Document 14255218

advertisement
Construction Update
Prepared by Joseph Reyes, Director, Maintenance
Presented to the Board: May 5, 2015
CURRENT PROJECTS
1.
Building S – Science Building (813026) – 2013. 56,690 sq. ft. building, State of the Art Classrooms, Labs
and Technology. State of the Art Planetarium.
October 11, 2013 - (RFP) Request for Proposal
December 10, 2013 - Project out to rebid
January 14, 2014 - Rebid opening
February 4, 2014 - Board awarded contract to Dilbeck and Sons of Salinas, CA
August 14, 2014 - Foundation Piles installation completed
September 12, 2014 – 1st of 5 mat slab pours
October 17, 2014 – 5 of 5 mat slab pour.
November 6, 2014 - Structural Steel Deliver/Erect
November 30, 2014 – Erection of columns and beams
January 20 , 2015 – Decking being installed 2nd floor and roof
February 15, 2015 - Exterior framing & Rough Electrical started.
March 11, 2015 – Plumbing below slab started, Structural Steel scheduled for completion 3/20/15
April 17, 2015 - Site demo started, fire sprinkler & metal duct work started 2nd floor. Metal stud
framing continues.
Spring Semester 2016 - Open for classes
2.
Building D – Elevator (840104) – 2013. An elevator will be installed in D, north side of the building.
Currently, the elevator in D south is not reliable and often breaks down. The new elevator will tie into D’s
ADA compliance work and make it easier for students coming from the main entrance, 411 Central Avenue,
to get to the second and third floors of D.


DSA Approved Plans
Estimated Measure H cost $491,400
Page 1 of 3
3.
Building D – ADA Compliance (840103) – 2013. The area on the west side of D will get a complete ADA
upgrade to all of the pathways. In addition, the moat which is between the Student Center (C) and D will be
filled allowing better access between the two buildings.
 No plans
 Estimated Measure H cost $541,500
OCCUPIED PROJECTS IN FINAL STAGES OF COMPLETION
Alisal Building-D Technical Training Building (in DSA close out process)
COMPLETED PROJECTS*
Date Closed Out
October 2004
November 2005
June 2006
December 2008
February 2009
September 2010
September 2010
December 2010
June 2010
January 2011
April 2011
August 2011
September 2011
September 2011
December 2011
December 2011
January 2012
January 2013
January 2013
April 2013
June 2013
June 2013
June 2013
June 2013
July 2013
August 2013
May 2012
Project Name
Campus Infrastructure Phase I
Parking Structure
Learning Resource Center (LRC)
Buildings D & E - Classrooms Refresh #1
Buildings D & E - Classrooms Refresh #2
Lighting Phase II
Buildings D & E - Classrooms Refresh #3
U - Pool Renovation
NE Landscape Project
Buildings D & E - Classrooms Refresh #4
Alisal Landscape Project
City Sidewalk Replacement
City Sidewalk Phase II
Alisal Campus Sign
Alisal Campus Bus Turnaround
Buildings D & E - Boiler/Chiller and Roof
Campus Infrastructure
Alisal Campus Additional Parking
Student Center
Building S - Annex Demotion
Campus Safety & Security Improvements
Campus Maps & Directional Signage
Building P - PE Field House
Solar Canopy Structures, Alisal Campus
Building D - First Floor/North Remodel
Alisal Campus Center for Applied Technology
Student Services Building C
*Completed means that all of the claims and paperwork have been submitted and no further action/claims on this
project will be forthcoming from the District.
Page 2 of 3
FUTURE PROJECTS
Building E - 1ST Floor /South
Building N - Remodel
Keyless Entry
Safety Cameras
Project
1) Building S - Science
Building
2) Building D - Elevator
Budget
% Completed
Funding Source
$29,143,341
49%
Measure H
$432,675
0%
Measure H
$541,500
0%
Measure H
3) Building D - ADA
Page 3 of 3
Download