Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School PART 1 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN PHYSICAL PLANT RECOMMENDATIONS A. SITE 1 Circulation No specific recommendations 2 Driveways and Parking Lots Heavy traffic areas: Full-depth replacement with pavement base under drains. 3 4 5 6 7 Play and light traffic areas: Resurface worn areas Sidewalks and Curbs Repair / replace loose / damaged flagstone at entrance Remove / replace hazardous sidewalks and curbing X X Site ADA Accessibility Renovate site infrastructure to comply with ADAAG and PA-UCC (i.e., curb cuts, railings, signage, etc.) Play Areas Renovate play areas to comply with ADAAG and PA-UCC ( i.e., new equipment and play surfaces) Landscaping Remove trees and shrubs for selected removal / replacement as needed Physical Education Areas No specific recommendations Rose Tree Elementary School Page 1 of 11 X X X X X X X X X X X Investigate / redesign / renovate storm water system X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Utilities Investigate / renovate / replace cistern tanks Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 8 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X B. BUILDING EXTERIOR 1 2 Masonry Miscellaneous repairs to cast stone and parged corner accents and joints Clean cast stone sills at windows Refinish rusting support lintels, clean and restore masonry on north wall X X X X X X EIFS Replace damaged areas of EIFS; consider a more durable material and / or landscaping to protect the surface 3 Curtain Wall Not Applicable 4 Windows No specific recommendations 5 Doors and Entryways Replace or modify egress doors (30" pair) near the girls' restroom to provide required clearances Provide an alternative to the existing locked gate as a means of egress from the boiler room Replace remaining doors (not done in 1995); repair seals to correct water infiltration Rose Tree Elementary School Page 2 of 11 X X X X X X X X Clean cast stone copings and reseal joints Correct minor problems with membrane roof; plan for replacement in 5 years Repair / replace damaged, missing or loose flashing, copings and / or fascia Repair / replace all damaged / missing downspouts, connect to boots or provide appropriate splash blocks X X Canopies, Soffits, Fascia Repair or replace damaged / missing fascia (few areas) X X X X Correct leak over the Platform X X X X X X X X X X X X X C. BUILDING INTERIOR 1 Administrative Offices No specific recommendations 2 Athletic Facilities Replace missing ceiling tiles 3 Repair cracks in walls below windows Correct door seals and resultant water leaks X X X Art Keep stored materials away from Kiln in storage room. Ideally, provided a separate space for the kiln. Rose Tree Elementary School Page 3 of 11 X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. Maintenance Other Safety & Accessibility ACHIEVEMENT METHOD Roofs Repair / replace slate roof 7 Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 6 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN ATP See 'Classrooms' items 5 Cafeteria and Kitchen Relocate bollards outside receiving doors to improve access Correct the leak in the dry storage room Repair kitchen freezer 6 Classrooms No specific recommendations 7 Computer Lab No specific recommendations 8 Corridors Repair areas where floor tile is separating Correct water infiltration issues at doors Repair water damage to wall (basement) Replace damaged base material 10 Faculty Room Replace any sagging ceiling tiles Repair / replace warped carpeting Kindergarten Repair wall cracks Where toilet facilities are provided in classrooms, renovate per ADAAG and PA-UCC Provide additional kindergarten room(s) as needed to address changing / future program needs Rose Tree Elementary School Page 4 of 11 X X X X X X X X X X X X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility 4 Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 9 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X X 12 Library Repair areas of ceiling damage / staining Correct sagging ceiling tiles at recessed can lights 13 14 Lobby Maintain active and passive methods of security control at both key entrances Music Provide intercommunications to the Music and support rooms Provide acoustical treatments to improve performance 15 Nurse's Office No specific recommendations 16 Science Repair water stained ceiling (small area) 17 X X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. Maintenance ACHIEVEMENT METHOD X Special Education See 'Classrooms' items 18 Other Safety & Accessibility LGI Not Applicable Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 11 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Provide additional Special Education program spaces Stairways Replace square handrails with ADAAG compliant round railings Repaint handrails and guard rails Re-adhere loose riser covers Rose Tree Elementary School X X Page 5 of 11 X X X X X X Environmentally Sensitive Materials Maintain ACBMs in a non-friable state; consider the removal of all VAT and any other ACBMs, PCBs, etc., from the building Address temperature and humidity issues / improve circulation 21 22 X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility 20 Toilet Rooms All accessible stall doors should be out-swinging Minor modifications and fixture replacement as needed to provided all toilet facilities per ADAAG and PA-UCC Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 19 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X See individual descriptions for specific items to be addressed Accessibility (ADA) Issues - recommendations per ADAAG Provide accessible / modifiable sink bases where needed Provide accessible drinking fountains Provide accessible workstations in the Art and Science Rooms Eliminate step-down conditions at egress doors Provide required clearances at doors / room entrances Provide direct access to the Platform (Stage) from the Cafeteria by means of a ramp or lift Provide Area of Rescue Assistance in stair towers See individual descriptions for specific items to be addressed Building Code Issues and Safety Concerns Follow recommendations in CPTED-RED Report Although not necessarily required by code, it is highly recommended to replace the guard rail at the areaway with a more protective railing See individual descriptions for specific items to be addressed Rose Tree Elementary School Page 6 of 11 X X X X X X X X X X X X X X X X X X February 5, 2007 Summary of Recommendations Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN D. HVAC 1 Hot Water Heating System No specific recommendations 2 Air Conditioning System Replace air-handling units and condensers 3 Ventilation System Provide powered ventilation for the crawl-space Replace damaged exterior ventilation louvers Provide single-zone, rooftop units to condition the Computer Room, Gymnasium, Cafeteria and Multi-purpose Room 4 Exhaust System No specific recommendations 5 Terminal Heating Equipment Replace terminal heating equipment to match other system options 6 Temperature Control System Correct specific heating control problem in the Gymnasium Provide a new DDC control system with override night set-back with proper interface located off-site 7 X X X X X X X X X X X X X X Other Replace the di-electric union and all associated damaged ceiling components Rose Tree Elementary School Page 7 of 11 X X February 5, 2007 Summary of Recommendations Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN E. PLUMBING 1 2 Fuel Systems No specific recommendations; coordinate gas piping modifications with HVAC related improvements Domestic Water Service Add pipe insulation to provide a complete thermal barrier 3 Domestic Hot Water System No specific recommendations 4 Sanitary Waste System Option 1: Replace all the sanitary waste piping due to age Option 2: Replace all above-ground piping; scope and rod below ground piping; repair / replace as needed Option 3: Maintain system 5 6 Plumbing Fixtures Replace fixtures throughout the building for accessibility, appropriate use and water conservation Kitchen Systems 7 8 X X X X X X X X X X X X X X X No specific recommendations Fire Protection System Provide an automatic sprinkler system for the entire building Stormwater Drainage Repair areaway drain at the Science Room Rose Tree Elementary School Page 8 of 11 X X February 5, 2007 Summary of Recommendations Low X Moderate PlanCon X PRIORITY LEVEL High C.I.P. ACHIEVEMENT METHOD Maintenance Other Educational Program Deferred Maintenance TYPE OF IMPROVEMENT Rose Tree Elementary School Safety & Accessibility Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN F. ELECTRICAL 1 Electrical Service No specific recommendations 2 Branch Panels Replace branch panels and add spares 3 4 5 6 7 8 9 Receptacles Provide additional receptacles / circuits as needed to support program Lighting Consider occupancy sensors Platform (Stage) Lighting Replace platform lighting Exit Signs / Emergency Lighting Replace exit signs and emergency lighting for better efficiency and compliance with current codes (will be required if any overall renovations work occurs) X X X X X X X X Emergency Generator Install emergency generator and an emergency power distribution Page 9 of 11 X Rose Tree Elementary School X Exterior Lighting Provide lighting at dim areas on site; utilize fixtures that reduce unwanted glare Telecommunications No specific recommendations X X X X X Intercom / Clock System No specific recommendations 12 Remote Sound System Provide remote sound system for the Platform, Gymnasium or LGI to support program uses 13 14 15 and / Fire Alarm System Test and maintain system Extend security panel to alarm all exterior doors Consider access card system Computer Cabling No specific recommendations Rose Tree Elementary School Page 10 of 11 X X X X X X X X X X X Low Moderate X PRIORITY LEVEL High PlanCon C.I.P. Security Install camera system with digital recording Maintenance 11 Other Safety & Accessibility CATV Repair television media retrieval system ACHIEVEMENT METHOD Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School 10 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Low Moderate PRIORITY LEVEL High PlanCon C.I.P. Maintenance Other Safety & Accessibility ACHIEVEMENT METHOD EDUCATIONAL PROGRAM RELATED RECOMMENDATIONS 1 Provide accommodations for potential future growth 2 Provide general building storage 3 Provide storage for instructional materials 4 Provide Instructional Support spaces Small Group Instruction Rooms 5 Educational Program TYPE OF IMPROVEMENT Rose Tree Elementary School PART 2 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Flexible space for itinerant specialists See individual descriptions for specific items to be addressed Rose Tree Elementary School Page 11 of 11 X X X X X X X X X X