the level of application of ‘Plan to Avoid Damage to Work by Subsequent Operations’ is high for 40% of the respondents, medium for 40%, and little for the other 20%. Table 4.41: Plan to Avoid Damage to Work by Subsequent Operations Little Application Medium Application High Application Total Frequency Percent 7 14 14 35 20.0 40.0 40.0 100.0 Valid Percent (%) 20.0 40.0 40.0 100.0 Cumulative Percent (%) 20.0 60.0 100.0 90 4.4.1.17 Consider Suitability of Designed Materials ‘Consider Suitability of Designed Materials’ level of application is high for 54.3% of the respondents, medium for 40%, and little for 5.7%. Table 4.42: Consider Suitability of Designed Materials Frequency Percent 2 14 19 35 5.7 40.0 54.3 100.0 Little Application Medium Application High Application Total Valid Percent (%) 5.7 40.0 54.3 100.0 Cumulative Percent (%) 5.7 45.7 100.0 4.4.1.18 Consider Adverse Weather Effect in Selecting Materials or Construction Methods 31.4% of the respondent agreed that this concept application is “high application”, followed by 48.6% of respond for “medium application”, 17.1% “little application”, and 2.9% of respond for “not applied at all”. Table 4.43: Consider Adverse Weather Effect in Selecting Materials or Construction Methods Not Applied At All Little Application Medium Application High Application Total 2.9 17.1 Valid Percent (%) 2.9 17.1 Cumulative Percent (%) 2.9 20.0 17 48.6 48.6 68.6 11 35 31.4 100.0 31.4 100.0 100.0 Frequency Percent 1 6 91 4.4.2 Average Index Analysis for Degree of Application of Constructability Concepts in the Design Phase in Highway Projects In analyzing the data using the average index, the following assumed values have used. “High Application”, “Medium Application”, “Little Application” and “Not Applied At All”, and were coded as 4, 3, 2 and 1 respectively. Table 4.44 shows the overall results for the Average Index Value for Degree of Application of Constructability Concepts during the Design Phase. From the result that shown in Table 4.44, the highest average index for the 18 constructability concepts is 3.66 which is “high application” and the lowest value is 2.83 which is “medium application”. The highest value 3.66 belongs to ‘Carry out Thorough Investigation of The Site’ and the lowest is ‘Consider Adverse Weather Effect in Selecting Materials or Construction Methods’ with the index value 2.83. The “high application” concept for the degree of importance of constructability concepts in design phase in highway project is the highest value, 3.66, and belongs to ‘Carry out Thorough Investigation of The Site’. The other concepts are “medium application”; ‘Employ Any Visualization Tools to Avoid Physical Interference’ (3.37), ‘Encourage Standardization/Repetition’ (3.31), ‘Consider Storage Requirement at the Jobsite’ (3.26), ‘Design for Minimum Time Below Ground’ (3.26), ‘Investigate the Practical Sequence of Construction’ (3.26), ‘Design for Simply Assembly’ (3.20), ‘Design for the Skills and Resources Available’ (3.20), ‘Investigate the Impacts of Design on Safety During Construction’ (3.17), ‘Analyze Accessibility of the Jobsite’ (3.17), ‘Design for Preassembly and/or Modularization’ (3.09), ‘Investigate Any Unsuspected Unrealistic or Incompatible Tolerances’ (3.09), 92 ‘Design to Avoid Return Visit by Trade’ (3.00), ‘Design for Early Enclosure’ (3.00), ‘Provide Detail and Clear Design Information’ (2.97), ‘Plan to Avoid Damage to Work by Subsequent Operations’ (2.97), ‘Consider Suitability of Designed Materials’ (2.86), and ‘Consider Adverse Weather Effect in Selecting Materials or Construction Methods’ (2.83). From the result above, it can be conclude that all the 18 constructability concepts that are studying can be groups into two groups; medium and high application. Only one concept is categorized “high application” and the others are “medium application”. The overall concepts are medium in application for the design phase in highway projects, with the overall average index of 3.15. 93 Table 4.44: Average Index Value for Degree of Application of Constructability Concepts during the Design Phase Respondent’s Frequency 1.Carry Out Thorough Investigation of The Site 2.Employ Any Visualization Tools to Avoid Physical Interference 3.Encourage Standardization/Repetition 4.Consider Storage Requirement at the Jobsite 5.Design for Minimum Time Below Ground 6.Investigate the Practical Sequence of Construction 7.Design for Simply Assembly 8.Design for the Skills and Resources Available 9.Investigate the Impacts of Design on Safety During Construction 10.Analyze Accessibility of the Jobsite 11.Design For Preassembly and/or Modularization 12.Investigate Any Unsuspected Unrealistic or Incompatible Tolerances 13.Design to Avoid Return Visit by Trade 14.Design for Early Enclosure 15.Provide Detail and Clear Design Information 16.Plan to Avoid Damage to Work by Subsequent Operations 17.Consider Suitability of Designed Materials 18.Consider Adverse Weather Effect in Selecting Materials or Construction Methods OVERALL AVERAGE INDEX f 0 0 0 0 0 0 0 0 1 1 1 1 1 1 0 0 0 1 % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.9 2.9 2.9 2.9 2.9 2.9 0.0 0.0 0.0 f 0 2 2 3 6 6 2 7 3 5 6 9 3 8 7 8 8 2 % 0.0 5.7 5.7 8.6 17.1 17.1 5.7 20.0 8.6 14.3 17.1 25.7 8.6 22.9 20.0 22.9 22.9 f 12 14 20 20 14 14 20 14 20 16 17 11 26 16 22 20 24 3 4 Total Average Position % f % f % Index 34.3 23 65.7 35 100.0 3.66 1 40.0 18 51.4 35 100.0 3.37 2 57.1 13 37.1 35 100.0 3.31 3 57.1 12 34.3 35 100.0 3.26 4 40.0 15 42.9 35 100.0 3.26 5 40.0 15 42.9 35 100.0 3.26 6 57.1 12 34.3 35 100.0 3.20 7 40.0 14 40.0 35 100.0 3.20 8 57.1 11 31.4 35 100.0 3.17 9 45.7 13 37.1 35 100.0 3.17 10 48.6 11 31.4 35 100.0 3.09 11 31.4 14 40.0 35 100.0 3.09 12 74.3 5 14.3 35 100.0 3.00 13 45.7 10 28.6 35 100.0 3.00 14 62.9 6 17.1 35 100.0 2.97 15 57.1 7 20.0 35 100.0 2.97 16 68.6 3 8.6 35 100.0 2.86 17 0 0.0 10 28.6 21 60.0 4 11.4 35 100.0 *1=Not Applied At All, 2=Little Application, 3= Medium Application, 4=High Application 2.83 18 3.15 94 4.0 3.66 3.37 3.31 3.26 3.26 3.26 3.20 3.20 3.17 3.17 3.09 3.09 3.5 Average Index 3.0 3.00 3.00 2.97 2.97 2.86 2.83 2.5 2.0 1.5 1.0 0.5 0.0 C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 Constructability Conce pts Where C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 Carry Out Thorough Investigation of the Site Employ Any Visualization Tools to Avoid Physical Interference Encourage Standardization/Repetition Consider Storage Requirement at the Jobsite Design for Minimum Time below Ground Investigate the Practical Sequence of Construction Design for Simply Assembly Design for the Skills and Resources Available Investigate the Impacts of Design on Safety during Construction Analyze Accessibility of the Jobsite Design for Preassembly and/or Modularization Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Design to Avoid Return Visit by Trade Design for Early Enclosure Provide Detail and Clear Design Information Plan to Avoid Damage to Work by Subsequent Operations Consider Suitability of Designed Materials Consider Adverse Weather Effect in Selecting Materials or Construction Methods Figure 4.8: Degree of Application of Constructability Concepts during the Design Phase 95 4.5 The Development of Design Phase Constructability Improvement Concepts For Malaysian Highway Projects From the study, the guidelines of Design Phase Constructability Improvement Concepts for Malaysian Highway Projects have developed by having the interview with Encik Kamaruzzaman and Mr Lai Ming Siong, the highway engineers from Gemilang Bina Sdn. Bhd. From the interview, they proposed the researcher to divide the guidelines into two parts which is ‘very important’ and ‘important’ concepts. The ‘very important’ and ‘important’ concepts are the concepts that are important and must be taken into consideration by the design engineers in design process, but the ‘very important’ should be more attention to the designer. The concepts developed represent current best practice in constructability that aim at encouraging the project team to apply them, where appropriate, to their projects. By the project team systematically addressing and expanding on all the issues presented in each of the concepts a high level of constructability on a project can be achieved. The titles of the concepts are given in Figure 4.9 below. 96 DESIGN PHASE CONSTRUCTABILITY IMPROVEMENT CONCEPTS FOR MALAYSIAN HIGHWAY PROJECTS VERY IMPORTANT CONCEPTS 1. Carry out Thorough Investigation of the Site Constructability is improved when the information gathered from site investigation is thorough and complete. 2. Provide Detail and Clear Design Information Constructability is improved when thorough and clear presentation of design information before the start of construction. 3. Analyze Accessibility of the Jobsite Constructability is improved when the accessibility needs of manpower, material and equipment are reflected in the detailed designs. IMPORTANT CONCEPTS 1. Investigate the Impacts of Design on Safety during Construction The design produced by the designers should enable the contractor to carry out their works in a safe like manner. 2. Consider Suitability of Designed Materials Products and materials to be specified during design should be selected with care, particularly, any which have not long been established and accepted within the industry. It is recommended that only products and materials, which have been proven suitable to be used, are selected. 3. Investigate the Practical Sequence of Construction The method of construction of project should encourage the most effective sequence of building operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimised delay. 4. Consider Adverse Weather Effect in Selecting Materials or Construction Methods Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimised. 97 5. Plan to Avoid Damage to Work by Subsequent Operations The design should enable work to be carried out in a workman like manner without risk of damage to adjacent finished elements and with minimum requirement for special protection. 6. Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Constructability is improved when the design for building assembly observe the tolerances which are normally achievable in site conditions, making allowances for the differences between fine factory tolerances and those of normal site construction. 7. Design for the Skills and Resources Available Constructability is improved when the technology of the design solution matched with the skills and resources available. 8. Consider Storage Requirement at the Jobsite Consideration should be given during the design stage to the location of material storage and unloading facilities. 9. Design for Minimum Time Below Ground Constructability is improved when the design minimize work below ground. 10. Design for Early Enclosure Constructability is improved when the design enables early enclosure of the construction. 11. Encourage Standardization/Repetition Constructability is improved when standardisation and repetition of design elements are maximised. 12. Employ Any Visualization Tools to Avoid Physical Interference Constructability is improved when visualisation tools are employed to visualise any possibility of physical interference during construction. 13. Design for Simply Assembly Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the building, particular element or group of elements. 14. Design to Avoid Return Visit by Trade Constructability is improved when the design enable work to be carried out by a trade at one work place and complete the work with as few return visit as possible. 15. Design For Preassembly and/or Modularization Constructability is improved when pre-fabrication, pre-asseambly, or module designs are considered early. Figure 4.9: Design Phase Constructability Improvement Concepts For Malaysian Highway Projects 98 4.4 Summary of analysis and results 35 sets of questionnaires were used to obtain data from the respondents who involved in highway projects in Kelantan, Terengganu and Johor Bharu. The questionnaire survey was divided into 4 major sections. The first part consisted of requests for relevant personal data of the respondent, such as the type of engineering work performing, years of experience and etc. The second part consisted of 18 Likerttype five scale questions each presenting one constructability concept in design phase in highway project and the third part was formulated to collect information regarding the rate of application of each constructability concept in design phase in highway project in Malaysia. The fourth part consisted of one question devoted to free response. All the collected data from the questionnaires are analysed by two methods which are Frequency and Average Index. Part One represent the demographic section which the related to respondent’s background as identify the type of organization, the level of study, the field of specialization, the position in organization and to determine the numbers of years practiced and working in highway projects. From the study, the researcher found that most of the respondent comes from the contractor and consultant firm. In Part Two, the respondents were asked to rate the degree of importance of the constructability concepts during the design phase in highway projects. The results show that for the eighteen concepts proposed, the total average index value is 4.04 which is importance in design phase highway projects in Malaysia. The average index values of the concepts also are consistent and it also can be seen same in the previous studies by Nima (2002) and Rosli (2004). It shows that most of the respondents have knowledge about constructability and its importance in achieving a good constructability. 99 In Part Three the respondents were asked to rate the degree of application of the constructability concepts during the design phase in highway projects. The results of the survey show that the respondents have categorized the concept as ‘medium application’. That shows that the respondents have applied these concepts but not fully in their projects. CHAPTER 5 CONCLUSION AND RECOMMENDATIONS 5.1 Conclusion From the literature review and the result obtained the conclusion according to the objectives of the study are as follows: 5.1.1 Objective 1: To identify the constructability concepts in highway projects. From the literature review, eighteen important design phase constructability concepts are applicable in highway projects. There were: 101 1. Carry out Thorough Investigation of the Site • Constructability is improved when the information gathered from site investigation is thorough and complete. 2. Provide Detail and Clear Design Information • Constructability is improved when thorough and clear presentation of design information before the start of construction. 3. Analyze Accessibility of the Jobsite • Constructability is improved when the accessibility needs of manpower, material and equipment are reflected in the detailed designs. 4. Investigate the Impacts of Design on Safety during Construction • The design produced by the designers should enable the contractor to carry out their works in a safe like manner. 5. Consider Suitability of Designed Materials • Products and materials to be specified during design should be selected with care, particularly, any which have not long been established and accepted within the industry. It is recommended that only products and materials, which have been proven suitable to be used, are selected. 6. Investigate the Practical Sequence of Construction • The method of construction of project should encourage the most effective sequence of project operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimised delay. 102 7. Consider Adverse Weather Effect in Selecting Materials or Construction Methods • Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimised. 8. Plan to Avoid Damage to Work by Subsequent Operations • The design should enable work to be carried out in a workman like manner without risk of damage to adjacent finished elements and with minimum requirement for special protection. 9. Investigate Any Unsuspected Unrealistic or Incompatible Tolerances • Constructability is improved when the design for building assembly observe the tolerances which are normally achievable in site conditions, making allowances for the differences between fine factory tolerances and those of normal site construction. 10. Design for the Skills and Resources Available • Constructability is improved when the technology of the design solution matched with the skills and resources available. 11. Consider Storage Requirement at the Jobsite • Consideration should be given during the design stage to the location of material storage and unloading facilities. 12. Design for Minimum Time below Ground • Constructability is improved when the design minimize work below ground. 13. Design for Early Enclosure • Constructability is improved when the design enables early enclosure of the construction. 103 14. Encourage Standardization/Repetition • Constructability is improved when standardisation and repetition of design elements are maximised. 15. Employ Any Visualization Tools to Avoid Physical Interference • Constructability is improved when visualisation tools are employed to visualise any possibility of physical interference during construction. 16. Design for Simply Assembly • Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the highway, particular element or group of elements. 17. Design to Avoid Return Visit by Trade • Constructability is improved when the design enable work to be carried out by a trade at on work place and complete the work with as few return visit as possible. 18. Design for Preassembly and/or Modularization • Constructability is improved when pre-fabrication, pre-asseambly, or module designs are considered early. 104 5.1.2 Objective 2: To identify the level of importance and application of constructability concepts in design phase highway projects. The respondents’ backgrounds were investigated in this research. From the total numbers of 35 respondents, majority are working with consultant and contractor firms. 48.6% work in consultant firms whereas 31.4% work with contractor. Mostly all of the respondents have B.Sc or Msc in Civil Engineering. They are civil engineers, designer and quantity surveyor. Most of them have achieved 0-5 years of practiced in designing and working in highway projects. In Part Two, the respondents was asked to rate the degree of importance of the constructability concepts during the design phase in highway projects. The result shows that all of the eighteen concepts that have been proposed are ‘important’ in design phase highway projects in Malaysia. This shows that most of the respondent have the knowledge about constructability and know how importance is these concepts in achieving a good constructability. In Part Three the respondent were asked to rate the degree of application of the constructability concepts during the design phase in highway projects. These concepts have been categorized in ‘medium application’, which shows that the respondents have applied these concepts but not fully in their projects. 105 5.1.3 Objective 3: To establish Design Phase Constructability Improvement Concepts for Malaysian Highway Projects. From the study, the concepts shown in Figure 4.9 are the Design Phase Constructability Improvement Concepts developed for Malaysian Highway Projects. The concepts developed represent current best practice in constructability that aimed at encouraging the project team to apply them, where appropriate, to their projects as shown in Figure 4.9. 5.2 Recommendations There are a few recommendations in achieving a successful constructability in design phase highway projects. a. The constructability guidelines proposed in this study is only limited to highway projects. It is recommended that similar guidelines should be developed for other types of projects. Since the similarity in term of the most important concepts of constructability that designers need to consider during the design process are obvious, therefore more effort should be focused on identifying the sub-factors under these most important concepts. b. It was highlighted that project performance will improve, as the level of design constructability gets higher. Since in this study there was no indication of the actual impact on project performance it is recommended that work should be carried out to determine the actual benefit gained from improved design constructability in highway projects. REFERENCES Adam, S. (1989). Practical Buildability. The Construction Industry Research and Information Association, London. Al-Hammad, A-mohsen and Assaf, S. (1996). Assessment of Work Performance of Maintenance Contractors In Saudi Arabia. Journal of Management in Engineering.ASCE. 16(1): 44-49. Anon (1986). Can Your Design Be Built? Civil Engineering. ASCE: 49-53. Boyce, W.J. (1991). Design for Constructability. Hydrocarbon Processing. 73(12): 81 CII (1986). Constructability – A Primer. Publication 3-1. Austin, Texas: Construction Industry Institute. CIRIA (1983). Buildability: An Assessment. Special Publication 26: CIRIA David N.Ford, Stuart, and Andrew. (2004). Managing Constructability Reviews to Reduce Highway Project Durations. Journal of Construction Engineering and Management, ASCE, Vol. 130, No.1, 33-42 Eldin, N.N. (1996). Constructability Improvements of Project Designs. Journal of Construction Engineering and Management. ASCE. 114(4): 631-639. 107 Felix, Geogina. (1997). Assessment of Constructability Practices Among General Contractors. Journal of Construction Engineering and Management, ASCE, Vol. 4, No.3, 114-123 Fischer, Tatum. (1997). Characteristics of Design Relevent Constructability Knowledge. Journal of Construction Engineering and Management, ASCE, Vol. 123, No.3, 253255 Fisher, D.J. and Rajan, N.(1996). Automated Constructability Analysis of Work-zone Traffic-Control Planning. Journal of Construction Engineering and Management, ASCE, Vol. 122, No.1,36-43 Ferguson, I. (1989). Buildability in Practice. London: Mitchell’s Professional Library. Ganah, A., Anumba, C. and Bouchlaghem, N. (2000). The Use of Visualisation to Communicate Information to Construction Sites. ARCOM 16th. Annual Conference. 6-8 September. Glasgow Caledonian University, UK: 833-842. Gambatese, J.A. and McManus, J.F. (1999). Discussion of the Constructibility Review Process: A Constructor’s Perspective, by Roy Mandelsohn. Journal of Management in Engineering. ASCE. 15(1): 93-94. Griffith, A and Sidwell, T. (1995). Constructability in Building and Engineering Projects. London: Mac Millan Press Ltd. Hassan, Z. (1997). CONPLAN: Construction Planning and Buildability Evaluation in an Integrated Intelligence Environment. Department of Surveying, University of Salford, UK: PhD. Thesis. Hugo, F., O’Connor, J.T. and Ward, W.V. (1990). Highway Constructability Guide. Research Project 3-6-88-1149. Centre for Transport Research. Uviversity of Texas. 108 James E. Rowing, Steven L. Kaspar. (1991). Constructability of Cable-Stayed Bridges. Journal of Construction Engineering and Management, ASCE, Vol. 117, No.2, 259275 Jergeas, P.E., John Van Der Put. (2001). Benefits Of Constructability On Construction Projects. Journal of Construction Engineering and Management, ASCE, Vol. 127, No.4, 281-290 Kirby, G..J, Douglas, A.F. and Donald, K.H. (1987). Improvement in Design Review Management. Journal of Construction Engineering and Management, ASCE, Vol. 114, No.1, 549-563 Madelsohn, M. (1997). The Constructability Review Process: A Constructor’s Perspective. Journal of Management in Engineering. ASCE. 13(3): 17-19. Nabil A Kartam. (1996). Making Effective Use of Construction Lessons Learned in Project Life Cycle. Journal of Construction Engineering and Management, ASCE, Vol. 122, No.1, 14-21 Nima, A.N. (2001). Constructability in the Malaysian Construction Industry., Faculty of Engineering, UPM, PhD. Thesis. Nima, Mohd R. Kadir, S. Jaafar. (2002). Constructability Concepts in West Port Highway In Malaysia. Journal of Construction Engineering and Management, ASCE, Vol. 128, No.4, 348-356. Nima, Mohd R. Kadir, S. Jaafar. (2004). Constructability Concepts in Kuala Selangor Cable-Stayed Bridge In Malaysia. Journal of Construction Engineering and Management, ASCE, Vol. 130, No.3, 315-321. 109 O’Connor J.T. and Davis, V.S. (1988). Constructability Improvement During Field Operations. Journal of Construction Engineering and Management. ASCE. 114(4):548-563. O’Connor, Tamer El-Diraby. (2000). Urban Freeway Reconstruction Planning: Case of Mockingbird Bridge. Journal of Construction Engineering and Management, ASCE, Vol. 126, No.1, 61-67. Philip, Gambatese, James. (2005). Assessing State Transportation Agency Constructability Implementation. Journal of Construction Engineering and Management, ASCE, Vol. 131, No.5, 569-578 Rosli Mohamad Zin (2004). Constructability Improvement of Project Design. Dept of Civil Engineering, UTM, Johor, Ph.D. Thesis. Russell, J.S. and Gugel, J.G. (1993). Comparison of Two Corporate Constructability Program. Journal of Construction Engineering and Management. ASCE. 119(4): 771-785. S.L. Hon, D.A. Gairns, O.D. Wilson. (1988). Buildability: A Research and Practice. Australian Institute of Building Papers. Stuart, Fisher, Suhel. (1998). Integrating Constructability Into Project Development: A Process Approach. Journal of Construction Engineering and Management, ASCE, Vol. 126, No.2, 81-88. Stuart, Fisher, Suhel. (1999). Constructability Issues In Highway Projects. Journal of Construction Engineering and Management, ASCE, Vol. 15, No.3, 60-68. Thomas E. Glavinich. (1995). Improving Constructability During Design Phase. Journal of Construction Engineering and Management, ASCE, Vol. 1, No.2.73-76. APPENDIX A Part One: Demographics Please, thick one box and fill in the blanks if you select others. Company Name: ………………………………………………………………………. Address: ………………………………………………………………………. ………………………………………………………………………. 1. What is the type of your organization or company? Owner Contractor Consultant Others, please Specify……………….. 2. What is the highest level of school you have completed? B.Sc M.Sc Others, please Specify……………….. 3. What is your field of specialization? Civil Engineering Mechanical Engineering Electrical Engineering Architect Others, please Specify……………….. 4. State your position in the organization? Designer Planner Quantity Surveyor Others, please Specify……………….. 5. State the number of years you have practiced designing of highway projects? 0-5 Years 6-10 Years 11-15 Years 16-20 Years More than 20 Years 6. State the number of years you practiced in working in highway projects? 0-5 Years 6-10 Years 11-15 Years 16-20 Years More than 20 Years Name: Date: Signature: Part Two: Opinions 112 1 Carry Out Thorough Investigation of the Site Constructability is improved when the information gathered from site investigation is thorough and complete. Thorough site surveys (including determination of ground conditions, underground hazards and other potential problems) are essential to avoid risk of delays and design changes during construction. 2 Design for Minimum Time Below Ground Constructability is improved when the design minimize work below ground. The application of this concept is important especially when the ground is hazardous, poor or wet. 3 Design for Simply Assembly Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the building, particular element or group of elements. 4 Encourage Standardization/Repetition The standardization of components is based on recognition that savings can be realized when the number of variations of components is kept minimum. 5 Design for Preassembly and/or Modularization Preassembly is a process by which various materials, prefabricated components and/or equipment are joined together at a remote location for subsequent installation as a unit. Preassembly often involves decoupling sequential activities into parallel activities; and A module is a product resulting from a series of remote assembly operations; it is usually the largest transportable unit or component of a facility. Modules may contain prefabricated components or preassemblies and are usually constructed away from the job site. 6 Analyze Accessibility of the Jobsite The effect of accessibility can sometimes be quite serious such as delay in progress, slowed productivity and increased damaged to completed work. 7 Employ Any Visualization Tools to Avoid Physical Interference Constructability is improved when visualization tools are employed to visualize any possibility of physical interference during construction. Computer visualization allows investigations to iron out difficulties that may occur before construction commences on site. 8 Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Particular attention should be given to the problems of fit which occur at the interfaces between different products, methods of construction, materials and method of manufacture, and suitable jointing methods should be adopted. 9 Investigate the Practical Sequence of Construction Constructability is improved when adequate consideration of practical sequence of construction is given. The method of construction of project should encourage the most effective sequence of building operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimized delay. 10 Plan to Avoid Damage to Work by Subsequent Operations Constructability is improved when the damage to work by subsequent operations is considered. Not Important Little Importance Moderate Important Constructability Concepts During the Design Phase Very important In your opinion, what is the degree of importance of the following concepts? (Tick one, please) 11 Consider Storage Requirement at the Jobsite Constructability is improved when storage requirement is adequately considered. Consideration should be given during the design stage to be location of material storage and unloading facilities. 12 Investigate the Impacts of Design on Safety During Construction Constructability is improved when the impact of design on safety during construction is adequately considered. The design produced by the designers should enable the contractor to carry out their works in a safe like manner. The design should be arranged so as to facilitate safe working in works such as foundation and earth works, when materials and components are being handled, and wherever traversing for access is necessary. 13 Design to Avoid Return Visit by Trade Constructability is improved when the design enable a trade or specialist to complete all its work at a work place with as few return visit as possible. 14 Design for the Skills and Resources Available Constructability is improved when the technology of the design solution matched with the skills and resources available. Any design is only good as skills available to execute it, either off-site or on-site. 15 Consider suitability of Designed Materials Constructability is improved when suitable and robust materials are used. Products and materials should be selected with care, particularly, any which have not long been established and accepted within the industry. 16 Provide detail and clear Design Information Constructability is improved when thorough and clear presentation of design information before the start of construction. Sufficient time and resources must be allowed for this in design budget. 17 Design for Early Enclosure Constructability is improved when the design enables early enclosure of the constructed building. 18 Consider Adverse Weather Effect in Selecting Materials or Construction Methods Constructability is improved when the effect of adverse weather is considered. Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimized. Not Important Little Importance Moderate Important Constructability Concepts During the Design Phase Very important 113 Part Three: Opinions 114 1 Carry Out Thorough Investigation of the Site Constructability is improved when the information gathered from site investigation is thorough and complete. Thorough site surveys (including determination of ground conditions, underground hazards and other potential problems) are essential to avoid risk of delays and design changes during construction. 2 Design for Minimum Time Below Ground Constructability is improved when the design minimize work below ground. The application of this concept is important especially when the ground is hazardous, poor or wet. 3 Design for Simply Assembly Constructability is improved when designs are simplified and configured to enable efficient construction. Designers should produce the simplest possible details compatible with the overall requirements for the building, particular element or group of elements. 4 Encourage Standardization/Repetition The standardization of components is based on recognition that savings can be realized when the number of variations of components is kept minimum. 5 Design for Preassembly and/or Modularization Preassembly is a process by which various materials, prefabricated components and/or equipment are joined together at a remote location for subsequent installation as a unit. Preassembly often involves decoupling sequential activities into parallel activities; and A module is a product resulting from a series of remote assembly operations; it is usually the largest transportable unit or component of a facility. Modules may contain prefabricated components or preassemblies and are usually constructed away from the job site. 6 Analyze Accessibility of the Jobsite The effect of accessibility can sometimes be quite serious such as delay in progress, slowed productivity and increased damaged to completed work. 7 Employ Any Visualization Tools to Avoid Physical Interference Constructability is improved when visualization tools are employed to visualize any possibility of physical interference during construction. Computer visualization allows investigations to iron out difficulties that may occur before construction commences on site. 8 Investigate Any Unsuspected Unrealistic or Incompatible Tolerances Particular attention should be given to the problems of fit which occur at the interfaces between different products, methods of construction, materials and method of manufacture, and suitable jointing methods should be adopted. 9 Investigate the Practical Sequence of Construction Constructability is improved when adequate consideration of practical sequence of construction is given. The method of construction of project should encourage the most effective sequence of building operations. Simple sequences enable each operation to be completed independently and without interruption. The sequence should assist the coordination of trades and minimized delay. Not Applied At All Little Application Medium Application Constructability Concepts During the Design Phase High Application In your opinion, what is the degree of application of the following concepts? (Tick one, please) 10 Plan to Avoid Damage to Work by Subsequent Operations Constructability is improved when the damage to work by subsequent operations is considered. 11 Consider Storage Requirement at the Jobsite Constructability is improved when storage requirement is adequately considered. Consideration should be given during the design stage to be location of material storage and unloading facilities. 12 Investigate the Impacts of Design on Safety During Construction Constructability is improved when the impact of design on safety during construction is adequately considered. The design produced by the designers should enable the contractor to carry out their works in a safe like manner. The design should be arranged so as to facilitate safe working in works such as foundation and earth works, when materials and components are being handled, and wherever traversing for access is necessary. 13 Design to Avoid Return Visit by Trade Constructability is improved when the design enable a trade or specialist to complete all its work at a work place with as few return visit as possible. 14 Design for the Skills and Resources Available Constructability is improved when the technology of the design solution matched with the skills and resources available. Any design is only good as skills available to execute it, either off-site or on-site. 15 Consider suitability of Designed Materials Constructability is improved when suitable and robust materials are used. Products and materials should be selected with care, particularly, any which have not long been established and accepted within the industry. 16 Provide detail and clear Design Information Constructability is improved when thorough and clear presentation of design information before the start of construction. Sufficient time and resources must be allowed for this in design budget. 17 Design for Early Enclosure Constructability is improved when the design enables early enclosure of the constructed building. 18 Consider Adverse Weather Effect in Selecting Materials or Construction Methods Constructability is improved when the effect of adverse weather is considered. Project constructed in localities where weather conditions are adverse presents a great challenge to both the designer and the constructor. Designers should investigate ways in which the exposure to temperatures extreme and the effects of rain may be minimized. Not Applied At All Little Application Medium Application Constructability Concepts During the Design Phase High Application 115