Director of Facilities and Operations
North Penn School District
To:
From:
Date:
Re:
Support Services Committee
Thomas Schneider
August 2015
Capital Project Update
Following is a capital project update for Hatfield Elementary, Secured Entrances and the Security
Window Film projects:
Hatfield Elementary
Hatfield is complete with the exception of punch list items and ready to open for classes September 1st.
Teachers started to unpack on August 19th and the building was setup and unpacked by August 28th.
Secured Entrances
The Secured Entrance projects are 100% complete at Bridle Path, Gwynedd Square, Knapp and Walton
Farm. Gwyn-Nor and Oak Park are completed with the exception of some exterior metal panels which
is expected in the next week. The remaining work does not prohibit the use and functionality of the
entrance.
Commercial Window Shield, Inc.
Work is commencing throughout the District. To date the following buildings have received the security
window film and are 100% complete:
Inglewood Elementary
Montgomery Elementary
Nash Elementary
North Wales Elementary
York Elementary
High School
Walton Farm Elementary
Northbridge
Gwyn-Nor Elementary
Oak Park Elementary
Hatfield Elementary
The installation crew is currently installing the security window film at the Pennbrook.