Director of Facilities and Operations North Penn School District To: From: Date: Re: Safe Schools Committee Thomas Schneider September 2015 Capital Project Update Following is a capital project update for Hatfield Elementary, Secured Entrances and the Security Window Film projects: Hatfield Elementary Hatfield is complete with the exception of punch list items and ready to open for classes September 1st. Teachers started to unpack on August 19th and the building was setup and unpacked by August 28th. Secured Entrances The Secured Entrance projects are 100% complete at Bridle Path, Gwynedd Square, Knapp and Walton Farm. Gwyn-Nor and Oak Park are completed with the exception of some exterior metal panels which is expected in the next week. The remaining work does not prohibit the use and functionality of the entrance. Commercial Window Shield, Inc. The window security film project is completed. All entry doors, side lights and other glass was coated with a window film to slow down a forced enrty. Y:\Department\Facilities\Safe Schools Committee\2015-16\Sept 2015\CapitalProject_SafeSchools_Sept2015.docx