Construction and Engineering Alert May 2007 Authors: Andrew H. Davies +44.20.7360.8190 andrew.davies@klgates.com Inga Hall +44.(0)20.7360.8137 inga.hall@klgates.com K&L Gates comprises approximately 1,400 lawyers in 22 offices located in North America, Europe and Asia and represents capital markets participants, entrepreneurs, growth and middle market companies, leading FORTUNE 100 and FTSE 100 global corporations and public sector entities. For more information, please visit www.klgates.com. www.klgates.com Withholding payment in the event of insolvency Since the Housing Grants Construction and Regeneration Act 1996 (‘the Construction Act’) came into force in 1998 the construction industry has known that in order to withhold payment of a sum due under a construction contract, the paying party must serve a valid withholding notice. On 25 April 2007 however, the House of Lords in Melville Dundas Limited (in receivership) v. George Wimpey UK Limited decided that there is a limited exception to this general rule in the case of a contractor’s insolvency. This is the first occasion on which the House of Lords has considered the Construction Act and their Lordships’ finding that a withholding notice is not required in all circumstances may cause some surprise in light of the various decisions in lower courts (including Rupert Morgan Building Services (LLC) Limited v. David Jervis and Harriet Jervis) which have established that a withholding notice should always be given. Facts Wimpey engaged Melville Dundas to construct a housing development in Glasgow under a Scottish JCT 1998 Contract (‘the Contract’), which provided that the final date for payment of an interim payment was 14 days after receipt of an application. Melville Dundas applied for an interim payment on 2 May 2003, making the final date for payment 16 May 2003. Wimpey did not pay and served no withholding notice. Six days later, on 22 May 2003, Melville Dundas’ bank appointed administrative receivers. The Contract provided that if Melville Dundas appointed an administrative receiver, Wimpey was entitled to determine the employment of the contractor under the Contract. Wimpey did so, bringing into effect clause 27.6.5.1, which provided that on the occurrence of an insolvency event (which included the appointment of administrative receivers): “the provisions of this Contract which require any further payment…to the Contractor shall not apply; provided that [this clause] shall not be construed so as to prevent the enforcement by the Contractor of any rights under this Contract in respect of amounts properly due to be paid by the Employer to the Contractor which the Employer has unreasonably not paid and which [where an administrative receiver has been appointed] have accrued 28 days or more before the date when…the Employer could first give notice to determine the employment of the Contractor”. This clause was central to the dispute and Wimpey relied on it in support of its contention that it was not required to pay Melville Dundas despite not serving a withholding notice. Melville Dundas issued proceedings claiming payment. Construction and Engineering Alert Scottish Court Decisions The Scottish courts examined the apparent conflict between this clause and section 111(1) of the Construction Act, which clearly provides that: “A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment”. The first instance decision (that there was no conflict) was overturned in the Scottish appeal court which decided at the end of 2005 that Wimpey could not refuse payment as the Contract did not comply with section 111(1) of the Construction Act. This decision was seen as consistent with the general trend in how the courts were dealing with withholding notices. Wimpey appealed to the House of Lords. House of Lords Decision The House of Lords (by a three to two majority) reversed the decision and held that no payment was due to Melville Dundas for two main reasons. Interpretation of clause 27 Melville Dundas argued that once a sum had become due under a contract it could not cease to become due. It argued that the words “any further payment” in clause 27.6.5.1 should not therefore be read as including an interim payment which the employer was already obliged to pay because the final date for payment had passed (without the issue of a valid withholding notice) by the date of the determination of the contractor’s employment. Their Lordships did not agree. The words “any further payment” are unqualified and their plain meaning is that (until the final accounting which the contract also provides for), the employer is not required to pay any more money whether or not the money was already due. Wimpey was not therefore required to pay Melville Dundas interim payments that had become due before the determination of the Contract. Potential conflict with the Construction Act Their Lordships then considered whether clause 27.6.5.1 was invalidated by the Construction Act and held that there was no conflict. Sections 109 to 110(1) of the Construction Act were drafted to introduce clarity and certainty as to the terms of a construction contract and require only that the contractor should be entitled to payment by instalments and that there should be an adequate mechanism for determining what he was entitled to be paid and when. Section 109(2) says: “The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due” Lord Hoffman in particular considered that this reference to circumstances shows that Parliament did not require that stage payments should become “inexorably due” at fixed intervals but that liability to pay could be contingent on other events (such as intervening insolvency). Melville Dundas also sought to rely on section 111(1) of the Construction Act as Wimpey had failed to serve a withholding notice before the final date for payment. Their Lordships found that it would not have been possible for Wimpey to serve a notice by this date (16 May 2003) as it only became entitled to withhold the interim payment when Melville Dundas’ receivers were appointed six days later. Their Lordships held that section 111(1) had to be construed to allow clause 27.6.5.1 to operate and not so as to require a withholding notice to be served when it not possible for Wimpey to have done so within the relevant time period. The alternative construction would mean that the parties were not free to enter May 2007 | 2 Construction and Engineering Alert into a contract as a result of statutory machinery, the operation of which would serve no practical purpose. The House of Lords allowed Wimpey’s appeal and confirmed that commercial parties are free to agree contractual terms that suit their business interests and that Parliament was not able to interfere in such dealings. Conclusion due without issuing a withholding notice. Although this decision is final as far as clause 27 of the JCT form of contract is concerned, parties seeking to rely on this decision in the context of different contracts or factual situations (such as where it is feasible to issue a withholding notice before the final date for payment) should still serve a valid withholding notice. Even in the JCT insolvency situation, if you are able to serve a withholding notice, this will strengthen your position. This important decision means that if a contractor with whom you have a contract becomes insolvent, and provided that the contract allows you to determine the contractor’s employment in such circumstances, you can withhold payment that might otherwise have been K&L Gates comprises multiple affiliated partnerships: a limited liability partnership with the full name Kirkpatrick & Lockhart Preston Gates Ellis LLP qualified in Delaware and maintaining offices throughout the U.S., in Berlin, and in Beijing (Kirkpatrick & Lockhart Preston Gates Ellis LLP Beijing Representative Office); a limited liability partnership (also named Kirkpatrick & Lockhart Preston Gates Ellis LLP) incorporated in England and maintaining our London office; a Taiwan general partnership (Kirkpatrick & Lockhart Preston Gates Ellis) which practices from our Taipei office; and a Hong Kong general partnership (Kirkpatrick & Lockhart Preston Gates Ellis, Solicitors) which practices from our Hong Kong office. K&L Gates maintains appropriate registrations in the jurisdictions in which its offices are located. A list of the partners in each entity is available for inspection at any K&L Gates office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1998—We may contact you from time to time with information on Kirkpatrick & Lockhart Preston Gates Ellis LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail london@klgates.com if you would prefer not to receive this information. ©1996-2007 Kirkpatrick & Lockhart Preston Gates Ellis LLP. All Rights Reserved. May 2007 | 3