DRI #271
Robinson Gateway
Manatee County
Final Report
Project Entitlements
(Buildout: Dec. 31, 2015)
Robinson Gateway
Notable Recommended Conditions
• Specific approval of single-phase project with an
established buildout date of December 31, 2025;
• Establishment of a development commencement
date to coincide with a period of five years from
the Development Order adoption date;
• As committed, the Applicant shall provide
parkland and recreational facilities as well as
connection to Manatee County’s greenway trails
program along the northern boundary of the
project;
Robinson Gateway
Notable Recommended Conditions
• Preparation and submittal of a Stormwater
Management Plan and a Parks Master Plan;
• Conduct of Surface & Groundwater Quality
Monitoring;
• Mitigation to offset the impacted roadway
segments and intersections identified in the
Council’s Final Report; and
• Voluntary Affordable Housing/Workforce
Housing Program.