Construction Update Prepared by Joseph Reyes, Director, Maintenance Presented to the Board: May 5, 2015 CURRENT PROJECTS 1. Building S – Science Building (813026) – 2013. 56,690 sq. ft. building, State of the Art Classrooms, Labs and Technology. State of the Art Planetarium. October 11, 2013 - (RFP) Request for Proposal December 10, 2013 - Project out to rebid January 14, 2014 - Rebid opening February 4, 2014 - Board awarded contract to Dilbeck and Sons of Salinas, CA August 14, 2014 - Foundation Piles installation completed September 12, 2014 – 1st of 5 mat slab pours October 17, 2014 – 5 of 5 mat slab pour. November 6, 2014 - Structural Steel Deliver/Erect November 30, 2014 – Erection of columns and beams January 20 , 2015 – Decking being installed 2nd floor and roof February 15, 2015 - Exterior framing & Rough Electrical started. March 11, 2015 – Plumbing below slab started, Structural Steel scheduled for completion 3/20/15 April 17, 2015 - Site demo started, fire sprinkler & metal duct work started 2nd floor. Metal stud framing continues. Spring Semester 2016 - Open for classes 2. Building D – Elevator (840104) – 2013. An elevator will be installed in D, north side of the building. Currently, the elevator in D south is not reliable and often breaks down. The new elevator will tie into D’s ADA compliance work and make it easier for students coming from the main entrance, 411 Central Avenue, to get to the second and third floors of D. DSA Approved Plans Estimated Measure H cost $491,400 Page 1 of 3 3. Building D – ADA Compliance (840103) – 2013. The area on the west side of D will get a complete ADA upgrade to all of the pathways. In addition, the moat which is between the Student Center (C) and D will be filled allowing better access between the two buildings. No plans Estimated Measure H cost $541,500 OCCUPIED PROJECTS IN FINAL STAGES OF COMPLETION Alisal Building-D Technical Training Building (in DSA close out process) COMPLETED PROJECTS* Date Closed Out October 2004 November 2005 June 2006 December 2008 February 2009 September 2010 September 2010 December 2010 June 2010 January 2011 April 2011 August 2011 September 2011 September 2011 December 2011 December 2011 January 2012 January 2013 January 2013 April 2013 June 2013 June 2013 June 2013 June 2013 July 2013 August 2013 May 2012 Project Name Campus Infrastructure Phase I Parking Structure Learning Resource Center (LRC) Buildings D & E - Classrooms Refresh #1 Buildings D & E - Classrooms Refresh #2 Lighting Phase II Buildings D & E - Classrooms Refresh #3 U - Pool Renovation NE Landscape Project Buildings D & E - Classrooms Refresh #4 Alisal Landscape Project City Sidewalk Replacement City Sidewalk Phase II Alisal Campus Sign Alisal Campus Bus Turnaround Buildings D & E - Boiler/Chiller and Roof Campus Infrastructure Alisal Campus Additional Parking Student Center Building S - Annex Demotion Campus Safety & Security Improvements Campus Maps & Directional Signage Building P - PE Field House Solar Canopy Structures, Alisal Campus Building D - First Floor/North Remodel Alisal Campus Center for Applied Technology Student Services Building C *Completed means that all of the claims and paperwork have been submitted and no further action/claims on this project will be forthcoming from the District. Page 2 of 3 FUTURE PROJECTS Building E - 1ST Floor /South Building N - Remodel Keyless Entry Safety Cameras Project 1) Building S - Science Building 2) Building D - Elevator Budget % Completed Funding Source $29,143,341 49% Measure H $432,675 0% Measure H $541,500 0% Measure H 3) Building D - ADA Page 3 of 3