SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging IEC61850 Cooper Power Systems Oong, O’Reilly Keywords: Estimating, 61850, GOOSE Messaging 1 Abstract Summary The advent of the 61850 protocol and the tools associated with it, and especially with the use of GOOSE messaging between relays to replace the hardwiring of protection signals between this equipment has caused a radical change in the way we have been doing our cost estimating for electrical engineering projects compared to traditional methods. In this new area we have to be more network conscious and ensure that we plan our networking infrastructure more than ever before. This can become the weak part of the whole project and can cause tremendous problems in the overall performance that is required for such implementations. This new approach to building our protection and control infrastructure changes in a massive way how we have been estimating costs and planning the work for our different electrical projects. Since all of us are measured in terms of performance to quality, budgets and performance to meet our project dates we have had to come-up with new ways to perform this task and still provide to our managements the information they require for their planning processes. In the past we have had ten of years of experience in doing in the old way (hardwiring) but today this has changed with this new environment, since it is new for the industry very little experience currently exists to properly work out different schemes for the costing and time estimating for doing an electrical project. Today we have had to develop new techniques to properly estimate the costs in doing electrical projects in this new reality. In this paper we will define this new paradigm and give examples on how we are developing new ways to perform the costing estimates which take into account the shifting of the work from very manual labour intensive with new systems capable of being more integrated and requiring very little wiring requirements. This paper will also present some recent examples of 61850 projects and an overview of how the evaluations where performed for developing the overall project cost and associated time-lines. We will also explore what were the results in terms of final cost and the execution time frame compared to the initial estimates and the experiences that we have been learning from these 61850 implementations Page 1 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly 2 Our Legacy The traditional method of implementing and completing a project has not really changed in its basic art for many years. During this period of time and particularly with the deceasing costs of computing power we have developed many and sophisticated tools to allow us to perform our engineering work in an efficient and cost effective manner. Figure One and Figure Two show examples of traditional panels with copper wiring for most of the interlocking and protection signals, these are known items which people in the industry have been working with for many years and understand the wiring approach from a point A to a point B. In these installation Fibreoptic cable (orange sheath) have been installed for electrical isolation and not data communication. The work is traditionally done by electrical tradesman. Figure One – Traditional Panel with copper wiring for interlocking and protection signals Page 2 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly Figure Two – Traditional panel with copper wiring for interlocking and protection signals Over the years as the engineering tools have become more sophisticated they have evolved from hand drawn sketches, to basic wiring diagrams to database driven complete systems providing an integrated information environment of cable schedules, wiring details for control panels to pre-commissioning check sheets for Factory Acceptance Tests to commissioning and Site Acceptance Tests. Page 3 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly Figure Three – Example of a database of engineering information Figure Four – Example of output of database used in Factory Acceptance Testing Figure Three show an example of an engineering database and Figure Four 4 shows the output in the form of a query. These integrated engineering tools have provided the required information to the different teams working on the project, thus allowing an easier integrated environment while reducing at the same time the cost for the overall project because of the easy and accurate exchange of information. Page 4 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly 3 Today Today we are in a period of transition. We know that 61850 will not go away; hence we have to work at refining our different tools required to properly plan and execute these new types of projects, and ensure that we will provide the right information to our senior management to help them in their initial decision making, budgeting process and provide suitable information in the management and delivery of the project. Some elements of the project are relatively easy to adapt to. For example Figure Four show a typical 61850 Panel during a Factory Acceptance Test. There is a substantial reduction in wiring as the traditional point to point wiring for interlocking and protection signals are sent via fibre optic cable. The traditional panel power distribution is still required. Figure Four is of two bays that are completely 61850. In this approach the bay controllers are being used to perform interlocking with information being received from the different protection relays and hardware Input / Output devices receiving different contact information. In this project process bus has not been implemented however has been allowed for tine the overall architecture. Figure Four – Example of a 61850 Panel during a Factory Acceptance Test Page 5 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly What we have seen is that 61850 combined with modern relays provide a new and large quantity of information that we could not imagine just a few years ago. Now we must learn to work and use this new hefty data information warehouse but also to use it in an overall strategic approach, otherwise this wealth of information will be lost or we will not be extracting the potential value with the systems we are working with. A key element in our overall strategy of integrating information is that we do want to make it available to other systems but we also want to know who will be using it (the goal of providing any information is to understand who will be using the information and for what purposes then it is useful). Within this new framework of information, the overall approach to providing information via 61850 from the substation to control centers is not totally defined; a number of utilities are still partially using some of their old software tools. These Tools where not conceived to properly provide the correct information in a complete 61850 compliant environment and we do not have the fully integrated Engineering Tools equivalent to the existing engineering tools that have been developed over many years. 4 Our Challenges In Properly Evaluating Costs In this environment of transition a significant challenge is how do you properly evaluate costs when developing the business case for a project. The traditional tools of using spreadsheets, defining work breakdown structure, defining assumptions and estimating costs is still valid. The new paradigm is the changing of areas in the work breakdown structure and how we define some of the assumptions when developing the cost model. At this point in time multi-IED vendor fully integrated engineering tools do not exist so substantial potential engineering savings from these tools cannot be quantified. Some of the key issues that need to be considered are: 4.1 Panel Design and Implementation We can easily understand that there is a significant reduction in common drawings as required for the design, manufacture and testing of the panels. This is visually shown when comparing Figures Two showing a traditional panel with copper wiring for interlocking and protection signals and Figure Four of a 61850 Panel during a Factory Acceptance Test. Review of a number of recent projects shows that there are savings in the area of 30 % reduction in engineering time Page 6 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly 4.2 Documentation Even though there is substantial reduction in the costs and resources to produce the Panels there is a requirement to have documentation that effectively replaces Input / Output lists. We are seeing a requirement for a different set of information to allow easy testing and troubleshooting in this new environment. To properly document this set of information represents an increase in approximately 10 to 15% of the allotted engineering time 4.3 Skill Set The major change in adopting 61850 is the change in skill set that is now required. We are evolving from tradesmen that have worked with hard-wiring of devices and now we are migrating to a more network and system environment. People require greater knowledge of networking infrastructures and the application of Virtual LAN’s are becoming mandatory. A typical example of the changes in skill-set is where the change from hardwiring to GOOSE messaging for interlocking and tripping is occurring. The skill set involved has changed from working with an Input Out put list to now be able to set-up and configure networks and Virtual – LAN’s. Typically the protection engineer is performing most of the work while setting-up the protection relays with the messaging requirements. There are a number of approaches to acquire this knowledge such as hire people with appropriate experience (which is at a premium to traditional people) or train and up skill our existing workforce. In general what we are also seeing from a work force point of view, is the increase in labour costs due to the high skill set now required for these new types of systems; this does not time impact the project timeline, but increases the cost of the overall project because of the type of personnel required. 4.4 Factory Acceptance Testing In this new environment the Factory Acceptance testing has been more rigorous and in some cases repeated to ensure confidence in the implementation What we are seeing is the increase in the time being expensed in Factory Acceptance Test has increased by 15 to 40% depending on the size of the project (i.e. number of I.E.D.s being integrated using 61850 and depending on the level of use of GOOSE messaging). 4.5 Site Acceptance Testing Because of the nature of this new environment, currently we are seeing an increase in the time required for the Site Acceptance Test’s by approximately 15 to 20%. Page 7 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly 5 Estimating Tools In the development of Project Estimating Tools that cater for the substantial variations of the different projects, we have used a mix from the older approaches within a context based on a networking infrastructure approach. This has provided us with at least a planned budget for the unforeseen surprises these types of systems will provide. We have performed better than the some of the system integrators that we have referenced above in regards to the project overruns because of the different situations due to 61850. The development of new estimating tools is more demanding than first anticipated. Drivers include variations due to interactions between the different types of devices communicating within a 61850 application environment and the scope and breadth of projects. We know the rules and the general guidelines but the integrated estimating portion is not has easy as one would think!!!! 6 Conclusion In general the goal of 61850 was to simplify our overall engineering approach and indirectly potentially reduce the project costs. Since this is a new approach currently the cost saving have not been substantiated in the projects that the authors have seen to date. This is due mostly to the fact that this whole environment is new and no chances are being taken hence large amounts of time are being used in the testing of these new systems before putting them on-line to ensure that no surprises will happen. When more tools become available and that the engineering management has more experience and feels more confident with the overall technology, it is more than probable that the cost will then become lower and bring with it the promise of this new environment of being self documenting and providing all of the configuration for the IED’s in an easy and integrated environment. Page 8 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc SEAPAC 2009 CIGRE Australia Panel B5 Melbourne 17 – 18 March Estimating of Engineering Costs When Using 61850 and GOOSE Messaging Oong, O'Reilly, O’Reilly 7 Biography Matthew Oong Matthew Oong has been involved in Power Distribution and Industrial Automation for more than 25 years. His initial training was with the former Sydney County Council’s Test Branch, where he undertook the Electrical Engineering Certificate and Bachelor of Engineering (Electrical). Has had broad practical experience with Rolls Royce Industrial Power as a Commissioning Engineer, Design Engineer and Project Manager before moving into Sales Management roles at Rolls Royce, Siemens and Otis Elevators. At Cooper Power Systems Mr. Oong is responsible for Energy Automation business development in Australia and New Zealand. Email Address: matthew.oong@cooperindustries.com Robert O’Reilly Robert O’ Reilly has been involved in the development of different technological applications in numerous industries for more than 35 years with 20 of these years within the power industry. During this period he has participated in the writing of more than 25 technical papers, ranging from applications in different industrial sectors in regards to automation, control and protection systems. Mr. O’ Reilly has also been guest speaker for numerous engagements with universities and graduate level conferences, including key-note speeches at international conferences. He has also produced a number of articles for different technological magazines for the energy industries among others. Email: robert.oreilly@cybectec.com Page 9 of 9 M. Oong, R. O'Reilly - Cooper Power Systems - Estimating of Engineering Costs When using 61850 and Goose Messaging.doc