DRI #271 Robinson Gateway Manatee County Final Report Project Entitlements (Buildout: Dec. 31, 2015) Robinson Gateway Notable Recommended Conditions • Specific approval of single-phase project with an established buildout date of December 31, 2025; • Establishment of a development commencement date to coincide with a period of five years from the Development Order adoption date; • As committed, the Applicant shall provide parkland and recreational facilities as well as connection to Manatee County’s greenway trails program along the northern boundary of the project; Robinson Gateway Notable Recommended Conditions • Preparation and submittal of a Stormwater Management Plan and a Parks Master Plan; • Conduct of Surface & Groundwater Quality Monitoring; • Mitigation to offset the impacted roadway segments and intersections identified in the Council’s Final Report; and • Voluntary Affordable Housing/Workforce Housing Program.