Wortham/Alley renovations Status update for Wortham/Alley projects Minor & Planned Projects Director- Shannon Jones Project Managers: Kerry Prejean/Mike Wheeler Parking Theron Mathis Rigging Ken Oliver Alley Prep Susan Vail Campus Wide Signage Dean Ruck Grove Project Mark Aycock UH/IT Update – November 12, 2013 Attendees: Emily Mesa, Sameer Kapileshwari, Dean Roberts, Professor Jim Johnson, Rachel Bush, Shannon Jones, Susan Vail, Rebecca Gentry (Executive Director, Strategic Initiatives) Quintero room – Items completed: New LED light system installed and functional 2 additional Curtain orders completed waiting on the arrival UH/IT add CAT 6 Data Cable Pending issues 11.30.13-Replace double doors with fire rated doors 12.12.13-Rewiring of Light Control Panel (end of semester). Commissioning by StageLight Horizon Minor Punch list items as schedules allow All Call- Speakers- 5 speakers are functional but additional cable rewiring required by UH/IT Ms. Rachel Bush stated that the sprinklers still do not meet the customer’s requirements and there is additional work remaining. Shannon Jones stated that he would establish a follow up walk thru with Ms. Bush to determine the additional requirements. Ms. Rachel Bush stated that the Horizon has not identified a timeframe when they plan to complete all of the items remaining on the Punch List. The Project Meeting Notes Page 1 of 5 Wortham/Alley renovations Wortham Team has established the times when areas will be open and free for them to complete their tasks. S. Jones will follow-up with Horizon and establish those times. Laundry room- Shop is fully operational Items Completed: 09.30.13 Substantial Completion Inspection Pending issues Cover plates for two outlets Structural clips for the newly installed CMU wall (HORIZON) Scenery shop/Wortham Theatre- Shop is fully operational Items Completed: 09.30.13 Substantial Completion Inspection 10.29.13- Structural inspector and URS completed the floor integrity test (final report pending 17 Nov) 10.30.13- Ranger completed the electrical relocation and wrapping of sprinkler pipe 11.07.13- Wortham theatre sprinkler pipe in pit re-route. Pending issues 11.08.13- Walter P. Moore will provide design for Life safety project for caging, platforms and assemblies Ms. Rachel Bush pointed out that there may be a larger issue than just the requirement for the floor integrity test. Issue is that the floor may not have been installed correctly by the initial vendor. MPP will monitor and discuss the situation when we receive the result from the integrity test. Costume shop- Shop is fully operational Items completed: 09.30.13 Substantial Completion Inspection Pending issues N Z-Schedule maintenance painting—as schedule permits (Winter Break?). Wortham RiggingPending Issues: 12.15.13-Arrival and installation for Counterweight rigging system by Stage Light. Equipment will be installed during Winter Break. Parking-- Scope: The project consists of refiguring parking spaces in lots “16B, C and F” to accommodate Project Meeting Notes Page 2 of 5 Wortham/Alley renovations Alley Theater parking patron’s and construct a new driveway into parking area from Elgin St. Parking includes: 60 Alley Employee Parking Slots, 340 Alley Patron Parking Slots, 20 (+) slots for ADA parking. All actions completed by 1 May 2014. Approx. Cost $215K. Pending Actions: Alley employee parking card access reader: Parking & Transportation provided Alley an estimate form BP Equipment for an offline reader. Parking & Transportation will purchase it and have it installed thru T2 and bill it back to the Alley. NZ maintenance will relocate and paint wheel stops for the parking lots. (20 Jan) Parking & Transportation will produce Patron Parking Signs displayed at each entrance to 16B. RESERVED – ARTS EVENTS THEATRE PARKING MONDAY- FRIDAY 3pm TO MIDNIGHT ALL DAY SATURDAY AND SUNDAY Parking & Transportation will pay for all of the temporary signage for 16B and FM will erect. 12.15.13- 01.10.14- Repair, seal coating and line painting will be completed during Winter Break for 16B. Solar Powered Parking Meters will be emplaced by Parking & Transportation by 20 April. Elgin Egress: Request was submitted to the City Of Houston on 10 Oct by Mike Wheeler. Received an RFI on 11-07-13. Shannon Jones updated that MPP will purchase and oversee the installation of the card access reader. Alley Phase II— Pending issues: Cameras--close circuit video feed sending images to the lobby. Infrastructure, wiring/audio LIGHT SWITCH, 120 dedicated below the booth @200C Wortham stage. UH/IT will complete by April 15. Camera to be supplied by Alley. Card Access—Being coordinated in conjunction with the phased campus wide access control program currently underway. In the instance that the campus wide program has not progressed to the point where the openings of concern are not upgraded in time for Alley’s arrival, a separate endeavor will be undertaken to ensure that the appropriate hardware is installed in time. We will continue to track the progress of this Project Meeting Notes Page 3 of 5 Wortham/Alley renovations work and coordinate with UH Security stakeholders to ensure a timely implementation of the appropriate scope. UH/IT will work with FPC and DPS for those locations for card access and installation. Panic Buttons—David Sarkozi recommended Panic Buttons as part of the package. 7 locations were identified as potential locations. Ongoing. UH/IT will work with Client to establish these locations and to identify all stations to be tested for DPS monitoring. Trailer and PODs: 11.01.13 Mod Space provided Rough Order magnitude (ROM) for (1) - 24x72 Trailer and (3) -8x20 Climate Control PODS. 11.01.13-Mod Space Contract via COOP/By Board in development. All shop support is being coordinated and priced should be completed by 11/14/13. Once compiled a PFA and PCB will be sent to Dean Roberts. Grounds will coordinate and remove two trees and associated bushes during Winter Break. Will replant trees, bushes and sod after trailer is removed. UH/IT will install 5 “On-Call Speakers” in Trailer and complete prep for A/V feed. MPP is researching awning requirement from trailer to Quintero Stage door. Meeting to discuss will be scheduled week of 18 Nov. Awning Structural Analysis will be completed by Walter P. Moore. Internal Shop coordination for Trailer support with: o NZ Maintenance o Electrical Shop o Grounds o Custodial Signage—Campus Wide Signage Pending Issues: Review RFP format Identify additional main entry points to add to the first bid for the Arts District Creation of construction documents for bid that reflect these items Identification of Lead / Key people for decision process Grove—SWA Contract Update: SWA continues to work towards preparing design documents that can be translated into a GMP contract to start construction by February 1st. Construction Manager at Risk services were solicited and proposals were received last week, which are currently under review and analysis to ensure scope and budget conformance. To remain on schedule, an award must be made by November 20th. Project Meeting Notes Page 4 of 5 Wortham/Alley renovations Ms. Rebecca Gentry (Executive Director, Strategic Initiatives) stated that there will be a Donor and UH Leadership meeting to acknowledge the Kickoff of the Grove Project on Jan 29 at 10:30. Ms. Gentry requested brochures with the Grove information and conceptual drawings to pass out at this meeting along with Grove displays. She also requested information on the fencing plan and overall project planning. Ms. Bush requested a follow-up meeting with Dean Ruck to discuss the requirement in detail. Project Meeting Notes Page 5 of 5