GDS Commissioning Worksheet The stations on this worksheet are connected to the following lighting panel: LCP-1 Quick Checklist: GDS Network is run in a daisy chain configuration GDS Network does not exceed 1000 feet in total length The beginning and end GDS devices on the network have their terminatiors in the termination ON position The middle GDS devices on the network have their terminators in the termination OFF position To be completed by installing contractor Station Reference Number Station Location 1 2 3 Lobby Open Office East Wall Room 203 Station Model q GDS-1TLB q GDS-2TLB q GDS-3TLB GDS-4TSB q q q q q q q q q q q q q 4 5 6 7 Lab q q q q q q q q q q q q q q q q q q q q q q GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB GDS-1TLB GDS-2TLB GDS-3TLB GDS-4TSB GDS-5TSB GDS-6TSB Button Number 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 Panel Name & Relays Controlled LCP-1: 1 - 4 LCP-1: 5 & 6 LCP-1: 17 Not Used Button Action Describe what you want each button to do For example: ON/OFF, RAISE, LOWER, ALL ON, ON/OFF ON/OFF ON/OFF ON/OFF ON/OFF ON/OFF ON/OFF ON/OFF ALL ON RAISE ALL 25% ALL 50% LOWER ALL OFF ALL ON ALL OFF