Wortham/Alley renovations Status update for Wortham/Alley projects Minor & Planned Projects Director- Shannon Jones Project Managers: Kerry Prejean/Mike Wheeler Parking Theron Mathis Rigging Ken Oliver Alley Prep Susan Vail Campus Wide Signage Roger Warner Grove Project Mark Aycock UH/IT Update – October 8, 2013 Attendees: Emily Mesa, Dean Roberts, Professor Rigdon, Craig Ness, Rachel Bush, Shannon Jones, Roger Warner Quintero room – Items completed: 9.26.13 Curtains/Soft Goods purchase requisition request. 9.27.13 Repaired Ceiling holes 9.28.13-UH/IT AV lights and XLR connections installation 9.27.13 Ethernet Installation 10-5-13-Removed Kickstands from rated doors, seal and patch. 8.28.13 Two–way switching for lights completed 8.14.13- Ordered Lights/ controls and delivery approximately 6 weeks. Some lights are arriving 9.15.13-Floor transition completed 8.15.13-The lights and LED fixtures for the lighting system are (ordered PO 730 0000029594) 9.20.13- Some Lights and LED fixtures are arriving now. 9.20.13 Re-Painting the walls (Flat Black) in progress 10.01.13 Substantial Completion Inspection Pending issues Clean vent and filter system (NZ Maintenance scheduled). Simplex Grinnell (contract W445001) installing additional sprinkler and electronic 10.09.13-FA devices installed but will be Retested 10.10.13-Add generator to egress lighting Project Meeting Notes Page 1 of 5 Wortham/Alley renovations Additional DMX and controls by U H/IT Commissioning system by Stage light 11.30.13-Replace double doors with rated doors Punch list items Professor Rigdon stated that the additional DMX and controls installation must be completed by UHIT by 20 Oct to be ready for the performance on 25 Oct. This includes commissioning the system by Stage Light. Laundry room- Shop is fully operational Items Completed: 9.25.13 Lower sink to meet ADA requirements 9.26.13 Washer and Dryer installed Water lines insulated 9.26.13 Removal of the fume hood for disposal 9.27.13 Installation of New lights 9.30.13 Washer dryers combinations installed 10.01.13 Substantial Completion Inspection Pending issues Ongoing--Design for paint booth One cold water line needs to be turned on Minor Punch list items Scenery shop/Wortham Theatre- Shop is fully operational Items Completed: 9.30.13 Substantial Completion Inspection Pending issues Minor Punch List Items DBR Design fee proposal for Life safety project for caging, platforms and assemblies Professor Rigdon stated that the floor in the Scenery Shop needed to be repaired after 16 Oct when the area is cleared. Costume shop- Shop is fully operational Items completed 9.27.13 Patch and paint sheet rock wall 9.27.13 Installation of new lights 9.30.13 Substantial Completion Inspection Pending issuesProject Meeting Notes Page 2 of 5 Wortham/Alley renovations N Z-Schedule maintenance painting—scheduled Minor Punch list items Wortham RiggingPending Issues: Counterweight rigging system is on-order. Working with Stage Light to get an estimate arrival date. Meeting scheduled for 8 Oct with Professor Rigdon to discuss any additional requirements. Professor Rigdon stated that the Rigging list was not complete (per Stage Light) and they had additional equipment that should be ordered. Professor Rigdon will provide the completed list. Signage—Campus Wide Signage is being coordinated by PM Susan Vail with Dean Oliver. Pending Issues: Met with Dean Oliver on October 3, 2013 and confirmed one vendor will complete the entire project to ensure continuity of all signs. The Design Team is working to provide the Total Project Cost in order to move forward with funding and selection of the contractor. Parking-- Scope: The project consists of refiguring parking spaces in lots “16B, C and F” to accommodate Alley Theater parking patron’s and construct a new driveway into parking area from Elgin St. Currently developing the POR, working with the design team and conducting a parking flow evaluation. All actions completed by 1 May 2014. Approx. Cost $215K. Met with Bob Browand, Paul Lozano and Professor Rigdon to discuss milestones and upcoming events. Parking includes: 60 Alley Employee Parking Slots, 340 Alley Patron Parking Slots, 20 (+) slots for ADA parking Pending Actions: Alley employee parking: has an existing parking gate and it is functional but Alley will need to provide “card access reader”. Alley will need to purchase and have installed. Obtained the vendor information from Parking and Transportation and will coordinate with Alley to complete. Work order #1 – to NZ maintenance for Wheel stops for the parking lots has been submitted. All Alley patron lot wheel stops will be painted bright yellow. Project Meeting Notes Page 3 of 5 Wortham/Alley renovations Parking & Transportation will produce and erect Patron Parking Signs displayed at each entrance to 16B. Dean Roberts met with the Performing Arts Directors and developed the following: Arts Events Visitor Parking No Student Parking From 3:00pm to 10:00pm Daily Parking & Transportation will pay for all of the temporary signage for 16B (FM awaiting work order from T&P) The new “Elgin Egress” is being addressed with the City Of Houston by Mike Wheeler. This is recommended by Parking & Transportation and intended for long-term use. Not officially part of the Alley requirements. Ms. Rachel Bush stated that the posted time should read “From 2:00pm to 10:00pm”. The correction was made. Alley Phase II— Pending issues: Data Point Entry-- UH/IT has a work order for all associated cabling/ voice/data/ Ethernet. Mark Aycock is approximately 98% complete. Cameras-- Requirements requested but not limited to: close circuit video feed sending images to the lobby. Infrastructure, wiring/audio LIGHT SWITCH, 120 dedicated below the booth @200C Wortham stage. Ongoing. Card Access--David Sarkozi is coordinating with the Dean Ruck, the FPC PM for the ACHW Retrofit Project to add Wortham Theatre their Phase III projects. Still awaiting the exact dates for completion of Phase III. UH/IT will work with FPC and DPS for those locations for card access and installation. Panic Buttons—David Sarkozi recommended Panic Buttons as part of the package. 7 locations were identified as potential locations. Ongoing. UH/IT will work with Client to establish these locations and to identify all stations to be tested for DPS monitoring. DBR is developing an estimate for the additional safety requirements including platform, ladders, railings, cages and follow-on installation. This action will be funded by CRDM. Project Meeting Notes Page 4 of 5 Wortham/Alley renovations Meeting is scheduled for 8 Oct with Professor Rigdon to determine the exact requirements for the trailers and PODs. PFA and PCB to follow for funding. Professor Rigdon and Craig Ness requested an exact breakdown on work completed and pending work for Phase II from UHIT. Grove—SWA Contract Update (Roger Warner) Contract is prepared and currently with SWA for review and signatures. The project is on schedule. The committee requested the exact construction start date for the next meeting and that that date be coordinated with the Logistics Group. Dean Roberts requested that all actions be coordinated through all of the Arts Directors. The committee requested the detailed Phasing Plan. Plan should include the temporary entry/exit/access to MSM and other Arts buildings during the 6 months of construction. It was noted that Alley’s first performance is 1 Aug 2014. The committee requested a meeting with presentations from SWA on the Grove Project to include a narrative of the Phased Plan with photos/conceptual drawings of the construction. To be followed by an official communication plan for students and the Arts Faculty. Emily Mesa stated that presented schedule needs to be revised to start the Winter Break and the work should be completed by 15 June 2014. Roger was tasked to contact SWA and develop a new schedule for the next meeting. Project Meeting Notes Page 5 of 5