Director of Facilities and Operations North Penn School District

advertisement
Director of Facilities and Operations
North Penn School District
To:
From:
Date:
Re:
Safe Schools Committee
Thomas Schneider
September 2015
Capital Project Update
Following is a capital project update for Hatfield Elementary, Secured Entrances and the Security
Window Film projects:
Hatfield Elementary
Hatfield is complete with the exception of punch list items and ready to open for classes September 1st.
Teachers started to unpack on August 19th and the building was setup and unpacked by August 28th.
Secured Entrances
The Secured Entrance projects are 100% complete at Bridle Path, Gwynedd Square, Knapp and Walton
Farm. Gwyn-Nor and Oak Park are completed with the exception of some exterior metal panels which
is expected in the next week. The remaining work does not prohibit the use and functionality of the
entrance.
Commercial Window Shield, Inc.
The window security film project is completed. All entry doors, side lights and other glass was coated
with a window film to slow down a forced enrty.
Y:\Department\Facilities\Safe Schools Committee\2015-16\Sept 2015\CapitalProject_SafeSchools_Sept2015.docx
Download