Construction Update

Prepared by Joseph Reyes, Director of Facilities

Presented to the Board: October 7, 2014

CURRENT PROJECTS

1. Building S – Science Building (813026) – 2013. 56,690 sq. ft. building, State of the Art Classrooms, Labs and Technology. State of the Art Planetarium.

October 11, 2013 - (RFP) Request for Proposal

December 10, 2013 - Project out to rebid

January 14, 2014 - Rebid opening

February 4, 2014 - Board awarded contract to Dilbeck and Sons of Salinas, CA

August 14, 2014 - Foundation Piles installation completed

September 12, 2014 – 1 st

of 5 mat slab pours

Spring Semester 2016 - Open for classes

2. Building D – Elevator (840104) – 2013 . An elevator will be installed in D, north side of the building.

Currently, the elevator in D south is not reliable and often breaks down. The new elevator will tie into D’s

ADA compliance work and make it easier for students coming from the main entrance, 411 Central Avenue, to get to the second and third floors of D.

DSA Approved Plans

Estimated Measure H cost $491,400

3. Building D – ADA Compliance (840103) – 2013.

The area on the west side of D will get a complete ADA upgrade to all of the pathways. In addition, the moat which is between the Student Center (C) and D will be filled allowing better access between the two buildings.

No plans

Estimated Measure H cost $541,500

OCCUPIED PROJECTS IN FINAL STAGES OF COMPLETION

Alisal Building-D Technical Training Building (in DSA close out process)

COMPLETED PROJECTS*

Date Closed Out

October 2004

November 2005

June 2006

December 2008

February 2009

September 2010

September 2010

December 2010

June 2010

January 2011

April 2011

August 2011

September 2011

September 2011

December 2011

December 2011

January 2012

January 2013

January 2013

April 2013

June 2013

June 2013

June 2013

June 2013

July 2013

August 2013

May 2012

Project Name

Campus Infrastructure Phase I

Parking Structure

Learning Resource Center (LRC)

Buildings D & E - Classrooms Refresh #1

Buildings D & E - Classrooms Refresh #2

Lighting Phase II

Buildings D & E - Classrooms Refresh #3

U - Pool Renovation

NE Landscape Project

Buildings D & E - Classrooms Refresh #4

Alisal Landscape Project

City Sidewalk Replacement

City Sidewalk Phase II

Alisal Campus Sign

Alisal Campus Bus Turnaround

Buildings D & E - Boiler/Chiller and Roof

Campus Infrastructure

Alisal Campus Additional Parking

Student Center

Building S - Annex Demotion

Campus Safety & Security Improvements

Campus Maps & Directional Signage

Building P - PE Field House

Solar Canopy Structures, Alisal Campus

Building D - First Floor/North Remodel

Alisal Campus Center for Applied Technology

Student Services Building C

* Completed means that all of the claims and paperwork have been submitted and no further action/claims on this project will be forthcoming from the District.

FUTURE PROJECTS

Building E - 1

ST

Floor /South

Building N - Remodel

Keyless Entry

Safety Cameras

Project

1) Building S - Science

Building

Budget

$29,143,341

% Completed

22%

Funding Source

Measure H

2) Building D - Elevator

$432,675 0% Measure H

3) Building D - ADA

$541,500 0% Measure H

Page 2 of 2