CHRONOLOGY OF PROJECT:
Transportation Methodology Meeting
Preapplication Conference
ADA Submittal
Site Inspection
ADA Comments
First Sufficiency Response Submittal
Third Sufficiency Response Submittal
Third Sufficiency Response Submittal
Declaration of Sufficiency by TBRPC
TBRPC Final Report
Pasco County BOCC Meeting
-
First Sufficiency Response Comments -
Second Sufficiency Response Submittal
Second Sufficiency Response Comments -
Third Sufficiency Response Comments -
Notify Pasco County to Set Hearing Date -
Notification Received of Hearing Date
-
-
-
-
-
-
-
-
-
-
-
-
November 7, 2001
January 28, 2002
June 6, 2002
June 26, 2002
July 5, 2002
October 11, 2002
November 8, 2002
March 7, 2003
April 4, 2003
September 4, 2003
October 3, 20032
February 13, 2003
March 12, 2004
March 12, 2004
March 31, 2003
April 12, 2004
July 27, 2004
PROJECT DESCRIPTION
The applicant for the Cypress Creek Town Center Development of Regional Impact (DRI) is seeking specific DRI approval for Phase 1 of a two-phase, 510+ acre, mixed-use development in southern
Pasco County. The first phase is proposed to contain 1.996 million square feet (sq. ft.) of commercial uses including a regional mall, 120,000 sq. ft. of office development, 230 multi-family residential units, and 350 hotel rooms. Specific approval for Phase 2 will be contingent upon further transportation and air quality analyses. This phase would consist of a 215,000 sq. ft. Expansion of the regional mall, 300,000 sq. ft. of additional office space, 400 more multi-family residential units and 350 additional hotel rooms. The entitlements requested for each Phase are identified in the table provided below.
Commercial
LAND USE
(Sq. Ft.)
PHASE 1
(2002-2008)
1,996,000
Hotel
Regional Mall
Retail Center
Highway Commercial
Office
Residential/Multi-Family
(Sq. Ft.)
(Units)
(Rooms)
1,300,000
600,000
96,000
120,000
230
350
PHASE 2
(2009-2011)
215,000
215,000
0
0
300,000
400
350
TOTAL
2,211,000
1,515,000
600,000
96,000
420,000
630
700
Cypress Creek Town Center - Introduction Page 2