Estimating of engineering costs when using 61850 and GOOSE messaging

advertisement
Estimating of engineering
costs when using 61850 and
GOOSE messaging
Robert O’ Reilly
Senior Application Engineer
Cooper Power Systems – Canada
Matthew Oong
Regional Sales Manager
Cooper Power Systems - Australia
Australia
AP B5
SEAPAC 2009
Overview
Australia
AP B5
SEAPAC 2009
Where we came from (our heritage)
Today
Our challenges in properly evaluating costs
Tomorrow
Potential examples and tools
Conclusions
2
Traditional Installation
Methods
Australia
AP B5
SEAPAC 2009
3
Traditional Pre
Commissioning
Australia
AP B5
SEAPAC 2009
4
The New Generation of
Protection Cabinets
Australia
AP B5
SEAPAC 2009
• Power distibution to devices
• Fibre Optic for data
• Bay controller for interlocking
5
Evolution of
Engineering Tools
Australia
AP B5
SEAPAC 2009
• Cabling information still required (Less)
• IED Power Distribution still required
• Existing databases update to 61850
• Interlocking via GOOSE msg not hardware
• System Configurator
6
61850 Projects
Implementation
Australia
AP B5
SEAPAC 2009
Change in Skills Sets
• change from Hardwire to GOOSE interlocking or tripping
• Change from I/O Lists to set-up the networks and V-LANS.
• The protection engineer is doing most of the work while setting-up
the protection relays with the messaging requirements.
7
Challenges in properly
evaluating costs
Australia
AP B5
SEAPAC 2009
• Reduction in engineering drawings, wiring and panel testing.
• Increase in information to allow future trouble shooting
• Increase in amount of time being expensed in FAT’s (factory
acceptance tests)
• Increase in amount of time in SAT (Site Acceptance tests)
• Increase in labour costs due to high skills set
8
Cast Study
Australia
AP B5
SEAPAC 2009
• in engineering drawings, wiring and panel testing. (Down ?? %)
• Increase in information to allow future trouble shooting (Increase
?? %
• Increase in amount of time being expensed in FAT’s (factory
acceptance tests) Increase ?? %)
• Increase in amount of time in SAT (Site Acceptance tests)
Increase ?? %)
• Increase in labour costs due to high skills set (Increase ??)
• Overall Project Cost (Inc/Dec%)
9
Some General Comments
Australia
AP B5
SEAPAC 2009
• While 61850 has been around for some time, we are just starting
to use it.
• It is a new paradigm compared to our previous ways of putting
wires everywhere.
• We are saving costs in regards to the drawings, cabling, etc…
BUT
• We are using more time from highly valuable personnel.
• The Factory and site acceptance tests are much more involved
and time consuming
Future System Configuration Tools will help to reduce Engineering
10
Thank You!
Australia
AP B5
SEAPAC 2009
Robert O’ Reilly
Senior Application Engineer
Cooper Power Systems – Canada
Matthew Oong
Regional Sales Manager
Cooper Power Systems - Australia
11
Download